Title: Category I Amendment Process
CITATION THUMBNAILS PAGE IMAGE ZOOMABLE
Full Citation
STANDARD VIEW MARC VIEW
Permanent Link: http://ufdc.ufl.edu/WL00004646/00001
 Material Information
Title: Category I Amendment Process
Physical Description: Book
Language: English
 Subjects
Spatial Coverage: North America -- United States of America -- Florida
 Notes
Abstract: Jake Varn Collection - Category I Amendment Process (JDV Box 70)
General Note: Box 24, Folder 4 ( Water Supply Issues - Linking Water Supply Planning and Land Use Planning ), Item 9
Funding: Digitized by the Legal Technology Institute in the Levin College of Law at the University of Florida.
 Record Information
Bibliographic ID: WL00004646
Volume ID: VID00001
Source Institution: Levin College of Law, University of Florida
Holding Location: Levin College of Law, University of Florida
Rights Management: All rights reserved by the source institution and holding location.

Full Text


uI
( Z


f-.
U .- .
: ..
S Ii.-


C


IF DCA AGREES THAT
PROPOSED CHANGE IS
CATEGORY I OR
DCA FAILS TO COMMENT


PUBLIC HEARINGS
WIIN 20 DAYS NOTICE


IF DCA ADVISES THAT
PROPOSED CHANGE IS NOT
A CATEGORY I AMENDMENT

PUBLIC HEARINGS
WONl 20 DAYS NOTICE


DEVELOPER
ELECTS TO HAVE
PROPOSED CHANCE
PROCESSED AS
CATEGORY II or 1I
AMENDMENT


LOCAL GOVT MAY
1) APPROVE
2) APPROVE WITH CONDITIONS
31 DENY


DCA HAS VERY
LIMITED RIGHT TO
APPEAL


LOCAL O0VT MAY
I) APPROVE
2) APPROVE WITH CONDITIONS
3) DENY


DCA MAY APPEAL


1. PUBLIC HEARING BY LOCAL GOV'T AND DECISION WITHIN 00 DAYS OF RECEIPT OF REQUEST FOR CHANGE.

2. LOCAL COVT MUST RENDER DECISION WIIN 14 DAYS OF PUBLIC HEARING.

3. PROPOSED HEARING BY LOCAL GOVERNMENT SHALL NOT BE HELD EARLIER THAN 45 DAYS FROM RECEIPT OF REQUEST FOR CHANGE.


CATEGORY I AMENDMENT PROCESS

DEVELOPER FILES REQUEST FOR
AN AMENDMENT WILOCAL GOVERNMENT.
RPC AND DCA


WIIN 45 DAYS


DCA PROVIDES WRITTEN
COMMENTS. INCLUDING WHETHER
CHANGE IS CATEGORY I


?1 :1











CATEGORY II AMENDMENT PROCESS

DEVELOPERS SUBMITS REQUEST FOR AN
AMENDMENT TO LOCAL GOVT. RPC & DCA


WITHIN 45 DAYS OF CATEGORY
II Mt AMENDMENT DETERMINATION
OCA ADVISES IF ADEQUATE
MITIGATION IS PROPOSED


IF DCA AGREES
THAT PROPOSED CHANGE
IS CATEGORYJI-




PUBLIC HEARINGS)

1.


LOCAL GOV'T MAY
1I APPROVE
2) APPROVE WICONOITIONS. OR
31 DENIES
(RENDERS DECISION)



APPEAL


WOlN 60
DAYS



LOCAL GOV'T SCHEDULES PUBLIC
HEARING


WITHIN 45 DAYS OF RECEIPT OF REQUEST
DCA ADVISES WHETHER IT IS A
CATEGORY AMENMENDMENT
II


IF DCA INDICATES THAT
PROPOSED CHANGE IS NOT
CATEGORY III


PUBLIC HEARINGSIS)


DEVELOPER ELECTS
TO HAVE PROPOSED
CHANGE PROCESSED
,AS CATEGORY III
AMENDMENT


LOCAL COVT MAY
11 APPROVE
21 APPROVE WICONDITIONS
31 DENY
(RENDERS DECISION)


APPEAL


r












CATEGORY III AMENDMENT PROCESS


SAME PROCESS AS FOR DRI












LAND USE CATEGORY I CATEGORY M
AMENDMENTS AMENDMENTS

1. ATTRACTION OR RECREATION FAC. 1. MAY NOT EXCEED ANY OF THE FOLLOWING INCREASES: 1. MEETS OR EXCEEDS ANY OF THE FOLLOWING INCREASES:
HOSPITALS A. 125 EXTERNAL P.M. PEAK HOUR TRIPS A. 450 EXTERNAL P.M. PEAK HOUR TRIPS
INDUSTRIAL DEVELOPMENTS B. 40 D.U. OF ADEQUATE HOUSING DEMAND B. 225 D.U. OF ADEQUATE HOUSING NEEDS
OFFICES C. 80 HURRICANE SHELTER SPACES DEMAND C. 500 HURRICANE SHELTER SPACES DEMAND
RESIDENTIAL DEVELOPMENTS
RETAIL DEVELOPMENTS
HOTELS
MOTELS
RECREATIONAL VEHICLES DEV.

2. MINING 2. MAY NOT EXCEED ANY OF THE FOLLOWING INCREASES: 2. MEETS OR EXCEEDS ANY OF THE FOLLOWING INCREASES:
A. 750,000 GPO ANNUAL AVG. DAILY WATER WITHDRAWAL A. 3.0 MGD OF ANNUAL AVG. DAILY WATER
B. MINE SIZE BY 2% OR 300 A. WIIN DRI, WHICHEVER IS LESS WITHDRAWAL
C. ANY OF 1. ABOVE B. MINE SIZE OF 5% OR 750 A. WfIN DRI, WHICHEVER
IS LESS
C. ANY OF 1. ABOVE

3. AIRPORTS 3. MAY NOT EXCEED ANY OF THE FOLLOWING INCREASES: 3. MEETS OR EXCEEDS ANY OF THE FOLLOWING INCREASES:
A. 4% IN LENGTH OR WIDTH OF EXISTING RUNWAY A. NEW RUNWAY
B. 8% IN FLOOR AREA OF EXISTING TERMINAL B. NEW PASSENGER TERMINAL
C. ANY OF 1. ABOVE C. 10% IN LENGTH OR WIDTH OF EXISTING RUNWAY
D. 20% INCREASE IN FLOOR AREA OF AN EXISTING
TERMINAL
E. ANY OF 1. ABOVE

4. CHEMICAL ANO PETROLEUM 4. MAY NOT EXCEED ANY OF THE FOLLOWING: 4. MEETS OR EXCEEDS ANY OF THE FOLLOWING:
STORAGE FACILITIES A. INCREASE IN CAPACITY OF A. INCREASE IN CAPACITY OF
1) 2% 1) 5%
2) 8,000 BARRELS, OR 21 20,000 BARRELS, OR
3) 2.8 MILLION POUNDS 31 7.0 MILLION POUNDS,
WHICHEVER IS LESS WHICHEVER IS LESS
B. ANY OF 1. ABOVE B. ANY OF 1. ABOVE











5. MARINASIPORTS 5. ANY MARINA OUTSIDE OF OUTSTANDING FLORIDA WATERS. CLASS II 5. ANY MARINA OR PORT WHICH MEETS OR EXCEEDS ANY OF
WATERS AND DESIGNATED MANATEE BREEDING AREAS MAY NOT EXCEED THE FOLLOWING:
ANY OF THE FOLLOWING: A. INCREASE IN NO. OF SLIPS OF
A. INCREASE IN NO. OF SLIPS OF 1 5%
11 2% 21 20 WET SLIPS. OR
2) 8 WET SLIPS. OR 31 30 DRY SLIPS
3) 12 DRY SLIPS WHICHEVER IS LESS
WHICHEVER IS LESS B. NEW CRUISE SHIP SLIP
B. ANY OF 1. ABOVE C. ANY OF 1. ABOVE



PROVISIONS APPLICABLE TO ALL PROVISIONS APPLICABLE TO ALL
CATEGORY I AMENDMENTS CATEGORY II AMENDMENTS

1. EXTENSION OF BUILDOUT OR PHASES MUST BE LESS THAN 5 YEARS 1. EXTENSION OF BUILOOUT OR PHASES BY FIFTEEN YEARS
2. CANNOT INCLUDE: OR MORE
A. AREAS SET ASIDE FOR PRESERVATION OR SPECIAL PROTECTION. 2. SIGNIFICANT DEVELOPMENT OR DEGRADATION OF ANY
B. ADDITION OF NEW ACREAGE AREAS SET ASIDE FOR PRESERVATION OR SPECIAL
C. A CHANGE TO SEPTIC TANKS PROTECTION
0. REDUCTION OF DEVELOPER'S MITIGATION OBLIGATION OR 3. INCREASE IN SIZE OF PROJECT BY 20% OR 320 A..
REQUIREMENT FOR INFRASTRUCTURE. WHICHEVER IS LESS
E. AN ELIMINATION OF APPROVED LAND USE. 4. EXTENSION OF TIME OF 10 YEARS OR MORE FOR
F. REDUCTION IN EXCESS OF DECREASES IN 380.06(19b.6.c. CONSTRUCTION OF ONE OR MORE TRANSPORTATION
3. MAY INCLUDE IMPROVEMENTS
A. CHANGES IN PROJECT NAME, DEVELOPER, OWNER OR MONITORING
OFFICIAL
8. CHANGES IN SETBACK NOT RELATED TO ENV., ARCH OR HISTORICAL
RES.
C. CHANGES TO MIN. LOT SIZE
0. CHANGES IN CONFIGURATION OF INTERNAL ROADS
E. SIMULTANEOUS INC. OR DECREASES IN FLOOR AREAS OF LESS THAN
100,000 SOUARE FT.
F. CHANGES TO BUILDING WIIN FOOTPRINT ; e
G. CHANGES REQUIRED BY DEP. WMD OR FED. REG. AGENCIES
H. ANY OTHER CHANGES AGREED TO BY OCA




University of Florida Home Page
© 2004 - 2010 University of Florida George A. Smathers Libraries.
All rights reserved.

Acceptable Use, Copyright, and Disclaimer Statement
Last updated October 10, 2010 - - mvs