Proposed Revision
November 16, 1987
Mining in Wetlands
Problem: Mining in wetlands requires multiple agency permits
with diverse standards and conditions.
Proposed Solution:
Provide that the reclamation program remain in DNR, but that in
those wetland areas where mining occurs, WMD decisions regarding
permits will be binding. If the proposal for dredge and fill
is accepted (See p. 2) permits may be required from WMDs rather
than from DER.
-10-
i
Proposed Revision
November 16, 1987
Mining in Wetlands
Problem: Mining in wetlands requires multiple agency permits
with diverse standards and conditions.
Proposed Solution:
Provide that the reclamation program remain in DNR, but that in
those wetland areas where mining occurs, WMD decisions regarding
permits will be binding.