Citation
SWFWMD Minimum Requirements from WRDA Funds

Material Information

Title:
SWFWMD Minimum Requirements from WRDA Funds
Language:
English
Physical Description:
1p.

Subjects

Subjects / Keywords:
City of Tampa ( local )
Canals ( jstor )
Spatial Coverage:
North America -- United States of America -- Florida

Notes

General Note:
Box 1, Folder 7 ( FUNDING WATER MANAGEMENT DISTRICTS ), Item 78
Funding:
Digitized by the Legal Technology Institute in the Levin College of Law at the University of Florida.

Record Information

Source Institution:
University of Florida
Holding Location:
Levin College of Law, University of Florida
Rights Management:
All applicable rights reserved by the source institution and holding location.

Downloads

This item has the following downloads:


Full Text






SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT
MINIMUM REQUIREMENTS FROM W.R.D.A. FUNDS



PRIORITY

CONSTRUCTION

1 17% State of Florida cash contribution for
continuation of construction of the following
on-going water management projects:

To complete Lake Tarpon Outfall canal structure;
To complete section 1-B Tampa By Pass Canal;
To continue construction section 1-C and 2,
Tampa By Pass Canal (to be completed in
late 1972);
To complete Levee 212 Oklawaha River Basin;

(Note: Rights of way already acquired. Paid
for from local ad valorem tax money)

Federal contribution at 83% $3,280,000
Absolute minimum necessary (17% of above) 557,600


LAND ACQUISITION

2. To complete purchase of Lower Hillsborough
Reservoir based on current appraisals -
(11,400 acres already acquired at cost
of $3,708,000)

4,621 acres 1,400,000

3. To complete purchase of Green Swamp
Reservoir (42,000 acres already acquired
at cost of $2,355,000)

16,998 acres 2,180,000


Based on current appraisals

BRIDGE CONSTRUCTION

4. I-4 bridges over Tampa By Pass Canal (9 lanes
of traffic) this could be divided into two
contracts and the first contract deferred for
one year and the second contract deferred for
two years. 2,500,000