Importance of Multidisciplinary Collaboration in Building Information Modeling

Permanent Link: http://ufdc.ufl.edu/UFE0042642/00001

Material Information

Title: Importance of Multidisciplinary Collaboration in Building Information Modeling
Physical Description: 1 online resource (108 p.)
Language: english
Creator: Villanueva-Meyer, Sergio
Publisher: University of Florida
Place of Publication: Gainesville, Fla.
Publication Date: 2010

Subjects

Subjects / Keywords: 3d, 4d, 5d, archicad, architecture, autodesk, bim, building, collaboration, construction, cost, descriptive, design, efficiency, environment, information, leed, management, methods, modeling, multidisciplinary, navisworks, scheduling, software, statistics, survey, sustainability, techniques, technology
Building Construction -- Dissertations, Academic -- UF
Genre: Building Construction thesis, M.S.B.C.
bibliography   ( marcgt )
theses   ( marcgt )
government publication (state, provincial, terriorial, dependent)   ( marcgt )
born-digital   ( sobekcm )
Electronic Thesis or Dissertation

Notes

Abstract: Abstract of Thesis Presented to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Degree of Master of Science in Building Construction IMPORTANCE OF MULTIDISCIPLINARY COLLABORATION IN BUILDING INFORMATION MODELING (BIM) Sergio Villanueva-Meyer December 2010 Chair: R. Raymond Issa Cochair: Svetlana Olbina Major: Building Construction The global economic downturn has affected almost every market in the world, and the architecture, engineering and construction (AEC) industry has been particularly vulnerable. The AEC industry has been busy in its technological advancements, which have originated significant transformations. Building Information Modeling (BIM) software vendors have been active in providing solutions, tools, and problem-solving updates at an unprecedented rate. The way the AEC industry operates is being deeply re-thought and the way business will be done in the future is simply not the same as it is today. A collaborative environment is being established, and its presence is inevitable for the proper adoption and development of the latest building methodologies. The increased demand for high performance green buildings and the implementation of rating systems, such as Leadership in Energy and Environmental Design (LEED), requires an elevated degree of multidisciplinary collaboration which has been established by the advocates of these methodologies.
General Note: In the series University of Florida Digital Collections.
General Note: Includes vita.
Bibliography: Includes bibliographical references.
Source of Description: Description based on online resource; title from PDF title page.
Source of Description: This bibliographic record is available under the Creative Commons CC0 public domain dedication. The University of Florida Libraries, as creator of this bibliographic record, has waived all rights to it worldwide under copyright law, including all related and neighboring rights, to the extent allowed by law.
Statement of Responsibility: by Sergio Villanueva-Meyer.
Thesis: Thesis (M.S.B.C.)--University of Florida, 2010.
Local: Adviser: Issa, R. Raymond.
Local: Co-adviser: Olbina, Svetlana.

Record Information

Source Institution: UFRGP
Rights Management: Applicable rights reserved.
Classification: lcc - LD1780 2010
System ID: UFE0042642:00001

Permanent Link: http://ufdc.ufl.edu/UFE0042642/00001

Material Information

Title: Importance of Multidisciplinary Collaboration in Building Information Modeling
Physical Description: 1 online resource (108 p.)
Language: english
Creator: Villanueva-Meyer, Sergio
Publisher: University of Florida
Place of Publication: Gainesville, Fla.
Publication Date: 2010

Subjects

Subjects / Keywords: 3d, 4d, 5d, archicad, architecture, autodesk, bim, building, collaboration, construction, cost, descriptive, design, efficiency, environment, information, leed, management, methods, modeling, multidisciplinary, navisworks, scheduling, software, statistics, survey, sustainability, techniques, technology
Building Construction -- Dissertations, Academic -- UF
Genre: Building Construction thesis, M.S.B.C.
bibliography   ( marcgt )
theses   ( marcgt )
government publication (state, provincial, terriorial, dependent)   ( marcgt )
born-digital   ( sobekcm )
Electronic Thesis or Dissertation

Notes

Abstract: Abstract of Thesis Presented to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Degree of Master of Science in Building Construction IMPORTANCE OF MULTIDISCIPLINARY COLLABORATION IN BUILDING INFORMATION MODELING (BIM) Sergio Villanueva-Meyer December 2010 Chair: R. Raymond Issa Cochair: Svetlana Olbina Major: Building Construction The global economic downturn has affected almost every market in the world, and the architecture, engineering and construction (AEC) industry has been particularly vulnerable. The AEC industry has been busy in its technological advancements, which have originated significant transformations. Building Information Modeling (BIM) software vendors have been active in providing solutions, tools, and problem-solving updates at an unprecedented rate. The way the AEC industry operates is being deeply re-thought and the way business will be done in the future is simply not the same as it is today. A collaborative environment is being established, and its presence is inevitable for the proper adoption and development of the latest building methodologies. The increased demand for high performance green buildings and the implementation of rating systems, such as Leadership in Energy and Environmental Design (LEED), requires an elevated degree of multidisciplinary collaboration which has been established by the advocates of these methodologies.
General Note: In the series University of Florida Digital Collections.
General Note: Includes vita.
Bibliography: Includes bibliographical references.
Source of Description: Description based on online resource; title from PDF title page.
Source of Description: This bibliographic record is available under the Creative Commons CC0 public domain dedication. The University of Florida Libraries, as creator of this bibliographic record, has waived all rights to it worldwide under copyright law, including all related and neighboring rights, to the extent allowed by law.
Statement of Responsibility: by Sergio Villanueva-Meyer.
Thesis: Thesis (M.S.B.C.)--University of Florida, 2010.
Local: Adviser: Issa, R. Raymond.
Local: Co-adviser: Olbina, Svetlana.

Record Information

Source Institution: UFRGP
Rights Management: Applicable rights reserved.
Classification: lcc - LD1780 2010
System ID: UFE0042642:00001


This item has the following downloads:


Full Text

PAGE 1

1 IMPORTANCE OF MULTIDISCIPLINARY COLLABORATION IN BUILDING INFORMATION MODELING (BIM) By SERGIO VILLANUEVA MEYER A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT OF THE REQUIREM ENTS FOR THE DEGREE OF MASTER OF SCIENCE IN BUILDING CONSTRUCTION UNIVERSITY OF FLORIDA 2010

PAGE 2

2 2010 SergioVillanueva Meyer

PAGE 3

3 To Kiki, Abita, Juanita and Herbert Ibi victoria, ubi

PAGE 4

4 ACKNOWLEDGMENTS First and foremost I would like t o thank my extremely hardworking mom and dad I have been able to overcome roadblocks in my academic, professional and personal life thanks to their continuous support and extraordinary influence. I would like to thank Tonky Beale from Beale & Associates, Mercedes Porcari from Exotic scape and John and Ame rica Gordon from Wildwoods Inc. They have provided me with i ndispensable experie nces in the AEC field. I am also very grateful to my committee members, Dr. Issa, Dr. Olbi na, and Dr. Lucas as well as Do ttie Beaupied, for having such a positive attitude. Finally, I would like to thank Laura Finton for her abiding happiness. I owe much of my academic and personal achievements to her. Thanks for making my two year journey at the Rinker School so enjoyable

PAGE 5

5 TABLE OF CONTENTS Page ACKNOWLEDGMENTS ................................ ................................ ................................ .. 4 LIST OF TABLES ................................ ................................ ................................ ............ 7 LIST OF FIGURES ................................ ................................ ................................ .......... 8 LIST OF ABBREVIATIONS ................................ ................................ ........................... 10 ABSTRACT ................................ ................................ ................................ ................... 11 CHAPTER 1 INTRODUCTION ................................ ................................ ................................ .... 13 Problem Statement ................................ ................................ ................................ 14 Research Objectives ................................ ................................ ............................... 15 Research Methodology ................................ ................................ ........................... 16 Summary ................................ ................................ ................................ ................ 17 2 LITERATURE REVIEW ................................ ................................ .......................... 18 Introduction ................................ ................................ ................................ ............. 18 The BIM Collaborative Environment ................................ ................................ ....... 18 Global Changes and Technological Advancements ................................ ......... 19 Web 2.0 ................................ ................................ ................................ ............ 19 Collaboration vs. C Three (Cooperation, Coordination, and Communication) .. 20 Defining Building Information Modeling (BIM) ................................ .................. 20 The BIM Process ................................ ................................ .............................. 22 The Urgency for Collaboration ................................ ................................ .......... 22 The Prob lems with BIM Collaboration ................................ .............................. 24 BIM Collaboration Software ................................ ................................ .................... 26 Interoperability and the Development of a Common Language ........................ 27 The buildingSMART Collaborative Efforts ................................ ........................ 28 Available Software ................................ ................................ ............................ 29 Summa ry of Project Information Management Software for Collaboration ....... 36 Integrated Project Delivery (IPD) ................................ ................................ ............ 37 BIM and IPD ................................ ................................ ................................ ..... 38 The AIA and IPD ................................ ................................ .............................. 39 Sustainability and BIM ................................ ................................ ............................ 40 Case Study One: Phoenix Chil Manager at Risk ................................ ................................ ............................ 41 Case Study Two: Encircle Health Ambulatory Care Center .............................. 43

PAGE 6

6 3 RESEA RCH METHODOLOGY ................................ ................................ ............... 45 Introduction ................................ ................................ ................................ ............. 45 Question Screening Process ................................ ................................ ............ 47 Research Objectives ................................ ................................ ........................ 47 Survey Questionnaire ................................ ................................ ............................. 47 Research Objective 1 Degree of Implementation and Experience ................ 48 Research Objective 2 Cost and Scale ................................ ........................... 50 Research Objective 3 Project Delivery and Sustainability ............................. 52 BIM Multidisciplinary Collaboration Questions ................................ .................. 52 Descriptive Statistics and Cross Tabulation Analysis ................................ ............. 53 Comparisons against Identified Improvements, Benefits and Difficulties ................ 54 Summary ................................ ................................ ................................ ................ 55 4 RESULTS AND ANALYSIS ................................ ................................ .................... 56 Research Objective 1 Degree of Implementation and Experience ....................... 56 Early Implementation for Collaboration ................................ ............................ 64 BIM Tasks Performed ................................ ................................ ....................... 66 Difficulties in the BIM Process ................................ ................................ .......... 68 Results on Software Used ................................ ................................ ................ 73 Research Objective 2 Cost and Scale ................................ ................................ 77 Research Objective 3 Project Delivery and Sustainability ................................ .... 84 5 CONCLUSIONS AND RECOMMENDATIONS ................................ ....................... 88 APPENDIX A IRB SURVEY PROPOSAL SUBMISSION ................................ .............................. 94 B SURVEY QUESTIONNAI RE ................................ ................................ .................. 97 LIST OF REFERENCES ................................ ................................ ............................. 105 BIOGRAPHICAL SKETCH ................................ ................................ .......................... 108

PAGE 7

7 LIST OF TABLES Table page 4 1 What disciplines are represented in your BIM projects? ................................ ..... 61 4 2 Verbatim regarding identified difficulties in BIM ................................ .................. 71 4 3 .. 76 4 4 ................................ ................ 77 4 5 Return on investment (ROI) ................................ ................................ ................ 82

PAGE 8

8 LIST OF FIGURES Figure page 2 1 ................. 23 2 2 C oordination versus flexibility 2009a) ................................ ................................ ................................ ................ 24 2 3 the overall submittals statistics (source: Khemlani 2009d). ................................ 34 2 4 Open a Revit family using the Organice Explorer interface (adapted from Khemlani 2009d). ................................ ................................ ............................... 36 4 1 Experience in the construction industry ................................ .............................. 57 4 2 ................................ ................................ ....................... 58 4 3 How many projects have you been involved with? ................................ ............. 59 4 4 Fields of practice ................................ ................................ ................................ 60 4 5 Fields represented in BIM projects ................................ ................................ ..... 61 4 6 Field most willing to collaborate ................................ ................................ .......... 62 4 7 BIM multidisciplinary meetings (per month) ................................ ........................ 63 4 8 Motivation for multidisciplinary collaboration ................................ ...................... 64 4 9 Early BIM multidisciplinary collaboration ................................ ............................ 65 4 10 Comparison of early BIM collaboration and identified improvements ................. 66 4 11 Hours a week of BIM tasks ................................ ................................ ................. 67 4 12 Hours of weekly BIM exposure and motivation to collaborate ............................ 68 4 13 Identifie d difficulties ................................ ................................ ............................ 70 4 14 Effectiveness of collaboration software ................................ .............................. 74 4 15 Software used ................................ ................................ ................................ ..... 75 4 16 Yearly volume of work ................................ ................................ ........................ 78 4 17 Average project size (using BIM) ................................ ................................ ........ 79

PAGE 9

9 4 18 Type of construction ................................ ................................ ........................... 79 4 19 Ideal project size ................................ ................................ ................................ 80 4 20 Initial investment ................................ ................................ ................................ 81 4 21 Compariso n of number of license s and accuracy of BIM models ....................... 83 4 22 Comparison of number of licenses and identified improvements ........................ 84 4 23 Project delivery method ................................ ................................ ...................... 85

PAGE 10

10 LIST OF ABBREVIATION S 2D A drawing that uses only the X and Y planes 3D A drawing that uses the Z plane in addition the X and Y planes 4D Refers to the implementation of Scheduling (time) in BI M 5D Refers to the implementation of cost analysis (estimating) in BIM AIA American Institute of Architects ABC American Building Council AEC Architecture/ Engineering/ Construction B Billion (US$) BIM Building Information Modeling BREEAM Building Research Establishment Environmental Assessment Method CAD Computer Aided Drafting DB Design Build FM Facilities Management IAI International Alliance for Interoperability IFC s In dustry Foundation Classes IPD Integrated Project Delivery ISO International Standards Organization LEED Leadership in Energy and Environmental Design M Million (US$) PIM Project Information Management RFI Request for Information ROI Return on Investment USGBC United States Green Building Council VDC Virtual Design and Construction

PAGE 11

11 Abstract of Thesis Presented to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Degree of Master of Science in Building Construction IMPORTANCE OF MULTIDISCIPLINARY COLLABORATION IN BUILDING INFORMATION MODELING (BIM) By S ergio Villanueva-Meyer December 2010 Chair: R. Raymond Issa Cochair: Svetlana Olbina Major: Building Construction The global economic downturn has affected almost every market in the world and the architecture, engineering, and construction (AEC) industry has been particularly vulnerable. Although several firms have vanished, projects have stalled, and unemployment rates have spiked, the AEC industry has been extremely busy in its technological and innovative advancements. These have originated significant and fu ndamental transformations. Building information modeling (BIM) software vendors have been active over the past decade, providing new solutions, innovative tools, and problem-solving updates at an unprecedented rat e. The way the AEC industry operates is being deeply re-thought and the way business will be done in the future is simply not the same as it is today. A collaborative environment is being established, and its presence is inevitable for the proper adoption and development of the latest building construction methodologies. Firms adopting BIM are setting higher goals and a high level of communication and coordination is vital throughout the lifecycle of projects. Therefore, corporate organizational structures have been altered with the introduction of new positions such

PAGE 12

12 as BIM Managers, BIM Coordinators and Model Coordinators. Challenging tasks are being performed and more work is being done by fewer personnel, meeting higher standards. Nevertheless in order to fully enjoy the benefits of BIM, the proper steps need to be taken and a well established collaborative setting is crucial for BIM and Integrated Project Delivery (IPD) implementation. Some of the focal shifts in the industry are a consequence of the economic downturn, the pursuit of sustainable ratings, the adoption of improved project delivery methods, the bitter history of litigation and a long felt sense of backwardness in the industry. The increased demand for high performance green buildings and the mainstream implementation of green rating systems, such as Leadership in Energy and Environmental Design (LEED), requires an elevated degree of multidisciplinary collaboration. This research explores the paradigm shifts occurring with the recent introd uction of BIM and the importance of coordination, communication and the formation of a c ollaborative environment. Multidisciplinary collaboration is a common denominator of the philosophies behind BIM, Design Build (DB) IPD, and LEED and a culture of coll aboration has been established by the advocates of these methodologies, which happened to be thriving simultaneously.

PAGE 13

13 CHAPTER 1 INTRODUCTION With the increase in complexity and the technicalities of the modernized world, a collaborative environment of multidisciplinary professionals is highly desired in almost every possible circumstance BIM is collaboration by the different stakeholders at different phases of the lifecycle of a facility to inser t, extract, update or modify information in the BIM to support and reflect Times are changing and the recent slowdown in construction provides time to reflect over the past challenges and troubles. The 21 st c entury has been exceptionally fast paced, and most industries around the globe, have focused on sustainability, efficiency and quality of life. These trends continue to be of fundamental concern, and the methods employed to reach them will swiftly become a ll encompassing. Building i nformation m odeling (BIM) brings high hopes to many of the issues experienced in the industry which has often been regarded as backward. Collaboration is a very desirable process, which creates an environment of two or more ent ities working towards achieving common goals. The advancements in the key industrial economic sectors have transformed the built environment. The a rchitecture engineering and c onstruction (AEC) industry is becoming highly specialized due to the constant d evelopment of advanced materials, high performance green system requirements and sophisticated methods of construction. Furthermore, the industry involves such a broad range of specialties, that a high level of multidisciplinary collaboration is imperative BIM has gained widespread popularity due to its broad applications and numerous functionalities. It encompasses most fields of practice, and

PAGE 14

14 in addition to the direct benefit s to individual organizations, it facilitates coordination and communication wit h external collaborators. Green building practices are facilitated through BIM, and most software developers are focusing in the sustainable aspects of their platforms. With the spike in Leadership in Energy and Environmental Design Accredited Professional AEC professionals utilizing BIM tend to have knowledge in sustainability and are helping guide the future of the industry through a greener path. Early BIM advocates have been essential in its adoption and are helping the industry adapt to t he changes while eas ing the transition to the new methodologies. BIM implementation has created alterations in corporate organizational structures, and new positions such as BIM Managers, BIM Coordinators and Model Coordinators have emerged. These positio ns are vital, and strive to facilitate benefits in productivity, coordination, scheduling, and planning as well as to reduce the burden of elaborate and conflicting processes involving multiple disciplines. Problem Statement As the AE C industry embraces technology, and its disciplines become progressively integrated, ample quantities of interconnected information catapults project complexities. With the blurred lines of traditional responsibilities and a vague software and contractual language, multidisci plinary relationships remain disconnected. The multidisciplinary collaborative climate is complex, making project coordination, model data management, and object based communication highly challenging tasks. BIM offers many solutions to past problems, how ever, the vast amount of data and in formation makes it hard to manage Additionally, with the in tegration of technical fields (e ngineering disciplines, energy analysis ) into the design phases, better and more

PAGE 15

15 sustainable solutions can be achieved Nevertheless, without the appropriate mediation and project delivery method, the excessive amount of input and cooperation could easily become conflicting and detrimental if mishandled. It is important to understand the widespread desire for a collaborati The fields of practice under the pre BIM and pre Design Build (DB) eras still shared mutual goals and benefited from multidisciplinary collaboration which has been praised for centuries. Therefore it is important to understand the links between the latest AEC trends and project delivery methods (IPD) and collaboration These trends enable a more collaborative environment geared towards solving issues in areas such as design, quality, cost, scheduling and sustainabili ty. There is a need to investigate the methods employed in the industry to foster this constructive reciprocity which enables improvements in the nexus of time, quality, cost and sustainability. Research Objectives The purpose of the research is to evalua te the effect of multidisciplinary collaboration experienced with the implementation of BIM under diverse scenarios. Three groups were created with the purpose of c overing the following topics: implementation and experience, scale, and project delivery m et hod. The following objectives attempt to formulate a better understanding of the industry perceptions regarding multidisciplinary collaboration. 1. To determine the degree to which experience and BIM implementation affect the perceived level of multidiscipli nary collaboration. 2. To determine the degree of multidisciplinary collaboration experienced in BIM in relation to the size of the project s and firms researched 3. To determine the perceived benefits and problems encountered in the multidisciplinary process of BIM implementation in relation to the selected project delivery methods and green rating systems pursued.

PAGE 16

16 Research Methodology The research objectives listed above relate to each other and a well structured c omparative analysis will be performed to estab lish relationships and patterns concerning the selected topics. The structure of the research compliments the findings and begins with a thorough research and analysis of relevant existing literature in Chapter 2. Issues regarding virtual collaboration and software platforms, as well as case studies concerning BIM use, sustainability, Design Build and Integrated Project Delivery (IPD) were discussed. Chapter 3 provides a descriptive analysis of the reasoning behind the survey deployed thought o ut the industry, which target ed BIM and virtual design and construction (V DC ) professionals. The section provides an in depth description of the strategy behind the questionnaire. Some questions have been cross tabulated as part of the statistical analysis and c hapter 3 clarifies the reasoning for the pairings and established relationships. Furthermore, a detailed analysis of the collected data is performed in Chapter 4. The data received was analyzed according to the guidelines established in Chapter 3 in order to better understand the research objectives. This chapter mainly consists of graphs, lists and tables which aim to represent the data in a visually appealing manner addressing the concerning topics. Chapter 5 consists of a set of conclusions drawn from Chapter 4, addressing the research objectives. The conclusions in this chapter re present the perceptions of the survey respondent s as well as the insights gathered in Chapter 2 This chapter consists of multiple cross references to the figures in Chapter 4 The conclusions are a product of the previous analysis which consists of graphs and tables containing pairings, cross

PAGE 17

17 tabulations and statistical methods used to understand existing relationships and dependencies. Moreover, this chapter suggests recommen dations for future studies regarding BIM research, and provides recommendations to the industry regarding advances in BIM and its relationship with multidi sciplinary collaboration in the AEC industry Summary This research attempts to target multiple issu es, trends and dependencies in regard to technology, collaboration and sustainability. Given that the BIM/VDC arena is going through an unsteady state of change, the research aims to stay in line with the industry updates throughout its duration. The purpo se of the research is to further understand the current trends and parameters established in the col laborative BIM environment and observe how these affect projects that follow sustainable practices. The industry is being shaped by technology and advanced project delivery methods such as Design Build and IPD are on the rise. It is vit al to understand the shaping of the collaborative environment and the role of its key players, including owners or facility managers.

PAGE 18

18 CHAPTER 2 LITERATURE REVIEW Introduction The introduction of BIM is enabling the pursuit of complex and more sustainable construction methods. As the construction scenario changes, opinions and observations are making their way throughout the industry as well as lectures, publications, product reviews, blogs, white pages, case studies, symposiums and conferences. The literature review seeks to identify the most pertinent sources of information that relate to the research purpose and objective s. It also aims to org anize the gathered information s ystematically, in order to understand the differences and commonalities in the d iverse viewpoints selected. The research perform s a set of comparative analyses in order to further understand the effect of b uilding i nformation m odeling (BIM) in relation wit h multidisciplinary collaboration, software implementation, experience, scale, project delivery method and sustainability. Hence, the most pertinent sources were selected and respectively cited. Relevant information was extracted and c ategorized under four main categories in order to back up our hypotheses and validate the research. The four categories were: 1) The BIM Collaborative Environment, 2) BIM Collaboration Software, 3) Project Delivery Methods and 4) Sustainability. The BIM Collaborative Environ ment The BIM Collaborative environment is a complex space that encompasses several entities and individuals and can be understood in diverse ways. It is constantly altered by technological updates as well as upcoming industry trends The following sections discus the factors altering the BIM environment, it defines the problems faced identifies

PAGE 19

19 the existing needs and solutions and displays relevant and updated sources concerning BIM collaboration. Global Changes and Technological Advancements After the c ollapse of the Berlin wall brought an end to the Cold War, the closing years of the twentieth century brought much change to the new one. Globalization is here and the recent obsession with speed and efficiency has transformed the everyday of everything. T he following 21 st Century factors identified by Friedman (2005) changed countless processes in most industries: 1. Workflow Software: It has enabled people to work with other people on more tasks than before and a global platform for multiple forms of collab oration has been established. 2. Outsourcing: It has allowed companies to divide the service from the manufacturing activities into more efficient and cost effective components 3. Off shoring : Refers to the internal ent country, with the purpose of benefiting from cheaper operations experienced in foreign lands. 4. Open Source : Refers to the growing involvement and collaborating in virtual c ommunities 5. Supply chaining : Is item sal es, distribution, and shipping more efficient. 6. Insourcing : This concept, refers to companies collaborating in logistics. FedEx and UPS employees are perform ing services for other company s Toshiba (repairing Toshiba computers a t the UPS hub, by UPS employees). 7. The Steroids: Digital mobile, personal and virtual. With the improvements in w ireless, voice over Internet Protocol (VoIP) and file sharing technology, personal and Virtual processe s can be done at high speed with total ease. Web 2.0 In addition to the specified factors above, web breakthroughs ha ve attracted the attention of many software developers. Among the most talked about words in rs to an apparent second generation of web

PAGE 20

20 based services. These ser vices include communication tools, social networking sites, wikis and collaborative compositions. As stated by Grilo and Jardim Goncalves (2009) Web 2.0 collaborative tools have emerged with similar functionalities to those in the commercially used Autodesk Buzzsaw or ProjectNet The need to enrich BIM interoperability has been largely triggered by what has come to be known as Web 2.0 (Grilo and Jardim Goncalves 2009). T he emphasis is o n online sharing and collaboration Collaboration vs. C Three (Cooperation, Coordination, and Communication) Collaboration is the process of collective creation or constructed knowledge. It can also be referred as a group of individuals or organizations wi th corresponding capabilities interacting to produce a shared solution that had not been pr eviously identified on their own. This course, creates a mutual sense about a process, a product, or an event, and there is nothing regular about it. The following s teps are vital when attempting and enabling collaboration environments (Denise 2010): Define the challenge Define the collaborators Create the space Allow the time Harness the result Defining Building Information Modeling (BIM) The AIA California Council (2007) defines b uilding i nformation m odeling as a computable representation of all the physical and functional characteristics of a facility. AEC professionals can now enjoy the new technology platform s, in order to support the old fashioned notion of ear ly planning. Building i nformation m odeling is bringing fundamental changes to industry's workflow structure by assisting previously unheard of

PAGE 21

21 degrees of collaboration, planning, coordination, and communication (Dispenza 2010) The integrated process of BI M allows its users to digitally explore the vital characteristics of a project before it is built. This helps minimize the environmental impact as well as in delivering the projects faster and at a lower cost (Cohen 2010). In the field of construction, wi th the arrival of BIM, new opportunities arise These opportunities include, collaborative communication with multidisciplinary parties at a model level in order to utilize the information and value s that were already in the model. However, due to the diff erent modeling applications (and their proprietary file formats) new issues arise as well. Three primary strategies (below) have been identified regarding the previously described obstacle (Vrkonyi 2009) : Common language: The International Alliance for I nteroperability (IAI) was formed by CAD vendors to develop the Industry Foundation Classes (IFC s ) an platform for model based collaboration. Direct interfaces: An alternative sol ution is for software vendors to implement specialized links between their specific solutions. Sometimes, this approach is only undertaken by one of the parties, utilizing the API (Application Programming Interface) of the other solution. Single platform: A fundamentally different strategy is where a software vendor aims to develop competence in each Architecture, Engineering, Construction (AEC) segment and tries to supply the whole spectrum of needs with their own design solutions. Obviously in this case, the proprietary file format dimension of data exchange is likely to be a non issue between the different applications in a applications should achieve seamless and efficient collaborat ion (Vrkonyi 2009). The 3D models created by BIM not only help the architects and engineers when conveying their design concepts t o owners, but they also assists with the process of multidisciplinary communication and collaboration as well as in the 4D ( scheduling) and 5D (cost) The introduction of BIM with its numerous collaborative platforms enables the use of a central database, from where the collaborating disciplines can easily extract or

PAGE 22

22 input information. Hence, the interaction, flow of communicat ion and collaboration are significantly improved (Hol ness 2006). The BIM Process Traditionally, contractors are responsible for the means and methods while the architects are responsible for the design. However, with the advances of BIM and the early invol vement set by Integrated Project Delivery ( IPD ) n ot only do these parties perform different tasks, they perform according to different standards in a collaborative fashion. This creates issues in relation to the degree in which disciplines can rely on the information furnished by the corresponding disciplines in the BIM process. It is important to identi fy the roles of the disciplines and allocate the risks and responsibilities involved in the participating disciplines BIM benefits from the ability of th e owner, designers, and contractors to share information boundlessly, however this is not always the case The contract needs to address information ownerships and protection methods. In IPD contracts, disciplines address contractual obligations, however, the information moves freely and is shared among the disciplines, consultants, and subcontractors. This approach would present a higher success rate if the parties have contractual obligations in order to increase collaboration and reduce or eliminate the traditional tension areas between owner, designer, and builder (Dirik 2009). The Urgency for Collaboration BIM introduces a variety of multi faceted capabilities. The common thread between these capabilities is that it provides an accurate and active comp uter model for the The successful implementation of BIM requires input from design teams and project participants from multiple disciplines. Because of this, collaboration is the most critical success factor for BIM and IP D as well (Laiserin 2009).

PAGE 23

23 Collaboration is essential when providing a place for the project participants to view, supply, change, and extract the necessary data throughout the project stages. The multidisciplinary collaboration existing in the interactive 3D model s, display information in terms of design, structure, construction as well as time and cost at any level of detail. Some of benefits from BIM in clude collision detection, improvements in constructability, cost reducti ons, schedule improvements, an d request for information ( RFI ) reductions Furthermore, the benefits provid ed by BIM do not just benefit the immediate users but all the associated parties as well. Substantial benefits are realized when BIM is used in conjunction with a compatible projec t delivery method (IPD or Design Build ) and a broad ecosystem of collaboration resources (Azar 2008) Figure 2 1 Multidisciplinary models c ombin ed (c o ntractor uide to BIM 2006)

PAGE 24

24 Figure 2 1 shows the multiple models in BIM and the process involved i n the creation of a composite model. The following section further explains the means in which the multidisciplinary participants and software vendors approach the issues faced with this process. The Problems with BIM Collaboration Th e associated benefit s from implementing BIM are evident, however these benefits a re not necessarily easy to achieve. Flexibility of workflow, and performance in collaboration is reduced as model data integration is amplified (Laiserin 2009 ). Team members can work seamlessly a nd uninterruptedly on the same model, however, in order to avoid inconsistencies, access to the model needs to be controlled and managed with great diligence. The users should be assigned a workspace so that other users are restricted from making changes t o the same features at the same time. Then, the changes made to each user local copy must be synchronized or updated to the central project model by integration the different local copies to the central model (Laise r in 2009). F igure 2 2 Coordination ve rsus fle xibility a ( Khemlani 2009a) Paper CAD BIM Flexibility Collaboration

PAGE 25

25 BIM has limitations in flexibility and Figure 2 2 helps better understand the tradeoff between collaboration and flexibility in BIM. As a result of the BIM collaborative style of organizati on, most BIM software are affected by the tradeoff between the workflow flexibility and the barriers set in collaborative performance. Individual users lose flexibility when trying to access the multidisciplinary models. Performance suffers, while waiting for each user to update the model. Th ese updates take increasingly longer as the project and team increases in size causing frustration over inflexible access to the necessary elements for their work (Laise r i n 2009). Design collaboration is a relatively ne w phenomenon to the AEC industry. Architects and engineers need to work together in order to a ccomplish the best outcome and utilization of a building. A s architects become increasingly specialized and projects become increasingly complex, the design disci plines work ing on the same building remain to use their own sets of tools and practices. Hence the well known issues with communication and coordination experienced in design collaboration are no surprise (Vrkonyi 2009). Collaboration in design and const ruction can be understood as internal and external. Internal collaboration occurs when the users that edit the model simultaneously belong to a single organization. External collaboration occurs when multiple modelers simultaneously view the combined or se parate multidiscipline models for coordination (Sacks 2010a). Furthermore, Sacks et al. (2009), noted the following: Whereas in the internal mode objects can be locked to avoid inconsistencies when objects might be edited to produce multiple versions, in the external mode only no editable representations of the objects are shared, avoiding the problem but enforcing

PAGE 26

26 the need for each discipline to modify its own objects separately before checking whether conflicts are resolved As stated by Grilo and Jord im Building information modeling should be perceived as a dynamic process rather than a model per se The process of dev eloping a n information rich 3D model is a progressive elaboration, with diverse functions and resulting benefits. BI M has the capability of supporting collaborative working environments by enabling improvements in the following (Grilo 2010) : o wner understanding of the nature and needs of the project, design, developmen t, and analysis of the project, construction manag ement, and the management of the operations of the project during its operation and decommissioning T he collaboration problem was not as complex prior to BIM, since the participants would just worked on different sheets. BIM effectively handles the proble matic inefficiencies and inaccuracies of the traditional methods, at cost of less flexibility and an increase in collaboration complexity. The collabor ation problem is more complex with the introduction of BIM, since the multidisciplinary team members have to work in a highly synchronized fashion The problem is intensified in applications that have a centralized model approach ( ArchiCAD and Autodesk Revit ) since most of the information ( drawings, schedules estimates) are contained in one file (Khemlani 2009a). BIM Collaboration Software The creation of a the virtual 3D environment may involve the efforts of multiple participants of the multidisciplinary team thus BIM tools are used to assist in the conflicts arising from the merging and collaborative wo rking of the teams. This process known as clash detection aims to discover and resolve issues in a proactive manner.

PAGE 27

27 Using a 3D model, allows team members to visually approach and coordinate the conflicting relationships of the building components (archite cture, structure, electrical, plumbing, etc.) making it a highly effective process. This process is highly desirable, since it enables teams to better understand conflicts during the earlier planning stages (Grilo and Jordim Goncalves 2010). Interoperabil ity and the Development of a Common Language T he buildingSMART International alliance is an international membership organization with representation in North America, Europe, Asia and Australia. It brings together professionals from multiple disciplines i ncluding architects, engineers, constructors, product manufacturers, and facility managers with the purpose of adopting BIM, developing protocols for data exchange (IFCs), as well as to contribu te to sustainability practices in the built environment (build ingSMART International 2010) The structure of responsibility is unclear with the increase of collaboration in BIM. With the growing interaction of multiple disciplines within the same mode, it has become increasingly complicated to allocate risk Therefor e, improvements are still to come in software compatibility a nd in contractual language. These should specify the collaborative risk s and compensations involved (Thomas and Miner 2006). Every day we see new software platforms and BIM solutions in competit ion. incompatible with the corresponding collaboration tools and platforms. The issues with i nteroperability have been addressed and solutions have come a long way over the recen t years. However, as mentioned by Thomson and Miner (2006), it remains as one of the most significant challenges in the adoption of BIM.

PAGE 28

28 The buildingSMART Collaborative Efforts The buildingSMART alliance has chapters and partners around the world and has a strong influence in the intero perability and collaboration of construction projects and facility management processes (International Alliance for Interoperability 2010). The goals of the organization are stated below ( buildingSmart 2010 ): Develop and mai ntain open international standards for b uilding i nformation m odeling. Accelerate market assimilation of interoperability through successful sustainable projects Provide networking opportunities, specifications and written guidance. Resolve high cost probl ems that hinder data sharing. Extend buildingSMART processes and technology to the whole built environment, over its lifecycle, and encompassing leadership, production, facilities management and engineering maintenance. The buildingSmart alliance, formerly known as the I nternational Alliance for Interoperability (IAI) was formed by CAD (Computer Aided Design) vendors with the purpose of develop ing IFC s ( s to form a universal communication platform for model based colla boration ) These neutral data format s aid in the information exchange in the building and facility management industry sector s (AEC/FM). The IFCs, now a n International Organization for Standardization (ISO) standard (and in the process of becoming the off icial ISO standard) is composed of a buil t in dictionary intelligent building elements These elements serve as a diagram which helps in the conversion of models among diverse applications compatible with IFC s Users benefit from collaborati ng with other specialists due to the IFC files capability of saving and opening generic files (Vrkonyi 2009).

PAGE 29

29 In its first major enhancement since 2003, the new IFC release (IFC2x4) has high hopes for interoperability advances International recognition of the standard is important. The buildingSMART began working towards making the IFC specification an ISO standard in 2008 and now, their goal is to complete the necessary requirements to make the IFC2x4 a full ISO standard. Currently, IFCs is a public ava ilable specification (PAS), and the goal has been set to s ecure acceptance as an ISO 16739 by mid 2010. The IFC2x4 has been in development since 2006 and it provides better coverage, higher quality and precise documentation due to the increased in collabor ative work Furthermore, it provides bet ter opportunities for energy and environmental analysis, as well as the ability to map design s into the GIS system. The improvements to the scheduling definitions (4D) as well as cost items 5D (estimating and constru ction resource management) are significant. IFC2x4 offers the most encompassing open specification for BIM data formats (Liebich 2010). Available Software The benefits from BIM can be incremented when a variety of software that f it under the BIM spectrum i s used in concurrence. A 3D model of a building can be displayed in reference to 4D information ( schedules and timing issues) as well as 5D information. A feedback loop is created by the i ncremental data computed by the participating members, streamlining the pro ject delivery (Dispenza 2010). The software options most pertinent to our study are discussed below. ArchiCAD 1 4 This product had continue d to based collaboration capabilities. The Teamwork module introduced with th e earlier version (ArchiCAD 13) last year has been enhanced with an expanded set of techniques to find data more efficiently. Another unique feature is the BIM Server

PAGE 30

30 performance monitor function, which purpose is to provide feedback to server administrato rs on the server computer performance as well as the BIM server application. Further on, remote access has been made easier by implementing automatic recognition to the multiple addresses, which is especially helpful for the BIM users who work from multipl e locations facilitates the interaction between architects and the various engineering disciplines by using model mapping, element classification, IFC management among other features. ArchiCAD 14 has significantly through enhanced use of the IFC format s by providing IFC translators optimized for several leading global and local structural and MEP applications (Khemlani 2010a). Furthermore ArchiCAD 14 offers tw o add ins for Revit that improve model translation with Autodesk software. In reference to multidisciplinary clash detection capabilities ArchiCAD 14 can d etect model conflicts between structures and the diverse building systems, thanks to its ability to precisely import engineering models from other applications Hence design coordination with the engineering disciplines can be drastically improved. Typically, multi disciplinary workflows consist of several rounds of information exchange. ArchiCAD 14 enha nces mult i di sciplinary collaborat ion by comparing IFC model versions and only i mport ing the differences. D esign changes are displayed with color codes in the architectural model context to further ease complex model visualization (Khemlani 2010a). Bentle y A significant difference between Bentley offers and its c ompetitors is that their BIM solution is integrated and multidisciplinary Meaning that the architectural, civil electrical, mechanical, a nd infrastructure work together. The information and the

PAGE 31

31 c omponents within the multiple disciplinary constantly interact. Furthermore, i n terms of sustainability, elements such as ins ulation values, solar loads, air movement, and lighting values require techn ical, numeric based analyses, which further optimize th e system These systems work together since all of the systems involve multiple disciplines (Livingston 2007). Bentley architecture V8i This software It belongs to the large integrated and multi disciplinary set of building solutions for design, analysis, and collaboration, which is built on the new MicroStation V8i platform. As noted by Khemlani (20 09b ), enhancements, according to Bentley: more intuitive conc eptual modeling capabilities; interactive dynamic views; intrinsic geo coordination capability; incredible project performance and speed; and finally, a high degree of interoperability Bentley ProjectWise Navigator Bentley has also continued to extend the capabilities of its solutions through the development of t he ProjectWise Navigator (comparable to Autodesk Navisworks ), which is used for coord ination, review, and collaboration. Furthermore, the ProjectWise platform is useful for project and file mana gement, particularly for large ly has a unique approach in where project data is distributed in several files and its capability to work with multiple file formats, allows it to be used in small or large projects (Khemla ni 2009b ). ProjectWise Navigator influences the interactive nature of information stored in the Bentley models, enabling high performance visualization and multidisciplinary insight

PAGE 32

32 which help s avoid costly errors. The following actions can be performed w ith P rojectWise Navigato r V8 (Bentley Systems Inc 2010): Open i models, native DGN and DWG files, and point cloud files. Explore models naturally and intuitively in real time Manipulate view settings to interactively change data display on screen Find bu siness intelligence behind the geometry with ease Measure distances, areas, volumes with complete engineering precision Simulate what ifs, optimize schedules, dynamically resolve clashes Group and classify items by leveraging the intelligence behind the content Mark up i models with simple geometry, register and preserve comments Produce rich 2D/3D PDFs, create photorealistic images and animations Autodesk Naviswork s. NavisWorks can combine multiple models including the architecture, structure, and ME P models that were exported from their respective Revit BIM applications The power of the application lays in its ability to import the corresponding 3D file formats and append multiple models into one file Navisworks is equipped with a powerful compress ion technology that allows them to be easily reviewed as a whole project, regardless of the file size or format. Additionally, it offers a 4D construction simulation in its Navisworks Simulate and Navisworks Manage products The 4D capabilities are powerfu l and intuitive and allow several sched uling options. The clash detection options are efficient and easily understood and offer the a bility to coordinate the project prior to construction reducing change orders, construction errors, reducing waste and kee ping costs under control. The lack of IFC support was improved in the 2009 version of the software and it now has the ability of read ing object data from the models (Khemlani 2008a). BIM and the Cloud Cloud Computing and SaaS (Software as a Service) servi ces are on the rise. France (2010) recognize d the benefits from workstation clouds when c ollaborating with outside firms on the same model collaborating over wide

PAGE 33

33 geographical a rea s g eneral b usin ess a pplications, mobility and BIM automation. Due to the f act that many firms do not have the necessary design resources they regularly work with outside consultants (engineering, fire protection, acoustical etc). However, since everyone is working on the same project, it would be ideal if they could all work a s seamlessly as internal company employees would Nevertheless project teams are forced to trade models via project websites Without cloud computing, r eal time collaboration is diff icult between external entities (France 2010). Newforma Project Ce nter (server b ased). Newforma Project Center is a project information management and collaboration application for AEC firms. Newforma Project Center has become one of the fas test growing applications in the AEC industry. It is used in 61 of the top 300 AE C firms, with over 120,000 projects managed. Furthermore, Newforma take s credit for the (PIM), which describes well its functions (Kheml ani 2009d). Newforma recently released the Seventh Edition of its application. Improvements have been perceived with the enhancement of the following features: automatic indexes project email management review and markup capabilities, web based collabor ation module, and dedicated interfaces for all project items including document sets, submittals, transmittals, requests for information ( RFIs ) and action items. Nevertheless, with the introduction of new features, the application is becoming increasingly complex and a BIM specific support has not been implemented yet. As the AEC industry transitions to multidisciplinary models, a demand is evident for BIM based project information management applications Newforma Project Center still has to

PAGE 34

34 to achieve a BIM project information management (PIM) application (Khemlani 2009b). Attolist (web b ased). Attolist is a relatively new web based solution for document management, construction administration, and project information management (PIM) With the increase of projects using IPD in the AEC industry, Attolist attempts to facilitate the workflow automation and collaboration capabilities of its application. Figure 2 3 presents an image of the web based site and its graphica l representation of infor mation (Khemlani 2009d). Figure 2 3 ubmittals dashboard, showing an overview of open submittals and the overall submittals statistics (s ource: Khemlani 2009d) All the project documents can be organized in a single storage unit with t he doc ument management capability provided by Attolist which also stores a history of the project

PAGE 35

35 from conceptual design to as builts. Furthermore, the company is working on creating a web based BIM model sharing sed application Attolist approach to projec t management and collaboration is decidedly a web based application. The project dat a the participating disciplines and team members use the web interface to communicate an d to access the data (Khemlani 2009d). SharePoint based Organice Organice is a suite of solutions for construction document management, control, and collaboration. Since it is not an AEC specific solution, its deployment can be challenging. Organice take s the powerful collaboration capabilities of SharePoint and customizes it for the AEC and related industries. The company has partnered with leading AEC technology vendors such as Autodesk and Bentley with the purpose of integrating their SharePoint based collaboration applications (Khemlani 2009d). The Organice product suite comprises several different applications that work together. The central application ( Organice Explorer ) provides the d ocument management functionalities to create, store, search, retr ieve, view, check in, check out, edit and revise documents. The project information management solution integrates with v arious CAD applications, including AutoCAD, Br icsCad, Revit and MicroStation. Th e files from multiple software vendors can be opened di rectly from S harePoint and saved back to it. For instance, when working with Revit, files that are stored in SharePoint can be easily retrieved and directly op ened (see Figure 2 4). R evised Revit RVT and RFA files can be opened and saved directly into the SharePoint document environment. Organice comes equipped with a for Revit. This

PAGE 36

36 function stores and loads all the com ponents that belong to a family. Once s tored in SharePoint it can be loaded into Revit in one step (Khemlani 2009d) Figure 2 4 Open a Revit family using t he Organice Explorer interface ( a dapted from Khemlani 2009d) Summary of Project Information Management Software for Collaboration The applications described above, vary extensively in their approach to address the issues faced in multidisciplinary collaboration. The AEC specific solutions such as ctWise, Navisworks, and Buzzsaw offer different functions than the PIM platforms (Attolis t, Newforma, Organice). Nevertheless they all attempt to impro ve collaboration by addressing the issues of information sharing, accountability, and transparency. Any of the described solutions above will cause efficienc ies when

PAGE 37

37 collaborati ng with external team members. Furthermore, a s IPD gains popularity, these inf ormation sharing and collaboration tools will become increasingly indispensible and will prove especially helpful w hen addressing integration. The AEC industry should experience impressive benefits once the mentioned PIM platforms achieve the desired level of BIM integration (Khemlani 2009 d ) Integrated Project Delivery (IPD) Inte grated Project Delivery (IPD) is a recent init iative in the building industry considered the most effective collaboration project delivery method Even though collaboration is not new to the AEC industry, or humanity, the process of collaborating e is one of the foundation stones of our society. One of th e largest collaborative effort s perceived are the Great Pyramids in ancient Egypt. The building industry continues to amuse us wi th collaborative efforts that have achieved great projects as illustrated by t he skyscrapers of our age ( Vrkonyi 2009). The following characteristics extracted from a case study document by Cohen (2010) for the AIA California Council, the Integrated Proje ct Delivery Steering Committee and the AIA National Integrated Practice Discussion represent key factors in the IPD pro cess (Cohen 2010): Mutual Respect and Trust Among Participants Collaborative Innovation Intensified Early Planning Open Communication wit hin the Project Team Building Information Modeling (BIM) Used by Multiple Parties Lean Principles of Design, Construction, and Operations Co Transparent Financials (Open Books)

PAGE 38

38 BIM and IPD The AIA California Council includes the definition for Design Build as an example within the definition of IPD IPD attempts to eliminate legal, financial, and organizational barriers hinders project members to collaborate around a BIM model (Azar 2008) BIM pr ovides design professionals with a novel concepts and technology in order to create an accurate digital parametric model of a building. Additionally, it create s the need for, and ability to engage in an environment of enhanced project collaboration (Cazier 2008) In addition to the increase of scheduling and costing information, legal documents and paperwork will increase as well. There is a need to document the excessive financial information as well as the daily decisions occurred (who made the decisions, when and where). Document management tools are n ecessary, in order to document and manage the share d information. The advantages of the IPD environment consists of a highly collaborative environment in where dec ision making, and information is well docum ented by the participa nts regardless the location or employer. This information, which includes a compilation of scheduling, costing, accounting, human resources, document management, and business pro cess management tools is used to create the collaborati ve system necessary for BIM success (Azar 2008) Integrated Project Delivery integrates people, systems, business structures and practices into a collaborative process, which harnesses the individual capabilities of the participants. Consequently, waste is reduced, and efficiency is optimized throughout the lifecycle of the project. The principles of IPD can be applied to a variety of contractual arrangements and it is not uncommon for the participating teams to include members not belonging to the AEC indu stry (AIA and AIA California Council 2007). At its

PAGE 39

39 minimum expression, IPD creates an intimate collaboration between the architect, general contractor and owner, from the early design stage, through project completion (Eckblad 2007). The AIA and IPD Integr ated project delivery, can be perceived as a contract mechanism at first Similar to a traditional project delivery structures ( design bid build ), it offers a legal outline that the architect, builder and use to collaborate. try (Roberts 2008) Furthermore, IPD enables the pursu i t of ambitious en vironmental goals, including specific targets for certification such as LEED Building information modeling (BIM) software tactics have the po tential to transform traditional trends in design and construction methods. Nevertheless, it is straining against conventional legal structures. IPD is not yet widely used, but advocates strongly believe that it will soon become a common practice (Roberts 2008). IPD Guide ( AIA and AIA California Council 2007) the defining characteristics of IPD include: Highly collaborative processes that span building design, construction, and project handover. Leveraging the early contributions of individual expertise. Open information sharing amongst project stakeholders. Team success tied to project success, with shared risk and reward. Value based decision making. Full utilization of enabling technological capabilities and support. In it s 2007 Environmental Scan, the AIA observed that alternate delivery models are on the rise and causing architects to engage in more collaborative processes with builders, su bcontractors, and fabricators. With the wide spread adoption of BIM, industry profe ssionals are becoming increasingly interested in the enhanced

PAGE 40

40 c ollaboration agendas set by IPD The AIA reported that on average 40% of firms surveyed ( 50 or more employees ) used BIM In a similar way to sustainable design, inte gr ated project delivery is the product of the union of opportunities that arise from the advances in technology and innovation. Moreover, it is inspired by the strong desire of the building industry for more predictable, accurate and respon sible results (Aut odesk Inc. 2008). Azar (2008) has point ed out that without the BIM is nothing more than a Sustainability and BIM Specific calculat ions and exhaustive amounts of paperwork go into certifying a LEED certification. BIM has the ability to gather building materials information as well as to analyze perti nent environmental information about specific projects. Hence, BIM lends a hand in the necessary documentation for certification. Currently, project data is computer into the LEED Online system by a designated user logging in to the website. IES Virtual En vironments, a closely related program to Revit MEP, comes equipped with a built of occupied space to achieve the 2% daylight requirement. Reporting these results based off t credits. If these types of requirements can be calculated and reported with the help of BIM tools, documentation could eventually be obtained directly from the multi disciplinary mod els. This could increase efficiencies across the board and assure certification at an earlier stage (Malin 2007).

PAGE 41

41 LEED Online service, which employs Adobe Lifecycle software. Portable Document Formats (PDFs) are a secure means for sharing BIM information. Adobe is currently working towards improving the ability of linking data to individual components in a 3D Acrobat file. The ability to submit the documentation easily into LEE D Online has many obvious benefits. It is likely possible that in the near future, project information will come directly from BIM since USGBC and Autodesk have had a partnership since the end of 2006 (Malin 2007). Case Study One : al using BIM and Construction Manager at Risk BIM helped Kitchell Contractors benefit from vital early decisions early in the PCH, one of the largest pediatric hospitals in the USA decided to build a $588 million expansio n to its facility. The project which spreads over 45 acres, includes a new patient tower, an ambulatory care building, a new main entry boulevard, four concrete parking structures, landscaped gardens and a central plant. Some of the reasons for PCH to sel ected Kitchell included their healthcare construction experience, their collaborative management approach and their ability to collaborative management culture, their h ealthcare construction knowledge and their experience with BIM (Mckenzie 2009) The project delivery method selected was Construction Manager at Risk (CMAR), and it focused on establishing a multidisciplinary collaborative project environment of trust and ceaseless communication. The owner did not require BIM however, d ue to the project scale and complexity, Kitchell decided to use BIM regardless. The architect

PAGE 42

42 (HKS) produced the construction documents using Autodesk Revit Architecture. The interaction thr ough the BIM process as well as the environment set by the delivery method encouraged collaboration between the owner (PCH), the builder (Kitchell) and the architect (HKS). The following list specifies the areas in where the BIM collaborative method brough t value to the project as identified by Mckenzie and Johnson (2009): 4D scheduling phasing. $3 million savings in parking shuttle costs due to re sequencing one of the new parking. PCH used the $3 million in savings to purchase additional adjacent property for future needs. Also used as a collaborative communication tool with Hospital Staff and Administration to explain campus disruptions throughout the construction process. 3D modeling Underground Utilities. Utilities (new and existing) were modeled (based on underground surveys) and fully coordinated prior to the start of construction. Scope gaps were identified, which assisted the Architect in producing a fully coordinated set of Civil Drawings. The process ensured that all work designed could be installe d thus eliminating the cost and schedule risks associated with underground work. 4D Sequencing & 3D Modeling Structural Steel Modeling and 4D sequencing steel which mitigated t ight site conditions. Earlier floor and roof access for other trades accelerated the overall project schedule. The project saved two months on Erection Schedule and significant savings in productivity for steel erection translating into over $1 million in cost savings. 4D Sequencing & 3D Modeling Modeling and 4D sequencing of the central plant allowed a construction CPM schedule logic error, regarding the caisson foundation system, to be identified which avoided a potential delay to slab placement and und erground pipe installation of 45 days. 3D Modeling & Structural Analysis Structural analysis performed early in the design resulted in identification of unique, high grade steel material and bracing requirements allowing Schuff Steel and Kitchell to iden tify a unique steel supplier and pre purchase (prior to a period steel material escalation) steel resulting in a $2 million total savings due to pre purchase of material. 3D Modeling/laser Survey Equipment. Translating x, y, z coordinate data from the 3D Revit models and downloading into digital survey equipment increased productivity and accuracy in building layout and component installation. 3D Modeling & Collaboration Project Management System Paperless construction documents and electronic distributi on saved a considerable amount

PAGE 43

43 of time and money in handling, postage and reproduction costs. In addition, this turned out to be an excellent green component of the project that followed the Green Guidelines to Healthcare Case Study Two: Encircle Health Am bulatory Care Center The Encircle Health Center is a 156,000 square, three story ambulatory care center. It includes physician practices with imaging, radiology, endoscopy, pharmacy and laboratories. The architect (HGA Architects and Engineers) and the bui lder (The Boldt Company) have had previous experience with BIM and IPD. One of the main e arly i nvolvement of k ey p T he key participants include the architect, owner, builder, design consultants and su bcontractors. The architect and builder were selected by the owner (ThedaCare) based on excellent past experience. The core team collaboratively selected the mechanical, electrical, plumbing and glazing subcontractors Each of the major subcontractors were present for the early schematic design stage and signed joining The collaborative decision making and control is vital in IPD. The multi disciplinary teams (Core Team) met weekly to r esolve the upcoming issues. Teams present at the meetings (MEP, consultants, LEED compliance, and building enclosure) and owner representatives (physicians) varied depending on the objectives of the meetings. However, the owner, architect and builder were alwa ys present. The collaborative decision making allowed to perform effectively under a very a tight schedule. (Cohen 2010) Project goals including budget schedule, LEED goals ( s ilver or higher) among others, were developed in a collaborative fashion by the core team. The project was able to overcome difficulties with the tight schedule under one of the coldest winters experienced and was still able to complete the project from start to move in in 18

PAGE 44

44 months. The design process was the result of strong collabo rative efforts from the architect and builders. All systems were modeled in BIM and Boldt and the subcontractors were in attendance at many of the programming and design meetings. Furthermore, the D esign B uild subcontractors offered some of the design serv ices One of the most notable benefits experienced from the collaborative efforts was that most costs were well predicted during the design stage. The architects were provided with a detailed spreadsheet of unit costs so they were able were able to make de cisions based on reliab le and updated cost information (Cohen 2010). In regard to BIM coordination, Boldt, using Autodesk Navisworks, managed the primary model The subcontractors used their preferred software and then, Navisworks was used to perform the necessary clash detection. said, money spent on building and maintaining the BIM was more than offset by less rework caused by coordination errors Moreover, Boldt decided to use a web based project information exchange site, which was made available to all the participating disciplines The field representatives were empowered to make quick decisions and most RFIs were solved and documented in the field making it effortless, and saving the architect valuable time. There were d isagreements about which participant should pay for a particular item. Nevertheless the built trust and the climate for collaboration prospered and the issues were resolved with smooth and honest discussion, which followed the program set by the IPD proces s (Cohen 2010)

PAGE 45

45 CHAPTER 3 RESEARCH METHODOLOGY Introduction The objective of the thesis is to determine the importance of collaboration between the main branches of the industry in regards to the new and upcoming technological trends. The architecture, engineering and construction (AEC ) sectors are experiencing a drastic change in the convergence methods of project delivery. The high tech uncharted setting seems to demand high levels of communication, cooperation, coordination and collaboration. These words c an be used interchangeably but have their own role in building information modeling ( BIM ) implementation and are addressed uniquely by each software platform, discipline, and individual firm. The research is composed of interconnected sections that add and complement each other. The rese arch begins with a thorough analysis of the current industry stance. The AEC industry is analyzed in terms of its need f or a collaborative environment, BIM software developments, project delivery methods, sustainable trends and finally, the direction the i ndustry is heading in the implementation of BIM mandates, guidelines and a common language. The first phase consists of a thorough research and identification of BIM literature, blogs, webinars, conferences, experiences, case studies among others. This inf ormation was gathered and analyzed in order to add substance and back the conclusions regarding the importance of multidisciplinary collaboration. BIM facilitates a wide spectrum of capabilities including scheduling (4D) estimating (5D), sustainability Leadership in Energy and Environmental Design (LE ED) and productivity. The second phase consists of the deployment of a survey, which seeks to understand the experiences regarding

PAGE 46

46 the interactions in the multidisciplinary scene enabled by BIM when examined from varying standpoints. The dilemmas of switc hing to BIM includes issues concerning cost, training, interoperability, coordination, among a multitude of reasons that switching to BIM challengers are not shy to point out. By understanding the confronted roadblocks and difficulties, as software develop ment and language breakthroughs we can better comprehend the solutions. We can narrow down the list of problems and focus on the fundamental needs in order to make better decisions on BIM implementation, especially in regard to environmentally friendly sol utions. The benefits and disadvantages of BIM are to be weighed against each other in order to decide whether or not collaboration is fundamental to achieve a successful sustainable project. The survey will be used to supplement the literature review in o rder to better understand the opinion of the experienced BIM Managers, BIM Coordinators and AEC professionals. The survey population is composed of AEC professionals who work for leading AEC firms ( Engineering News Record ( ENR ) Top 100, Fortune 500, Giants 300 ) who focus on susta inable (LEED) projects. The importance of collaborative teams will be evaluated to decide whether a collaboration plan would be helpful in order for a partnering team, a D esign B uild joint venture or an Integrated P roject Delivery ( IPD ) system to produce a successful project. Furthermo re, the implications regarding LEED implementation will be analyzed in order to decide if it actually facilitates or hinder the BIM process. The introduction of LEED has brought changes in the way companies perform since LEED proposes and suggests that tea ms from different fields work together from the beginning (pre design) stages of the project in order to achieve the

PAGE 47

47 best results. Ideally, the benefits from one method (e.g. LEED, Design Build) will facilitate the work flow, collaboration and productivity of the other (e.g. BIM, Design Build). The general methods of the research will follow the steps below: Literature selection and review (BIM, LEED, Collaboration, Design Build, IPD) Locate firms employing BIM technologies into their projects Prepare surve ys and interviews Carry out the data and information analysis using statistical techniques Evaluate the results (advantages, disadvantages) of the degree of collaboration in BIM Produce conclusions regarding future trends and solutions Question Screening Process In order to assure the validity of the research, i ncomplete questionnaires with unclear answers were screened out. Even though the objectives of the research seek to understand broader trends and patterns in the industry, each response was analyzed o n an individual basis. Initially, this exercise was helpful in trying to understand the experience and viewpo ints of the population studied Research Objectives The goals of the research were broken down into three parts with the purpose of establishing systematic relationships in order to reach statistical conclusions. Following, An explanation of the research objectives and the questionnaire can be seen below. The questionnaire focuses observed were intended to further compliment and help understand the research objectives described ahead. Survey Questionnaire The questions have been broken down into four categories i n o rder to guide the respondents: general questions, BIM teams and performance, BIM benefits, and, the

PAGE 48

48 ideal BIM scenario. The questions also addressed the preferred method of delivery as well as the currently sustainability measures employed. Additionally the questionnaire was aimed at understanding the ideal BIM scenario according to the experience of the surveyed individuals. The following section further explains the different categories of questions used to understand the collaborative environment crea ted by the implementation of BIM. Research O bjective 1 D egree of I mplementation and E xperience To determine the degree of multidisciplinary collaboration experienced in the BIM process concerning the following factors: 1) field of practice, 2) experienc e 3) stage of implementation and 4) software used and 5) number of licenses. Q.1: How long have you been working in the industry? Due to the demographics patterns and recent spike in technology, the industry BIM leaders and experts do not necessarily have the most experience in the industry. BIM has been adopted by the new generation of construction professionals and this question aims to understand and correlate expertise in BIM with years in the industry. Q.2 : What is your BIM title? This question was des igned to understand the audience more in depth. Additionally, extracting this information would enable a better grouping of the subsequent answers and results adding more validity to the research. Q.3 : How long have you held this title? The responses to t his question were used to understand how long the participants have been involved with BIM specific activities. Q.4: What field do you work most closely with? The more diverse the pool of responses, the more substantial the research will be. An attempt wil l be made to reach construction professionals across the multiple disciplines in the AEC industry. This

PAGE 49

49 question will provide some challenges, due to the limited exposure to all the fields, and the lack of implementation of some fields as in the case of ME P and subcontractors. Q.7 : Please indicate the BIM software currently in use at your firm? This question was asked to indicate whether the firms used collaboration tools or just field specific software. This question is fundamental since there are sever al BIM vendors and software available, and they approach the issues faced with multidisciplinary collaboration in different ways. Q.10 : How many hours a week do you work on BIM related tasks? The years of experience, and the professional title, helped u However, this study gave great value to the number of hours involved with BIM activities. Since BIM technology is constantly changing and being updated, it is important to understand the number of hours that the part icipants are currently investing in BIM. Q.23 : What BIM collaboration software does your company employ? This question relates to Q.7 however it asks to specify the software which brings the disciplines together. Q24: How effectively did the software fa cilitated collaboration and communication throughout the teams? This question attempts to rank in a qualitative scale the effectiveness of the mentioned software platforms. Q26 : Which field of practice (excluding yours) seemed most willing to collaborat e? This question attempts to collect data regarding perceptions among the different disciplines mentioned. In this case, it attempts to identify the field of practice which seemed to be the most willing to collaborate.

PAGE 50

50 Q27 : Which field of practice (excludi ng yours) seemed the least willing to collaborate? Similar to Q.26, the question attempts to collect data regarding perceptions among the different disciplines mentioned. In this case, it aimed to identify the field of practice which seemed the least wil ling to collaborate. Q.32 : What field of practice should spend the most time in BIM training? Q. 32 identify which field of practice seems to be lacking in BIM traini ng from the perspective of the participants of the survey. Q.33 : At what stage should BIM practices be implemented? Even though it is well understood that BIM should be implemented from the beginning, many firms fail to establish a proper BIM plan. Ther efore, this question aims to identify patterns in multidisciplinary collaboration in accordance with the BIM implementation stage. Q.34 : During what stage should teams meet? Similar to Q. 33, the purpose is to understand the perceptions in the industry ab out BIM implementation. Q.35 : Which teams should meet at the design stage? The responses to this question were used in conjunction with the responses of Q.34 and Q.35, in order to better understand the importance of early BIM implementation. Research O bjective 2 C ost and S cale To determine the degree of multidisciplinary collaboration experienced in the BIM process concerning the following factors: 6) yearly volume of work, 7) size of project, 8) initial investment, 9) Return on investment (ROI). Q.6 : The responses to this question were used to understand the trends in collaboration depending on the size and amount of work produced by the company.

PAGE 51

51 Q.9 : How many licensees does your company have? Th e number of licenses a company holds is a direct representation of the scale and of the cost invested in the implementation of BIM. Therefore, a cross tabulated analysis of number of BIM licenses against five questions regarding the level of collaboration were performed. Q.16 : What type and size of projects are you employing BIM processes in? This as the average project size in where BIM is used. The responses were compa red with questions about BIM collaboration in order to identify trends and links concerning size and type of work performed. Q.19 How large was the initial investment when you first adopted the BIM methodology? This question relates to scale and cost is sues as well as to the degree of BIM implementation. The initial investment in BIM includes software, training, time, new hires, among others. This question was valuable in helping the researcher understand the differences in BIM investments across the com panies studied. Q.20 : What was the Return on Investment (ROI) in BIM? (US $) This question was asked to understand the ROI and its relationship with collaboration. However, after completing the literature review and understanding the lack of ROI tracking it was noted that the question might not provide the study with the necessary information, due to the lack of expected responses. Q.29 : What is the ideal project size? The responses of this question were used to determine the perceived BIM project siz e that might bring more benefits to the multidisciplinary teams.

PAGE 52

52 Research O bjective 3 P roject D elivery and S ustainability The purpose of this objective was to determine the perceived benefits and problems in sustainability and project delivery method enc ountered in the multidisciplinary process of the BIM environment. The survey attempted to ask questions (listed below) related to the mentioned issues. However, due to the lack of responses and validity of information, a set of case studies were used in or der to better understand the facts behind trends such as IPD and LEED and their influence in the multidisciplinary BIM implementation. Q.28 : Which project delivery method facilitates collaboration the most? Q.30 : What is the ideal project delivery method? Q.37 : What is the ideal Green rating system to implement BIM with? BIM M ultidisciplinary C ollaboration Q uestions The following questions were used in order to compare the results from the questions on the three categories described above. The comparison s established, and the trends identified from these questions were used to generate the conclusions and recommendations presented in Chapter 6. Q.12 : How would you rate the difficulty in working with multidisciplinary teams with their various discipline b ased BIM Models? The responses to these questions were used to understand the level of difficulty perceived in relation to the factors and questions described above. Q.15 : How often should the multidisciplinary teams meet (monthly) to discuss the BIM pr ocess? This question related to collaboration through the number of multidisciplinary meetings perceived to be ideal (per month). The answers of these

PAGE 53

53 questions were compared among questions regarding company size, discipline, level of implementation amo ng others, in order to establish patterns. Q.17: What are the primary areas that you have identified improvements in? The purpose of this question was to better understand the benefits and improvements experienced. The areas of improvements selected were: design, productivity, cost, estimating and scheduling. Q.18 : What in the multidisciplinary process did you encounter the greatest difficulty with? Similar to Q.1 2, this question attempts to identify the difficulties encountered in the multidisciplinary process. Q.25: From your experience, how would you rate the motivation for collaboration of the multidisciplinary members? This question attempts to understand the degree of collaboration experienced by the multidisciplinary members. The purpose is to qualitatively account for positive or negative trends in the motivation perceived from the disciplines to collaborate when using BIM. Q.38. From your experience with BIM projects, how would you rate the degree of multidisciplinary collaboration? The resp onses to this question were used to determine relationships in the perceived degree of multidisciplinary collaboration. Similar to Q.25, the question attempts to qualitatively account for positive or negative trends in the perceived degree of multidiscipli nary collaboration when using BIM. Descriptive Statistics and Cross Tabulation Analysis In order to generate valid research results, the relationships and patterns in the items and groups described above have to be understood. The selected data was tabulat ed and graphed in order to determine patterns. Subsequently, the data was cross tabulated in order to address the specified research objectives. Multiple statistical

PAGE 54

54 methods were used to find patters and relationships such as the Pearson Chi Square and the Mann Whitney method to compare the groups. However, due to the small sample size, an in depth descriptive analysis was performed. Therefore, sets of comparisons were established, in order to compare the retrieved data with several levels and types of coll aboration. These comparisons helped the researcher better understand the trends in the industry with regards to the scale and initial investment of BIM. The factors of collaboration include the following: disciplines represented in BIM projects, perceived difficulty in working with multidisciplinary teams, importance of early (design stage) BIM implementation, number of multidisciplinary meetings, identified improvements, encountered difficulties, unexpected benefits, perceived degrees of collaboration and perceived levels of motivation for collaboration. Comparisons against I dentified Improvements B enefits and D ifficulties A comparative analysis and cross tabulation was performed in order to understand the perceptions and expected results with the implemen tation of BIM depending on the multiple interchangeable factors among the many firms surveyed. These factors were compared against questions regarding scale, initial investment, preferred project delivery method and sustainability rating system, among othe rs factors. The following questions belong to this category: Q.11: How would you rate the accuracy of the BIM models you have been exposed to? This question was used in order to identify trends that work and produce accurate BIM models. Q.12 : How would y ou rate the difficulty in working with multidisciplinary teams with their various discipline based BIM Models? The responses to this question were used to identify the degree of difficulty perceived in the multidisciplinary environment.

PAGE 55

55 Q.17 : What are th e primary areas that you have identified improvements in? This question was used to understand the improvements in the following areas: design, productivity, cost, estimating and scheduling. Q.18 : What in the multidisciplinary process did you encounter the greatest difficulty with? Similar to Q. 12, this question attempts to identify the encountered difficulties in the multidisciplinary BIM environment. Q.21 : What were the benefits realized by using BIM on projects? The survey participants were prese nted with a checklist including the following benefits: reduction in overhead cost, improved management of project logistics, planning, communication and reporting, reduced cost and design, enhanced estimating capabilities, reduction of design errors, cust omer service improvements, production/fabrication improvements, and better understanding of the project. Q.22 : What were the unexpected benefits realized by using BIM (Please Specify if any)? Similar to Q. 21, this question attempts to identify the benef its presented with the introduction of BIM. However, this question asks to list the unexpected benefits. Summary The questionnaire was designed with the purpose of allowing for comparative analyses. First, the questions were intended to gather background a nd personal information from the respondents. Secondly, the questionnaire was intended to understand factors such as project size, initial BIM investment, and company size among other experiences in the multidisciplinary BIM environment. Finally, the quest ions were combined, cross tabulated and compared in order to establish relationships among the several factors considered.

PAGE 56

56 CHAPTER 4 RESULTS AND ANALYSIS A total of 680 invitations were sent out inviting professionals to participate and it was deployed tw ice, achieving a total of 58 responses which were received electronically. Due to the limited number of responses and the subjective nature of some questions, the results were evaluated using descriptive statistics only The majority of the individuals wh o completed the survey worked for large international architecture, engineering, construction ( AEC ) companies in the United States. In order to abide by the rules and regulations covering this study and to protect the privacy of the participants, any perso nal information is kept confidential and will remain undisclosed. The preceding methodology chapter specifies the strategy employed to extract the necessary information for grouping the answers according to the following factors: degree of implementation, scale and investmen t, project delivery method and s ustainability. The information extracted from the specified groups was cross tabulated in order to generate conclusions which address the research objectives. Research Objective 1 Degree of Implementati on and Experience As stated by Estman et al. (2008): The questions under this category helped confirm the importance of early building information modeling ( BIM ) implementat ion (design stage or earlier) in order to better enjoy the benefits of BIM. Q .1 How long have you been working in the construction industry? Due to the recent spike in technology and change in demographics, the BIM leaders and experts do not necessarily ha ve the most experience in the industry. BIM has been adopted by the new generation of younger construction professionals. This

PAGE 57

57 question aims to understand and correlate expertise in BIM with years in the industry. Among the individuals and companies survey ed, 34% (19) of the respondents indicated that they had more than 15 years of construction experience while the majority (66%) of the respondents had less than 15 years of construction experience (Figure 4 1). These result help describe the demographics of the respondents and provide a reference point for the subsequent analys e s as well, which use experience as a filter Figure 4 1 Experience in the construction industry Q.2 What is your BIM title? This question was asked in order to further understand the existing BIM titles and wording use d to describe them. Most people utilizing BIM technology do not have a specific BIM title since BIM spreads easily throughout offices reaching and affecting most areas of work. However, the survey was design ed specifically for BIM Managers. As seen in Figure 4 2, from the 56 responses received, 20% of the participants were BIM Managers, 5% were BIM Coordinators, 2% were Model Coordinators, while 52% do not have a BIM Title specified and 21% have another no n BIM specific title.

PAGE 58

58 Figure 4 2 titles Q.8 How many projects have you been involved with? The importance of the experience of the participants in actual BIM projects affects the validity o f their responses. The development of BIM has been felt in the industry in many companies. H owever, the full implementation of BIM on a project is still young and the percentage of the industry population that has been involved in multiple projects is stil l small. From the results of the survey, only 25% of the participants have been involved in multiple projects in a period of 4 years or more, 47% of the participants have been involved in multiple projects in a period of one to three years, while 24% of th e participants have been working with BIM projects for less than one year (Figure 4 7). This analysis helps in further understand ing the level of development of BIM in the field and provides the reader with an idea of the duration of the projects employing BIM methodologies.

PAGE 59

59 Figure 4 3. How many projects have you been involved with? The majority of the respondents (47%) have been exposed to multiple projects (in a period of one to three years). This fact is important to the validity of the research, sinc e BIM is still in its recent stages of de ploy ment While most professionals might be proficient with BIM software such as Revit, advanced exposure to BIM and its multidisciplinary capabilities is very limited. This result provides the study with significan t data about the level of experience of the population. Furthermore, the results for this question help produce better conclusions when cross tabulated against other factors such as difficulty of implementation and degree of collaboration. Q.4 What field do you work most closely with? The survey results obtained from this question had limitations due to the larger group belonging to the construction sector. An attempt was made to reach an even number of participants from the main fields involved, but the r esults obtained were limited. A significant number of participants specified multiple disciplines when answering this question. It is interesting to note how BIM foments a multidisciplinary approach Th e results suggest that many of the firms using BIM inc lude more than one

PAGE 60

60 field of practice under the same roof. As seen in Figure 4 4, most of the respondents came from the con struction industry. Even though 40% of the population worked most closely with the fields of Architecture, Engineering and mechanical, electrical, plumbing ( MEP ) 73% of the respondents worked most closely with construction. Figure 4 4. Fields of practice Q.5 What Disciplines are represented in your BIM projects? Figure 4 5 shows that the results were fairly consistent across the boa rd. The majority of responses included at least the three main AEC disciplines. An average of 72% of the responses specified included the AEC disciplines.

PAGE 61

61 Figure 4 5 Fields represented in BIM projects Even if multiple disciplines are performed by the same entity, for example in house design ( a rchitecture), there is a multidisciplinary collaboration that needs to be coordinated. The lowest represented field was engineering, with an average of 61% of the responses including engineering in their BIM model s. Additionally, 25% of the participants specified that other disciplines were involved. These included specified fields in engineering ( civil engineering, structural e ngineering), as well as: fire protection, facility management (FM ), curtain wall/skin co ordination, consultants, controls, glazing, kitchen equipment and pneumatic tube (see Table 4 1). Table 4 1 What d isciplines are represented in your BIM projects? # Response 1. About 50% of the architects we work with produce 2D documents form a BIM model 2. Fire protection, c ivil 4. Structural 5. We just began the integration process but we will work with all fields 6. Curtain wall /skin c oordination 7. Facility m anagement 8. Structure 9. W e incorporate structural, MEP FP & civil fire protection, controls, glazing, kitchen equipment, pneumatic tube 10. S tructural Q 26 What fi eld of practice seemed most willing to collaborate? This question attempts to understand the willingness of the different disciplines to collabo rate As s hown in Figure 4 6, the MEP field was regarded as the field most willing to collaborate with 51% (25 responses) of the votes. Nevertheless, it is important to note that several difficulties (6 responses) came from the MEP field, as seen in Table 4 2 The architecture field was regarded as the second most willing to collaborate with 27% of the responses, followed by the construction field (22%) and by the engineering

PAGE 62

62 field (16%). However, it is important to note that most of the participants (73%) came from the construction field and the question specifies to exclude the participants own field of practice when answering the question. Figure 4 6. Field most willing to collaborate Q 15 How often should the multidisciplinary teams meet to discuss the BIM process? (monthly) The question asks the participants to specify the number of times the multidisciplinary teams should meet each month. The results as shown in Figure 4 7, indicate that 75% of the respondents believe d that one to five meetings per month are enough. Furthermore, 19% of the respondents believe d that the teams should meet more than 5 times each month. l ess 3, 6%). These results help confirm the perception that there are opposing schools of thought in the adoption of BIM in the AEC industry. One that is stron gly supporting it and the other

PAGE 63

63 that is constantly challenging it. The more times the disciplines meet t o discuss the issues and needs of the projects, the higher the potential for proper collaboration. Figure 4 7. BIM multidisciplinary meetings (per month) Q. 25 Based on your experience, how would you rate the motivation for collaboration of the multidi sciplinary members? This question asks the surveyed respondents to rate the multidisciplinary motivation for collaboration o shown in Figure 4 8, a 12% (6) of the response low a Howev

PAGE 64

64 Figure 4 8. Motivation for multidisciplinary collaboration Five respondents (10%) believe d that there wa s ery h while the largest group of respondents (20 motivation for collaboration. Finally, 17 responses (35%) believe d that there wa s an Early Implementation for Collaboratio n The importance of early involvement has been a well discussed subject in BIM implementation. Project delivery methods such as integrated project delivery ( IPD ) help enforce early interaction of the corresponding fields in order to promote collaboration and reduce errors and litigation. The results obtained present many trends and patterns that suggest varying levels of success in the implementation of BIM, depending on the degree of multidisciplinary involvement. The questions and their responses discuss ed below, present scenarios that further explain the importance of a constant interaction among the fields of practice across the industry. In addition to regular communication, the timing of the implementation of BIM methodologies o n a project is fundamen tal.

PAGE 65

65 Q. 13 How important is it for the BIM teams to work together from the beginning? This purpose of this question was to understand the varying opinions of the participants. As shown in Figure 4 9, the vast majority of the respondents (82%), believe d t ( d esign s tage). A total of eight (15%) respondents stated that early BIM col laboration is q uite i mportant while two f airly i no s lightly i n The responses to Q. 13 indicate an optimistic environment and a common willingness for multidiscipli nary collaboration. Figure 4 9. Early BIM multidisciplinary collabor ation Figure 4 10, shows a trend in early implementation and identified improvements. 45% in cost reduction, 41% in estimating and 43% saw benefits in scheduling. On the

PAGE 66

66 improvements as well, but not as significant as the former group. Figure 4 10. Compar ison of early BIM collaboration and identified improvements BIM Tasks Performed Q. 10 How many hours a week do you work on BIM? This question asks the participants to specify the average number of hours a week involved in BIM related tasks in order to dete rmine the extent to which they used BIM. Design Productivi ty Cost Estimatin g Schedulin g Very Important 76% 74% 45% 41% 43% Quite Important 50% 63% 38% 25% 50% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percentage of Responses Identified Improvement

PAGE 67

67 Figure 4 11. Hours a week of BIM tasks As shown in Figure 4 11 most of the participants are either very involved in BIM tasks, or not that involved at all. A total of 26 responses (48%) indicated that they work ed more than 20 hours a week on BIM related tasks. On the other hand, 20 respondents (37%) stated that they use d BIM for less than 5 hours a week. The responses to this question were best understood when cross tabulated against the perceived motivation for c ollaboration within multidisciplinary teams. From th ose results, 17%(23) of the participants who had worked 20 weekly hours or more with BIM technologies, believed that there was a igh degree of motivation for collaboration while 0% of the particip ants who had worked 5 hours or less (17) believed that there was a igh level of motivation for collaboration (Figure 4 12). The responses to this question indicated that the true believers in BIM methodologies we re more likely to work more than 20 hours a week with BIM. Therefore this group was more likely to have a positive attitude towards collaboration and a better understanding of the essential necessities to collaborate to achieve a higher level of accuracy and success.

PAGE 68

68 On the other hand 9% of the participants that had a high exposure to BIM on a weekly basis, had elow a verage motivation for collaboration across the border, while more than twice the number of respondents (22%) that is barely exposed to BIM believe d that there is a ve rage level of motivation to collaborate. The goal of this question was to determine some factors that are out of the hands of the respondents and are directly related to the fields of practice outside their own across the industry. Furthermore, 76% of the populations studied (Less than 5 weekly hours and m ore than 2 verage verage degree of motivation to collaborate Hence the largest differences in motivation were noted between the groups at either end of the sp ectrum Figure 4 12. Hours of w eekly BIM exposure and m otivation t o c ollaborat e Difficulties in the BIM Process Table 4 2 helps further explain the difficulties faced when working with BIM. The participants were asked about w hat in the multidisciplinary process they encounter ed the greatest difficulty with The responses wer e grouped under nine categories and include difficulties with the following: architect (A), construction management (C), 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% Very High Above Average Average Below Average Percentage of responses Degree of motivation to collaborate Less than 5 Hours a week More than 20 Hoursper week

PAGE 69

69 engineers (E), MEP (M), collaboration, coordination or communi cation (Q), software (S), training (T), su bcontractors (U) and others (O), as shown in Table 4 2. Each problem was allocated a specific group in order to understand the patter n s presented. A total of 54 difficulties were reported with the highest number of difficulties belonging to the difficulties. difficulties. had a total of 6 difficulties each, while each. Construction management (estimating) accounted for one difficulty while the The in formation gathered from the Table 4 2 suggests that there are several problems with the collaboration, coordination and communication of BIM processes. Figure 4 13 helps visualize the data in Table 4 2

PAGE 70

70 Figure 4 1 3 Identifi ed d ifficulties 0 2 4 6 8 10 12 14 16 Design Construction Engineering MEP Software OTHER Collaboration Training Complexity Subs Number of Identified Difficulties Category of Difficulty

PAGE 71

71 Table 4 2 Verbatim regarding identified d ifficulties in BIM # Difficulty Described ** Identified Difficulty 1. Learning/training. S, T 2. MEP Coordination M, O 3. Finding systems in that all participants were comfortable using an d g etting MEP engineers onboard to use systems that can be integrated with Revit M, S, Q 4. M ep / C ivil M, E 5. The complexities of all systems is the difficulty; no single system brings more problems than others. X 6. L ack of subcontractor BIM proficie ncy and lack of design team BIM proficiency T U 7. Consultants not using BIM T 8. Other trades not taking the time to do their work correctly in the coordination process. T, Q 9. G etting designers to embrace BIM and f ixing poor drafting A 10. Struct ure E 11. C lose collaboration on design and cost estimating during the design process Q, C 12. Not having enough l ead t ime for th e BIM modeling and coordination and un informed or u nwilling participants. Q 13. Cross platform model consolidation and col laboration between tools from differing manufacturers. Q, S 14. Communication between the different partners Q 15. Fire s prinkler O 16. Some of the issues will be the liability issues associated with intellectual properties (model ownership), g etting subcontractors and our own employees up to speed with the software, and getting buy in from all the stakeholders of the project and ensuring that the service warrants the cost T, O 17. Coordination with Designers Q 18. Communication Q 19. Converting efficiencies into dollars and m aking it the norm in lieu of the exception O 20. Architecture (lack of BIM info) A 21. Coordination Q

PAGE 72

72 Table 4 2 Continued # Difficulty Described ** Identified Difficulty 22. Adoption T 23. Getting e verybody on b oard and setting common expectations T, Q 24. MEP M 25. Specific consultants and/or subcontractors that are not BIM savvy. T, U 26. S tructure E 27. Coordination between MEP trades Q 28. MEP. Because of the different software platforms used betwee n design intent and fabrication. M 29. I nterface with other systems S,Q 30. Obtaining a model from the design team A 31. Commissioning O 32. Software f ormat S 33. Merging models as sometimes not started at same point Q 34. Upper management under standing processes and the e xisting consultants not understanding the BIM work schedule T, O 35. Interoperability Q 36. MEP M 37. Initial pushback from subcontractors T, U ** Definition of Difficulty Categories : A = Problem linked to architec ture. S = Problem linked to software. E = Problem linked to engineering. M = Problem linked to MEP. C = Problem linked to construction management. Q = Problem linked to Collaboration, Coordination or Communication issues. T = Problem linked to trai ning. U = Problem lined to subcontractor. O = Problem linked to other reasons

PAGE 73

73 Results on Software Used The respondents were asked to indicate the BIM software currently in use. The selection and degree of implementation of software is vital to the su ccess of BIM in the industry. BIM can only be properly implemented with the right hardware and software and this aspect presents some of the most challenging barriers to its implementation. Research of the capabilities of the a vailable software is necessar y and fundamental for the overall success of its implementation. Further on, a cost benefit analysis or value engineering of the available options would help better understand its power and capabilities in order to justify the initial investment. Figure 4 15 shows the ratings for the specified software. Most of the respondents had a preference for the Autodesk Revit Suite and for Autodesk Navisworks A wide variety of software has been introduced in the market and has proven to be exceptionally helpful in t rying to document the necessary building information. Chapter 2 cover ed the benefits and pitfalls of most of the widely used software in the industry, and while competition intensifies and software pioneers such as Graphisoft and Bentley are making progres sive strides in attracti ng market share, Autodesk still seems to dominate the BIM software market. Q. 23 How effectively did the software (Collaboration Software, e.g. Navisworks) facilitate collaboration and communication throughout the teams? This quest ion has some limitations since the majority of the respondents used Autodesk Navisworks. However, 8% believe d that Navisworks was believe d that it was d it was collabo ration. No respondents reported Navisworks as being ineffective in facilitating collaboration. Furthermore, 100% of the users of Solibri believe d that the software wa s e

PAGE 74

74 It is important to note that participants had good reviews for Solibri and Tekla products. Both software products offer ed model collaboration tools such as the free of charge Tekla Model Reviewer app lication and the Solibri Issue Locator. As d iscussed in Chapter 2, both companies are active members of the buildingSMART Alliance and have been making strides in sharing models between disciplines and addressing the issues faced due to lack of interoperab ility. The web as well, this software attempts to address the issues of collaboration by using their high s peed web service. ArchiCAD has also made strides in its collaborative capabilities w ith the launch of ArchiCAD 14 pen between architects and engineers With the introduction of its server based Teamwork solution described in Chapter 2, the management of team working on BIM projects has been opti mized. Figure 4 1 4 Effectiveness of collaboration software Very Effective Effective Slightly Effective Not Effective Navisworks 8% 53% 39% 0% Solibri 33% 67% 0% 0% Glue Platform 100% 0% 0% 0% ArchiCAD 100% 0% 0% 0% ProjectWise 0% 50% 50% 0% Teckla 0% 100% 0% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percentage of Responses Degree of Effectivenes

PAGE 75

75 Figure 4 15. Software used 0 5 10 15 20 25 30 35 40 45 50 Autodesk AutoCAD Suite Autodesk Quantity Take-Off Autodesk Navisworks Autodesk Revit Suite Beck Technology: Dprofiler Bentley Suite CodeBook International: Codebook Eagle Point Software Corp. Google: Google SketchUp Graphisoft: Archicad Innovaya LCC: Innovaya Horizontal LLC: Horizontal Glue Leica Cyclone QuickPen DuctDesiner 3D Rhinoceros Solibri Inc. Solidworks Corp. StructureWorks, LLC Synchro Ltd: Synchro Pro Tekla International: Teckla Vela Systems Vico BIM is Outsourced Number of Responses Software Used

PAGE 76

76 Table 4 3 week do you work on B Less than 5 Hours 5 10 Hours 11 15 Hours 16 20 Hours More than 20 Hours Reduction in Overhead Costs 2 (10 %) 0 (0 %) 1 (25 %) 2 (100 %) 11 (46 %) Improved Project Logistics 12 (60 %) 0 (0 %) 2 (50 %) 2 (100 %) 17 (71 %) Planning 13 (65 %) 0 (0 %) 1 (25 %) 2 (100 %) 18 (75 %) Communication and Reporting 7 (35 %) 0 (0 %) 2 (50 %) 2 (100 %) 15 (62 %) Reduced Cost of Design 3 (15 %) 0 (0 %) 2 (50 %) 2 (100 %) 10 (42 %) Enhanced Cost Estimation C apabilities 6 (30 %) 0 (0 %) 2 (50 %) 2 (100 %) 10 (42 %) Reduction of Design Errors 11 (55 %) 1 (100 %) 4 (100 %) 1 (50 %) 18 (75 %) Improvement in Customer Service 8 (40 %) 1 (100 %) 3 (75 %) 1 (50 %) 16 (67 %) Production/Fabrication 10 (50 %) 0 (0 %) 3 (75 %) 1 (50 %) 19 (79 %) Better C o mmunication 11 (55 %) 1 (100 %) 4 (100 %) 2 (100 %) 19 (79 %) Other, please specify 6 (30 %) 0 (0 %) 0 (0 %) 0 (0 %) 7 (29 %)

PAGE 77

77 Research Objective 2 Cost and Scale The questionnaire focused on several areas regarding cost and scale. The purpose was to gather information from a variety of firms including size, average project size, initial investment, and return on investment ( ROI ) in order to better understand their collaborative practices. Q. 6 What is your c This quest ion asks the respondents to specify the com volume of work (in US $). Table 4 4 shows the information gathered from the participants. Table 4 4 ork? # Yearly Volume of Work # Yearly Volume of Work 1. $70,000,000 24. $15,000,000 2. $600,000,000 25. $1,000,000,000 3. $180,000,000 26. $1,000,000 4. $200,000,000 27. $1,500,000,000 5. $150,000,000 28. $10,000,000 6. $10,000,000 29. $4,000,000,000 7. $4,000,000,000 30. $2,000,000,000 8. $4,000,000, 000 31. $2,700,000,000 9. $2,000,000 32. $7,000,000,000 10. $50,000,000 33. $75,000,000 11. $10,000,000 34. $4,600,000,000 12. $100,000,000 35. $60,000,000 13. $800,000,000 36. $250,000,000 14. $3,400,000 37. $3,000,000,000 15. $10,000,000 38. $4,00 0,000,000 16. $100,000,000 39. $700,000,000 17. $10,000,000 40. $4,000,000,000 18. $200,000,000 41. $22,000,000 19. $1,750,000,000 42. $35,000,000 20. $4,000,000,000 43. $1,600,000,000 21. $1,500,000,000 44. $10,000,000,000 22. $8,000,000 45. $500,0 00,000 23. $500,000,000 46. $700,000,000 Average $1,435,247,826

PAGE 78

78 Figure 4 16 shows the d iversity in the size of the studied group. As expected, the largest group of participants (37%) belongs to firms with a yearly volume of work of $1 billion (B) or higher followed by the range of $1million (M) to $10M (20%) and $11 M to $100 M (20%). Subsequently, 13% of the respondents were from companies who se volume of work was between $101 $ 500 M and 9% do work in the $501 M to $1 B range Figure 4 1 6 Yearly volume of work Q. 16 What type and size of projects are you employing BIM processes in? The answers to this question varied but the replies range d from $1 million (M) to more than $1 billion (B). The most frequent project size range (16%), was between $20 0 M and $300M. The data collected indicate d that only 3% of the respondents work ed on projects of $2 M or less, while only 6% work on projects $500 M or larger. Figure 4 17 shows the distribution of the answers. 0% 5% 10% 15% 20% 25% 30% 35% 40% $1M $10 M $11 M $100 M $101 M $500 M $ 501 M $1 B > $1 B Percentage of Responses Yearly Volume of Work

PAGE 79

79 Figure 4 1 7 Average project size (using BIM) The question also asks to specify the type of construction involved with. The literature in Chapter 2 suggests that BIM is especially useful in complex projects. Healthcare and commercial construction can present some complex situations and BIM seem s to be the most popular in these types of construction. Figure 4 1 8 indicates that 19 (31%) of the respondents use BIM for commercial construction. Healthcare cons truction accounted for 19% (12 ), while Institutional was the third most popular type of cons truction with 16%. Figure 4 18. Type of construction 0 2 4 6 8 10 12 $1 M $2 M $2 M $10 M $11 M $20 M $21 M $50 M $50 M $100 M $100 M $200 M $200 M $300 M $300 M $400 M $400 M $500 M $500 M and up Number of Responses Size of Project 0 5 10 15 20 25 Other Commercial Heavy Civil Healthcare Govenrment Institutional Residential Transportation Number of Responses Type of Construction

PAGE 80

80 Towards the end of the survey, the participants were asked to state the ideal project size for BIM purposes ( Q. 31) the information has been displayed in Table 4 19 The question is subjective and t he purpose was to find a pattern rather than to find a specific project size. The answers provide an idea on the experiences and viewpoints from the BIM professionals. A total of 44 responses were collected, and as shown in Figure 4 19 the more frequent r esponses include the following ranges: $21 M to $50 M $51 M to $100M Some of the participants felt comfortable specifying a range or a specific number; however, most believe d that any size larger than $5 M will highly benefit from BIM. Figure 4 1 9 Ideal project s ize Q. 19 How large was the initial investment when you first adopted the BIM methodology? This question asked the respondents to specify the initial investment when transitioning to BIM. As shown i n Figure 4 20 t he majorit y of the respondents (40%) indicated an initial investment of more than $30,000. BIM software can be expensive 0 2 4 6 8 10 12 14 16 Any Size Less than $5 M $5 M $10 M $11 M $20 M $21 M $50 M $51 M $100 M $101 M $200 M $201 M $300 M $301 M $400 M $401 M $500 M $500 M and up Number of Responses Size of Project

PAGE 81

81 especially when accounting for time spent in training and the learning curve It is hard to quantify the time spent at the initial stage of BIM i mplementation so t his question can be challenging to address. The larger the company, the more seats are needed and the larger the investment. It is important to consider that, 40% of the participants work for companies with a yearly volume of less th an $1 00 M (yearly), as s hown in F igure 4 16 With an average yearly volume of work of $1,435,250,000 (ra n ge of the 48 responses), 60% of the participants experienced an initial investment of less than $30,000. This is remarkable, since this represents a very sm all fraction of the average work performed and project budgets involved. Figure 4 20. Initial i nvestment Q. 20 The return on investment (ROI) has been a highly discussed topic in the implementa tion of BIM. However, it has been challenging to calculate, due to the many variables involved. McGraw Hill (2008 p.3) found that 48% of industry professionals who participated in their survey, pointed out that they were tracking the ROI in relation to BIM This report found that initial ROI values ranged anywhere from 300 500%. The study also reported that many While the 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% Less than $1000 $1000 10,000 $10,001 20,000 $20,001 30,000 > $30,000 Percentage Initial Investment

PAGE 82

82 expectations for this question were low, the results pr esented some interesting facts. From the 39 respo nses received, only 9 replies indicated a value or a percentage. The answers var ied drastically and indicated a lack of ROI monitoring and tracking in the industry. Table 4 5 includes some of the numbers received as well as fragments from the original resp onses Table 4 5 Return on i nvestment (ROI) # Answer 1 50% 2 Millions 3 0 4 10 Fold 5 500% 6 14% 7 300 500% 8 200% 9 Millions 10 Difficult to measure different on all projects 11 It has not been tracked 12 Difficult to measure di fferent on all projects 13 I'm not upper management don't have a clue. I know they probably lost their client. 14 We do not calculate ROI 15 I'm not upper management don't have a clue. I know they probably lost their client. 16 Villanueva Meyer, you' ll find it hard to measure this one. 17 Presently unknown The number of licenses held by a company is a key indicator when trying to understand the scale of the company, as well as the ir investment on BIM implementation. Hence, a set of comparisons wer e established, in order to compare the retrieved data with several levels and types of collaboration. These comparisons (presented below) help us better understand the trends in the industry in regards to s cale and investment.

PAGE 83

83 The cross tabulated analysis shown in Figure 4 2 1 shows the relationship between the number of BIM software licenses and the perceived accuracy of the BIM models. The data presents a trend and a positive relationship between number of licenses and perceived accuracy. A total of 83% of the respondents who work ed for companies with 20 or more licenses believe d Nevertheless, 55 % of the responses from companies with "less than 5 licenses" and with "10 to 15 licenses Usually, the more seats a company hold the larger and more complex their projects are, and the higher their budgets and time invested in BIM accuracy. However, smaller companies with less than 15 lice nses tend to work on less intricate pro jects, and are able to achieve higher accuracy wi th less effort and investment. Figure 4 21. Comparison of number of licens es and accuracy of BIM models In order to better understand the benefits of BIM, the five factors presented in Figure 4 2 2 : design, productivity, cost, estimating and scheduling were compared Very Accurate Accurate Neither Inaccurate V. Inaccurate More than 20 24% 59% 18% 6% 0% 16 to 20 0% 80% 20% 0% 0% 10 to 15 22% 33% 39% 6% 0% Less than 5 22% 33% 39% 6% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Percentage Accuracy of BIM Models

PAGE 84

84 against the number of licenses held by the studied firms. These factors were used in order to understand different perceptions towards BIM in relat ion to the scale of the firms. Companies with more than 20 licenses perceived the highest improvements in design, productivity, estimating and scheduling. Companies with 16 to 20 licenses experienced the highest improvements in productivity. A trend is perceived, suggesting that companies with more licenses identified more improvements with the introduction of BIM. Nevertheless, companies wit h less than 5 software licenses reported high benefits. 53% reported improvements in design, 71 % indicated improvements in productivity, while improvements in cost reduction (47%), estimating (35%) and scheduling (29%) also presented significant values. Figure 4 2 2 Comparison of number of licenses and i dentified i mprovements Research Objective 3 Project Delivery and Sus tainability The information gathered from the surveys regarding project delivery methods and sustainability was limited Although some findings from the survey are described, two Design Productivity Cost Estimating Scheduling Less than 5 53% 71% 47% 35% 29% 16 20 40% 100% 0% 20% 40% More than 20 72% 78% 50% 39% 56% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percentage Identified Improvements

PAGE 85

85 case studies were also selected in order to further evaluate the importance of multidisciplinary collaboration in the BIIM environment. The results of these case studies are presented below along with conclusions relating to the project delivery methods and successful sustainability approaches. Q. 28 Which project delivery method facilitates collaboration the most? The options provided in cluded the traditional Design Bid Build, as well as Design Build, IPD, and an option to specify other. As shown in F igure 4 23 T he most popular project delivery method with 59% of the responses wa s IPD, followed by Design Build with 45%, and finally, Design Bid Build, had a total of 15% of the responses. The other specified delivery methods included Construction Manager at risk (CMAR) which obtained 4% of the responses. Figure 4 2 3 Project del ivery m ethod In order to compare and better understand the project delivery methods and the green rating systems, two similar case studies were analyzed The purpose of the case studies was to find trends in the collaborative environment created by the mul tidisciplin ary teams using BIM, IPD, CMAR and Leadership in Energy and

PAGE 86

86 Environmental Design ( LEED ) The first selected case study used the CMAR delivery method, and used BIM to aid in the collaborative goals established from the beginning. The Phoenix Chil established collaborative management culture. Numerous benefits we re attributable to BIM, a multidisciplinary approach and the collaborative environment. The new parking area was re sequenced in the 4D scheduling phasing, which accounted for a $3 million savings in parking shuttle costs. The savings were attributed to the collaborative communication with hospital staff and administration which explained ca mpus disruptions through out the process. The $3 million saved were then used to buy adjacent property 3D modeling of the underground utilities ensured that all of the design ed work could be installed and the process was fully coordinated prior to the sta rt of the project. Furthermore, the 3D modeling and collaboration proje ct management system, helped achiev e a paperless environment. The electronic distribution saved time and money while being an acceptable component for the requirements under the prescri bed Green Guidelines to healthcare. Case study two, involve d the construction of the Encircle Health Ambulatory Care Center. The project delivery method used was IPD and the sustainability goal was to achieve LEED Silver certification. The main characteri stics of the c ase study included the following: early involvement of key participants, BIM collaboration, collaborative decision making and control j ointly developed and validated project goals and shared risk and reward. The initial design cost of the pr oject was $2,901,071 and the final cost end ed up being $3,185,917. The initial construction cost was $34, 977,404, and the final cost ended up being $35,408,131. However, an owner initiated change order of

PAGE 87

87 $1,514,911, caused variations in the project cost a nd schedule. Due to the way the project was organized, following a multidisciplinary structure, the participants enjoyed several benefits. Most costs were well predicted during the design stage, allowing for important changes to take place before construct ion. s were solved in the field, avoiding miscommunications and excessive time consumption. One of the projects most important goals was to achi eve a LEED Silver certification. D ue to the benefits of the teams working together with the owner, the necessary adjustments were made for the project to achieve the LEED Gold certification which was eventually achieved.

PAGE 88

88 CHAPTER 5 CONCLUSIONS AND RECOMMENDATIONS In the modern high tech building information modeling ( BIM ) construction environment there i s no doubt that multidisciplinary collaboration is indispensible. Even though collaboration alone is a highly regarded factor which helps pave the way for success the recipe for a profitable sustainable and successful BIM project lays in the ideal combin ation of the many factors discussed i n this research. Project delivery methods like integrated project delivery ( IPD ) and D esign B uild ( DB) and green rating systems can be customized depending on the company, project budget, or team size in order to addre ss the indicators for successful BIM implementation. Furthermore, an adequate set of BIM collaboration tools is vital and needs to be carefully selected Moreover factors including: geographical location distance bet ween team mem bers, BIM experience, har dware, software, sustainability goals, type of construction, and stage of BIM imple mentation, need to be acknowledged early on with a proactive approach The analyzed survey data in conjunction with the selected literature supports the following conclusion multidisciplinary roles, is indispensible for the proper execution of b uilding i nformation m BIM users have not been able to take full advantage of its power due to factors such as cost of software, training time, and lack of It is interesting to note that 47% of the surveyed individuals have been exposed to multiple projects or more in a range of one to three years. It is evident that a superior level of consistent communication and co ordination is necessary to avoid wasted time and negative consequences. However, these factors, usually enabled by a high level of collaboration will help achieve the

PAGE 89

89 multiple benefits experienced by many (see Table 4 3). Hence, experience with m ultiple BI M projects is fundamental. This e xperience will be passed along and the industry will continue to educate itself in BIM and collaborative practices. The m ost experienced BIM users will have to take a leadership position and facilitate the coordination to e nsure a high degree of collaboration across the fields for each project. Moreover, early BIM implementation is another substantial indicator for collaborative BIM success. From the survey conducted, 82% of the participants believe that design stage multid of The Encircle Health Ambulatory Care Center included all the major subcontractors in the early schematic design stage, and the teams met weekly to perform collaborative decision making pro blem solving. Therefore it is evident that the early creation of a collaborative culture is important in the facilitation of the BIM process. In regard to scale factors, the results suggest that larger companies seem to be on the cutting edge of technolo gy, and are taking full advantage of the latest BIM collaboration tools and project delivery methods However smaller companies involved in less intricate projects, have also indicated monetary benefits arising with the implementation of BIM. If properly implemented, BIM will bring vast benefits and improvements to its users as well as to the multidisciplinary environment. From the results, companies with a yearly volume of work ranging between $1 M to over $1 B and projects ranging from $1 M t o $500 M re ported benefits in multiple areas (planning, scheduling, e stimating, etc.) regardless of their size. BIM has brought an ocean of change to the architecture, engineering, construction ( AEC ) industry and recent literature suggests that technological advancem ents are

PAGE 90

90 facilitating a collaborative environment However it is essential to understand the complexity of the highly interconnected and collaborative environment. New challenges arise from the implementation of BIM and accurately worded contractual agree ments ( often seen in IPD ), which account for risks and rewards are vital. The results indicate that wi th the successful implementation of BIM across the industry is evident that the highest the exposure to BIM, the more benefits attained and the higher t he level of collaboration. From the performed analyses, individuals who worked more than 20 hours a week in BIM related activities experienced the most benefits. The higher involvement with BIM meant higher perceived l evels of collaboration and less obstac les and costly errors experienced. economic benefits of BIM to the global building industry are widely acknowledge d and increasingly well understood. Further, the technology to implement BIM is readily and rapidly maturing. Yet despite the obvious benefits and readiness of BIM software, BIM adoption has been slower than anticipated. Why? The research verifies the importance of collaboration in relation to field of practice, experience, scale, and cost among other factors. inquiry can be better addressed in terms of lack of experience, interoperability barriers, slow multi disciplinary adoption and weak collaboration. Among the individua ls and companies surv eyed, 34% reported to have more than 15 year s of experience in the industry; nevertheless, only 25% of the studied population had been involved in multiple projects in a period o f four years or more. These facts help better understand the issues regarding BIM maturity and experience, which plays a big role in its adoption. There are many factors affecting BIM

PAGE 91

91 implementation and since most of the procedures are relatively new to most AEC professionals and the expectations involve a lot of hype, the experienc es and perceptions may be distorted. However, it is evident that as the learning curve fades in the horizon, an environment of collaboration will rise The software tools that help bring the disciplines together be comes the backbone of the BIM project and its efficiency, compatibility, ease of use, speed, coordination, communication and collaboration capabilities are essential for the appropriate implementation of BIM. Many things can go wrong in the fast paced, high risk, construction environment and a pr oactive approach that nurtures a collaborative environment needs to be established. Moreover, t he software of preference needs to b e highly reliable, and all the team members should have access to the corresponding BIM models. There is a lopsided preferen ce for the Autodesk Revit Suite and for Autodesk Navisworks This affects the degree of collaboration but the necessary steps are being taken by software developers and by the buildingSMART International Alliance, in order to solve the compatibility proble ms while addressing i nteroperability. Some of the most significant achievements seen in the past year include language and IFC development. The development and accessibility of web based BIM collaboration and coordination servers is transforming the way BI M is being used and it will continue to foster a collaborative environment. There are several options for BIM software. Vendors around the world are polishing the capabilities of their products, and there is no doubt that uninterrupted workflow and multidi sciplinary collaboration have become priorities With the influence of the buildingSMART alliance and the industry foundation classes (IFC)

PAGE 92

92 strides in interoperability, companies are turning to other options. The market still belongs to Autodesk, but due t o the affordability and high effectiveness of other vendors and software solutions, the market shares are bound to even out to some extent. It was remarkable to find out that one of the largest difficulties experienced when working with BIM teams was perc eiv ed in the collaboration process; m ay it be through lack of coordination or communication. I t appears that the industry is not fully satisfied with the BIM tools and their utilization. Out of the 54 difficulties identified, 26% were attributed to issues in collaboration, coordi nation or communication I n regard to the project delivery method of choice, IPD is regarded as the most helpful in stimulating an environment of collaboration from the beginning. One of the goals of IPD is to promote collaborative dec ision making and control (Cohen 2010). As seen in the Encircled Health Center case study the combination of experience, early multidisciplinary collabora tion, and BIM implementation le d the project to surpass its goal of achieving a Leadership in Energ y and Environmental Design ( LEED ) Silver certification and to obtain the LEED Gold certification instead. Both the survey results and analysis of the case study implementing IPD indicated that IPD is successful in establishing a collaborative work environ Hospital used a construction manager at risk ( CMAR ) project delivery method, the well esta blished collaborative culture employed by the contractor allowed the project to obtain significant successes Communication allowed for savings, efficient u se of time, and superior sustainability achievements. The implementation of BIM in both case studies allowed for design issues to be resolved before construction began, saving time and money without sacrificing quality or the sustainability goals.

PAGE 93

93 Retrosp ective i mprovements to this r esearch In order to obtain a better understanding of the different views of the industry, the survey should have been distributed evenly across the multiple disciplines in the industry. Ideally the same number of responses sh ould have been collected from the a rchitecture, e ngineering, and c onstruction m anagement fields as well as from subcontractors, s tructural, m echanical e lectrical and p lumbing branches of work. With a more balance d set of dat a the study would gain more val idity and the comparisons among the fields of practice could have been use to better understand the existing issues practitioners face in the BIM collaborative environment. Moreover, the processes involved in BIM are meant to be adopted by facility manage rs in order to effectively track the lifecycle of the buildings. By including project owners and facility managers in the research and survey questionnaire the study would have had a broader impact Furthermore, as the main disciplines in the architecture, engineering construction ( AE C ) industry become more integrated and projects become increasingly complex, it is essential to take advantage of the right software tools BIM implementation comes at a cost, and while the learning curve, spent time training and i nitial investment may be problemat ic, i t is important to bear in mind that the end result makes it all worth it.

PAGE 94

94 APPENDIX A IRB SURVEY PROPOSAL SUBMISSION UFIRB 02 Social & Behavioral Research Protocol Submission Form This form must be typed. Send this form and the supporting docu ments to IRB02, PO Box 112250, Gainesville, FL 32611. Should you have questions about completing this form, call 352 392 0433. Title of Protocol: Importance of Multi Disciplinary Collaboration in Building Information Modeling (BIM) Principal Investig ator: Sergio Villanueva Meyer UFID #: __________ Degree / Title: Masters of Science in Building Construction Mailing Address : ______________ Email: _________________ Department: M.E. Rinker Sr, School of Building Construction T elephone #: __________________ Co Investigator(s): None UFID#: _________ Email:N/A Supervisor (If PI is student) : Dr. R. Raymond Issa UFID#: ____________ Degree / Title: Prof & Director Mailing Address: _________________ Email : ___________________ Department: Building Construction Telephone #: ___________________ Date of Proposed Research: August 2010 December 2010

PAGE 95

95 Source of Funding (A copy of the grant proposal must be submitted with this protocol if funding is involved): None Scientific Purpose of the Study: To identify the importance of multidisciplinary collaboration in construction projects employing Building Information Modeling (BIM) technology. Describe the Research Methodology in Non Technical Language: (Explain what will be done with or to the research participant. ) The participants will answer an online questionnaire that would indicate how they utilize Building Information Modeling and how the process of collaboration and coordination is re flected in the projects Describe Potential Benefits: To understand the importance of collaboration throughout the design, pre construction and construction of the project and provide the industry of a better understanding of proven practices and method s regarding the topics of the research. Describe Potential Risks: ( If risk of physical, psychological or economic harm may be involved, describe the steps taken to protect participant.) No more than minimum risk. Describe How Participant(s) Will Be Rec ruited: An online survey link will be sent to various construction companies via e mail. Maximum Number of Participants (to be approached with consent) 1,000 Age Range of Participants: 18+ Amount of Compensation/ course credit: None

PAGE 96

96 Describe the Informed Consent Process. (Attach a Copy of the Informed Consent Document. See http://irb.ufl.edu/irb02/samples.html for examples of consent.) An e mail would be sent the participant where it describes the purp ose and consent of the survey, the participant will agree to the consent by clicking on the link to the survey website. (SIGNATURE SECTION) Principal Investigator(s) Signature: Date: Co Investigator(s) Signature(s): Date: PI is a student): Date: Department Chair Signature: Date:

PAGE 97

97 APPENDIX B SURVEY QUESTIONNAIRE 1. How long have you been working in the construction industry? 1 year 3 2 5 years 10 6 10 years 17 11 15 years 7 More than 15 years 19 Total Number of Replies: 56 2. What is your BIM Title? BIM Administrator 0 BIM Coordinator 3 BIM Manager 11 Model Coordinator 1 No specific BIM title 29 Other (Please Specify): 12 Total Number of Replies: 56 3. How long have you held the title? Less than 1 year 10 1 3 years 23 4 6 years 7 7 9 years 2 10 years or more 6 Total Number of Replies: 48 4. What field do you work most closely with? Architecture 12 Engineering 4 Construction 41 MEP 7 Other, please specify 3

PAGE 98

98 5. What Disciplines are represented in your BIM projects? Architecture 44 Engineering 34 Construction 42 MEP 40 Other, please specify 14 Total Number of Responses : 56 (US $) 48 Responses 7. Please indicate the BIM Software currently in use at your firm? 52 Responses 8. How many projects have you been involved with? Single Project (Just Started) 7 Multiple Projects (1 year or less) 6 Single Project (1 year or more) 2 Multiple Projects (1 3 years) 26 More than 4 years of BIM Projects 14 Total Number of Responses: 55 9. How many licensed profession al s does your company have? Less than 5 18 5 to 10 6 11 to 15 4 16 to 20 5 More than 20 18 Total Number of Responses: 51

PAGE 99

99 10. How many hours a week do you work on BIM related tasks? Less than 5 Hours 20 5 10 Hours 2 11 15 Hours 4 16 20 Hours 2 More than 20 Hours 26 Total Number of Responses: 54 11. How would you rate the accuracy of the BIM models you have been exposed to? Very Accurate 10 Accurate 29 Neither Accurate nor Inaccurate 13 Inaccurate 3 Very Inaccurate 0 Total Number of Responses: 55 12. How would you rate the difficulty in working with multidisciplinary teams with their various discipline based BIM Models? Very Easy 0 Easy 11 Neither Easy nor Hard 33 Difficult 9 Very Difficult 1 Total Number of Responses: 54 13. How important is it for the BIM teams to work together from the beginning? Very important 45 Quite Important 8 Fairly Important 2 Slightly Important 0 Not at all important 0 Total Number of Responses: 55

PAGE 100

100 14. How important is it for BIM teams to work together during construction? Very important 42 Quite Important 11 Fairly Important 2 Slightly Important 1 Not at all Important 0 Total Number of Responses: 56 15. How often should the multidisciplinary teams meet to discuss the BIM process? (monthly) Less than once 3 1 5 times 40 5 10 times 6 11 15 times 1 More than 10 times 3 16. What type and size of projects are you employing BIM processes in? 44 Responses 17. What are the primary areas that you have identified improvements in? Design 37 Productivity 39 Cost 23 Estimating 20 Scheduling 24 18. What in the multidisciplinary process did you encounter the greatest difficulty with? 41 Responses

PAGE 101

101 19. How large was the initial investment when you first adopted the BIM methodology? 2 $1000 10,000 8 $10,00 1 20,000 14 $20,001 30,000 5 > $30,000 19 Total Number of Responses: 48 20. What was Return on Investment (ROI) in BIM? (US $) 39 Responses 21. What were the benefits realized by using BIM on projects ? (Ch eck all that apply) Reduction in Overhead Costs 16 Improved Management of Project Logistics 34 Planning 35 Communication and Reporting 27 Reduced Cost of Design 18 Enhanced Cost Estimation capabilities 21 Reduction of Design error s 36 Improvement in Customer Service 30 Production/Fabrication 34 Better understanding of the project by team members 38 Other, please specify 14 22. What were the unexpected benefits realized by using BIM (Please Specify if any)? 20 Responses 23. What BIM collaboration software does your company employ? (e.g. Autodesk Navisworks) 45 Responses

PAGE 102

102 24. How effectively did the software facilitated collaboration and communication throughout the teams? Very Effecti ve 6 Effective 24 Slightly Effective 13 Not Effective 2 Total Number of Responses: 45 25. From your experience, how would you rate the motivation for collaboration of the multidisciplinary members? Very High 5 Above Aver age 20 Average 17 Below Average 6 Very Low 0 Total Number of Responses: 48 26. Which field of practice (excluding yours) seemed most willing to collaborate? Architecture 13 Engineering 8 Construction 11 MEP 25 Othe r, please specify 3 Total Number of Responses: 56 27. Which field of practice (excluding yours) seemed the least willing to collaborate? Architecture 21 Engineering 15 Construction 3 MEP 8 Other, please specify 3 Total Nu mber of Responses: 50

PAGE 103

103 28. Which project delivery method facilitates collaboration the most? Design Bid Build 8 Design Build 22 Integrated Project Delivery (IPD) 29 Other, please specify 4 29. What is the ideal BIM team si ze? 43 Responses 30. What is the ideal project delivery method? 46 Responses 31. What is the ideal project size? (US $) 43 Responses 32. What field of practice should spend the most time in BIM training? Architectur e 27 Engineering 14 Construction 6 The same 18 Other, please specify 3 33. At what stage should BIM practices be implemented? Design Stage 51 Preconstruction Stage 22 Construction Stage 16 34. During what st age should teams meet? Design Stage 48 Preconstruction Stage 30 Construction Stage 21

PAGE 104

104 35. Which teams should meet at the design stage? 40 Responses 36. Is there a field of practice that you think should have a larger involv ement in the BIM development and implementation? Architecture 21 Engineering 12 Construction 21 MEP 12 Other, please specify 10 37. What is the ideal Green rating system to implement BIM with? LEED 37 Green Globes 2 Green Star 2 BREEAM 3 Other, please specify 7 Total Number of Responses: 51 38. From your experience with BIM projects, how would you rate the degree of multidisciplinary collaboration? Excellent 5 Above Average 17 Average 22 Below Average 8 Low 1 Total Number of Responses: 53

PAGE 105

105 LIST OF REFERENCES AIA and AIA California Council. (2007). Integrated project d elivery: A g uide 1.2 34. Retrie ved from http://www.msa ipd.com/IPD_Guide_2007.pdf ( Dec 11 2009) Autodesk, Inc. (2008a). Improving b uilding industry results through integrated project delivery and building information modeling Retrieved from http://images.autodesk.com/adsk/files/bim_and_ipd_whitepaper.pdf (June 26 2010). Azar, C. (2008). Collaboration: Paving a win win road to profit Northwest Construction 28. Bentley Systems Inc. (2010). Dynamic collab oration for iterative project review Retrieved from http://www.bentley.com/en US/Products/ProjectWise+Navigator/Product Overview.htm (Aug 12 2010). Bernstein, P. Pittman, J. (2004). Barriers to the adoption of building information modeling in the building industry Retrieved from http://images.autodesk.com/adsk/files/bim_barriers_wp_mar05.pdf (Nov 12 2009) Building Design and Construction. (2009). ASHRAE research targets tying together BIM energy efficiency Retrieved from http://www.bdcnetwork.com/article/CA6675774.html (Aug 13 2009) B uildingSmart International. (2010). About us. Retrieved from http://www. buildingsmart.com/content/buildingsmart_international (Dec 25 2009) Cohen, J.W. ( 2010 ) Integrated p roject d elivery: Case s tudies AIA California Council 9 34. Denise, Leo. (2000). Collaboration vs. C t hree ( cooperation, coordination, and communication) Innovating, 7 (3) 1 6 Dirik, J. (2009). Integrated project de livery, part two: Legal issues. Texas Construction, 38 Dispenza, K. (2010) The dail y life of building information modeling (BIM) Retrieved from http://buildipedia.com/in studio/item/1212 the daily life of building information modeling bim ( Jun 15 2010) Eastman, C., Teicholz, P., Sacks, R., and Liston, K. (2008). BIM handbook: A guide to building information modeling for owner, managers, designers, engineers, and contractors ( 1st ed. ). New Jersey : Wiley. Eckblad, S ( 2007 ) Integrated project delivery A working definition AIA Califo rnia Council, Sacramento, California

PAGE 106

106 France, C. (2010 ). BIM and the c loud Retrieved from http://www.aecbytes.com/feature/2010/BIM_Cloud.html (Oct 21 2010) Friedman, T. L. (2005). The world is flat: A brief history of the twenty first centur y New York: Farrar, Straus and Giroux. GGHC. (2010). A bout GGHC : W ho we are: O verview Retrieved from http://www.gghc.org/about.whoweare.overview.php (12 Oct 2010) Grilo, A., an d Jardim Goncalves, R. (2010). Value proposition on interoperability of BIM and collaborative working environments Autom.Constr., 19 (5), 522 530. Holness, G. (2006). Building information m odeling ASHRAE Journal 48 (8), 38 46. Khemlani, Lachmi. (2006). T he AGC's BIM i nitiatives an d the contractor's g uide to BIM Retrieved from http://www.aecbytes.com/buil dingthefuture/2006/AGC_BIM.html (J uly 15 2010 ). Khemlani, L. (2008a). Autodesk NavisWork 2009 Retrieved from http://www.aecbytes.com/revi ew/2008/NavisW orks2009.html ( May 14 2010). Khemlani, L. (2009b). Bentley a rchitecture V8i Retrieved from http://www.aecbytes.com/revi ew/2009/BentleyArchV8i.html ( Feb 26 2010). Khemlani, L. (2009d). Collaboration, project management, and p roj ect i nformation management solutions in AEC Retrieved from http://www.aecbytes.com/feature/2009/Collaboration_PM_PIM_Solutions.html ( Feb 26 2010). Khemlani, L. (2009e). Revit a rchitecture 2010 Retrieved from http://www.aecbytes.com/rev iew/2009/RevitArch2010.html ( Feb 26 2010). Khemlani, L. (2010a). ArchiCAD 14 Retrieved from http://www.aecbytes.com/review/2010/ArchiCA D14.html (Sep 10 2010). Khemlani, L. (2010b). Newforma project center seventh edition Retrieved from http://www.aecbytes.com/review/2010/NewformaProjectCenter7.html (Aug 18 2010). Laiserin, J. (2009). Next G en BIM: Graphisoft t eamwork 2.0 will revoluti onize BIM/IPD workflow and collaboration. The LaiserinLetter, 25 Liebich, T. (2010). Next g eneration of o pen i nteroperable w orking with BIM B uildingSMART, 1. Livingston, H. (2007 ). BIM and s ustainable d esign Retrieved from http://www.cadalyst.com/cad/building design/bim and sustainable design part 2 3618 (May 7 2010).

PAGE 107

107 McGraw Hill Construction (2008). Building i nformation modeling ( BIM ): T ransforming design and construction to achieve greater industry productivity New York: McGraw Hill. Malin, N. (2007). B uilding information modeling and green design. EBN, 21 Mckenzie, J., Johnson S. (2009). BIM means business: P project c ase study Retrieved from http://au.autodesk.com/?nd=material&session_material_id=6036 (Oct 12 2010) Roberts, T. (2008). I ntegrated project delivery: A platform for efficient con struction Retrieved from http://www.buildinggreen.com/auth/article.cfm/2008/10/29/Integrated Project Delivery A Plat form for Efficient Construction (Nov 1 2008) Sacks, R., Koskela, L., Dave, B. A., and Owen, R. (2010a). I nteraction of lean and building information modeling in construction. J.Constr.Eng.Manage., 136 (9), 968. Sage Software, Inc (2008) Collaborative c onstruction: Making BIM w ork for b uilders. Retrieved from http://www.aspenational.org/Files/13/Sage_White_Paper_ _Making_BIM_Work_for_Builders.pdf (Aug 2 2010) Suermann, P. (20 10 ). Evaluating the impact of building information modeling (BIM) in construction Retrieved from http://buildinginformationmanagement.wordpress.com/2010/02/02/evaluating the impact of building information modeling bim on construc tion (Sep 14 2010). Thomson, D. and Miner, R. (2006). BIM: Contractual risks are changing with technology Consulting Specifying Engineer, 40 (2), 54 66. Vrkonyi, V. (2009). s halt c o ollaboration s trategies in the a ge of BIM Retrieved from http://www.aecbytes.com/viewpoint/2009/issue_43.html ( Sep 10 2010)

PAGE 108

108 BIOGRAPHICAL SKETCH Sergio l of Building Construction with a concentration in sustainable construction. In 2008 he College of Design, Construction and Planning with a degree in a rchitecture. he worked as a BIM Coordinator for Wildwoods Incorporated (Williston FL), where he dealt with the intricacies of healthcare construction and design. Sergio worked for Beale and Associates (San Juan, PR) and for Exot icscape (Key Biscayne, FL). There he developed his architectural skills, while being exposed to the design, coordination and management of several high end residential projects. He obtained his Leadership in Environmental Energy and Design Accredited Prof essional ( LEED AP ) credential in 2009 and has been involved in residential, commercial and healthcare projects in Florida, Peru, Puerto Rico and the Bahamas. Sergio grew up in Peru, where he developed a pa ssion for sailing and the ocean. He has traveled a round Asia, Europe, South America and the Caribbean while competing in international regattas. He is continuously learning about sustainable license and becoming a registe red architect.