Building Information Modeling and Its Impact on Design and Construction Firms

Permanent Link: http://ufdc.ufl.edu/UFE0022211/00001

Material Information

Title: Building Information Modeling and Its Impact on Design and Construction Firms
Physical Description: 1 online resource (59 p.)
Language: english
Publisher: University of Florida
Place of Publication: Gainesville, Fla.
Publication Date: 2008

Subjects

Subjects / Keywords: Building Construction -- Dissertations, Academic -- UF
Genre: Building Construction thesis, M.S.B.C.
bibliography   ( marcgt )
theses   ( marcgt )
government publication (state, provincial, terriorial, dependent)   ( marcgt )
born-digital   ( sobekcm )
Electronic Thesis or Dissertation

Notes

Abstract: The Construction industry is a business focused around providing a product through the traditional construction process, which remains for the most part, independent of the design process. With the growing changes in technology, many areas of production and business (outside of construction) are being refined and redefined, leaving the construction industry behind. Process of construction is still basically the same as it was hundreds of years before, from a set of drawings, a building in erected. For the most part, these drawings are never without errors and omissions, causing many delays, multiple change order items, and late projects completion. With the advent of Building Information Modeling (BIM) software, the Designer/Architect is given the opportunity to design the building, and the software develops the appropriate plans and sections needed for construction. This is good for the designers because the project is completed in 3-D and most, if not all conflicts can be resolved before construction begins. These are just the initial benefits that BIM can potentially help the design and construction industry. Design/Build firms can be extremely efficient because they house both the designers (Architects and Engineers) and the Construction Management professionals; however they still operate with the same flawed system of designers generating construction drawings and the construction team erecting the building. More advancements can be made to increase productivity in construction, reduce requests for information, eliminate coordination problems, decrease construction time, and increase quality. The BIM Software is the gateway to solving these issues. With dynamically linked on demand modeling, changes can be made by Designers in a remote location that would update digital construction drawings at the jobsite. Project managers on site can propose changes to the design team with no delay time. Means of construction can be displayed in 4-Dimensions for an increased understanding of construction sequencing by the contractor on site. Any and all questions can then be answered immediately and virtually from any location. Understanding the potential that BIM software has to offer and implementing it into the construction industry can be the next great advance since the advent of power tools and equipment, however this innovation has many issues that need to be resolved before implementation of the software would be generally accepted. Once done, its full integration to improve productivity for the AEC industry will be significant. This change over will be market driven by the owners of projects and come at a large initial cost for all construction companies, large and small.
General Note: In the series University of Florida Digital Collections.
General Note: Includes vita.
Bibliography: Includes bibliographical references.
Source of Description: Description based on online resource; title from PDF title page.
Source of Description: This bibliographic record is available under the Creative Commons CC0 public domain dedication. The University of Florida Libraries, as creator of this bibliographic record, has waived all rights to it worldwide under copyright law, including all related and neighboring rights, to the extent allowed by law.
Thesis: Thesis (M.S.B.C.)--University of Florida, 2008.
Local: Adviser: Issa, R. Raymond.
Local: Co-adviser: Olbina, Svetlana.

Record Information

Source Institution: UFRGP
Rights Management: Applicable rights reserved.
Classification: lcc - LD1780 2008
System ID: UFE0022211:00001

Permanent Link: http://ufdc.ufl.edu/UFE0022211/00001

Material Information

Title: Building Information Modeling and Its Impact on Design and Construction Firms
Physical Description: 1 online resource (59 p.)
Language: english
Publisher: University of Florida
Place of Publication: Gainesville, Fla.
Publication Date: 2008

Subjects

Subjects / Keywords: Building Construction -- Dissertations, Academic -- UF
Genre: Building Construction thesis, M.S.B.C.
bibliography   ( marcgt )
theses   ( marcgt )
government publication (state, provincial, terriorial, dependent)   ( marcgt )
born-digital   ( sobekcm )
Electronic Thesis or Dissertation

Notes

Abstract: The Construction industry is a business focused around providing a product through the traditional construction process, which remains for the most part, independent of the design process. With the growing changes in technology, many areas of production and business (outside of construction) are being refined and redefined, leaving the construction industry behind. Process of construction is still basically the same as it was hundreds of years before, from a set of drawings, a building in erected. For the most part, these drawings are never without errors and omissions, causing many delays, multiple change order items, and late projects completion. With the advent of Building Information Modeling (BIM) software, the Designer/Architect is given the opportunity to design the building, and the software develops the appropriate plans and sections needed for construction. This is good for the designers because the project is completed in 3-D and most, if not all conflicts can be resolved before construction begins. These are just the initial benefits that BIM can potentially help the design and construction industry. Design/Build firms can be extremely efficient because they house both the designers (Architects and Engineers) and the Construction Management professionals; however they still operate with the same flawed system of designers generating construction drawings and the construction team erecting the building. More advancements can be made to increase productivity in construction, reduce requests for information, eliminate coordination problems, decrease construction time, and increase quality. The BIM Software is the gateway to solving these issues. With dynamically linked on demand modeling, changes can be made by Designers in a remote location that would update digital construction drawings at the jobsite. Project managers on site can propose changes to the design team with no delay time. Means of construction can be displayed in 4-Dimensions for an increased understanding of construction sequencing by the contractor on site. Any and all questions can then be answered immediately and virtually from any location. Understanding the potential that BIM software has to offer and implementing it into the construction industry can be the next great advance since the advent of power tools and equipment, however this innovation has many issues that need to be resolved before implementation of the software would be generally accepted. Once done, its full integration to improve productivity for the AEC industry will be significant. This change over will be market driven by the owners of projects and come at a large initial cost for all construction companies, large and small.
General Note: In the series University of Florida Digital Collections.
General Note: Includes vita.
Bibliography: Includes bibliographical references.
Source of Description: Description based on online resource; title from PDF title page.
Source of Description: This bibliographic record is available under the Creative Commons CC0 public domain dedication. The University of Florida Libraries, as creator of this bibliographic record, has waived all rights to it worldwide under copyright law, including all related and neighboring rights, to the extent allowed by law.
Thesis: Thesis (M.S.B.C.)--University of Florida, 2008.
Local: Adviser: Issa, R. Raymond.
Local: Co-adviser: Olbina, Svetlana.

Record Information

Source Institution: UFRGP
Rights Management: Applicable rights reserved.
Classification: lcc - LD1780 2008
System ID: UFE0022211:00001


This item has the following downloads:


Full Text
xml version 1.0 encoding UTF-8
REPORT xmlns http:www.fcla.edudlsmddaitss xmlns:xsi http:www.w3.org2001XMLSchema-instance xsi:schemaLocation http:www.fcla.edudlsmddaitssdaitssReport.xsd
INGEST IEID E20101106_AAAAFE INGEST_TIME 2010-11-06T21:02:40Z PACKAGE UFE0022211_00001
AGREEMENT_INFO ACCOUNT UF PROJECT UFDC
FILES
FILE SIZE 8830 DFID F20101106_AABHWI ORIGIN DEPOSITOR PATH kuehmeier_j_Page_21thm.jpg GLOBAL false PRESERVATION BIT MESSAGE_DIGEST ALGORITHM MD5
546390cbf1500acd948f8b5085d61c1d
SHA-1
d6a0f98b96c67a1b0adadc74824bf30cbf6fe595
25271604 F20101106_AABIID kuehmeier_j_Page_05.tif
dbd77d721a7f13529de6d2ecc8ce5a50
c32ecd603f5b8162ea5f1456d62a0a61f5e2ad11
2936 F20101106_AABIDG kuehmeier_j_Page_04thm.jpg
8c3d2e593a4d094f19f4ec733cd463a5
b7ff3c2c34eb3da212735c68fd70d99d437ba01d
F20101106_AABHWJ kuehmeier_j_Page_18.tif
0ad33ddd00e62991f07efd4943cd402c
e87d6d03af10246af546472e1fabd798f06cd9ce
F20101106_AABIIE kuehmeier_j_Page_23.tif
586ebe96cbbfa3ed985e74daa208ae21
84ebeda2f2382717c82d6c4005b8391bd6eef308
55005 F20101106_AABIDH kuehmeier_j_Page_20.pro
75f9defcb69d9a237ff03003e3e1c587
dcde671f5909ef4602f228b1c21e9f5ac3c6fa59
4942 F20101106_AABHWK kuehmeier_j_Page_06thm.jpg
980c78c4fcb383b657421029fece5829
0e95c6ab312c7912c424a0b12e106737811d33f8
F20101106_AABIIF kuehmeier_j_Page_28.tif
b4d230fcf78150b8e28e3cd917d709f7
55a3553f9234e806b10af53c796aa163c82c50cb
1053954 F20101106_AABIDI kuehmeier_j_Page_38.tif
6196f0fa0b6af57aa4f7e49eb15486ff
5559e3594983948f50d0b50478203d9afc80adf4
105248 F20101106_AABHWL kuehmeier_j_Page_40.jp2
e209887ac4a66c1ce25c467cd2aa23dc
568e20b28414badde3d7635b49330ebae0f61690
F20101106_AABIIG kuehmeier_j_Page_44.tif
f8b565e93107ccb91dce3318b0da4b76
a02766dfa0632c4ef1d03028cfa07cd44e9f7940
33764 F20101106_AABIDJ kuehmeier_j_Page_49.QC.jpg
29765266178c805ad5e347e66abfb829
0b4fedc9fb59f661c23c9774f4c5ae23bceab569
6787 F20101106_AABHWM kuehmeier_j_Page_27thm.jpg
343f26c5c0b6bed90fc0646ac8d87c03
8ebaa78e5b47861f285a886eb24464fcfe54967e
F20101106_AABIIH kuehmeier_j_Page_51.tif
7d5f5aefc7bd62545e659913a303a8dc
a8149c2278d92a8ba029171bdf55465b2ada212d
100372 F20101106_AABIDK kuehmeier_j_Page_43.jpg
ca7b8ab22fbd40d88bd545221257ae32
a1802932925e1b2c6262cff097e4f694b3233026
94030 F20101106_AABHWN kuehmeier_j_Page_51.jpg
ae33b1dac75a6f715b98dc3f1c498dc3
f8429d194924bb83f77d41614eae7863640009e2
F20101106_AABIII kuehmeier_j_Page_53.tif
7670b862dd38fde394c9b35f2e96af5a
ef988a00617d883451dc033acbac927eaf609597
F20101106_AABIDL kuehmeier_j_Page_42.tif
87860d785cdf34c2916fee5f07d71d9c
fdc9164dc102fa61ac24a4e5dd3f7df2e064980d
8259 F20101106_AABHWO kuehmeier_j_Page_13thm.jpg
4a34a78d90e1d3cfb234d42ff7cd0d06
c71e7ff349739f27a9468c12d224a916d8c74862
F20101106_AABIIJ kuehmeier_j_Page_56.tif
3dbb5c195343c943071e4563d7cbeab6
4bf86a092ac45ed52443a5da58517dc3ab0c7eec
98867 F20101106_AABIDM kuehmeier_j_Page_50.jpg
5ad8cc2361aa51c4a5abc333bf92dbc6
cf70a2edb2d89f84d8b20d375f4826f95fc55680
86811 F20101106_AABHWP kuehmeier_j_Page_55.jp2
5e9a2fc6b2ae4cfb16425cbe44ba08a0
e315496097b619a6cb7f90a747450c800a0eb288
40177 F20101106_AABIIK kuehmeier_j_Page_09.pro
15c3bb5f7b7ba9ce811c5588a9d2c64e
590f1f73e053f8a264f4c48c7b38852a9b4c0f07
105714 F20101106_AABIDN kuehmeier_j_Page_13.jpg
a968d92e575bc451e2eac5712b5d1c27
5a94d1b34a70c93376c5ca49da3ffcb8fa1669b6
8288 F20101106_AABHWQ kuehmeier_j_Page_11thm.jpg
754a185c21c0821378bc3a50f0fb71d5
567de8032cfcc2b4dd30559594f4d1513c7eeaec
4888 F20101106_AABIDO kuehmeier_j_Page_58thm.jpg
6226c370b4652c473fa371dd416c793d
d2d9a4d2c13413bd6f45653335e6cfa7bf4c3712
101186 F20101106_AABHWR kuehmeier_j_Page_42.jpg
a099c89319dde1d58e26ca22e6a24171
e14882141d2de8af68f394b1437f25ff909a8ae8
52834 F20101106_AABIIL kuehmeier_j_Page_13.pro
2624269d01ce758ca4daa169eeef9f78
cf21bd571aa81016a024f1a7933d243dbfd9dc8e
6916 F20101106_AABIDP kuehmeier_j_Page_31thm.jpg
67ef0edfdadb3ca289bc15d6b75f5a22
b013154ea8c1a286527cc6ce95e05a63631ac054
F20101106_AABHWS kuehmeier_j_Page_21.tif
2423e94c7957c849c8df6d2ae7df16e9
2dd066a75506088e51969fe866d511ea71fef781
31570 F20101106_AABIIM kuehmeier_j_Page_24.pro
1c134934f72d9f94b3d2fad659d1aaa1
1fe8f0066f6782ec4cc13e5f28ef0ea6118a1a6c
119780 F20101106_AABIDQ kuehmeier_j_Page_47.jpg
98dad16c094783fa4e452673ac39323f
ad8d914120280c8619a389203f004f6f718ddcb0
211 F20101106_AABHWT kuehmeier_j_Page_03.txt
ea8504a8776c42a0416f20f601ada8d2
d2e774b389523d95f24f25f2b1e6d4ff209474a6
39244 F20101106_AABIIN kuehmeier_j_Page_28.pro
5530c2f8157e0f85f7c7459847104145
4b0399f84ae0e016585f996c1204caf312d2bdd4
9120 F20101106_AABIDR kuehmeier_j_Page_20thm.jpg
772c49f84c1d2d69ba05f8f973a32209
5f9f3cba068dc3a4d0fd8ac1f048cbe9eac09215
20328 F20101106_AABHWU kuehmeier_j_Page_06.QC.jpg
93647be255a9925aaac5c3d291e741cc
82d95bbe5e9a0512adce6fc6e6170247b003518c
30006 F20101106_AABIIO kuehmeier_j_Page_47.pro
c1966104f520664f7c67dfaac026f367
7f30911bc6249309e1c491c7afd11bbf269bcff7
8451 F20101106_AABIDS kuehmeier_j_Page_12thm.jpg
443da1a5aa32a15a60884f3c04534434
33fc271483209a1c010c9a034ad70579be1c7101
33212 F20101106_AABHWV kuehmeier_j_Page_11.QC.jpg
f29cc8d13ab6cd082a27317a9451accb
0c35e55ea69c257a2d815bf1c5087bfcb2c2ee5d
55198 F20101106_AABIIP kuehmeier_j_Page_48.pro
f40d17aada43d34258a8ea8a2e45d086
60b8c2cd34f32868436560ac7ee257e2940ddc4c
22254 F20101106_AABIDT kuehmeier_j_Page_52.pro
37e88814cf69d3ce6e5c222156df6d9f
cd5dabfc35d4d95507bd8099860cbf9385693fce
4066 F20101106_AABHWW kuehmeier_j_Page_05.txt
6940c6ca95f3c00205bdef279d47c213
aed481170335a098bd40a6a12abfd5ebdc66d591
6236 F20101106_AABIIQ kuehmeier_j_Page_56.pro
dfa3c4f17e66a8218a014ad38fac8383
00c53b5992684fa1a4171fbd3be9ce19917d46d7
2969 F20101106_AABIDU kuehmeier_j_Page_41thm.jpg
5be664a28a5c7e0c59a9c8f2edecf3d8
222216cdd85aa015ad84a9e449a42919745a6a9a
109386 F20101106_AABHWX kuehmeier_j_Page_37.jp2
1b3a394314e317fa777527e77f5c1a2d
a9af0b9961107590a128004ea2f0fa33937a56c1
56673 F20101106_AABIIR kuehmeier_j_Page_57.pro
a836102d73b465a3eff0ac8790918951
2eb53d3f684a519432d3ee2b15a75a9a1f7c648c
1625 F20101106_AABIDV kuehmeier_j_Page_56thm.jpg
a72464611dfc14d1d3e579c7ae44bf43
0dc39493b8c5839c268dbe88b999d218ffd54045
34227 F20101106_AABHWY kuehmeier_j_Page_54.QC.jpg
a608c8917403aff540a6935a5ba3cfbc
e4ce73d6b9dc28a25077f8929f00e43375c958f0
92 F20101106_AABIIS kuehmeier_j_Page_02.txt
afe0d3a68717340a97aa61b4ab7a2cde
ce9fee8707c67aad16cf7e5fb8a9539ac4ad0d21
1997 F20101106_AABHUA kuehmeier_j_Page_40.txt
47f62ece3aa887904af3b2bcc58e9ce6
0d767edff6bf3c00ed7ad2e7af29536063c499c9
35636 F20101106_AABHWZ kuehmeier_j_Page_04.jpg
097949e00838a78873d3df6424677646
228f26564748029e95e0ecf6d91021d4a4983aea
2229 F20101106_AABIIT kuehmeier_j_Page_06.txt
a3b701e80d763e48acfbb8dcace98c1e
7c19ca7b2fa7b394b9ebbb6241bd271e945b86b3
12738 F20101106_AABIDW kuehmeier_j_Page_14.jp2
45a9894e1af775b1bb140c87de14afc9
fc197d3faae6e39e08bb909f7b38d4e370050ce7
89129 F20101106_AABHUB kuehmeier_j_Page_09.jp2
6358fece3d09f75c6022796e77cd6544
b0858fe20a06b0b210d13682ef618ac8c8b91757
2105 F20101106_AABIIU kuehmeier_j_Page_19.txt
fffca95b52c42a5fe8234e43ee5a358c
b088a20789b9dfaf9c404492ee0391bd747f4037
8755 F20101106_AABIDX kuehmeier_j_Page_01.pro
12f17515ad1a9bf610f56f521c4aad9c
410e3d4aeebd3da1b9e6cfa7fa6ab4ead054a991
1951 F20101106_AABIIV kuehmeier_j_Page_27.txt
0d4da3787e2295a4622e965b720233ce
daa0d69dc5a08481992b0645208035342c656809
4018 F20101106_AABIBA kuehmeier_j_Page_03.QC.jpg
b0b2131d3b037ed1beff8a48d562c9c6
58e9f83d09b9b16166eaa05dac36eb01c8db8a55
F20101106_AABIDY kuehmeier_j_Page_41.tif
bba68edc3e2584d5bfb11c03d84aa5f0
22833fbae7897c751ff7e876c4ced54960e86077
29569 F20101106_AABHUC kuehmeier_j_Page_51.QC.jpg
4bf83dccdaa6f4111c5d5db7997b6f12
e1dad60cf4098544f4dc8ab781e6d1bb113f3336
2586 F20101106_AABIIW kuehmeier_j_Page_54.txt
a06f7eae331e51ee92c4b9350add359f
95ab60a88674f8f03818167b532dce6533b3a820
111519 F20101106_AABHZA kuehmeier_j_Page_48.jpg
ccd77aab919253ba5caf7fd30f5301bb
69eea0390148111383fcfaa36a195b9ce741f099
9215 F20101106_AABIBB kuehmeier_j_Page_25thm.jpg
8a097a5b80b3144daeeb1a6cad11f862
74f2594d950e939324b0ed95fbe257ab69994b40
1007224 F20101106_AABIDZ kuehmeier_j_Page_30.jp2
2fac0c5614cc1d68d29c6903f3cfb794
0ac04ac23cc29e401a53eb337842c250869f08b3
1573 F20101106_AABHUD kuehmeier_j_Page_31.txt
e5297cc34695576370ecee0723efc64e
948e8d3a0b0ceec522d476eb9a3bc2b152523cd9
35812 F20101106_AABIIX kuehmeier_j_Page_34.QC.jpg
f38fe6395c12271deb926e6171607f9c
c9f8d52e02892f797260aa308b0994aac3097386
F20101106_AABHZB kuehmeier_j_Page_16.tif
c15248197d59300017017bdc35e374d3
cb4d383ff9d036173f660199e7e21d8ac22beaea
24731 F20101106_AABIBC kuehmeier_j_Page_22.QC.jpg
52f4b29a41bc52ef1bcade624ba2c882
2100fa7ffc051de5411a30b336feeb4090bf417e
121787 F20101106_AABHUE kuehmeier_j_Page_08.jpg
65ee0d5d3099cfae003440e7aaf42421
3a5b76509f5b923b12a693bc6114932a0029b302
116009 F20101106_AABIGA kuehmeier_j_Page_16.jpg
0b9307bc1d6c4b543c821d23da6336a4
98c5de951a0e2b7e050cdff3e5d33944644281f5
6028 F20101106_AABIIY kuehmeier_j_Page_53thm.jpg
5e7b63e87a384f28b1b9b706bac5a391
2bb8bdeeafb81f26e77a87428eac3eb7e07bd43f
F20101106_AABHZC kuehmeier_j_Page_39.tif
8e3c7f5b0459eee812e5547a3b7dad91
9449f1dcc55dd7cbb7d781657a805518ff8c96cb
26419 F20101106_AABIBD kuehmeier_j_Page_01.jp2
6200e0aa1f58c03891e1ae1b7bb34802
0560e551623c61edf82c08dbe5c9ed30677bef66
2515 F20101106_AABHUF kuehmeier_j_Page_08.txt
4f879b91ca0f9dbe7992a21787faee9e
51e46e4dc848f873e21d94f7ee27e368e1d632a0
9737 F20101106_AABIGB kuehmeier_j_Page_18thm.jpg
ad16dc8391e578b7dfdc11a44b919bd0
42d408cb736505be65a7aa737391c0fcbe306c75
6744 F20101106_AABIIZ kuehmeier_j_Page_05thm.jpg
2e0e7b41995f838c71d4b82fcdb39183
9bf0ceb83af8e8d309f771d0647f7033eced7996
120647 F20101106_AABHZD kuehmeier_j_Page_36.jpg
81bb3d12b688cbb0929b507541cd98d6
4945a231563f4d3e888ff38c419b572d92ed8cfa
2266 F20101106_AABHUG kuehmeier_j_Page_16.txt
effe413c04f8fe656efa3c56f1f025dc
559e53221db417d938dd53ffd53b8754598c8e61
41945 F20101106_AABIGC kuehmeier_j_Page_10.pro
9487f432a10ec055239aeb4b41f6ae86
ee8e424cc102fdf0ca859ecaadfee3d8e4df3ea2
32270 F20101106_AABHZE kuehmeier_j_Page_53.pro
be3ae22072bbde6fddf68d2ffcf29114
3d98c8cc7711ccec201346ea221f4da677f4b4a4
60228 F20101106_AABIBE kuehmeier_j_Page_52.jpg
493365d877ab226e4af5b82b15340f8f
e3616d5b9fa747639d91bc44d3f4d5236260731e
F20101106_AABHUH kuehmeier_j_Page_40.tif
72721a9a28ffa998c61cb48397d5d369
1878c0f6ae06208b28bbb5b3901ddbe6c320a34f
25311 F20101106_AABIGD kuehmeier_j_Page_55.QC.jpg
068e7c9aab44d1afa38943adbf81be63
807cdce9db41f27c61ea3b25bd3bea7395342428
12440 F20101106_AABHZF kuehmeier_j_Page_03.jp2
28b5cb33824c3e4568c4ffba655df8fc
bd24e5f92f3682391c438538d6964ef771c0074c
36758 F20101106_AABIBF kuehmeier_j_Page_48.QC.jpg
008840a208cea1c7fb10bced53a74a31
d58a64e501a6e25af6bf2ca56b06a46cd0772e95
F20101106_AABHUI kuehmeier_j_Page_32.tif
773602957e422eae7dcd5d1880b2c96d
8406989d6041877350ec4306a84a1b23f81f1117
662 F20101106_AABIGE kuehmeier_j_Page_04.txt
144a8bacfe13b0f83e228b86f121d8e9
6f3770e515032d0b8d2d9a4b6ed8252228c04f87
37062 F20101106_AABHZG kuehmeier_j_Page_25.QC.jpg
30a4ac1f45bd796c6ac13db2249253ca
a0080818fcd0115ce6464f49fc170beef4e6eaff
F20101106_AABIBG kuehmeier_j_Page_54.tif
c401fe6c168dee06d32498aa71178db9
c64b5e109b9956ac1698db5a33a7841948d97706
8620 F20101106_AABHUJ kuehmeier_j_Page_54thm.jpg
6dd4277c6a7809f18149213e51508233
988109a5cc9e6b837784c9c24c2ca34f209704ba
2169 F20101106_AABIGF kuehmeier_j_Page_29.txt
432e3a2569bb763473fdc630dbf79023
ed4ebb87d6b5e9cf3e40a0f59b2f538d29ee7d6f
1051982 F20101106_AABHZH kuehmeier_j_Page_23.jp2
9f43ac27e927e7221a3e4d0819fe8133
693416ece46b2d3af746ba9250dcf657b5a92872
24115 F20101106_AABIBH kuehmeier_j_Page_59.pro
0e0d6dee261807131053e0a2ca634384
499b052af4b9b1f86295c388165610b1ecb28bc8
17190 F20101106_AABHUK kuehmeier_j_Page_56.jp2
63bf326367e051d60af24d440dc9588d
a74ed59bea88dde8a0a666f216c9bdc226508cce
100104 F20101106_AABIGG kuehmeier_j_Page_05.pro
4797fd30e4c09a53cf70870f610d650d
3778c7fdcb7c2a189b763124d4bae845ba289999
36053 F20101106_AABHZI kuehmeier_j_Page_21.QC.jpg
32ab8671a21fbd84821719f4705635ed
e48f1930ae690592db43191216499f00d257fa99
83891 F20101106_AABIBI kuehmeier_j_Page_06.jpg
47d63b23936c7ea5ebc36dc3dca27ca7
01db9f1fde0f938678bdc18f7c2d4c6a7ac45670
36938 F20101106_AABHUL kuehmeier_j_Page_04.jp2
997626ebbbe4e3bc7dba871abb727821
cfaf15a1478dc625f82a46145f16b8c2bf457768
57976 F20101106_AABIGH kuehmeier_j_Page_35.jpg
f59e40014487522dbb45dbc12e3dfe4c
1a3314cc6a40f6fe8edc7660a761c228b736d127
F20101106_AABHZJ kuehmeier_j_Page_45.tif
d20ff949eb085755e0c92806d728af34
97d2d5d72c8ac8d8354724955cf0f4f3149f08e6
97108 F20101106_AABIBJ kuehmeier_j_Page_51.jp2
0c41efa1aae80117896a2d07e79877d9
c914a2e42742409e55e2b65679a7769e4c3ef2af
114819 F20101106_AABHUM kuehmeier_j_Page_34.jpg
d05482bdb11851c938f38071db91802f
faf2ce4b4e9a07d978d076c6427da99292d46e35
104684 F20101106_AABIGI kuehmeier_j_Page_15.jp2
8fd24d84236a9491e7d06a79c2048b3d
b70654f1dde576caeb90f55b9ff89f77d056f616
61964 F20101106_AABHZK kuehmeier_j_Page_45.jpg
a8eb344225babf8c3ebada166db3a636
a3e8c92430f4805bb45cea8c5676c9a7125a22a6
33044 F20101106_AABIBK kuehmeier_j_Page_42.QC.jpg
5effa5bc858e3354e3b19720b88749eb
9794140178c91bc72037df8ad53df6840293f793
6669 F20101106_AABHUN kuehmeier_j_Page_09thm.jpg
a7ebf61c0dd0bfc22b8cb6316d8f4d4c
3db6a35afbb3618ac1dcd903d89c9980670f3b09
F20101106_AABHZL kuehmeier_j_Page_08.tif
4e547afa11f20ff74e4d65519d6f410d
d90affad3e072075565708aa5d2fc8c174da32b1
1174 F20101106_AABIBL kuehmeier_j_Page_14thm.jpg
96a3ebf212a79030a87580174498a72a
37dfa68203f382c605efeded2061557c72d8abf8
F20101106_AABHUO kuehmeier_j_Page_24.tif
1dfdfd4a066028d063fbc74627b7587a
e771e0301213940aed475adfd34ca8e545a1770d
28805 F20101106_AABIGJ kuehmeier_j_Page_10.QC.jpg
0dd0f801281f6e9c32609153ce351322
15c7b73f6d5c31b7d2b7016094bd1c18beacf133
52751 F20101106_AABHZM kuehmeier_j_Page_12.pro
a20abf42692609f12f3f41b9d0f30bf2
748b2903c786e5be9783188f3dd405ae23e4853d
112720 F20101106_AABIBM kuehmeier_j_Page_38.jp2
f9d49a19a9aa3944f0a1921dd9a42e9a
b9c17b7eb123197aa76a73a4f601067cdda8288c
261 F20101106_AABHUP kuehmeier_j_Page_56.txt
b9427dcf9e600c0fc0d28bb41aae4dc5
d692883fd62a14857539a979ac6ee0d5f7afafa0
8418 F20101106_AABIGK kuehmeier_j_Page_33thm.jpg
6726ef151b8716dd0ef8cd94295f9ea6
3ea5d4591f05b778b198e04e43a7a0a3fabc1bef
F20101106_AABHZN kuehmeier_j_Page_12.tif
17301643c6b6b08e73849eb670028f61
484cc59896d05d5b52ce3a478d6d5cca39d930c5
2049 F20101106_AABIBN kuehmeier_j_Page_42.txt
ab76a8d9c8e79b39202fe1c1720f4f9b
88a3bef70bece6c94a8b499a25036baa80c05117
38021 F20101106_AABHUQ kuehmeier_j_Page_23.pro
256e93dbc8e0bd4a59415282c982cbb1
ee4c6de42bd34e434776972b70f51bad225b32cd
1563 F20101106_AABIGL kuehmeier_j_Page_46.txt
b36192a644f8fb75d97d43e8745c5d74
3b196c8e98d7b2d671f99a83b10f16d94d2bba69
61836 F20101106_AABHZO kuehmeier_j_Page_17.pro
fd1adb00c7f6acc50ca9bc7d71d1033a
e6d765b828f629df623d37ac59a5369bd0854a92
F20101106_AABIBO kuehmeier_j_Page_55.tif
0d0a9734e1eaae7aafb1a3e2acbeffbd
3c5ff32aa0145d1735a9e0e39f2e97537a0d81ba
54491 F20101106_AABHUR kuehmeier_j_Page_26.pro
51945d72071f9fb01ed82e0b3afc6820
822a792aa8ce15d9ab8607e78f5974305574e1b3
31884 F20101106_AABIGM kuehmeier_j_Page_15.QC.jpg
d559b0c4f546a10349520c78c2bf2793
a500fc002b039ebcd0e750021ec60ad6d8864e92
2457 F20101106_AABHZP kuehmeier_j_Page_36.txt
d1073c50649c1e03f7940e0d5ef70cbd
4e67d15f9c775fb2415d274ee2e07aec95320b37
107474 F20101106_AABIBP kuehmeier_j_Page_19.jpg
1c2bf469d7b0f9fc41dce8c6811db3bc
41e38f773aaa2087b8ecade84375146986c29e70
8600 F20101106_AABHUS kuehmeier_j_Page_49thm.jpg
47aef2ec0258f84ba14e81f5fad217cf
6813a949535b10b4edc6ff4b113a0fefa480fc11
1005 F20101106_AABIGN kuehmeier_j_Page_59.txt
5bc4e02728bade3aa5d53217e07f8c5e
3d931ba503b03fc0120a1ab0de05ad088cd1cebf
115212 F20101106_AABHZQ kuehmeier_j_Page_25.jpg
240a17d46b1aa80798fae7e600932907
53e6ec8929ce9fb2b92f18f4ba53b196194ffbb3
34568 F20101106_AABIBQ kuehmeier_j_Page_23.QC.jpg
541accf3c83d64154cad1ae0af30e5bc
336ad633d7c0121d91168589e0bc7fdb04ab9f93
105246 F20101106_AABHUT kuehmeier_j_Page_44.jpg
da358906bd19414b4abf84e0252c080d
8785802b245b475e5344aa19e667f54e04532286
1557 F20101106_AABIGO kuehmeier_j_Page_23.txt
e293777f95c597a059935d9a5163a98f
8abac0af6259c4163805af502c65adc8c54160c6
1034451 F20101106_AABHZR kuehmeier_j_Page_35.jp2
48b2e8fa19c213c39e2f6b27d324f9a9
dadfc13bd78cfd37bb85bb838481386192f658be
109980 F20101106_AABIBR kuehmeier_j_Page_44.jp2
f3f06b11694fba93455bfcb5c63e06a1
0157d3aa536eff43a107b1efb0e245c3339c7bad
F20101106_AABHUU kuehmeier_j_Page_33.tif
31cce3ae50624cb8d21233d431a611c0
9c02a8d9f5657a1161e63b77865073695c168ca6
F20101106_AABIGP kuehmeier_j_Page_01.tif
fd2fa84f627a9d5b5594819de1e750c6
1489140d211a4acd271bae358c9204150d94a786
F20101106_AABHZS kuehmeier_j_Page_03.tif
774d50b3e44adbe0707785aaf42f6af5
029d213dd47ac94672480d77ef1839a36e2c8883
51439 F20101106_AABIBS kuehmeier_j_Page_11.pro
92defe7a276d9253a64370edeef34ebc
09d0ca7ba53ad954241dbf0fa823c4859c1a3fbb
122786 F20101106_AABHUV kuehmeier_j_Page_16.jp2
989655c491688543f3030be202253f5d
80bd01a8ddc95ed38a61a5f4bd3deb58948c8804
74364 F20101106_AABIGQ kuehmeier_j_Page_22.jpg
0fb1c027d192fc22180abaf9ed1943db
3d1f0abb0eea21af1bce9dcc16302357590866d5
1056475 F20101106_AABHZT kuehmeier_j.pdf
212b0d9586caf7aab784632b0d472327
e145cb28d68ac98557b04ad73d10fbd52c47dfeb
F20101106_AABIBT kuehmeier_j_Page_34.tif
8e9c9398d5dc074e51a4b5285f2c54fb
2060655ee8e5af9d7ef80e9a391783624d8d2875
123730 F20101106_AABHUW kuehmeier_j_Page_17.jpg
31fb5d1e3000e2680e8f6764be3ca652
687f083c741bbe8bae6d22e7eef51c21f3be0a9b
115301 F20101106_AABIGR kuehmeier_j_Page_32.jpg
21716a37ff416f9aca4b06c99b0ebc2f
27a2e879a2acf9a3f64d32bae42aec2e8e8cce7a
1051827 F20101106_AABHZU kuehmeier_j_Page_47.jp2
8d3ce60b5905c5d666af081733d2d071
801e5ea0d591834bae51460fd428ec449b1814e1
1844 F20101106_AABIBU kuehmeier_j_Page_55.txt
5f2313490b478798d527b346bb7c9bcf
0120c6e975662f4ba0f145e91acdbe66da9f8437
F20101106_AABHUX kuehmeier_j_Page_31.tif
10d9f2ff23a5d35833357e8e5fede26c
6407d26f138d70a8dd1c07c15ca4565c5e80445c
F20101106_AABHZV kuehmeier_j_Page_27.tif
ede8a6664c522b5d8be6759c2b0b3a1e
b9ac4e80177f57db8da766bcdd52bd9a984cca01
F20101106_AABIBV kuehmeier_j_Page_48.tif
acdf1226a36c1b0c37b292aa07b140e8
c20567e4bc2944cb05aff58c13705bde7a226d53
28372 F20101106_AABIGS kuehmeier_j_Page_58.pro
f657ace6ec6289177a0cf49b23f7b626
492c4ef60cdbc8ff5e974f834ec848b9b6dcd0f0
1870 F20101106_AABHZW kuehmeier_j_Page_51.txt
a2729857f629aba0cbd68c1250afc20f
4638dba8f3419301fe4fbad1af38a3cbc46a30be
F20101106_AABIBW kuehmeier_j_Page_11.tif
dc737a4866725338c7361d872ef117fc
b031f268a4655d96d0d264a7344d4801481d4107
7149 F20101106_AABHUY kuehmeier_j_Page_55thm.jpg
8f258d49c3e37b1274a82d16350eb23c
86bbb185ae0bcd827923a176ee2da91e3229a4fa
53484 F20101106_AABIGT kuehmeier_j_Page_19.pro
602ccdc695ff896e327a9859fc9c1bee
7f70d4da50b47f7d01b0e967554671931d23e472
34807 F20101106_AABHZX kuehmeier_j_Page_44.QC.jpg
66f913e7ced265eb9983fb7bd6d3bdb7
6b553023a6b257c352f4dfa59b2bd90dc6709703
4412 F20101106_AABIBX kuehmeier_j_Page_14.pro
5a81d47c92be6a4b758dc0c060408e97
d1a32e435948061d0ea71af3f124b5efe0701861
48436 F20101106_AABHUZ kuehmeier_j_Page_40.pro
2beff1034cc163a65d617bc82f4d170e
9fe61a5812bc0fad5712c4a176dfce0327ee2851
1051981 F20101106_AABIGU kuehmeier_j_Page_06.jp2
6b71d7bae016a1290b55da2ad0885987
52be136ca8f8ff7df629ea0bb5082ec13293aca6
49151 F20101106_AABHZY kuehmeier_j_Page_50.pro
451d5fbab164a06c5d0bbc70a878e841
794fbabcbdc3d5d54628fa9e4612b84823d016af
F20101106_AABIBY kuehmeier_j_Page_50.tif
810cd4127601cebed32ee8fb60adb3ba
e811f29ca123f8bfd20fcd981df426541ae770b4
122119 F20101106_AABIGV kuehmeier_j_Page_34.jp2
9bae7a7aab31b5d6f72fde002cb5b1de
ccbd783388475d76daaf67680088b53c08f3cd4d
109194 F20101106_AABHZZ kuehmeier_j_Page_39.jpg
a66ef0bdf26fdd3533f97637d853e94e
70e0bc713c4ce9b768e6c6cbc830ce5839ef76ec
57375 F20101106_AABIBZ kuehmeier_j_Page_16.pro
436fc26b0c5674aad1db4255c600690b
e350bbfd7e85ad34b6947c72f67c4bb5814ddda2
112985 F20101106_AABIGW kuehmeier_j_Page_20.jpg
3c04e1cd930cbcb6078e0849a834cad1
8f009ae1daad778a65ee024e34ab44fee8074cb8
F20101106_AABHXA kuehmeier_j_Page_36.tif
5fde0c2424baad74c96aba8f44a8480c
d03a04137544948e7cf7ec71aeebec757968afe1
31938 F20101106_AABIGX kuehmeier_j_Page_40.QC.jpg
4dc7c74530e436fb61afee4b46a77368
99834207f99e99bb7147715923e5bac349410def
36694 F20101106_AABHXB kuehmeier_j_Page_47.QC.jpg
b1d003dcca68e3247ec71003223fe536
bf0a54faf8aafbdca6a3d0c7c838c2051f46ce18
135740 F20101106_AABIEA kuehmeier_j_Page_24.jpg
35bce04e93dec0c9fab28c71ca54e33e
232dd3a096f83129b31619dbf1d642592c8ba5c8
104936 F20101106_AABIGY kuehmeier_j_Page_49.jpg
47cc508aaf62657abcfe6762cfa1334a
4d579be9f629b173f0b16fb1e63306780405b25b
24797 F20101106_AABHXC kuehmeier_j_Page_27.QC.jpg
a6053760aa8bf81bbc63ee26ab9e58d3
ea3824ad3d425a0a7cc069b7ce732418317190fa
130345 F20101106_AABIEB kuehmeier_j_Page_17.jp2
c731494c9ec14fa42f531554694e0f70
d2b14cbc81859df216130e69d1075b15f2cfafef
39963 F20101106_AABIGZ kuehmeier_j_Page_27.pro
f7b46581881c98a0d694a33b2430bb81
fe036ec6f6f68a134b58724693b1dfc8bae304f6
69376 F20101106_AABHXD kuehmeier_j_Page_53.jpg
7f3ceac9d2071b7d700e6da3600df833
d1f97594c92e93a7bd994b4db691f09e65eda958
17327 F20101106_AABIEC kuehmeier_j_Page_59.QC.jpg
c7f228120cbd08406ed580f8fa2c4e22
b65b116147a0595043a767423f4b4f692de017b4
F20101106_AABHXE kuehmeier_j_Page_49.tif
cd8a3bacb55af0920fe412ac4e3a33f7
6bf801ba13d3a92ccb0a1c3b11c13e8fbe340dfc
38040 F20101106_AABIJA kuehmeier_j_Page_17.QC.jpg
cabe73f684a47cf8438740d1cfee4279
a76cbf881fdf361f0b9b5ee54f703864334f1302
121524 F20101106_AABIED kuehmeier_j_Page_54.jp2
5171332fe145daa11c0056070be34d4b
b2ff8459dfb6f1f0da22d8cd965db818d4419bd2
27706 F20101106_AABHXF kuehmeier_j_Page_30.pro
009229f6866bbd4bb24166e1c25a016d
9a084feb5dbdc5cd4660671281e712f17695b6a9
8596 F20101106_AABIJB kuehmeier_j_Page_32thm.jpg
10ed383f91dc48ed2295d6a894e566e9
5e5c1269181f037f7ea2051789949559534e0dff
15987 F20101106_AABIEE kuehmeier_j_Page_41.pro
72ba42981890d65e90fe9f514842d4f3
cbc3f448ec8b1ea5798f84d1ab7ec73db6ac43d0
126540 F20101106_AABHXG kuehmeier_j_Page_36.jp2
e603d33d4bf37409e7925286db9f4a0c
8d14c4d656bb59472d5d41b71385eac4030841a1
33309 F20101106_AABIJC kuehmeier_j_Page_43.QC.jpg
cbbe34b1a629485c836d505302727118
dd75e9a501b22799a8d999d4502cdb876d3db39e
108331 F20101106_AABIEF kuehmeier_j_Page_42.jp2
7774635da752258afdcc72309a5fb215
fce8633de4324530c876db21959a1d3d03e4b4f8
112096 F20101106_AABHXH kuehmeier_j_Page_46.jpg
a578780a689d6bdab55f2dd3a301cbc7
5e7437625ef425c2eab331a2d95483aa7d4f5aef
6880 F20101106_AABIJD kuehmeier_j_Page_10thm.jpg
070c36a17307512eae82c72bdbda7e6e
068bf9cfca6468cd2a661d0b642abc9f926746ad
2170 F20101106_AABIEG kuehmeier_j_Page_20.txt
438ac9646f3ec31c0e33307dda7677ce
c61d8897a7e1d84d3d0f238042010c086212b0c7
35765 F20101106_AABHXI kuehmeier_j_Page_46.QC.jpg
cf9398e1baa434a2d8d1da2f6e154230
1d281fef120cf434ecc65d678fddb66d10de53d8
8524 F20101106_AABIJE kuehmeier_j_Page_38thm.jpg
4e579912a0dfbca46366d1066840d65a
e969579c59b207530499fff8902bec052d7d6808
1797 F20101106_AABHXJ kuehmeier_j_Page_09.txt
18deda5d4a5474d9662604e504c6fda5
22f413b80f6c464eba00aecc0a4606d3f28ac6b9
25638 F20101106_AABIJF kuehmeier_j_Page_31.QC.jpg
f07b45cf4716df7f0303329eb58c2b50
8a13b76e2212685d721268d1363b64aaf8f4c02b
F20101106_AABIEH kuehmeier_j_Page_19.tif
0698389d74f7a5ae0f8cff1545cb5d0b
ed93d6f2bcdd94cd9edc082b889ef4d988322f6a
2315 F20101106_AABHXK kuehmeier_j_Page_34.txt
c24d3cdfef2bfc449eb7290e1864a4c9
bc66eddeff32785eb43afbcbb76832ace9d65deb
34927 F20101106_AABIJG kuehmeier_j_Page_19.QC.jpg
cb2d209ff2313ee97882c5b7ab9e10d7
fb75f0d374cbeedc5e913f100facdc4dbc89866f
8263 F20101106_AABIEI kuehmeier_j_Page_01.QC.jpg
5a7d94abf3aa46e4194408a2b3e93a7e
9da5a5a4fd241de820332c1ee19cb2908ce2ad97
58652 F20101106_AABHXL kuehmeier_j_Page_32.pro
fafe25bf8bc82fbfdb60bd4e76a19ae8
51b2175ff01dd7e6ca5b84b8cf1260c728f92a12
5317 F20101106_AABIJH kuehmeier_j_Page_52thm.jpg
498258f7f0c8cd8c040fd74920667d23
2b6272a6c91cd9d4336415089852df316219468b
9060 F20101106_AABIEJ kuehmeier_j_Page_34thm.jpg
f3c243d690186f8cab2f6c02819dbf5a
3e660141154a5190f09ea90351579f35c48e8016
40202 F20101106_AABHXM kuehmeier_j_Page_55.pro
ddf3b2aab81c7cf4aa2b8c78c2b382c4
8d8146be2ec2b7636178600b72382e10951e3849
8419 F20101106_AABIJI kuehmeier_j_Page_43thm.jpg
45db791657d379b1bc759175f38646ad
d8c144029a9c6d58aca09fa652afa17979e46d00
106817 F20101106_AABIEK kuehmeier_j_Page_50.jp2
529c1c522f9dabca533c5b818c3a801e
4cc6d8a57854715b2a31f44b1e605bc37e0d0592
106717 F20101106_AABHXN kuehmeier_j_Page_43.jp2
4f3936e4ab651ae312bfbf4362f1b422
abec4c08365dac8c61d10fcd50bf9a221b14458c
17444 F20101106_AABIJJ kuehmeier_j_Page_35.QC.jpg
473420591e32976b7c0e40fa0cb9c175
14fc45386a657b576d8a007d7a371de241da2b45
27288 F20101106_AABIEL kuehmeier_j_Page_05.QC.jpg
b14f3714bb9f9a2622a9f7d31b0f76e6
89db1a8c5d8b58bfeefacceafac5540e1a3eda79
2081 F20101106_AABHXO kuehmeier_j_Page_37.txt
224bc8867de40d13a763d53d9a405d7a
9b579c8d338556e41b651c94c8d4b1c7e18a9898
8227 F20101106_AABIJK kuehmeier_j_Page_44thm.jpg
e17c5dac7f1682466a5511478b5133f9
3c0066fd957729c0393f36614b13371fdafd83f8
1631 F20101106_AABIEM kuehmeier_j_Page_28.txt
37b018e2b849e3601d064cc7b3fbc912
3b296fb9f04db5258042cee76b713eddf510263c
1950 F20101106_AABHXP kuehmeier_j_Page_50.txt
b0518afadae1e38a6a51f796d94db03c
1b63bb38ca0e7e0311e2a799c91086439b48e087
92005 F20101106_AABIJL UFE0022211_00001.xml FULL
52b500e593a94580e6a4d5f4939ce174
1d52046302fe4d796d0b981c6b1e15ad61da27d5
30319 F20101106_AABIEN kuehmeier_j_Page_28.QC.jpg
4cbdf8f2636c71ed24abfb4e94ec92a8
fcd080ee840b1d1c60a695b8a0d592860a1c46ab
9006 F20101106_AABHXQ kuehmeier_j_Page_48thm.jpg
619ac63d20239155c85482967442c84b
1802eaae82223a04ed85a59e08d29d0992b5604a
35495 F20101106_AABIEO kuehmeier_j_Page_39.QC.jpg
b39abec15f95fa58b225aab1142e90b7
2740830f50db7d790455613a8b44afe668dda8f1
52304 F20101106_AABHXR kuehmeier_j_Page_59.jpg
8624ebd8e8fdca7c7179502fcdba5430
e452dea812d58f53efaa22b72c0b6b7ba27abf72
7988 F20101106_AABIJM kuehmeier_j_Page_28thm.jpg
5a9e3946c47a5bd3e2c74002f525b99a
4ab69301a2393e72fecd9c68e85fd3e342088321
61202 F20101106_AABIEP kuehmeier_j_Page_08.pro
b5c0e9f28af41382015f38e5e316d6cb
467f5eddfa7598f018bbc3303478251ba30ff7c4
8716 F20101106_AABHXS kuehmeier_j_Page_39thm.jpg
f34f715e4cefba902aac1611d1451d6b
fa0655c8215742cbe5606fbe3a8d48f09c1fb9e6
7929 F20101106_AABIJN kuehmeier_j_Page_29thm.jpg
f31f98011d4e217885ab68d05af5b7fe
a6b295c0d9f19161be2e4cfa797c38c44cdc4765
123575 F20101106_AABIEQ kuehmeier_j_Page_25.jp2
baa6bbc48ab32cf3e41d9e64d13dbc25
7328355c75fd6e28ebbc6488ba0d529b84164a25
1516 F20101106_AABHXT kuehmeier_j_Page_07thm.jpg
602998d591331ea2ea1c9c5b199f786a
123096005f15c41b448e49ba9fed9a773cf18579
32898 F20101106_AABIJO kuehmeier_j_Page_50.QC.jpg
69a5e3717075b2b8c7ee70a43e49c772
c5e161bbcba4be4cd6d0a694488659ed5035ee18
33730 F20101106_AABIER kuehmeier_j_Page_18.QC.jpg
7f788f7323eb8c20ed9da207b7fac6cc
a9ba466bbd32649c6eb222a86e672d5c87318f8c
F20101106_AABHXU kuehmeier_j_Page_13.tif
430f68d0101e44ba59b407dba441810b
b2fe32478bac4f11e7227dcee3b10241d1ceb9dc
8301 F20101106_AABIJP kuehmeier_j_Page_50thm.jpg
a81bebc53be3c4f88521944e649988a4
927ede10650477b0796284eee97863cdcb868d3c
1176 F20101106_AABIES kuehmeier_j_Page_58.txt
4759daff3ce0d50bf4bf71b734e717ab
e72f2da6d58bbcae3b3b61586b3f170d2c1962d0
F20101106_AABHXV kuehmeier_j_Page_58.tif
63725a0b80850999bf5420a6d01edea5
9a0be7707ff33ac4be75a1fa7533eee57a9ff37c
22874 F20101106_AABIJQ kuehmeier_j_Page_53.QC.jpg
ae8055423817d5a5a40be1da8cd0fc08
859e64c92adc9871515caafcb7ac1782812f41c0
101129 F20101106_AABIET kuehmeier_j_Page_37.jpg
440839f4b53f8be35b0825fa86454155
15cd8052187c3180788d6e63ee4b3adc67abaf45
44787 F20101106_AABHXW kuehmeier_j_Page_51.pro
2a34d04ea7b3274b8bd660c4614fdc5a
530f1be1687d7313bc38a8f7f1f9da30b38db667
1051963 F20101106_AABIEU kuehmeier_j_Page_46.jp2
fb494c7f23790f76ed1d750400e4ab86
62b7fad675ede46fa7511a670e5a50d621733e69
F20101106_AABHXX kuehmeier_j_Page_22.tif
e6a85024a70631864e9fe138852d3cc4
a1a018beeae38b7ad066452eddb833fb5c401487
2666 F20101106_AABIEV kuehmeier_j_Page_33.txt
2633c48dcfc1f622ec7bb34e4390aaff
3dd934ffec4c71616ce6c2b83ec2ab10e133d474
13192 F20101106_AABHXY kuehmeier_j_Page_35.pro
53912199547aee302d31535919247c6d
99a9907a923504e38d5195b295859b2f91d30294
1978 F20101106_AABIEW kuehmeier_j_Page_15.txt
bcaf2506256008b912b3fa6eb0329a28
341db5eba4ce663cbde5fd085215ee1c47ed665b
15489 F20101106_AABHVA kuehmeier_j_Page_04.pro
dc68b04a6c6dd8c6e5569b8eca916a35
c9b2fef6169b021b155210933d3458045484c36c
2142 F20101106_AABHXZ kuehmeier_j_Page_26.txt
c7ab97074d6aaac5f96bd74d958f9374
f633938b6b0f3b778098e9ddf419e4175b24f14c
F20101106_AABIEX kuehmeier_j_Page_15.tif
c4772b50e8aad0d014fe2d2b035ca672
132010643c07ef4b8ddeea7ce769c92ffde234d2
8210 F20101106_AABHVB kuehmeier_j_Page_42thm.jpg
1adb1b3f3a325f3f1ae0a2babff76606
22d3a1438f3d7efac730fab9b732cfdb161a3eb3
10478 F20101106_AABICA kuehmeier_j_Page_24thm.jpg
e6fc92d4fbbc32f1c1ae2deac54242f6
fb4d1817883ba33f21f42a5626a8e8fe4c648f95
15717 F20101106_AABIEY kuehmeier_j_Page_07.jpg
4e93ed103071c3977cf79ecac1a19e82
9601539f954a79ecd51289ab660c6dc346aba997
F20101106_AABHVC kuehmeier_j_Page_49.txt
8356d034c06481554f7501a03b570fe3
2be58be574468fa81b81fb8a3cbe984030e939f2
1051927 F20101106_AABICB kuehmeier_j_Page_57.jp2
9976c9d2b145077485e006c8d40e11e0
674db36b85a567c239ea4d566f2ff0814de45379
52773 F20101106_AABIEZ kuehmeier_j_Page_39.pro
eebbe939f2dd39c6079629c2766995b9
b36ce698c8a0d4d887be7a4f3afa933f6bdb19dd
30628 F20101106_AABHVD kuehmeier_j_Page_37.QC.jpg
c0ffd7b8eadf9516757aac8f2c725e11
64105236a70972867fdca51c696bff96e7f08136
993 F20101106_AABHVE kuehmeier_j_Page_02.pro
ca61bed828eaa6be9d9c6e097993f692
094fd64cd357cf332b205b0b2ce7c99d85937194
2146 F20101106_AABICC kuehmeier_j_Page_12.txt
cb32fcce7bb938c86b298aca72773aab
6bdd12902d8aaf44f6b7c4974ceaf0488f5b0988
F20101106_AABHVF kuehmeier_j_Page_11.txt
c6608684b972ce106ef512c24c0c7876
9e25dabbbfb0d5c820e045fb0ba07e4080bdcc4f
F20101106_AABIHA kuehmeier_j_Page_09.tif
363051f1efa473dc8adacb24287b7b2e
f956c413a67b8bb898e348d1dee2aeecfd13deb3
9201 F20101106_AABICD kuehmeier_j_Page_17thm.jpg
b188275c2c1494152783dd0d85435f68
7fcd615fdcad74e43fa5f1892525f21617e42986
F20101106_AABHVG kuehmeier_j_Page_43.tif
57920bd4290533a7d209f669dd4bd269
7ca2a30524fdb4b101170b03d5923a565f9fcc1d
F20101106_AABIHB kuehmeier_j_Page_46.tif
63fcabfa12b1ae9fb62b878452475162
45a7b9fa7c931cf23dfcf65bd9962a36290af0a0
8866 F20101106_AABICE kuehmeier_j_Page_16thm.jpg
3288e0b03964415251f55e2cd84ba122
f620fafc9003cdb652275e34204e61ff7966fd9e
80482 F20101106_AABHVH kuehmeier_j_Page_31.jpg
f2099153029f5c604a965b68b42ca508
6ac54cc48c3dcbe11fcd674deb2a5f09a3a7bb2a
8485 F20101106_AABIHC kuehmeier_j_Page_23thm.jpg
7874f518af9cb5ba9269db13a1deb7f3
06e5b1409643b786ff709f8b8c6cfe10498023b9
28254 F20101106_AABHVI kuehmeier_j_Page_22.pro
fd34b6e15ca381c476b5f9c8d34d32a8
3801ec056e3dfa693f31cc39ca899ce77aac2925
93499 F20101106_AABIHD kuehmeier_j_Page_10.jp2
f001efecbcfd37f05fc6f2cf4b2b4ccd
da835a46c852d76a993cafd1e9a15f771099c957
4126 F20101106_AABICF kuehmeier_j_Page_03.pro
bf3a16be9cdfa4490f08bad2a70ed520
b54ea999c67ea29f79ee68e95ce17cf3368c5ce5
583 F20101106_AABHVJ kuehmeier_j_Page_35.txt
60f3c40ff42d851c3a375f09fed81cea
d5071825d6bf8e89f7e406e58d47b61834e8f0f9
107779 F20101106_AABIHE kuehmeier_j_Page_21.jpg
5cebcdc39a117ef0ddba199d1c1575ed
6a577d07a97e53fc993bd612da68820f224841e8
F20101106_AABICG kuehmeier_j_Page_48.txt
53d728a84e988fca5e2ea17a31c5e967
d49ed03d49c8302a8fd70e606ec060985ea1d90e
1209 F20101106_AABHVK kuehmeier_j_Page_03thm.jpg
501229d36acbb1d8ea4b926adba69000
c59f9bb3375f980a1a2ae5e50f295734e1bb1a93
790863 F20101106_AABIHF kuehmeier_j_Page_22.jp2
09d6971b758faabb5b330e52049f5032
02448996ab809fd5bd8571ec4611c4b1195cc0a3
104266 F20101106_AABICH kuehmeier_j_Page_11.jpg
089b36a64fd7cb10268a4cd32c81a98c
fed31ef33561976a07623097fcbe2a217545a45e
20092 F20101106_AABHVL kuehmeier_j_Page_52.QC.jpg
d7340f3cee3f44a3e7cc1289af057f83
edc246bf3537296ec70b34b435a87c5cba91f400
7737 F20101106_AABIHG kuehmeier_j_Page_51thm.jpg
27f2aeb942d412b806cac5eb598a51c5
feb2fab0a6d9829926fe3070ac724b9cb22f3611
1359 F20101106_AABICI kuehmeier_j_Page_53.txt
bb898cc9f6b2e97eb912cb3ff312d1a2
e9878f6314b3b31c7acd5c2d3ea6228b93f8fdbf
38700 F20101106_AABHVM kuehmeier_j_Page_41.jp2
fad9a1697c493fc5f2ab89a81dbb0ef6
997f8d770889c98da91f67d03798012457aedd53
86005 F20101106_AABIHH kuehmeier_j_Page_09.jpg
5151641138d6a7a93b01c84e1469d8e2
1cee266491fc5fea2d318e024ba3405c00fcb2dc
9156 F20101106_AABICJ kuehmeier_j_Page_57thm.jpg
9a03efe8740ea3799b71d1d2a9cfda18
19e9177c0a7af7d7aa40f993bef527843ad83a67
2147 F20101106_AABHVN kuehmeier_j_Page_38.txt
00383a63f0144e6c005a197d046e7e9b
dc7d320f38e0beaa57d08fbfe6c555fa5d671116
71361 F20101106_AABIHI UFE0022211_00001.mets
7e0f37031ba9081a89992d70c71b92da
2b1c1e1395d2f4ecdcdeecbad6ca4cdec7d307d1
34681 F20101106_AABICK kuehmeier_j_Page_13.QC.jpg
4ed64600581d1b384ac0b77455178e04
00e0125430e74d5ab6394ad1f19a6fdc8cb1de75
27252 F20101106_AABHVO kuehmeier_j_Page_18.pro
69aba9b1d8617aabb0956e6b774dbff4
786d77fe26e8ad3c5ad0b50c09e09e059fc62cfd
53265 F20101106_AABICL kuehmeier_j_Page_21.pro
061a125a6ab759add0994fd99be6fe4c
a0c66fabdee2d8b3d7da5e0075fd34d2c7a77a09
65283 F20101106_AABHVP kuehmeier_j_Page_33.pro
5d58468fe223adc014840d97f10d5793
88637cce0099c95f632283835fd5fa5fcdcafefd
2108 F20101106_AABICM kuehmeier_j_Page_21.txt
fee1fb61b9b322895fee89956d18e03e
fbfcd86d02222e7a5a83badc6cc5ff0c29c270e1
8173 F20101106_AABHVQ kuehmeier_j_Page_07.pro
5fdda64e0aafbbc3f65df95908827502
e03402357b53f4a7ffe76ca3d4321efcca2a43c3
1104 F20101106_AABICN kuehmeier_j_Page_30.txt
1aedbe849e060ee898c9a4ddf942b4f4
1f2e71c92bdaeab7b93c843b34cf66656ac62045
10733 F20101106_AABHVR kuehmeier_j_Page_04.QC.jpg
7a852b4c4b701545c6804d6958c53221
78f7db5cb7774961ac92abd89e4e02dfdb4d3fd9
4020 F20101106_AABIHL kuehmeier_j_Page_02.jpg
a35c5061713e493ffa0ccfa83dadb4fc
fc54d8d110c90ce3b17ed551a17f9564df4cde1d
1051986 F20101106_AABICO kuehmeier_j_Page_05.jp2
4bfc09d85ca0e0eabeb82912cbd90043
6acf920552a5706e68ad95bd8454247cad5dcf19
27202 F20101106_AABHVS kuehmeier_j_Page_09.QC.jpg
b1546d988178286fa3b1d39e73da710e
3e1112e147cd28093f4c484cd56eb184307c0a5c
119712 F20101106_AABIHM kuehmeier_j_Page_05.jpg
dbef9178b75bf93b50d3ca4cb480e371
1cb51483f62b18fe85c93ca27e49426edd2f7584
12359 F20101106_AABICP kuehmeier_j_Page_41.QC.jpg
b27aa241ac51014f8577f523582e9010
8f00c73cd708aeb64267bd1e7e32e0d4dea5442d
4431 F20101106_AABHVT kuehmeier_j_Page_14.QC.jpg
f01a5ace42cefbf9363f6915dc3dc3f6
c3bbcefab750609d2ce47115aab577ba7590a7bc
106431 F20101106_AABIHN kuehmeier_j_Page_12.jpg
3f8e4b95b472040598d6680d74ce54d0
7c7bcb13343a77d008ad6a59898f7a4488b91491
99623 F20101106_AABICQ kuehmeier_j_Page_15.jpg
77689df9ca8760f8a503a24a529d6906
f45c8eca966979e50a8ee3b3e272df64a80a2d2f
30007 F20101106_AABHVU kuehmeier_j_Page_30.QC.jpg
0e83e1cc38f5f5844da43f74d5d7d249
0f38143e8fc9a87c7f335b03df14489899333608
80351 F20101106_AABIHO kuehmeier_j_Page_27.jpg
53cfe857d62cd84e1e82b5bf58ce8956
983c623c73f36801587c84a8c08d3140a6b9a0b9
132860 F20101106_AABICR kuehmeier_j_Page_33.jp2
1b5248eab6683a4b98d672f1a2122594
1d8913a057027443b802399064f288ad685668e6
36706 F20101106_AABHVV kuehmeier_j_Page_46.pro
a166c4207ec10d4c87095e8bfb4c5474
4fd7a7f5b7de92e535c968ac2b06b873a770a464
90905 F20101106_AABIHP kuehmeier_j_Page_28.jpg
5c6987b3398a23d997c74d8ad7426fb1
45067c9ad0196a81345a3aa9e85500765901edf5
57945 F20101106_AABICS kuehmeier_j_Page_25.pro
7be115c5c77c2a202a14008cbbb5fc77
af55e0767e148136ed859a9760071790016e8119
38405 F20101106_AABHVW kuehmeier_j_Page_24.QC.jpg
e7a79bed91b49344bca53d7d8d6ff7de
b3e8b98b106b4b522d37a327473d54a94ce25833
105853 F20101106_AABIHQ kuehmeier_j_Page_38.jpg
17b4b53d8135cf9e85c951ac3899aba3
2dcc91ad6337ca53fa121c7abe9b79518858a7aa
F20101106_AABICT kuehmeier_j_Page_37.tif
2a1be14831d3bc134fe85fbd8c47a17d
54b3a3805b16d329eaab8e7581dbc01f4558b5b0
36024 F20101106_AABIHR kuehmeier_j_Page_41.jpg
8b450b20d11b82fc1239e7a674e9488c
7a3b79d874b191ab7ce1954ddee5fde9cc089700
F20101106_AABICU kuehmeier_j_Page_06.tif
4f9e304e75f0021bd547d25a521fd466
41ef360ae8ea7d7b372645e470619fde70f673a6
36642 F20101106_AABHVX kuehmeier_j_Page_16.QC.jpg
5c3a915968e7e2d77297f666774b08e7
a48ac12c360fb11284c5d64034db1a83d3f57f15
16517 F20101106_AABIHS kuehmeier_j_Page_56.jpg
30e6acd935f19000ee879e7fc6b78e78
f4e5754419e4a225ee4185dd080935d7c105313e
8631 F20101106_AABICV kuehmeier_j_Page_19thm.jpg
8b5da39816932a61c545a8725771bd87
6d92d6e4ef01d7a9fb6b4dba7083d482014d56dd
F20101106_AABHVY kuehmeier_j_Page_07.tif
95c9868f6997fd7556be8f796c6f1516
984115bbd512bdfe16083b1c260588985092e07c
1051932 F20101106_AABIHT kuehmeier_j_Page_18.jp2
4ac4cbfc658fe8a36f7161d067e71f8e
1c1f5a331f9661f31bde77e5207648969489893d
34225 F20101106_AABICW kuehmeier_j_Page_38.QC.jpg
5f55ff57286cebe02817adfdccca2ece
2ce5c2db54f5fc3df430c16037a385e0a71da668
113333 F20101106_AABIHU kuehmeier_j_Page_19.jp2
08a24f97162382ba0ebac18a3277b036
07a78f138a80d3951980cff22d454edb91f728e4
32790 F20101106_AABICX kuehmeier_j_Page_08.QC.jpg
6d2bd31f63ed054646116fcd0294c2e9
da3e3c64115b798169592f694b5dcb91246f7270
1349 F20101106_AABHVZ kuehmeier_j_Page_24.txt
a142ab3280522e5f6c15c803e3ae0331
a8f4af2fc74877fd95651c2120623f968936392b
1051954 F20101106_AABIHV kuehmeier_j_Page_24.jp2
9bdf94934ac517e33453d836999e3cd7
7f07026b4f137d905d5e21cee349849570322006
5886 F20101106_AABIAA kuehmeier_j_Page_56.QC.jpg
1b7a1d18e8d5dc3847232b496a4a5064
7d886204bb3f5e875ac4796b319601106e49ebcb
1685 F20101106_AABICY kuehmeier_j_Page_10.txt
1d025a21e367c8684c101db22659dbf4
47b04b2b93ce672bf477a86d589c10daed96b448
950957 F20101106_AABIHW kuehmeier_j_Page_28.jp2
9cfc41b197b0050b9f4ed64d32a3e76c
9dcc14c6540bb8e9dca116a38562e890951b373b
1479 F20101106_AABHYA kuehmeier_j_Page_02.QC.jpg
df8f9e5e6dafc4c90c53f450cb775c7d
224ef96ad4374b682c6cb3ec5f6f8de72e0965eb
21357 F20101106_AABIAB kuehmeier_j_Page_45.QC.jpg
aba12db6137bba16e292120b58a46e6c
f52a1ade63880e5931a7974398ff4ecbf94d9437
2321 F20101106_AABICZ kuehmeier_j_Page_32.txt
bd15ac718c696dd964eeaa9e146c47eb
5f115f40e4899ec29d19aec96f5488bcbb003a21
85149 F20101106_AABIHX kuehmeier_j_Page_31.jp2
75de3f9005a9f3b7de3fc3df3df54294
5e91b13cc26864f40615b9d04691792f6d787d1d
1981 F20101106_AABHYB kuehmeier_j_Page_43.txt
a40887062c6665486781b27985214b71
f2077c64912f866cee3858f2be418237c3b44308
71692 F20101106_AABIAC kuehmeier_j_Page_53.jp2
a75b8b50c3e89e4ae1d651394ad5acb6
b5a8b5c7e7e6b84e5bd2e1f7fd770ce6d6928d46
122613 F20101106_AABIHY kuehmeier_j_Page_32.jp2
fefd73f8592bb4d41ae601d448aeda64
a59c8efd256c85a98531c003f62cb2531db06a35
2114 F20101106_AABHYC kuehmeier_j_Page_01thm.jpg
0d81d2b49db5c710c1003f2b462b64df
a165165c7359d6f2f9f57ba772a4b3d313234f4e
39832 F20101106_AABIFA kuehmeier_j_Page_29.pro
83068a5c9ee76c11e3dfd3a9dc6ef465
05eee84761840cd957127bea609ba884cb8d4586
118723 F20101106_AABIHZ kuehmeier_j_Page_48.jp2
0e45ca4b208d23582a459913a7da7b14
f2f2dcd6e7eed8a6a0d0b58da15158e63b9b40c2
F20101106_AABHYD kuehmeier_j_Page_57.tif
8aa173a7ac0ed246628f4c2144955bda
902bc55b9c86ed81420964172b3f5db3bf645f4b
110815 F20101106_AABIAD kuehmeier_j_Page_23.jpg
de92d630b2bd30a0204216e3c488a2e0
d364a5e499c9150a07e2b9f9379a4b9bf2ce0079
4128 F20101106_AABIFB kuehmeier_j_Page_59thm.jpg
c07c3432a6379be176d16379b871a405
82198690d774c62701b76a221fa295eb428dbb6a
F20101106_AABHYE kuehmeier_j_Page_20.tif
d03ea4ff2ebc0fd2d8a33541fb990450
cc2422af654ac02748b9f6962ce49ee2f04bc5bb
27030 F20101106_AABIAE kuehmeier_j_Page_01.jpg
b01484b881e1c0031720d1d8fed900e1
716816be89ccb22aa8f8387bdeb60e0b91ddef2d
119244 F20101106_AABIFC kuehmeier_j_Page_20.jp2
0cc1f57e8cf8b8f6514547ed23b6e373
63f3380e51ab4eb750878b959b864ca41f5d090b
2068 F20101106_AABHYF kuehmeier_j_Page_44.txt
b5dbeb1686c2478e545f69b9bd6daf05
97e083da72e007ad0ad21a0b75f20bfbb084c056
7357 F20101106_AABIAF kuehmeier_j_Page_37thm.jpg
7c2645ca72fdd68ee7b16566b521404a
d6e57535a3c10202a22ee55e6434644ba1aa0a66
30121 F20101106_AABIFD kuehmeier_j_Page_45.pro
2b781a8642a079497ee5055be3d4f45b
7873cfd77c57516d1f400f4b87863df17764db39
109281 F20101106_AABHYG kuehmeier_j_Page_26.jpg
60bbccd62615ff801a1d55ed96888316
476f6dd366bf8713aca57cf752a5f66d0052d1ed
48858 F20101106_AABIAG kuehmeier_j_Page_49.pro
22ea8f03e9c85fd547ddedc511fa5839
b4d36a518bc40fc39b95722bd934c06ef0aff90a
8568 F20101106_AABIFE kuehmeier_j_Page_40thm.jpg
d7c666867653b565f3005070e5ea92ac
913e35b9f835df08e5a086ac1dbfed8f545c6e0f
35834 F20101106_AABHYH kuehmeier_j_Page_12.QC.jpg
853749584942c16fe3c2f498ce939a09
879c969d03763a45f7168ad1739ff9d1b4ffc0eb
F20101106_AABIAH kuehmeier_j_Page_29.tif
412cc4cb6c9d89252a207ba6bdb20ea6
da481ba7d41611eea17cd70096f033e5718aba42
114052 F20101106_AABIFF kuehmeier_j_Page_13.jp2
4ff5f9867c82acf7185658b4d4c88031
8004c77bc07da01eb7fce87b361247e839c2bf36
8815 F20101106_AABHYI kuehmeier_j_Page_26thm.jpg
ca70077f9a82160e055fac716f1fa096
b9c75880d7653e3543881a01339f6f908b2d122c
126712 F20101106_AABIAI kuehmeier_j_Page_33.jpg
cf5e99a9fb4000332d9fcecdcb4c0aa3
d678f3c7e4f1a9b622e430fb2c93a67b9c014b12
125749 F20101106_AABIFG kuehmeier_j_Page_57.jpg
a2c079f2dcdb3840ae22587d14e14ad4
29049ed1148a1c71b422360480bf517a67b72f20
10902 F20101106_AABHYJ kuehmeier_j_Page_03.jpg
2528ef01fcdc31be9225dd3f029d3c94
80cd7eab5575134de7781e792712a10b13e8cc27
120519 F20101106_AABIAJ kuehmeier_j_Page_54.jpg
d6526eb8296b95dd8b38b5e3451fa868
e2d428b70659aa535befd769668151a618798dfe
37971 F20101106_AABIFH kuehmeier_j_Page_31.pro
c1b3276a7ad1d09e0c703b4ed1dad64d
8626ead9648bf338ed77ba7bd66df9534b12839c
35345 F20101106_AABHYK kuehmeier_j_Page_33.QC.jpg
b5390074429dd343e8a44512c23228da
338f05c85ef6b621a1bd676f19748bbf196056af
59523 F20101106_AABIAK kuehmeier_j_Page_54.pro
02a031d0fb6f961b07a27e1b4c6ea3fe
4a8749d63260231c254738553624f04c9a00103d
2330 F20101106_AABHYL kuehmeier_j_Page_57.txt
dba8538611c2554db041415f505a9f13
0b41d6e90d28f00cb246d388e90687a7a1391ff4
1297 F20101106_AABIAL kuehmeier_j_Page_47.txt
cbc9311eb9ceefc5a3b988989dbd315a
395ac6f394b742f1631cbeddc151568fc0ea17b4
1051959 F20101106_AABIFI kuehmeier_j_Page_08.jp2
2736f7526d2256b530dd39da564df802
a91bfaaa54eec040f62c10c634967bb96ca8abbe
86966 F20101106_AABHYM kuehmeier_j_Page_10.jpg
80a026a1b489808d9544b9b07063c483
27f7dfdcfbebdbee64005eea310974a9f28c7fea
115286 F20101106_AABIAM kuehmeier_j_Page_26.jp2
3e556101f7bdbe9a3bbe033afebdf19c
32540cf365c51a57b047d9cdfc9863703520a840
19328 F20101106_AABHTP kuehmeier_j_Page_58.QC.jpg
de78ff616bab851ef8da2f83f2f6e664
c6403be43980b2ffcd5d30b0787e791b865f95ba
F20101106_AABIFJ kuehmeier_j_Page_04.tif
ec6b16c16a56132e4c86b66ef529b06d
b348467e11b3600e88cc918d7ac8d094fc2e2811
87472 F20101106_AABHYN kuehmeier_j_Page_30.jpg
7d61d62f56e05c774c42ed3df47c62e6
b1b24cb2c4faa75ade7a1b22da89b42b7b42fee9
1173 F20101106_AABIAN kuehmeier_j_Page_18.txt
94c36bf170a061fcfc65c6f26adb4881
7cae1591492c407cef307edd21eda1cbaaf2811e
50916 F20101106_AABHTQ kuehmeier_j_Page_44.pro
99b050d091030e8184edfdeef5810348
acf4d4e1f53515728e32b2e41b0105d095bc6f7b
87488 F20101106_AABIFK kuehmeier_j_Page_29.jpg
6667243020aba6fd76a847d37d85ef9e
3e12548ddbcd3d8fa07c20728a34457f5609dc8c
1233 F20101106_AABHYO kuehmeier_j_Page_45.txt
c0330f060e3860db3954909926c01dca
d31b705a619b3e4c07700edad462fd229f9dc6f6
101328 F20101106_AABIAO kuehmeier_j_Page_18.jpg
26d5de7e95aebb072f8f5b4439ee3fad
8da4d8a1d110a903e1a0f00211d34a3b086bb216
67655 F20101106_AABHTR kuehmeier_j_Page_58.jpg
386ea331653927e949e0713d1509faaa
33a1fa9f005a13d4864e4b4607f76ca1450de58d
643 F20101106_AABIFL kuehmeier_j_Page_41.txt
9746e937a898ca870b6988b688d4425b
d7c22e92d99317a2cb8c2560610375cbb45d62bc
51414 F20101106_AABHYP kuehmeier_j_Page_38.pro
b4baf6b53f45a22d88ae292619291fdd
1008f2337b30dbd90dca409a128fcdd67c0dfe47
49484 F20101106_AABIAP kuehmeier_j_Page_42.pro
e1583625478af4511954e2a1303cee7d
7a9f43721d38c9de87f5cc28fbe904783d4c4ea6
1051935 F20101106_AABHTS kuehmeier_j_Page_29.jp2
60ef9fd8e1264c464f74c0bf30b4931f
81960de398bc98dd5d00923047c3725127851937
54094 F20101106_AABIFM kuehmeier_j_Page_06.pro
c68e8b9f588c17623321e4486d4c534d
c3d51907c6c305172bef8ce2dfcae5ee8b778d5a
5333 F20101106_AABHYQ kuehmeier_j_Page_45thm.jpg
ec8b82e2c180a3371b976f922133d675
7dade788218843f4fa4677af0f7ae549a24bb5cd
354 F20101106_AABIAQ kuehmeier_j_Page_07.txt
42cc7e405911148e3ce87eccd2663f40
131333df994dd4f88a69b690e806f175ca943650
2284 F20101106_AABHTT kuehmeier_j_Page_25.txt
b3214931dac736f6ac7a0c220f32c0cb
1e55e19dd3f4c48e2dcb7feb88473aa307134675
9108 F20101106_AABIFN kuehmeier_j_Page_46thm.jpg
66564ce42a040fe056280016b3f31483
d951a938376ea7f22549ef239d4f01202faaf4fa
1665 F20101106_AABHYR kuehmeier_j_Page_22.txt
6593a80d7f4c791a3eb3aa7e6067640d
f42aa599bf51276b4226bffdf674e72e240285d9
F20101106_AABIAR kuehmeier_j_Page_47.tif
bacdfafb327fa286c62d8cdcc254dfa8
7e5180ba6c9748f22c76e406599cd0c8b816f7cc
29571 F20101106_AABHTU kuehmeier_j_Page_29.QC.jpg
bbca080f63d71e0b317482feb316180b
8409133270b3ebcd8f2d2a5bef59c72c2d6c5e4e
47505 F20101106_AABIFO kuehmeier_j_Page_15.pro
2678d33e66527945805c10df3527e497
b6f66325309dc9da7bdfcbba415edb0d974f9d14
912627 F20101106_AABHYS kuehmeier_j_Page_58.jp2
658bd1140bf3d0fbbbcc4099ccee6689
cdbbfa97f17a28f2a26e0e6d81524fdacdc409fc
5015 F20101106_AABIAS kuehmeier_j_Page_07.QC.jpg
824a51fa4e3124f0b279912cae6af037
1cd0865a5bae26f2d7b2733e32a3eb9c7d847d3d
7990 F20101106_AABHTV kuehmeier_j_Page_15thm.jpg
657f920eea25bcffec2f47ce077187d4
d39d41ff98ea67b0ef869c69a0956e0e73653e93
6237 F20101106_AABIFP kuehmeier_j_Page_02.jp2
d1bb165d638e41c0581d8746bf0f55a0
e28c2d88e925429f4b5144810920da63cc47ba07
51075 F20101106_AABIAT kuehmeier_j_Page_37.pro
8047df023b6d30606e556e97100cd015
f51b9a4bfe7beff2784ab43580e619f24a197153
35713 F20101106_AABHTW kuehmeier_j_Page_26.QC.jpg
c8530b216ca6773ad1c2a29094f55761
5d718dd3894fbe39ab8f5408410b8c32f18ed5fe
57815 F20101106_AABIFQ kuehmeier_j_Page_34.pro
751b8794af5513b2f4debf794f5f41a4
851f30f5e216d9ab34a0028d1804901e3031e93d
5477 F20101106_AABHYT kuehmeier_j_Page_35thm.jpg
2bb7642877342c5eab9d1db06d633b2e
f2e3a5884f9d920feae96de94de6a72e6e985874
2462 F20101106_AABIAU kuehmeier_j_Page_17.txt
8fbceaa3370a9a20c4f5f0c6183f63d9
35aa12f93e4054d27f9686e4fd5029858b0f21aa
927 F20101106_AABIFR kuehmeier_j_Page_52.txt
015a8049c8b3bafd7df0e6c044c8309a
a4f819dc26124d83c0f1b1430b28287e3c407f9f
1051983 F20101106_AABHYU kuehmeier_j_Page_21.jp2
08e6c65b70b93272ed8582feae605d33
4329e7dfa4d68eb7186e67ef46898d84de97ac53
67043 F20101106_AABIAV kuehmeier_j_Page_45.jp2
2801897c0050942ead78cf3835c26216
5ea87cc1e0cf87f7a5ad6058ae5c067977c59efa
116123 F20101106_AABHTX kuehmeier_j_Page_39.jp2
05335cf75bafeccbdc2e98940de6792f
43b2d0457f1e8338275efa3c938a71a22668c2e2
542 F20101106_AABIFS kuehmeier_j_Page_02thm.jpg
edff9f55d5572904454f31a9c199a4fe
711da745b0cba95dcae58794e6d92bdbeaf9711e
F20101106_AABHYV kuehmeier_j_Page_52.tif
2b22ba0709a0a36686f477490b260fc2
9b76c24cce1ab61b9eeae8b74fa726f4a078c67c
832226 F20101106_AABIAW kuehmeier_j_Page_27.jp2
b0745b656ae6394fc1290e852b4e55d7
600b8d2f3b9e78e9eaef73505a04f820d19abee4
F20101106_AABHTY kuehmeier_j_Page_17.tif
58059428cf872f32fde46bc377b88195
3c76aa24b3c59807b58e9689b834695284126aa6
49930 F20101106_AABIFT kuehmeier_j_Page_43.pro
03616c7214f87e5847b83361f0e0172c
b5baaea898f328187c3da9791fb6416102670e32
113853 F20101106_AABHYW kuehmeier_j_Page_12.jp2
4577e4b9c39dac4fbb3b9bb6d65bf33b
919b3d779f1d2b277b7dc2847b37cc3a90b9833b
9245 F20101106_AABIAX kuehmeier_j_Page_36thm.jpg
e9eb453061e54d2585330bb8eca9fd38
e0b23c6e71824f7bcb4b11b04f5aa880d7498f1c
8162 F20101106_AABHTZ kuehmeier_j_Page_08thm.jpg
5bb76b11a65e05553d829ffc23e4ed1e
0e6ec13b3fbdf9b5db4afa9ece942baa38ec1a8c
11886 F20101106_AABIFU kuehmeier_j_Page_14.jpg
2cfa26ef4155f756867dc1d4ff55ec2e
831cd93b237b96a7885605eb24b406e1cb1da1c3
F20101106_AABHYX kuehmeier_j_Page_10.tif
b443f018319050cda4f27b55087c8feb
8e12d944542fafe90576c601156918893f3b6e8b
8251 F20101106_AABIAY kuehmeier_j_Page_30thm.jpg
e5952aa14a940e48560d70e4d08a5cfc
f2c5a607b8eff9768ee6f27a9c45201f04ddbbac
35873 F20101106_AABIFV kuehmeier_j_Page_32.QC.jpg
1b5abd142838c17416a1b5d63a169f99
6858ed37ac91e2dae9c6a462b4c0bb2c1166a2e7
2149 F20101106_AABHYY kuehmeier_j_Page_13.txt
f3d2cc61dad06857b2d23630bcc98508
1afcf6c11b7917a44f3ad64b4bff4486149c0c32
F20101106_AABIAZ kuehmeier_j_Page_59.tif
95abc116fa4c9082e57e6d6eac00cd31
8af2ef53309801f8b8b70b29b2519fe5bb34f465
F20101106_AABIFW kuehmeier_j_Page_30.tif
4de807e74ae2511dd99b49835b0ec6b3
35646ac928794dede0f7f10b45c4c0acb4fdd21c
F20101106_AABHWA kuehmeier_j_Page_25.tif
c017a9385cb16e123eae3c52c3113fea
d46d924740ffa676c2be6d2262b52e9ec1327ecd
83256 F20101106_AABHYZ kuehmeier_j_Page_55.jpg
5782ce3523446ae770dc62c02f8e807b
f5b0cc18e075fea7f1d0832b7a053f8fbce1a50c
F20101106_AABIFX kuehmeier_j_Page_26.tif
82d94ca79b0ab803f2c1b200f903ef97
95b9e8c9ec48eec64c4458ce8e496bb5692a240b
178 F20101106_AABHWB kuehmeier_j_Page_14.txt
db9b0a14a2afa4e797ff2da6c8edbf43
f7935409bf314a8fd03209782f8aae64dc0047d9
236541 F20101106_AABIDA kuehmeier_j_Page_07.jp2
41a26088756a4e9174f2e122f867980a
a59331f9f93b96fb7e6bee7c47a088859117a579
106296 F20101106_AABIFY kuehmeier_j_Page_49.jp2
be7e62cb345cd4600f4a2ce99c276680
779284aca3ac089d877b67f7153229b28dc38bf6
10341 F20101106_AABHWC kuehmeier_j_Page_47thm.jpg
529442ff16d84dc2d9596dde38b46356
9dafee80b0346c4473693825efd3f1359514b44e
F20101106_AABIDB kuehmeier_j_Page_14.tif
dcc38ba5f8c4a35e3f80a79d7eb2dcdf
60f377b8f037d8aa575d55d09cd5f2549eeb462b
111043 F20101106_AABIFZ kuehmeier_j_Page_11.jp2
d0ed6b4573d4854ae1a6c002d8efcf7a
64fd1ff3be40a69b1b125000f926232761359642
60382 F20101106_AABHWD kuehmeier_j_Page_36.pro
5b520271f64d74683c4b2c78af980d2d
db39e31cef19f7d3ce126f373a490e7ddf61a5d0
35911 F20101106_AABIDC kuehmeier_j_Page_57.QC.jpg
9f8e390f7bc08579270de809e8c824dc
0aeab366881798f2d03d81b1da3f1106780a2e3b
7344 F20101106_AABHWE kuehmeier_j_Page_22thm.jpg
dc94abe41b169924c9c18a2c655faa8f
c016e828559be30b7649657c0c4974bc2e231892
37501 F20101106_AABIDD kuehmeier_j_Page_36.QC.jpg
464981d9789cc3cd8f7d0cb1f7cafc0d
7321d9ddda275eb39703978b24feb3bc29139817
97366 F20101106_AABHWF kuehmeier_j_Page_40.jpg
a5491cd6e87ace3ef152397484aed294
80e015eaead9496795223ff2425ce70f126e8e48
593671 F20101106_AABIIA kuehmeier_j_Page_52.jp2
92098b804f1de2bfd8560adea530bc11
a69ac2f31683b7d08ebc9be079bdb4d5315e0941
37461 F20101106_AABIDE kuehmeier_j_Page_20.QC.jpg
9dc2a38a1ed3c91fcc8e243dd39313d8
ee36733720ba7cb38d97b170d287b2c1363de063
497 F20101106_AABHWG kuehmeier_j_Page_01.txt
64ac30177cece9a0bae2a0fbca07809c
34cfa4860c6c64a885de71ccb3cc7e267de34b4d
55787 F20101106_AABIIB kuehmeier_j_Page_59.jp2
34f053f7005b1779bf9618552582b256
316830ad32211c25e2ab768165f1da84f7fff6ea
F20101106_AABIDF kuehmeier_j_Page_35.tif
3fc2846a481797a2d785a18826c955e6
7fac35d996f6a57fff601144a75d9fcf60501b04
2139 F20101106_AABHWH kuehmeier_j_Page_39.txt
217c45c2e7a29a707890b32bbdb5afe4
57517d3611286e1c9c9427a5b14b01f48afbd8ea
F20101106_AABIIC kuehmeier_j_Page_02.tif
8fa8308e1b4b2a896a8bc56894fec648
b5d6cdba68ac039ec8ff92644099221b177cfde5







BUILDING INFORMATION MODELING AND ITS IMPACT ON DESIGN AND
CONSTRUCTION FIRMS
























By

JOSEPH CARL KUEHMEIER


A THESIS PRESENTED TO THE GRADUATE SCHOOL
OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT
OF THE REQUIREMENTS FOR THE DEGREE OF
MASTER OF SCIENCE IN BUILDING CONSTRUCTION

UNIVERSITY OF FLORIDA

2008
































2008 Joseph Carl Kuehmeier































To my wife and family, for keeping me focused on the prize, and for giving me the opportunity

to better myself. To them I will be forever grateful.









ACKNOWLEDGMENTS

I would like to thank the School of Building Construction for accepting me into their

program and the faculty for passing their knowledge and life experiences to me. I would like to

thank Dr. R. Raymond Issa, Dr. Svetlana Olbina, and Dr. E. Douglas Lucas for serving as my

committee members. Their knowledge and direction were critical to the completion of my

thesis.

I would like to thank my family, for without their support, I would not be finishing school

right now. They have been the foundation and all that I have done is in honor of them and their

support.









TABLE OF CONTENTS

page

A CK N O W LED G M EN TS ......... ................. ....................... ................. .....................4

L IST O F T A B L E S ......................................... ....................................................... . 7

LIST OF FIGURES .................................. .. ..... ..... ................. .8

A B S T R A C T ............ ................... .................. .......................... ................ .. 9

CHAPTER

1 INTRODUCTION ............... ................. ........... ................................. 11

1.1 Building Inform action M odeling................................................ ............................ 12
1.2 Statem ent of Purpose ..................................................... .......... ............... 12
1.3 Objective of Study ..................................................... ............ ............... 13
1.4 Scope and Lim stations .................................... .. .......... .. ............13

2 L IT E R A TU R E R E V IE W ........................................................................ .. ....................... 15

2.1 Principles of Building Information Modeling .............. .............................................15
2.1.1 Increasing Value Through Shared Information ..................................................19
2.1.2 National Building Information Modeling Standards (NBIMS)............................20
2 .1.3 C ollab orativ e W working ................................................................ .....................2 1
2 .2 P ro d u ctiv ity .................... ... ... ... ... ........ ..................................... 2 4
2.2.1 Productivity in the Construction Industry ................................... .................26
2.2.2 Input into D esign .................. ................. .... ................ .... ...... .. ...... .... 28
2.2.4 Ten Step Program for Improving Productivity............... .......... ............... 31
2.3 Advantages and Disadvantages of BIM ........................................ ....................... 31
2.3.1 Proponents of B IM .......................................... ................... .. ......33
2.3.2 D isadvantages of B IM ........................................... ........ .... .. ............... .36

3 METHODOLOGY ............................. ...................... ........38

3 .1 P ro d u ctiv ity ................................................................................................................. 3 8
3.2 A advantages and D isadvantages ............................................... ............................. 39
3 .3 In te rv ie w s ................................................................................................................... 3 9
3 .4 P ro c e ss o f B IM ........................................................................................................... 4 0

4 IN TE R V IE W R E SU L T S ..................................................................... .... .........................42

4.1 Sm all Construction Com panies ............................................... ............................. 42
4.1.1 C construction C om pany 1 .............................................. .............................. 42
4.1.1 C construction C om pany 2 ............................................... ............................. 43
4.2 Com pany 3: Large D esign / Build Firm ........................................ ....................... 44
4.3 Com pany 4: Architectural D esign Firm ........................................ ....................... 44









5 CONCLUSIONS AND RECOMMENDATIONS...................................... ............... 46

5.1 Increasing Productivity with BIM Using Adrian's Model ...............................49
5.1.1 Making the Project Look Like a Firm Rather Than a Job: Developing a
Personnel M anagem ent Program ........................................ ........................... 49
5.1.2 Improved Communications .................. ................. .................. 49
5.1.3 Planning a Productive Site Layout ........................................ ...... ............... 49
5.1.4 Challenging the W ork Process ....................... ... .. .. ..... ........ ............50
5.1.5 Developing a Scientific Work Standard Versus an Accounting Based
Standards ......... .............. ....................................................................50
5.1.6 Planning and Scheduling ........... ..... ............ ........................ 50
5.1.7 Project Control and Productivity Improvement ...............................................50
5.1.8 Equipment Management to Enhance Productivity ...............................................51
5.1.9 Productivity Improvement through Safety .................................. ............... 51
5.1.10 Productivity through Attention to Quality ....................................... ............... 51
5.2 C onclu sion ..................................................................... ....................... 5 1
5.3 R ecom m endations...... .......... ...................................... .. .... ........ ........ .. 51

APPENDIX

A LIST OF TERMINOLOGY AND ABBREVIATIONS................................................. 53

B INTERVIEW QUESTIONS AND ANSWERS .......................................... ............... 54

L IS T O F R E F E R E N C E S .................................................................................... .....................57

B IO G R A PH IC A L SK E T C H .............................................................................. .....................59









LIST OF TABLES


Table page

2-1 Productivity increases for various industries (2002)................................... .................27

2-2 Reasons for nonproductive time in the construction industry .............................................27









LIST OF FIGURES


Figure page

2-1 Relationship of a BIM to all facets of the AEC industry. Courtesy of NBIMS
A E dg ar 2 006 ........................................................... ................. 18

2-2 Combining multiple models into a composite model (Contractors Guide to BIM 2006)......22

2-3 A section of the BIM model for One Island East tower in Hong Kong, Gehry
Technologies' (The Architects Newspaper 2006) .................................. ............... 23

2-4 Frank Gehry's Stata Center located at the Massachusetts Institute of Technology (MIT).
Image courtesy of 2006 http://philip.greenspun.com/copyright/ ...............................24

2-5 Distribution of construction company size by number of employees, 1996. (Dr. E.
Douglas Lucas, 2008) ................................... ..... .. ...... .. ............28

2-6 Analysis of productive and non productive time during a typical construction project
(A drian 2004) .............. ............................................ .................. 29

2-7 Reciprocal relationships between various parties involved in the design process and the
B IM proj ect ............... ............. ........................... ..............................30

2-8 Computer modeling to analyze air temperature distribution to determine the benefits of
displacement ventilation in the courtroom lobby (Google image 2007) .........................35

2-9 The Pearl River Tower includes integrated wind turbines and photovoltaic panels to
offset its energy use. (Fortm eyer 2008) ........................................ ......................... 35

5-1 A 3D polygon model and 2D lines and text compose a set of integrated construction
documents. Images courtesy FacilityGenetics (NIBS 2006) ........................................46

5-2 Virtual construction documents and installation photograph. Images courtesy
FacilityGenetics, LLC and Ghafari Associates (NIBS 2006)................ ..................47

5-3 Installation process and equipment requirement. Accurate steel sizes, members, weight
and cost. Images courtesy Kling (NIBS 2006). ..................................... ...............47

5-4 Section details from Revit Tutorial (Revit 2008). ...................................... ............... 52









Abstract of Thesis Presented to the Graduate School
of the University of Florida in Partial Fulfillment of the
Requirements for the Master of Science in Building Construction

BUILDING INFORMATION MODELING (BIM) AND ITS POTENTIAL IMPACT ON
SMALL CONSTRUCTION FIRMS

By

Joseph Carl Kuehmeier

May 2008

Chair: R. Raymond Issa
Cochair: Svetlana Olbina
Major: Building Construction

The Construction industry is a business focused around providing a product through the

traditional construction process, which remains for the most part, independent of the design

process. With the growing changes in technology, many areas of production and business

(outside of construction) are being refined and redefined, leaving the construction industry

behind. Process of construction is still basically the same as it was hundreds of years before,

from a set of drawings, a building in erected. For the most part, these drawings are never

without errors and omissions, causing many delays, multiple change order items, and late

projects completion.

With the advent of Building Information Modeling (BIM) software, the

Designer/Architect is given the opportunity to design the building, and the software develops the

appropriate plans and sections needed for construction. This is good for the designers because

the project is completed in 3-D and most, if not all conflicts can be resolved before construction

begins. These are just the initial benefits that BIM can potentially help the design and

construction industry.









Design/Build firms can be extremely efficient because they house both the designers

(Architects and Engineers) and the Construction Management professionals; however they still

operate with the same flawed system of designers generating construction drawings and the

construction team erecting the building. More advancements can be made to increase

productivity in construction, reduce requests for information, eliminate coordination problems,

decrease construction time, and increase quality. The BIM Software is the gateway to solving

these issues.

With dynamically linked on demand modeling, changes can be made by Designers in a

remote location that would update digital construction drawings at the jobsite. Project managers

on site can propose changes to the design team with no delay time. Means of construction can be

displayed in 4-Dimensions for an increased understanding of construction sequencing by the

contractor on site. Any and all questions can then be answered immediately and virtually from

any location.

Understanding the potential that BIM software has to offer and implementing it into the

construction industry can be the next great advance since the advent of power tools and

equipment, however this innovation has many issues that need to be resolved before

implementation of the software would be generally accepted. Once done, its full integration to

improve productivity for the AEC industry will be significant. This change over will be market

driven by the owners of projects and come at a large initial cost for all construction companies,

large and small.









CHAPTER 1
INTRODUCTION

Construction is a labor intensive industry that has remained relatively unchanged for

hundreds of years. Traditionally, a construction project, consisting of drawings and

specifications, is delivered by architects and engineers to the owners/clients of the proposed

project, with a warranty that the design is complete and free of any defects. Owners then put the

project up for bid among a selected list of contractors; the lowest bid typically being awarded the

job. Once the construction documents are in the possession of the general contractor and

construction begins, the relationship between general contractors, architects and engineers also

begins. This relationship tends to be typically limited and distant. Any changes or discrepancies

that occur in the drawings are corrected, typically, by a long trail of paperwork, for a contractual

period of time per each request for information (RFI). This can stifle productivity on the job site

because of trades waiting for pertinent information, and it can decrease morale among crew

members, which also decreases productivity.

Over the years, there have been many technological advances for architects, engineers

and contractors. Architects and engineers are constantly updated with the most advanced

computer programs to help in all aspects of their specific profession. Contractors have relied on

large construction equipment to perform tasks, and computer programs to help in the estimating

and scheduling process for construction, both of which are integral in determining whether on

not a construction project will be profitable and if the construction company will continue to stay

in business. There have been numerous advances in technology between the two sides of the

industry, Architects/Engineers (A/E) and Contractors, but when information is exchanged

between the two, it is continually done on paper in a 2-Dimensional (2D) representation.









This is an inherent problem between the A/E, and Contractors; the problem being that

Architects take a 3-Dimensional (3D) image in their mind and, to the best of their ability, relate

that information in 2D drawings on paper. Drawings are then realized in physical form by the

general contractor, based on their ability to infer the design intent of the A/E. With the influx of

technological advances in the construction industry, it stands to reason that the advancement

having the largest, most influential impact would be one that changes the way in which the

Architects and Engineers exchange information with the general contractors, sub-contractors,

and suppliers.

1.1 Building Information Modeling

This technological advancement is being heavily promoted by Autodesk with the

program Revit, which is used to develop Building Information Models. Building Information

Modeling (BIM) software is a dynamically linked interface designed to take the place of

redundant computer aided drafting (CAD) work. Idea being, architects are free to design, and

the software generates the plans, sections, and elevations. Any changes to the documents change

any other instance of it throughout the drawings, to improve coordination. Reduction in

coordination issues will reduce RFIs, which will increase productivity. Knowledge of the

program is essential for the general contractor on site to make suggestions to the architects and

engineers who address unanticipated field conditions, this will reduce non-productive time on a

jobsite and increase construction job efficiency and productivity.

1.2 Statement of Purpose

Purpose of this study is to research BIM and how it can be used successfully by both

designers and builders. Since BIM is supposed to be the process that both sides of the

construction industry can use for their specific needs, just how well can this BIM software meet

their needs in conjunction with the specially tailored programs developed for designers and









builders? Interviews were conducted to gage how BIM is being received by architects,

engineers, and contractors; and how BIM can help construction companies improve their

methods of construction and increase productivity. Intention being, to gain an understanding of

BIM, to determine the shortcomings of the program and to become aware of the barriers to

implementation that this program will offer in today's very technological world.

1.3 Objective of Study

Objective of this thesis is to study both the assets and limitations/complications with

implementing a BIM program in the design/construction industry. With knowledge of the

program and how it works; the benefits of how BIM can increase productivity in the construction

industry can be projected. With this objective, interviews were conducted with local large (1)

and small (2) construction companies, to determine the possibility of implementing BIM into

their daily operations. Their perspectives will also be attained about using BIM on projects, it

benefits to productivity and its disadvantages.

1.4 Scope and Limitations

Scope of this thesis involves doing research on what Building Information Modeling

actually is, based on its core components. Research on BIM will make the benefits and

limitations more readily understood. Research was also done on productivity improvements in

the construction industry. Knowledge of practical concepts and initiatives used in the present

construction industry are essential in knowing how the construction industry works, and more

importantly, how BIM can influence the construction industry.

How BIM is being used in the AEC industry is revealing difficulties that have to be

addressed. Limitations are encountered because historical data is not readily available due to the

lack of recordkeeping. This software is still in its infancy, and although most experts consider

BIM to be the future of the construction industry, the change over by architects and engineers is









very slow. In the construction industry, BIM is more widely accepted because of the ways that it

links with currently used scheduling and estimating software.









CHAPTER 2
LITERATURE REVIEW

With the rapid adoption of BIM in the construction industry, and its gradual

implementation in the design industry, careful considerations have to be taken when making the

change over from the traditional method of creating construction documents towards a BIM

approach. There are plenty of positives, negatives, and unknowns that have to be considered

when implementing BIM. This chapter will discuss research that was done about the

background of BIM, its perceived positive and negative effects, and productivity improvements

for the AEC industry.

2.1 Principles of Building Information Modeling

International Alliance for Interoperability (IAI) was formed in September 1995, and since

its release, has published three major releases of the Industry Foundation Classes (IFC). This

was the beginning of setting standards for object based data modeling. Standards that would

define the interoperability of object based data modeling for the AEC industry. Idea being that

multiple vendors would be able to access a building model to supply data to the architects and

engineers in a 3D space. Interoperability is the dynamic exchange of information among all

applications and platforms serving the entire building community throughout the life cycle of

facilities (Keller 2004). Therefore, no matter what programs were being used across the broad

spectrum of vendors, there would be a medium to transfer data to something that others in the

industry could access, this medium being the 3D model.

Although these guidelines were set, they would need backing from major software

companies in order to gain a foothold. Once Autodesk decided to acquire Revit (the same

company that controls the most widely used computer drafting program, AutoCAD) the BIM era









began to hit the main stream. With so large of a parent company, Revit has become the staple

in the industry for BIM.

BIM is a brand new design methodology and is defined by Autodesk (2004) as: "a building

design and documentation methodology characterized by the creation and use of coordinated,

internally consistent computable information about a building project in design and

construction". BIM incorporates the use of 3D visualization techniques with real-time, data

driven, object- based imaging as a tool by all facets of the industries (Holness 2006). This is a

change from the current practice of; designs being manifested and put to paper with engineers

then designing the structure and other supporting elements of the building. After completion of

the design documents, a 3D model can be generated for the owner showing digital walkthroughs

and to provide 3D renderings of spatial relationships. These tools are very useful to convey

design intentions to owners and clients that who not able to visualize 3D space from 2D

drawings. These can be very expensive and time consuming to produce.

BIM greatly increases the user's ability to control and manipulate data and information in

an unprecedented way and in an interoperable format. Moving from paper-centric information to

parametric, model-based information means that the digital design can be used for cost

estimations, simulations, scheduling, energy analysis, structural design, GIS integration,

fabrication, erection, and facilities management (Seaman 2006). All of which are relative to

each other, and changes in one category will have impacts on the others that are automatically

accounted for. Since all of the above information is dynamically linked, productivity from

recalculation of simple and minor changes will be greatly increased because the computer

program will be able to handle the changes and calculations internally.

BIM application software has the capabilities of other modeling programs like
sketch-up and 3D studio max, which architects traditionally use for generating
walkthroughs and to convey spatial relationships. The difference being that this









program will also be able model the HVAC, steel, structures, hot water pipes,
cold water pipes, and communications. Not only will the program model this, but
will correlate them with each other to find conflicts. Upon recognition of one, the
program will mark it and send a flag for corrections to be made. Changes will
then be made to make the program satisfied, but this could prove to be detrimental
if the code does not allow the change. Careful consideration needs to be taken
when implementing changes to accommodate the BIM software (Seaman 2006).

Documents a BIM can generate include, but are not limited to, drawings, lists, tables, and

3D renderings related to the project. Thereby contributing more to efficiency, and provide

superior accuracy than traditional 2D CAD drawings (OCA 2006). Building models embedded

with detailed information about a construction project are far beyond the capabilities of most

design firms at present (which is why historical data is difficult to find and analyze, as it relates

to productivity). These models are not just the electronic drafting tools that firms now think of as

digital practice, nor are they three-dimensional renderings with separate construction

documentation (Seaman 2006). These are object based digital models which the program itself

constructs the appropriate plans, details, and sections from. Any change in one aspect of the

drawings, will automatically be accounted for in the other drawings. The BIM process has the

potential to remove the guesswork about how the most difficult parts of a building come

together, which tend in most cases to be the corners. These models also transcend 3D and can be

manifest in 4th dimension (4D) and 5th dimension (5D). Projects can digitally be built in the

computer environment, showing any possible conflicts with the schedule; this is an incredible

tool to relate information to the owners and show models for future production. If delays arise,

they can be input into the model, and BIM will be able to determine any the necessary changes in

the schedule. Four D (4D) models link components in 3D CAD models with activities from the

design, procurement, and construction schedules. Resulting 4D models allow project

stakeholders to view the planned construction of a facility over time on a computer screen and to









review the planned or actual status of a project in the context of a 3D CAD model for any day,

week, or month of the project (Fisher and Kunz 2004).

The 5D represents the money aspect of the program (Figure 2-1). Projects will have the

materials for construction estimated, and work up a cost of material proposal. Changing

materials for Bid Alternate purposes will be easy to see both the immediate cost impacts, but also

a life cycle costing to the owner (AEdgar 2006). Moving to an integrated, parametric, and

object-based system should lead to dramatic changes in design and construction as well as,

possibly, compensation and risk allocation. Life cycle cost analysis can project to the owners,

cost savings and operational costs over the lifetime of a building. This information can


E

0






Lifecycle Phases


Information
,7 Exchanges

-Vendor
H


SDesign Build OQ te Project Team
c Ad or 2008


Figure 2-1. Relationship of a BIM to all facets of the AEC industry. Courtesy of NBIMS
AEdgar 2006.









prove to be very important in determining feasibility of a project. This information is also very

important for determining whether a project meets Green Building specifications or LEED

accreditation.

A BIM can be used with distributors for estimating cost of materials and the ability to

control the cost of the building is very captivating to the owners. Material suppliers can insert

their specific data and cost into the BIM with the appropriate cost factors, and from this

information, a hard dollar cost and a solid estimate can be generated, which will be the actual

cost of the building. Changes can then easily be made to any of the specified products, creating

new estimates and building costs. When changes are made, they can then be assignable to the

architect, engineers, or owners. This can then determine responsibilities for payment on change

orders (Seaman 2006).

2.1.1 Increasing Value Through Shared Information

Results of this design methodology is not just a creation of the Architects design

intentions and spatial relationships shown in 3D, a BIM is a repository for digital information

and data generated by the design process and simulations; it is the design, fabrication

information, erection instructions, specifications, materials palette, schedule, and project

management logistics in one database (Schinnerer 2006). Data models will exist for the life of a

building, can be used to manage the client's asset, and will exist as the "As-Built" documents for

future additions, renovations, and upgrades.

Because the true benefit of a BIM is to the project owner, the push to use a BIM will

most likely be a client-driven development. Many owners see the single point of responsibility in

integrated practice as an attractive alternative to the "over-the-wall method" of design and

construction in which an architect completes a design and hands it over to a contractor for

construction (Elvin 2007). The value is in the significant building efficiencies and initial cost









savings and extends to the operations and maintenance of the facility (Guidelines for Improving

Practice 2007). Speed, accessibility, communality, and adaptability are achieved by the use of a

common database, early information user input, knowledge representation and information

technology, team collocation, and information exchange in small batches (Elvin 2007).

Based on expert studies, other benefits of BIM include reduced risks, improved

productivity, streamlined production, maintenance of design intent, and facilitation of quality

control through clear communication and sophisticated analytical tools (Guidelines for

Improving Practice 2007). All of which will be realized from conception, thru construction, to

the life cycle analysis of the building.

2.1.2 National Building Information Modeling Standards (NBIMS)

Once software had been established for the new design methodology and development of

construction drawings, NBIMS set forth to develop standards to be followed by those using the

software. With the adoption of CAD programs, a set of standards was never initiated, which is

why construction drawings from different Architecture firm can be virtually similar, but have

distinct differences in how they are shown, drawn, and notated. Early CAD programs were not

interoperable with other programs specific to the AEC industry.

National Building Information Modeling Standards advocates that BIM is the future of the

AEC industry and has been trying to develop a set of universal standards for the industry to

follow. This is one of many components that will make using BIM a more productive asset for

the AEC industry to use. Knitting together the broadest and deepest constituency ever assembled

for the purpose of addressing the losses and limitations associated with errors and inefficiencies

in the building supply chain is the goal (Davis 2006).

These standards are an integral part of making interoperability between all phases of a

construction projects life from inception onward. Without this, using a BIM would essentially be









pointless. Documents, that set standards for BIM, must overcome the impediments that have

begun to be identified so the implementation of BIM, for the entire industry, to be successful.

2.1.3 Collaborative Working

The most beneficial aspect of using BIM technology with software like Revit is the way

it changes the design process. A BIM's goal is to recognize the potential benefits that

collaborative working through all stages of design and construction can offer. This happens to

be the hardest thing to implement in the design process being that there are complications for the

interoperability of the design data. In all likelihood, multiple models will be produced in

different disciplinary BIM applications and these will have to be combined into one composite

model for visualization, clash detection, and other tasks (Figure 2-2). At the same time, the

guide emphasizes that it is not necessary to create all the models to derive the benefits of using

BIM on a project. Contractors can make many "partial uses" of BIM such as assisting with

scoping during bidding and purchasing, reviewing portions of the project scope for analyses such

as value engineering, coordinating construction sequencing (even if just for two trades),

demonstrating project approaches during marketing presentations, and so on (Khemlani 2006).

Despite the great potential for collaborative working in the design stage of a project, this

has not yet been fully exploited, due to the lack of applicable information exchange standards

that can be widely adopted by the project team. While a great deal of attention has been focused

on interoperability of design applications between design disciplines, there has been less focus

on the specific information needs and exchange capabilities of the cost consultant (The IT

Construction Forum 2006).

Cost consultants are integral to collaborative working in determining the costs of

construction. This is something that BIM software is programmed to calculate automatically,










from proper input in the digital model, this can save construction management firms time in the

estimating process.

It has been shown, however that BIMs sometime miss-calculate the measurements of high

level information. Currently, the wider uses of BIMs incorporate the capacity to generate

measurements automatically from objects created by designers. This capability is being actively

promoted although its application on live projects has been limited (The IT Construction Forum

2006). Forward thinking cost consultants can work collaboratively with design and construction

firms that implement BIM into their projects, however they will continue to rely upon the quality



Multple Models into a "Camposite Model

BIM
Archtecturl Archtecmral 'linked with
Dmorn 6o1el pha sing,
sequencing,
construction
Sreutural S.tU~ .=rl schedule]
Desyn I~Mdel





Model












SContractors ash election.
ShOp Drwvig Revinw and Feedback Procfss



Figure 2-2. Combining multiple models into a composite model (Contractors Guide to BIM
2006)









and consistency of design information. Since a BIM is produced by a computer program, it has

the same flaws that any other computer program has, it is limited by the ability of the user.

Garbage in, garbage out, will be a mantra that will have to be acknowledged and constantly

checked for. With the newest technologies and digital design, buildings are becoming more

complex, the state of the art HVAC systems (Figure 2-3), and buildings are breaking the mold in

a way that was never done before, and this is all attributed to computer design (Figure 2-4). Cost

consultants are developing new ways of working in order to provide the best cost estimates

possible given complicated designs.

Although BIM software is able to keep record of how much material is used, it is not able

to determine how much labor and effort are required to construct these new and complicated

designs, this is a specialty of cost consultants. They will become vital to construction estimators

on very complex projects. Additionally, there will be no overnight conversion to collaborative




















Figure 2-3. A section of the BIM model for One Island East tower in Hong Kong, Gehry
Technologies' project with structural engineers, Arup. The drawing shows several
floors of a mechanical zone halfway up the tower. HVAC systems are green;
plumbing and electrical are purple and blue, respectively; and steel is gray. (The
Architects Newspaper 2006)


































Figure 2-4. Frank Gehry's Stata Center located at the Massachusetts Institute of Technology
(MIT). The construction documents of this building are impossible to represent
totally and accurately in 2D. The use of BIM was essential to the construction of this
building. Image courtesy of 2006 http://philip.greenspun.com/copyright/

working, but for those practices which have the opportunity and capability to respond positively,

the eventual gains could be substantial (The IT Construction Forum 2006).

2.2 Productivity

Construction has remained unchanged for centuries, being a process where manual labor is

used to place building components to erect structures. This present delivery system, in its

current form, consists of:

* Programming: With the owner's input, an architect determines what the owners needs are
and what supporting programmatic elements are essential for the building.

* Schematic design: Architects draw a conceptual spatial plan on paper. The owner then
reviews the drawings and approves or suggests changes

* Designed development: Architect gets feedback from design professionals, i.e. the
structural, mechanical and civil engineers.









* Construction drawings: Final developed drawings passed onto owner. Owner then
approves the drawings to begin construction.

* Bidding: Contractors attain the construction drawings and estimates are prepared to submit
back to the owners.

* Construction: After awarding the job to the contractor, construction begins.

Adrian (2004) writes that over the years there have been many technological advances in

the construction process that have both increased the rate of construction, and supplemented the

complexity of the construction processes. Largest impacts are from the advent of the mechanical

crane, which enabled large heavy construction units to be moved quickly over vertical distances.

This is widely responsible for the completion of complex designs for Gothic Cathedrals. With

technological improvements to the crane, skyscrapers were able to be erected, something that

was previously not attainable. Mechanical cranes have had a tremendous impact on productivity

in the construction industry, but the construction process has remained unchanged.

Another great technological advance was with the advent of the cell phone. Lots of time

was wasted, in comparison to today's standards, either waiting for clarifications on information

or merely having to be off site to take calls. Productivity has dramatically improved, because

cell phones receive and place calls, but also come with personal organizers and phonebooks.

Now construction managers can make calls to Engineers and Architects while on the jobsite,

being able to maintain supervision on construction workers. Suppliers can contact the job

superintendent to confirm delivery appointments. This is perhaps the most recent technological

advance to improve productivity in construction but what lies on the horizon is BIM.

Building Information Modeling has the potential to revolutionize the construction

industry, although it is not without its potential drawbacks, and the benefits of BIM have yet to

be documented since it is still relatively new to the construction industry. Productivity is the

biggest selling point for the utilization of BIM in the AEC industry; therefore productivity has to









be studied and forecasted since information for BIM on productivity is limited, specifically to the

smaller construction firms that make up the majority of the construction industry.

2.2.1 Productivity in the Construction Industry

Productivity and quality in the construction industry have been on the decline over the

years. In fact, construction productivity increases (see Table 2-1) are the lowest out of all listed

individual industries according to the U.S. Department of Commerce (Construction Review

2002). Construction productivity increased was a dismal 0.80% in 2002. Reasons for this

dismal amount of increased productivity is because of the high turnover rate in the construction

industry, the duration on a project is typically only a year, so there is no chance for a learning

curve to have an affect for each specific job, and the sub-contractor/general contractor

relationships are continually changing. In one study, a Federal Price Commission concluded that

an industry's ability to increase productivity is directly dependent on the degree to which it can

set productivity standards (Adrian 2004). Implementation of BIM throughout the industry will

help set productivity standards to follow.

The biggest factor that reduces productivity on a construction job is the amount of

nonproductive time spent by laborers. Reasons for this can be attributed to a number of factors

(see Table 2-2). This study will examine the possibilities of utilizing BIM to increase

productivity in the following areas: industry related, labor related, and management related. This

is particularly important for small size construction firms. As shown in Figure 2-5, the majority

of construction firms that make up the construction industry are small companies, having less

than 15 workers. These firms account for more than 10% of the gross national product annually

and are most in need of some measures to improve productivity; unfortunately therein lays a

problem. Small firms are hesitant to invest in research and development (R&D) or optimal









Table 2-1. Productivity increases for various industries (2002)


Industry


Agriculture
Construction
Government
Manufacturing
Mining
Public Utilities
Transportation


Productivity
Increase (%)


3.64
0.80
1.64
2.60
3.17
5.40
4.60


Source: Construction Review, U.S. Department of Commerce,
Washington D.C., 2002


computer programs to improve productivity. There are number of barriers that keep contractors

from using the latest technology, including fears (legal/risk fears, fear of change, fear of the

unknown, etc.), initial investment costs, the time to learn how to use the software, and perhaps

Table 2-2. Reasons for nonproductive time in the construction industry

Industry-related Labor-related Management-related
factors factors factors


Uniqueness of many High percentage of Poor cost systems
projects labor cost and control
Locations at which Variability of labor Poor project
projects are built productivity planning
Adverse weather and Supply-demand Poor planning for
climate seasonality characteristics of measuring and
Dependence on the industry predicting
economy Little potential for productivity
Small size of firms labor learning
Lack of R & D Risk of worker
Restrictive building accidents
codes Union work rules
Government labor and Low worker
environmental motivation
laws


Source: James J. Adrian, 2004









70.00%


5000%-
40.00%




0-00% --
2.5 7 14.5 34.5 74.5 174.5 375 750 3000
Nunter f Employees In Firm

Figure 2-5. Distribution of construction company size by number of employees, 1996. (Dr. E.
Douglas Lucas, 2008)

the lack of support from the senior leadership of the company, which may be the biggest barrier

for many (Khemlani 2006). Building Information Modeling requires both research and

development to implement into a construction companies process and a rather large investment.

Software that can manipulate BIMs, like Revit, cost about $6,000 per license. Cost of the

software and training make it difficult for small construction companies to justify purchasing and

implementing. This study will make a case for small construction firms to invest in a BIM

program for their future survival in a changing industry. Estimates have also suggested that as

much as 30% of project costs are wasted through poor management of the design-construction

process (Brown and Beaton 1990). This is represented accurately in a study done by Adrian

(2004) showing that roughly 50% of a construction laborers day is wasted either waiting for

materials, or just not performing (Figure 2-6). Changes are an absolute necessity to increase

productivity.

2.2.2 Input into Design

With the traditional relationship between the architect, owner, and contractor, the

contractor has very little, if any, say about the design of a project. This gives the Architect the










Productive work
6%
Late Starts, early quits
2%
6% lO Punch List

2% 0O Late or inaccurate info

3% Waiting on Resources
50% M Accident related

14% Substance abuse

O Multiple material
5% handling
SWastage or theft related
3% 6%
SWaiting on instructions

O Redo work


Figure 2-6. Analysis of productive and non productive time during a typical construction project
(Adrian 2004)

complete freedom to design any type of building they wish, contingent upon approval by the

owner. Next, the drawings are turned over to the owner for competitive bidding by various

contractors. Since the relationship between the contractor and architect starts after the drawings

are complete, there is little input that the contractor can offer to improve productivity during the

construction process.

During the design phase of a project, the architect will prepare several levels of estimates

on the size, quality, and cost of the building. This is based on their conception of the cost for

building the project. Most architects base their costs on historical construction square foot costs

of similar projects and neglect market trends and cost of materials. Small cost increases can

have dramatic impacts of the final cost of a building. There is no doubt that if the estimates are

grossly incorrect, both the quality of the project and the time it takes to complete it suffer

(Adrian 2004).









Using a Construction Management (CM) firm early in the design process will result in

more accurate preconstruction estimates that will keep the owner more informed for bankroll and

cost purposes. Fully integrated BIM design process links the CM to the architect at the

beginning of the design phase. Each of them will have input to the design of the building, and

the end result will be a more cost effective building due to the increased productivity from this

type of relationship. They enable the exploration and improvement of the project executing

strategy, facilitate improvements in constructability with corresponding gains in on-site

productivity, and make possible the rapid identification and resolution of time-space conflicts

(Fisher and Kunz 2004). Although this system offers a more complex design process, it allows

all participants to input the best possible scenario for a construction project (Figure 2-7).


Figure 2-7. Reciprocal relationships between various parties involved in the design process and
the BIM project









2.2.4 Ten Step Program for Improving Productivity

The ten step program for improving productivity in the construction industry as written

by Adrian (2004) is as follows:

1. Making the project look like a firm rather than a job; developing a personnel management
program.

2. Improved Communications

3. Planning a Productive Site Layout

4. Challenging the Work Process

5. Developing a scientific work standard versus an accounting based standards

6. Planning and Scheduling

7. Project Control and Productivity Improvement

8. Equipment Management to Enhance Productivity

9. Productivity Improvement through Safety

10. Productivity Through Attention to Quality

2.3 Advantages and Disadvantages of BIM

Parametric modeling as the design and construction database is a difficult one to examine

from practice and insurance-coverage perspectives. Firms will have increasing challenges as they

realize that they are moving from a physical model-and hard-copy plans and specifications-to

the primary information generators for a digital database (Guidelines for Improving Practice

2007). Some problems with BIM will be related to liability. With the open access to the model

from all aspects, (anyone involved in the construction project) how can engineers or architects be

expected to sign a set of drawings, placing their liability on the line? This major issue could

have potentially huge detrimental effects on productivity.









As A/E firms move from an analog system, where original construction documents are

easy to identify and monitor, through our present "semi-integrated" system, to what could be

called a "super-integrated" future, those firms will have to deal with new business rules and

possibly unknown liability exposures. This happens because owners, CM, sub-contractors, and

suppliers are supplying information to the BIM; and has all been done in a collaborative effort to

streamline the design and construction process. Desired results are focused on a project that

takes less time, is more economical, and less costly.

The driving theory behind BIM is the elimination of change orders and RFIs that occur

because of missing information in the construction documents since all the parties involved in

creating the completed BIM will check for all possible conflicts and problems. Problems exist,

not in the coordination of the BIM, but in the coordination of all parties involved with access to

the BIM. Typically, design elements consist of (but are not limited to): surveying, architecture,

civil engineering, electrical engineering, mechanical engineering, structural engineering,

landscape architecture, fire/alarm engineering, communications, interior designs, owners,

tenants, construction managers, commissioning, etc. These professionals will have input to the

BIM before, up until, and after, construction begins. Once construction begins a secondary

group of people are necessary, these are (but are not limited to): general trades, site/excavation,

steel construction, mechanical construction, electrical construction, fire sprinkler construction,

concrete construction, roofing, masonry, glazing, elevator controls, finishes, technology, and

landscaping.

This is a large group of people to get together and coordinate to use a BIM model for all
construction information. Combine that with the fact that, the relationships between the
involved parties are all connected to the model and they are also connected to each other.
With such a complicated relationship, the biggest problem will be how to control who puts
what into the system, and what kind of problems will that generate (Seaman 2006.









2.3.1 Proponents of BIM


Building Information Modeling software is unique and advanced in its ability provide

architects, engineers, and construction managers the necessary interoperable program for all their

needs. Proponents of BIM indicate that the only limitations to using BIM are the abilities of the

users and list the following benefits of using BIM:

* Conflict Resolution conflicts will be identified ahead of time so changes to the drawings
can be made before construction begins.

* Adjusts costs as changes occur determine changes in projects as time progresses. The
costs for specific objects can be input into the BIM. Merely changing the objects will not
only coordinate with the drawings, but will update the schedules and estimates.

* Speeds up Design/Construction process BIM will speed up: programming, preliminary
design development, preplanning for construction, but it still is beholden to the speed at
which the architect produces drawings. Intelligent design takes time, and cannot be
compressed. The program can speed up the development of construction drawings.

* Reduces Ultimate Cost by compressing time for construction, generating specific costs
for changes, and handling changes up front.

* Single Entry Input only needs to happen once. When something is put into the plan view
of a drawing, it will be shown in the door schedule, interior elevations, exterior elevations,
and sections. Upon modification, when an object is changed, all instances of it in the BIM
change as well, along with all accompanying notations. The same can be said of
estimating. Changes in the estimate will trickle down throughout the BIM. It will even
help you coordinate anything that changes from substitutions of objects, i.e. electrical
demands on panels after changing lighting for the building.

* Alternates Since substitutions are easy to interchange in a BIM, this will give owners the
opportunity to request many more alternates to see how cost can be influenced.

* Design optimization important for addressing LEED issues.

* Conflict Identification and Resolution Is great for clarifying locations for running of the
mechanical/electrical/communication/fire. The only limitation is that the contractor must
run their system in the specified location, or other trades will face problems, especially in
tight spaces.

* Constructability Details can be developed to show how building components come
together









* Construction Sequencing/Scheduling the model will be sequenced and scheduled so you
can see the approximate progress. Viewing the BIM in 4D will help keep the construction
project schedule.

* Life Cycle Evaluations Energy calculations can be run using solar heating to determine
the cost of running the HVAC for a building. Useful for budgeting cost over time.

* Operational simulations animate the model to show activity, how the building would be
used i.e. a medical facility. Show how the patient would be moved from surgery or an
industrial plant, see how the plant operates and make sure that you will have all the
necessary clearances during operations. (Seaman 2006; Autodesk 2007; Sheldon 2007)

Interoperability is a huge component of BIM software. Manufacturing software will be

able to access a BIM and derive all their applicable data. Idea being that this transfer of

information will be seamless.

GSA use in Phase I Government Service Administration (GSA) is requiring that BIM

be used during Phase I of construction which means up to and including the schematic phase of

the construction process. This is just the first step, and BIM will be adopted and moved forward

in the construction process systematically. All GSA projects are encouraged to deploy mature

3D-4D-BIM technologies, spatial program validation and beyond. Contractual language has to

be developed for this to take root. This is the same way in which LEED Accreditation came to

the forefront in current government jobs. Typically, once government enacts something, the

private industry will follow suit.

Green building is leading BIM to a certain extent because of its ability to do Cost analysis

and Life cycle analysis over the lifetime of a building. Typically when doing the cost analysis

now, it is an energy saving analysis (see Figures 2-8 and 2-9). In Green Buildings it is just

applied to the Energy and recyclability side of it. A BIM allows the user to do cost analysis over

the entire construction process as well. Most of what is being seen in Green building and LEED

is a precursor for what is going to be seen from the implementation of BIM. United States Green






























Figure 2-8. Computer modeling to analyze air temperature distribution to determine the benefits
of displacement ventilation in the courtroom lobby, halfway up the tower, indicated
with a green stripe on the drawing. (Google image 2007)


'V


Figure 2-9. The Pearl River Tower includes integrated wind turbines and photovoltaic panels to
offset its energy use. Inset is an Ecotect model showing the amount of solar radiation
on the tower's various surfaces. (Fortmeyer 2008)









Building Council (USGBC) and Autodesk will explore opportunities to integrate Autodesk's

technology with the USGBC's Leadership in Energy and Environmental Design (LEED) Green

Building Rating System, to help the building industry more easily and rapidly meet goals for

reduced carbon dioxide emissions (Cole 2006). Commissioning is a requirement in a LEED or

green building. A BIM would allow the commissioning administrator to be involved from the

beginning of the construction process to ensure that certain criteria are certified and a building

will truly meet the specified commission rating.

2.3.2 Disadvantages of BIM

Below is a list of items that have to be considered before changing to a BIM

methodology. The question being, whether or not the problems with implementing BIM are too

big to overcome.

* Garbage in-Garbage out when suppliers enter data into the model, will they be held
responsible when things do not work, or will they blame the engineers for not checking
over the drawings.

* No Standard BIM Contract Documents if a set of standards is not developed,
interoperability of BIM will not be efficient.

* Electronic Data Transfer Engineers and architects are reluctant to providing digital data
to suppliers and contractors because the data can be modified. A/E want to protect their
data and work for liability and copyright purposes so pdf files are used. BIM gives access
of the model to suppliers for doing takeoffs.

* Interoperability How well will programs relate and talk to each other. BIM cannot
interface with other programs (yet). When a different program takes a BIM and opens it
with another program, who will check to make sure that all the engineered data is still
correct from the transfer into another program. (Seaman 2006)

Will the Architect remain the representative of the owner in charge of overseeing the entire

project, or will their role change, making the architect merely a supplier; the supplier of the

design. International Building Code dictates that Architects are responsible and have to sign and

seal documents, they will be the ones responsible for ADA and all code differences from state to

state, country to country. Architects could possibly take over construction management duties

36









since the software provides a lot of the specialized products that construction managers provide

i.e. scheduling and estimating. From this reasoning, BIM should be a great asset for a

design/build company, but currently this is not the case, as observed from my interview with a

large design/build company that is utilizing BIM.

Who is going to have copyright of data when it is done, (processes cannot be copy

written), will the architect be able to copyright drawings when the program actually makes

changes to the drawings?

In the current process, when changes need to be made to a set of drawings, the responsible
party annotates the drawings with a revision date, and a revision number. Then the part of
the drawing that is changed is marked with a cloud and the corresponding revision number,
making it very easy for anyone who looks at the drawings to determine what has been
changed. With BIM, revisions can still be made to the drawings, but instead of getting an
accurate account of what has been changed, a whole new set of drawings is issued, and
since the program has dynamic input, a change in one location is made throughout the
drawings. These will not be marked with revision clouds, so finding changes on a set of
drawings could be very difficult. Plus, who makes the change and why? This needs to be
carefully considered when using BIM (Seaman 2006).

Polygonal modeling is what architects currently use to show the owner what spaces and

buildings look like, this is a view of what exists, what is drawn on the paper. Parametric

modeling creates the design from the input you use. If the user wanted to put in a specific

window or door, product information could be retrieved from the manufacturer's database,

inserted in the wall, and the program can generate details provided by the manufacturer's

specifications. But who will be responsible for making sure that details are up to date, and who

will be held accountable?









CHAPTER 3
METHODOLOGY

Objective of this thesis is to study the potential use of BIM in the AEC industry and how it

can improve productivity for construction managers. A BIM is a design methodology that

breaches the gap between the design intentions of architects and engineers, and the

implementation of design by construction managers. It is a computer model that fulfills the

needs of all parties involved in the AEC industry, offering CAD services, cost calculations,

energy simulations, building code checking, life cycle analysis, and it is formatted to be

interoperable with other programs that are specific to the AEC industry.

Productivity improvements for the construction industry were researched by reading

various books and articles to understand the workings of a very labor intensive industry. History

of BIM was researched to determine the purpose of the program and the limitations that it may

have. The BIM program used for this study was Autodesk Revit because Autodesk is the

biggest software provider for the A/E industry. The author has over 10 years experience with

AutoCAD and 5 years of experience with construction documents. Using this experience, the

author was able to test the performance of the program, helping to discover more limitations.

Interviews with two small construction companies, one large design-build company, and one

design firm were also conducted to gage BIM acceptance by well established companies.

3.1 Productivity

Knowledge about productivity was attained from reading "Construction Productivity:

Measurement and Improvement" written by James J. Adrian (2004) along with other various

journals/articles. Specifics that were especially considered in determining BIM's impact on

productivity were Adrian's ten step program for improving productivity. Other various concepts

for improving productivity were also considered during the research i.e. labor productivity for a









typical day of construction, value engineering, the effect of information technologies on

construction, and human factors.

3.2 Advantages and Disadvantages

Positive and negative effects of BIM and how it relates to the construction industry have

to be considered when a construction company is deciding to implement BIM into their basic

operations. It is easy to find out all the positive effects that BIM can have on the construction

industry, but the negative effects have to be addressed as well. Drew Seaman, Esquire conducted

a professional development seminar at a combined meeting of the A/E ProNet membership, the

American Institute of Architects risk management committee, The National Society of

Professional Engineers' insurance committee, representatives of the American Institute of

Architects trust and representatives of The American Consulting Engineering Companies. This

seminar provided an in-depth analysis of the issues that affect the deployment of BIM on the

AEC industry. These are issues that need to be resolved and precedence that needs to be set for

BIM to be successful in changing the construction industry.

3.3 Interviews

Interviews were conducted with small construction management companies (Company 1

and Company 2), a large design build company (Company 3), and a large and innovative design

firm (Company 4). Representatives of construction Companies 1 and 2 interviewed about their

current working operations and were informed about the BIM process. Questions were asked to

evaluate their responses towards implementing such a system into their current operations.

Representatives at Company 2 were interviewed about perceived benefits from utilizing BIM on

some of their projects. Objective being: to attain knowledge from their first hand experience

about how BIM is being accepted in the workplace and their perceived benefits or perceived

drawbacks. Company 4 only utilized BIM for their operations because of the complexity of their









designs. It is essential for them to use BIM because conventional drawings are not adequate to

convey design intentions. These interviews along with the other studies conducted will provide

good insight on both, how BIM is being received in the construction industry and what the

barriers are for implementing BIM into small construction management firms.

Questions about issues related to productivity on the jobsite and issues about BIM in the

marketplace that have been determined to be essential to this research are as follows:

* How much time is spent analyzing construction documents prior to the construction
process?

* How long does it take to prepare a bid using a traditional set of construction documents?

* Approximately how many RFIs are submitted for a typical construction job?

* What is the average time spent waiting for a return on an RFI?

* How much time is spent conversing with the Architect/Engineers about the construction
job?

* Are you currently using Building Information Modeling at your office?

* If not, do you foresee changing over to some kind of a BIM system at your construction
company?

* If so, what problems have you encountered using the BIM process?

* Do you implement any productivity improvement practices with your construction crews
and if so, what?

It should also be noted that using BIM may provide all of these benefits, but designing and

development of the construction documents will be more costly than the traditional way of

creating construction documents.

3.4 Process of BIM

This research also involved learning the process of BIM first hand from continued use,

information seminars, and tutorials. Autodesk Revit seems to be the program of choice for the

A/E industry with their drafting program, AutoCAD therefore; the program that was used for









this experience was Autodesk's Revit. The author's personal experience in architecture has

given him ample experience with AutoCAD and how construction documents are created.

Revit gives the user an interface that is not very similar to AutoCAD. This is one of the first

drawbacks to changing from a drafting program to a BIM approach. Most of the A/E industry

utilizes AutoCAD in their operations. It is easier to learn BIM having no computer drafting

experience at all than it is with 10+ years of computer drafting experience (Imaging

Technologies, Autodesk Revit product representative 2007).









CHAPTER 4
INTERVIEW RESULTS

From the interview process, a good perspective of real world application was attained

from construction Companies 1, 2, and 3. Company 1 and Company 2 were a small general

contractor firm and a roofing sub-contractor, respectively. Company 3 was part of a large

design/build firm. A conference was also held with a large design firm (Company 4) that uses

BIM on their projects. Questions asked and answers provided are found in Appendix B. The

interviews and meetings were conducted in December 2007.

4.1 Small Construction Companies

4.1.1 Construction Company 1

General Contractors (GC) typically will have between three to four weeks to compose a

bid, and if awarded the contract, they have about two weeks to get finances and arrangements in

order before construction begins. Representatives do most of their estimates using hand written

notes. Although, thorough in reviewing the construction documents prior to bidding, (asking

many questions for addendum prior to the bid date) little coordination errors go unnoticed, which

become causes for change orders later on during construction. During the construction phase,

typical wait times are between two to three weeks before receiving an answer to an RFI which,

for the most part, does not impede progress on the job, but if something gets delayed because of

an RFI, another change order gets added to the job. During the construction process, both formal

and informal meetings are held with the Architects/Engineers to discuss progress on the job,

change orders that have been requested, and possible conflicts and future progress on the job.

This typically amounts to around three to four hours a week. From a small construction

company's perspective, there is no real advantage in acquiring BIM. Up front costs, in both time

and money, are more than can be justified.









From the interview, it is apparent that the amount of time used for all aspects of

construction and the amount of change orders that get issued for a job are detrimental to

productivity for Company 1.

4.1.1 Construction Company 2

This roofing sub-contractor has between two weeks and a month to compose a bid for

construction. Their scope of work is very limited and specific. Jobs are typically performed

with little coordination problems and few RFIs. They distribute the construction drawings to the

steel fabricator or truss fabricator to obtain the necessary shop drawings. Since their time on the

job is limited, they do not converse much with the architects and engineers until inspections are

required. Any RFIs are typically issued from the shop drawings to the engineers for approval

with the roofing sub-contractor acting as the middle man.

This roofing sub-contractor is opposed to the implementation of BIM for their

construction operation. Although 3D models make it easier to visualize space, productivity

advancements are not realized. This owner has been in the construction industry for more that

25 years. He is not prejudice against information technologies; but is unwilling to recognize the

advantages of utilizing LEED practices in construction.

The author beliefs that implementing BIM into normal operations would give small or

medium sized construction firms, a distinct advantage in the areas of: lost time and money and

increasing productivity. Obstacle to implementation would be training in this area, but the

current crop of building construction graduates will have a general knowledge of this program

and its assets for a company, and will not be able to ignore the possible benefits. In addition, the

new construction managers and job superintendents will be more computers savvy and will be

able to learn this program with relative ease.









4.2 Company 3: Large Design / Build Firm

Data acquired from representatives at a large design build firm generated mixed feelings.

One representative touted BIM as being the reason why construction on the new performing arts

center in Miami, Florida was completed. Before a BIM was constructed, the steel fabricator had

over 200 RFIs within the first three months because of the difficult angles and form of the

building. Putting the drawings into BIM cleared up virtually all questions involved with the steel

structure of the building.

This design/build firm has been implementing BIM on projects they are familiar and

comfortable with, that have owners willing to try using a new delivery system, so projects are

performing slower than their traditional method because of the learning curve. Most benefits of

using BIM are attained when the design is too complicated to portray in 2D. Unfortunately, the

pilot projects for BIM are very easy to attain through traditional means and this firm has an

office full of extremely proficient users of AutoCAD. It will take a while for the market to

switch to a more BIM centric approach, and this will be enabled with its implementation during

design and construction education in University curricula. Another representative has mixed

reviews with the benefits that can be acquired. Since this company is a design/build firm, they

fast track most of their projects, meaning that construction begins before construction documents

are completed. A BIM is most beneficial in the 3D, 4D, and 5D realms when the building has

been completely designed. Using BIM for fast track construction has not provided any

significant advancement in productivity.

4.3 Company 4: Architectural Design Firm

A conference was held with a representative of a large design firm. This firm is one of

the global innovators in BIM methodologies. During the conference, the benefits of a BIM were









discussed against the added cost of utilization. Benefits this firm uses to promote using BIM

included:

* A 40% elimination of unbudgeted changes (change orders)

* Cost estimate accuracy of 3%

* Less than 1% cost growth

* Bids within 2.5% of actual construction costs

* 60% less Requests For Information (RFIs)

* 80% reduction in time to generate a cost estimate

* Overall savings of 10% of contract sum through clash detection (coordination)

* 7% schedule cost reduction

* 10 to 20 times the return on investment though its life cycle analysis.

This provides convincing data for the implementation of BIM to owners. Inherent

complexity of their projects make it essential to use BIM, because 2D drawings cannot

accurately represent design intentions. Their projects have been very successful and they are one

of the few firms that have historical data on the benefits of using BIM, however the problem is

that results are subjective to interpretation by the design firm reporting them. It should also be

noted that using a BIM will be a more expensive process than the traditional method of

construction in up-front costs.









CHAPTER 5
CONCLUSIONS AND RECOMMENDATIONS

A BIM is, in its most basic form, the move from analog to digital design and

construction. It is a model-based, dynamically linked, technology with a database of project

information for coordination that has a real time, dynamic aspect associated with it; and is poised

to fundamentally change the way projects are built and how project stakeholders communicate

with each other through the unlimited transfer of information between the project stakeholders,

Architects, Engineers and all construction personnel.

A BIM is designed to be the mediating program between the specific programs used by

architects, engineers, contractors and suppliers/venders. It moves towards a completely universal

and interoperable program working with computer based models in 3D, 4D and 5D. From the

3D model, plans and sections can be developed (Figure 5-1). The 3D capabilities of the program

will visually solve any questions about material and spatial relationships. This makes conflict

resolution easier to detect as well. Engineers can design their respective systems (i.e. plumbing,

HVAC and fire sprinkler) and coordinate with each other. Once the model is composed,
















Figure 5-1. A 3D polygon model and 2D lines and text compose a set of integrated construction
documents. Images courtesy FacilityGenetics, LLC and Ghafari Associates (NIBS
2006).























Figure 5-2. Virtual construction documents and installation photograph. Images courtesy
FacilityGenetics, LLC and Ghafari Associates (NIBS 2006).

installers can follow the BIM to prevent any conflicts in future construction (Figure 5-2).

Models can then be created in 4D so contractors can both visualize construction before it actually

takes place, and predict the best locations for construction equipment and lay down areas.

Progress can also be monitored to ensure that productivity levels are being maintained (Figure 5-

3). With 50% of a typical construction day being non-productive, BIM applications can be used

to gain a 33% increase by addressing: late or inaccurate info, waiting on resources, multiple

material handling, waiting on instructions and rework. This will have a dramatic increase in

productivity for the construction industry, making it more compatible with productivity increases

in other industries like agriculture, manufacturing, transportation, etc.














Figure 5-3. Installation process and equipment requirement. Accurate steel sizes, members,
weight and cost. Images courtesy Kling (NIBS 2006).

47









Negative aspects of BIM have to be addressed for the technology to be successfully

integrated into the AEC industry. There are a lot of specific requirements with structure,

inspections, etc. that relate to the International Building Code. A BIM has to be capable of

recognizing project locations to meet regional building codes, especially for overseas projects.

All the input from users accessing the drawings may become problematic. Sealing of drawings

may prove to be difficult if 30 different people have input to the drawings, how will

professionals be able to verify that they witnessed what work had been done on the BIM model.

This also applies to the actual program, BIM is supposed to make changes for the user as well

when structures are changed, columns are inserted or removed. How will the engineers be able

to identify all the changes that the program itself can make to the model and would they be

willing to sign and seal the drawings not knowing what changes may have taken place from their

original intent or design.

Who will be held accountable for Coordination? Architects and engineers are the

professionals responsible for coordination. Since this new program is supposed to manage

coordination for you, who will be at fault and who will make the changes when things conflict.

Plus, the engineers and architects are going to have to learn a new program that is more

expensive, and their fees are not going to increase. This could cause some hesitation for the

AEC industry to change.

Future of BIM in the construction industry will be just as important as traditional computer

aided drafting (CAD) programs. It will require many years of gathering data and compiling a

databases, both from the Architecture/ Engineering side with traditional construction details, and

the construction side from gathering actual productivity data. Once a solid database has been

formed, productivity will begin to improve, and through continuing education, more

opportunities for improvement will begin to reveal themselves. Perhaps the most important issue









to remember is the program can only be as helpful and the information that is input to it. The old

adage "garbage in, garbage out" could have a significant impact on productivity using this

program.

5.1 Increasing Productivity with BIM Using Adrian's Model

Adrian's 10 step model can be used to increase productivity in the construction industry.

Results of this study suggest that using Adrian's model BIM can be used to improve

productivity.

5.1.1 Making the Project Look Like a Firm Rather Than a Job: Developing a Personnel
Management Program

This helps to encourage construction workers to take pride in their work, and sets

precedence for performance and appearance. Use of BIM during the planning phase can predict

the best location for lay down of materials through the animated construction process. This can

be relayed to all trades doing work long before they even get to the site. Having this knowledge

gets the job started immediately and without delay.

5.1.2 Improved Communications

Poor communication at ajobsite leads to low productivity, and redo work. A BIM will

be able to increase communications between the Architect/Engineers and the jobsite

superintendent. There needs to be knowledge of BIM on both sides so communications is

through the program. A BIM can also be used to document ajob and to keep all involved parties

free from problems, delays, and increases progress and achievements.

5.1.3 Planning a Productive Site Layout

Building information modeling can be used to determine proper locations for the

construction lay down of materials and the delivery times of materials because of the dynamic

scheduling ability that BIM has to offer. Coordination becomes easier, and as-built drawings

become more accurate. Construction site layout entails things such as trailer locations, materials,

49









equipment, and storage areas, signs and lavatory locations, break areas, etc. Properjobsite

layout can stem equipment theft. All of these things are critical for increases in productivity.

5.1.4 Challenging the Work Process

Questions like "why are we doing it the same way, where is the best place to do it, when

is the best time to do it, etc." need to be asked to find ways of improving the construction

process. Object being, to improve the work process, which will increase jobsite productivity.

BIM methodology is a new and inventive way to construct a building, and shall not be dismissed

because it is difficult.

5.1.5 Developing a Scientific Work Standard Versus an Accounting Based Standards

Utilization of BIM will, hopefully, introduce a new, more standard way to develop

drawings from multiple/different design firms. This new standard will increase the knowledge of

persons preparing bids and reading drawings because of the similar/typical styles to compose a

set of drawings, promoting a more cohesive work environment.

5.1.6 Planning and Scheduling

This was discussed earlier because of the 4D and 5D opportunities that BIM offers as part

of its database. Ability to render time lapse studies into a project will help in predicting better

more efficient ways to utilize time and improve scheduling.

5.1.7 Project Control and Productivity Improvement

One need's to know what problems are if they are to correct them and improve

productivity. Information needs to be recorded regularly to determine the productivity of the

current crew on ajobsite. This information could be cataloged and studies will determine what

needs to be done to find increases in worker productivity. This will also set a precedence on

which BIM projects can be judged, and compared to previous projects that used the traditional

construction method.









5.1.8 Equipment Management to Enhance Productivity

This is not relevant to BIM, it relates to the issues of renting rather than owning equipment

and worrying about maintenance. It is focused on using new and not outdated equipment to

improve productivity on ajobsite.

5.1.9 Productivity Improvement through Safety

It is clear that a safe jobsite is a more productive jobsite, helping to increase worker

moral and keep workers motivated (knowing that their employer is concerned about their safety).

A BIM can give early clues about potential hazards that may occur on the jobsite.

5.1.10 Productivity through Attention to Quality

Quality products are a necessity to improve productivity; it gives the workers something

to take pride in. With BIM, buildings will be able to be estimated and bid more accurately.

Cutbacks will not be necessary to bring a project back within budget. Through the use of

conflict resolution, more attention can be set on construction detailing.

5.2 Conclusion

True benefits of BIM will be realized when architects, engineers, and contractors use the

software seamlessly between each other. Although this is a great program for the industry, it is

not the "end all" program. It is a program that has to be used in conjunction with the already

used programs of the various trades, i.e. the details that it generates are not suitable for

construction, and a separate CAD program is necessary for detailing construction elements

correctly (Figure 5-4).

5.3 Recommendations

For future analysis of BIM and productivity in the construction industry, a set of design

and interoperability standards has to be adopted, and a shift from CAD to BIM needs to happen.


























Figure 5-4. Section details from Revit Tutorial (Revit 2008).

Once this takes place, historical data will become more readily available, and surveys can be

conducted to compare the traditional method of construction against the BIM methodology. This

kind of information will be essential in figuring out the future of the industry, instead of just

relying on projections.

Future research needs to be done on interoperability with the various programs that are

essential to the AEC industry to see how well BIM can be integrated into daily use. Surveys

should be conducted to determine how well BIM is improving productivity, and how

productivity levels compare against other U.S. industries. This will become more readily

available once more historical data is gathered from construction and design firms that have

implemented the program.









APPENDIX A
LIST OF TERMINOLOGY AND ABBREVIATIONS

* 2D. A drawing that exists in only the X and Y planes

* 3D. A drawing that exists in the X, Y, and Z planes

* 4D. A BIM that can also be shown in a time stamp sequence, to show progress

* 5D. A BIM that can forecast cost analysis over the lifespan of the building

* A/E. Architects and Engineers

* AEC. Architecture / Engineering / Construction

* AIA. American Institute of Architects

* BIM. Building Information Modeling

* CAD. Computer Aided Drafting

* CM. Construction Management Firm

* IAI. The International Alliance for Interoperability

* IFC. Industry Foundation Classes

* INFORMATION. The Information / data that is obtained from the building.

* LEED Leadership in Energy in Environmental Design

* LIFECYCLE. Describes all the phases of the building process: design, construction documents,
procurement, construction, maintenance, additions, and demolition.

* MODELING. The model that houses, maintains, and controls the flow of information needed to
manage the building

* NBIMS. National Building Information Model Standards

* NIST. National Institute of Standards and Technology

* R&D. Research and Development

* RFI. Request for Information









APPENDIX B
INTERVIEW QUESTIONS AND ANSWERS

1. Company 1 (small general contractor)
2. Company 2 (small roofing contractor)
3. Company 3 (large design/build firm)

* How much time is spent analyzing construction documents prior to the construction
process?
1. Typically have three weeks to a month to prepare bids for a project.
2. Between two weeks and a month.
3. Since most jobs are fast-track, we start building as soon as we get the drawings.
* How long does it take to prepare a bid using a traditional set of construction
documents?
1. It takes the entire time we have the construction documents for review. Typically
we get our sub contractors bids the day before the base bid is due.
2. Typically between one or two weeks
3. -
* Approximately how many RFIs are submitted for a typical construction job?
1. This is dependent upon the architect and the owner, they range from 0 to 35,
depending on the complexity of the job.
2. Typically roofing jobs do not have many RFIs, but when substituting materials or
adding a roof penetration, there can be as high as 10
3. Proj ects that are fast-track typically have a lot of RFIs numbering into the
hundreds on a single project
* What is the average time spent waiting for a return on an RFI?
1. the average time is around two weeks to three weeks
2. two weeks
3. It depends on how difficult the question is, but typically they are answered within
a week, and sometimes the same day.
* How much time is spent conversing with the Architect/Engineers about the
construction job?
1. Before the construction begins, very little during construction, regular monthly
progress meetings are held, and correspondence continually occurs
2. not much at all, both before and during construction
3. There is an open dialogue between the architects/engineers and contractors
throughout the entire project.
* Are you currently using Building Information Modeling at your office?
1. No
2. No
3. Yes, we are implementing BIM on projects that lack complexity, but use 3d
design regularly in the construction process.
* If not, do you foresee changing over to some kind of a BIM system at your
construction company?
1. No, it would be to large an investment and change for our company
2. No
3. -









* If so, what problems have you encountered using the BIM process?
1. -
2. -
3. BIM is a great concept, problems occur because fast-track jobs are started with
50% completion of construction drawings. The problem with BIM is that the
drawings have to be complete to gain any benefit from estimating the job and
developing the drawings.
* Do you implement any productivity improvement practices with your construction
crews and if so, what?
1. No
2. No
3. -


4. Company 4 (Design Firm)

* What BIM software do you use?
a. Digital Project

* When did you start utilized BIM in the design process at Ghery Technologies?
a. I was a co-founder of Ghery Technologies with Frank Gehry and Jim Glymph.
Ghery Technologies was established in 2002.

* How would you compare Digital Project with Autodesks Revit?
a. They similar in scope and are used to create BIMs, but Digital Project is a more
complicated and advanced system.

* What are the benefits of using BIM that Ghery Technologies has observed?
a. The benefits that we have been experiencing with BIM are:
A 40% elimination of unbudgeted changes (change orders)

Cost estimate accuracy of 3%

Less than 1% cost growth

Bids within 2.5% of actual construction costs

60% less Requests For Information (RFIs)

80% reduction in time to generate a cost estimate

Overall savings of 10% of contract sum through clash detection
(coordination)

7% schedule cost reduction

10 to 20 times the return on investment though its life cycle analysis









* How many projects have you used BIM on?
a. There have been 32 major projects accomplished using BIM

* How long before you expect the majority of AEC to convert over to a BIM system?
a. It will probably take around seven years









LIST OF REFERENCES


Adrian, James. (2004). Construction Productivity: Measurement and Improvement, Stipes
Publishing L.L.C., Champaign, IL.

The American Institute of Architects. (2007). "Preparing for Building Information Modeling."
(Nov. 12, 2007).
Originally published in "Guidelines for Improving Practice", Vol. XXXV No. 2.
Reprinted with permission of Victor O. Schinnerer & Company Inc.

Bedrick, James R, AIA. (2006). "The Architect's Handbook of Professional Practice". John
Wiley & Sons, New York, N.Y.

Cole, Noah. (2006). "Autodesk and U.S. Green Building Council Partner on Technology
Initiatives to Move Building Industry Toward Greener Future."
(Jan. 23, 2007).

Eastman, Charles M. (1999). Building Product Models: Computer Environments, Supporting
Design and Construction, CRC Press LLC, Boca Raton, FL.

Elvin, George. (2003). "Tablet and Wearable Computers for Integrated Design and
construction."(Oct. 8, 2007).

Elvin, George. (2007). Integrated practice in architecture: mastering design-build, fast-track, and
building information modeling / George Elvin, John Wiley & Sons, Hoboken, N.J.

Fischer, Martin and Kunz, John. (2004). "The Scope and Role of Information Technology in
Construction." (Jan. 12, 2008).

Fortmeyer, Russell. (2008). "SOM's Pearl River Tower."

(Mar. 22, 2007).

Fukai, Dennis. (2006). Building Simple: Building an Information Model, Insitebuilders, Archer,
FL.

Gehry Technologies. (2004). "Jim Glymph to Present at Conference on Building Information
Modeling."
(Nov. 12, 2007).

Ho, Cathy Lang and Menking, William. (2006). "Super Modeling."
(Sep. 15, 2007).

Howard, Rob. (1998). Computing in Construction: Pioneers and the Future, Butterworth-
Heinemann, Woburn, MA.









Keller, Chris. (2004). "Interoperability at Dow Jones & Company."
bility.pdf&vid=13676&CFID=627806&CFTOKEN=45406879> (Feb. 8, 2008).

Khemlani, Lachmi. (2006). "The AGC's BIM Initiatives and the Contractor's Guide to BIM."
(Jan. 22, 2008).

Mosca, Peter L. (2007). "Building Information Modeling Adoption Accelerating, CMAA/FMI
Owners Survey Finds."
(Jan. 13, 2008).

National Institute of Standards and Technology (NIST). (2007). "General Buildings Information
Handover Guide: Principles, Methodology and Case Studies."
(Feb. 3, 2008).

Office of the Chief Architect. (2006). GSA Building Information Modeling Guide, 1st Series,
Washington, D.C.

U.S. General Services Administration. (2006). "3D-4D Building Information Modeling." U.S.
General Services Administration. (Aug. 28, 2007)









BIOGRAPHICAL SKETCH

Joseph C. Kuehmeier earned his master's (MSBC) degree from the M.E. Rinker, Sr.

School of Building Construction at the University of Florida. During his studies he worked as an

associate architect for CRG Architects / Palatka Inc. where he dealt with all phases of the design

and construction process. Prior to earning his MSBC he earned a bachelor of design in

architecture from the University of Florida, graduating cum laude, and earned a Master of

Architecture (MArch) from the University of Florida. He is currently working on achieving his

architectural license in conjunction with his contractor's license.

Joseph's research interest are related to how the design and construction processes can

communicate together seamlessly using a common digital language. He has five years'

experience in the design industry and looks forward to future endeavors in the design/build

environment.





PAGE 1

BUILDING INFORMATION MODELING AND ITS IMPACT ON DESIGN AND CONSTRUCTION FIRMS By JOSEPH CARL KUEHMEIER A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLOR IDA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN BUILDING CONSTRUCTION UNIVERSITY OF FLORIDA 2008 1

PAGE 2

Joseph Carl Kuehmeier 2

PAGE 3

To my wife and family, for keeping me focuse d on the prize, and for giving me the opportunity to better myself. To them I will be forever grateful. 3

PAGE 4

ACKNOWLEDGMENTS I would like to thank the School of Building Construction for accepting me into their program and the faculty for passing their knowledge and life experiences to me. I would like to thank Dr. R. Raymond Issa, Dr. Svetlana Olbina, and Dr. E. Douglas Lucas for serving as my committee members. Their knowledge and direction were critical to the completion of my thesis. I would like to thank my family, for without their support, I would not be finishing school right now. They have been the f oundation and all that I have done is in honor of them and their support. 4

PAGE 5

TABLE OF CONTENTS page ACKNOWLEDGMENTS ...............................................................................................................4 LIST OF TABLES ...........................................................................................................................7 LIST OF FIGURES .........................................................................................................................8 ABSTRACT .....................................................................................................................................9 CHAPTER 1 INTRODUCTION................................................................................................................. .11 1.1 Building Information Modeling ........................................................................................12 1.2 Statement of Purpose ........................................................................................................12 1.3 Objective of Study ............................................................................................................13 1.4 Scope and Limitations ......................................................................................................13 2 LITERATURE REVIEW.......................................................................................................15 2.1 Principles of Building Information Modeling ..................................................................15 2.1.1 Increasing Value Through Shared Information ......................................................19 2.1.2 National Building Information Modeling Standards (NBIMS) ..............................20 2.1.3 Collaborative Working ...........................................................................................21 2.2 Productivity .......................................................................................................................24 2.2.1 Productivity in the Construction Industry ..............................................................26 2.2.2 Input into Design ....................................................................................................28 2.2.4 Ten Step Program for Improving Productivity .......................................................31 2.3 Advantages and Disadvantages of BIM ...........................................................................31 2.3.1 Proponents of BIM .................................................................................................33 2.3.2 Disadvantages of BIM ............................................................................................36 3 METHODOLOGY.................................................................................................................3 8 3.1 Productivity .......................................................................................................................38 3.2 Advantages and Disadvantages ........................................................................................39 3.3 Interviews .........................................................................................................................39 3.4 Process of BIM .................................................................................................................40 4 INTERVIEW RESULTS........................................................................................................42 4.1 Small Construction Companies ........................................................................................42 4.1.1 Construction Company 1........................................................................................42 4.1.1 Construction Company 2........................................................................................43 4.2 Company 3: Large Design / Build Firm ...........................................................................44 4.3 Company 4: Architectural Design Firm ...........................................................................44 5

PAGE 6

5 CONCLUSIONS AND RECOMMENDATIONS.................................................................46 5.1 Increasing Productivity with BIM Using Adrians Model ...............................................49 5.1.1 Making the Project Look Like a Firm Rather Than a Job: Developing a Personnel Management Program .................................................................................49 5.1.2 Improved Communications ....................................................................................49 5.1.3 Planning a Productive Site Layout.........................................................................49 5.1.4 Challenging the Work Process ...............................................................................50 5.1.5 Developing a Scientific Work Standard Versus an Accounting Based Standards ......................................................................................................................50 5.1.6 Planning and Scheduling ........................................................................................50 5.1.7 Project Control and Productivity Improvement.....................................................50 5.1.8 Equipment Management to Enhance Productivity .................................................51 5.1.9 Productivity Improvement through Safety .............................................................51 5.1.10 Productivity through Attention to Quality ............................................................51 5.2 Conclusion........................................................................................................................51 5.3 Recommendations .............................................................................................................51 APPENDIX A LIST OF TERMINOLO GY AND ABBREVIATIONS.........................................................53 B INTERVIEW QUESTIONS AND ANSWERS.....................................................................54 LIST OF REFERENCES ...............................................................................................................57 BIOGRAPHICAL SKETCH .........................................................................................................59 6

PAGE 7

LIST OF TABLES Table page 2-1 Productivity increases for various industries (2002) ..............................................................27 2-2 Reasons for nonproductive time in the construction industry ................................................27 7

PAGE 8

LIST OF FIGURES Figure page 2-1 Relationship of a BIM to all facets of the AEC industry. Courtesy of NBIMS AEdgar 2006. .....................................................................................................................18 2-2 Combining multiple models into a com posite model (Contractors Guide to BIM 2006) ......22 2-3 A section of the BIM model for On e Island East tower in Hong Kong, Gehry Technologies (The Architects Newspaper 2006) .............................................................23 2-4 Frank Gehrys Stata Center located at the Massachusetts Institute of Technology (MIT). Image courtesy of 2006 http: //philip.greenspun.com/copyright/ ...................................24 2-5 Distribution of construction company size by number of employees, 1996. (Dr. E. Douglas Lucas, 2008) ........................................................................................................28 2-6 Analysis of productive and non productive time during a typical construction project (Adrian 2004).....................................................................................................................29 2-7 Reciprocal relationships between various parties involved in the design process and the BIM project ........................................................................................................................30 2-8 Computer modeling to analyze air temperat ure distribution to dete rmine the benefits of displacement ventilation in the courtroom lobby (Google image 2007) ...........................35 2-9 The Pearl River Tower includes integrat ed wind turbines and phot ovoltaic panels to offset its energy use. (Fortmeyer 2008) .............................................................................35 5-1 A 3D polygon model and 2D lines and text compose a set of integrated construction documents. Images courtesy FacilityGenetics (NIBS 2006). ...........................................46 5-2 Virtual construction documents and installation photograph. Images courtesy FacilityGenetics, LLC and Ghafari Associates (NIBS 2006)............................................47 5-3 Installation process and equipment requirement. Accurate steel sizes, members, weight and cost. Images courtesy Kling (NIBS 2006). ................................................................47 5-4 Section details from Re vit Tutorial (Revit 2008). ..................................................................52 8

PAGE 9

Abstract of Thesis Presen ted to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Master of Science in Building Construction BUILDING INFORMATION MODELING (B IM) AND ITS POTENTIAL IMPACT ON SMALL CONSTRUCTION FIRMS By Joseph Carl Kuehmeier May 2008 Chair: R. Raymond Issa Cochair: Svetlana Olbina Major: Building Construction The Construction industry is a business fo cused around providing a product through the traditional construction process, which remains for the most part, independent of the design process. With the growing changes in t echnology, many areas of production and business (outside of construction) are being refined and redefined, leav ing the construction industry behind. Process of construction is still basica lly the same as it was hundreds of years before, from a set of drawings, a building in erected. For the most part, these drawings are never without errors and omissions, causing many dela ys, multiple change order items, and late projects completion. With the advent of Building Information Modeling (BIM) software, the Designer/Architect is given the opportunity to de sign the building, and the software develops the appropriate plans and sections needed for construction. This is good for the designers because the project is completed in 3-D and most, if not all conflicts can be resolved before construction begins. These are just the initial benefits that BIM can potentially help the design and construction industry. 9

PAGE 10

Design/Build firms can be extremely effici ent because they house both the designers (Architects and Engineers) and the Construction Management pr ofessionals; however they still operate with the same flawed system of desi gners generating construction drawings and the construction team erecting the building. More advancements can be made to increase productivity in construction, reduce requests for information, eliminate coordination problems, decrease construction time, and increase quality. The BIM Software is the gateway to solving these issues. With dynamically linked on demand modeling, ch anges can be made by Designers in a remote location that would update digital construc tion drawings at the jobs ite. Project managers on site can propose changes to the design team with no delay time. Means of construction can be displayed in 4-Dimensions for an increased understanding of constr uction sequencing by the contractor on site. Any and a ll questions can then be answered immediately and virtually from any location. Understanding the potential that BIM software has to offer and implementing it into the construction industry can be the next great a dvance since the advent of power tools and equipment, however this innovation has many i ssues that need to be resolved before implementation of the software would be gene rally accepted. Once done, its full integration to improve productivity for the AEC industry will be si gnificant. This change over will be market driven by the owners of projects and come at a large initial cost for all construction companies, large and small. 10

PAGE 11

CHAPTER 1 INTRODUCTION Construction is a labor intensive industry that has remained relatively unchanged for hundreds of years. Traditionally, a construc tion project, consisti ng of drawings and specifications, is delivered by architects and engineers to the owners/cli ents of the proposed project, with a warranty that the design is comple te and free of any defects. Owners then put the project up for bid among a selected list of contractors; the lowest bid typically being awarded the job. Once the construction documents are in th e possession of the general contractor and construction begins, the relationshi p between general contractors, architects and engineers also begins. This relationship tends to be typically li mited and distant. Any changes or discrepancies that occur in the drawings are corrected, typically, by a long trail of paperwork, for a contractual period of time per each request for information (RF I). This can stifle productivity on the job site because of trades waiting for pertinent inform ation, and it can decrease morale among crew members, which also decreases productivity. Over the years, there have been many tec hnological advances for architects, engineers and contractors. Architects and engineers are constantly updated w ith the most advanced computer programs to help in all aspects of thei r specific profession. Cont ractors have relied on large construction equipment to perform tasks, and computer programs to help in the estimating and scheduling process for construction, both of which are integral in determining whether on not a construction project will be profitable and if the construction company will continue to stay in business. There have been numerous advanc es in technology between the two sides of the industry, Architects/Engineers (A/E) and Contra ctors, but when information is exchanged between the two, it is co ntinually done on paper in a 2-Dimensional (2D) representation. 11

PAGE 12

This is an inherent problem between the A/ E, and Contractors; th e problem being that Architects take a 3-Dimensional (3 D) image in their mind and, to th e best of their ability, relate that information in 2D drawings on paper. Drawings are then realized in physical form by the general contractor, based on their ability to infer th e design intent of the A/ E. With the influx of technological advances in the construction industry, it stands to reason th at the advancement having the largest, most influential impact woul d be one that changes the way in which the Architects and Engineers exchange information w ith the general contractors, sub-contractors, and suppliers. 1.1 Building Information Modeling This technological advancement is being heavily promoted by Autodesk with the program Revit, which is used to develop Build ing Information Models. Building Information Modeling (BIM) software is a dynamically linke d interface designed to take the place of redundant computer aided drafting (CAD) work. Idea being, architects are free to design, and the software generates the plans, sections, and elevations. Any changes to the documents change any other instance of it throughout the drawi ngs, to improve coordination. Reduction in coordination issues will reduce RFIs, which w ill increase productivity. Knowledge of the program is essential for the general contractor on site to make suggestions to the architects and engineers who address unanticipated field condi tions, this will reduce non-productive time on a jobsite and increase construction job efficiency and productivity. 1.2 Statement of Purpose Purpose of this study is to research BIM and how it can be used successfully by both designers and builders. Since BIM is supposed to be the process that both sides of the construction industry can use for their specific n eeds, just how well can this BIM software meet their needs in conjunction with the specially tailored programs developed for designers and 12

PAGE 13

builders? Interviews were conducted to gage how BIM is being received by architects, engineers, and contractors; and how BIM can help construction companies improve their methods of construction and incr ease productivity. Intention bei ng, to gain an understanding of BIM, to determine the shortcomings of the progr am and to become aware of the barriers to implementation that this program will o ffer in todays very technological world. 1.3 Objective of Study Objective of this thesis is to study both the assets and limitations/complications with implementing a BIM program in the design/cons truction industry. With knowledge of the program and how it works; the benefits of how BIM can increase productiv ity in the construction industry can be projected. With this objective, interviews were conducted with local large (1) and small (2) construction companies, to determine the possibility of implementing BIM into their daily operations. Their perspectives will also be attained about using BIM on projects, it benefits to productivity and its disadvantages. 1.4 Scope and Limitations Scope of this thesis involves doing res earch on what Building Information Modeling actually is, based on its core components. Research on BIM will make the benefits and limitations more readily understood. Research was also done on productivity improvements in the construction industry. Knowledge of practical concepts and initiative s used in the present construction industry are essent ial in knowing how the construc tion industry works, and more importantly, how BIM can influence the construction industry. How BIM is being used in the AEC industry is revealing difficulties that have to be addressed. Limitations are encountered because hist orical data is not readily available due to the lack of recordkeeping. This software is still in its infancy, and although most experts consider BIM to be the future of the construction industr y, the change over by arch itects and engineers is 13

PAGE 14

very slow. In the construction industry, BIM is more widely accep ted because of the ways that it links with currently used scheduling and estimating software. 14

PAGE 15

CHAPTER 2 LITERATURE REVIEW With the rapid adoption of BIM in th e construction industry, and its gradual implementation in the design indus try, careful considerations have to be taken when making the change over from the traditional method of cr eating construction documents towards a BIM approach. There are plenty of positives, negati ves, and unknowns that have to be considered when implementing BIM. This chapter will discuss research that was done about the background of BIM, its perceived positive and ne gative effects, and productivity improvements for the AEC industry. 2.1 Principles of Building Information Modeling International Alliance for Interoperability (IAI) was formed in September 1995, and since its release, has published three major releases of the Industry Foundation Classes (IFC). This was the beginning of setting standards for object based data modeling. Standards that would define the interoperability of object based data modeling for the AEC industry. Idea being that multiple vendors would be able to access a buildi ng model to supply data to the architects and engineers in a 3D space. Interoperability is the dynamic exchange of information among all applications and platforms serving the entire building community throug hout the life cycle of facilities (Keller 2004). Therefore, no matter what programs were being used across the broad spectrum of vendors, there would be a medium to tr ansfer data to something that others in the industry could access, this me dium being the 3D model. Although these guidelines were set, they would need back ing from major software companies in order to gain a foothold. Once Autodesk decided to acquire Revit (the same company that controls the most widely used computer drafting program, AutoCAD) the BIM era 15

PAGE 16

began to hit the main stream. With so large of a parent company, Revit has become the staple in the industry for BIM. BIM is a brand new design methodology and is de fined by Autodesk (2004) as: a building design and documentation methodology characteri zed by the creation and use of coordinated, internally consistent computable information about a building project in design and construction. BIM incorporates the use of 3D visualization t echniques with real-time, data driven, objectbased imaging as a tool by all facets of the industries (Holness 2006). This is a change from the current practice of; designs being manifested a nd put to paper with engineers then designing the structure and other supporting el ements of the building. After completion of the design documents, a 3D model can be genera ted for the owner showing digital walkthroughs and to provide 3D renderings of spatial relationships. These t ools are very useful to convey design intentions to owners and clients that who not able to visualize 3D space from 2D drawings. These can be very expensive and time consuming to produce. BIM greatly increases the users ability to co ntrol and manipulate data and information in an unprecedented way and in an interoperable format. Moving from paper-centric information to parametric, model-based information means that the digital design can be used for cost estimations, simulations, scheduling, energy an alysis, structural design, GIS integration, fabrication, erection, and facilities management (Seaman 2006). All of which are relative to each other, and changes in one category will have impacts on the others that are automatically accounted for. Since all of the above inform ation is dynamically linked, productivity from recalculation of simple and minor changes will be greatly increased because the computer program will be able to handle the changes and calculations internally. BIM application software has the capabi lities of other modeling programs like sketch-up and 3D studio max, which archit ects traditionally use for generating walkthroughs and to convey spatial relati onships. The difference being that this 16

PAGE 17

program will also be able model the HVAC, steel, structures, hot water pipes, cold water pipes, and communications. Not only will the program model this, but will correlate them with each other to fi nd conflicts. Upon recognition of one, the program will mark it and send a flag for corrections to be made. Changes will then be made to make the program satisfie d, but this could prove to be detrimental if the code does not allow the change. Careful consideration needs to be taken when implementing changes to accommodate the BIM software (Seaman 2006). Documents a BIM can generate include, but ar e not limited to, drawings, lists, tables, and 3D renderings related to the project. Thereby contributing more to efficiency, and provide superior accuracy than traditional 2D CAD dr awings (OCA 2006). Building models embedded with detailed information about a construction project are far be yond the capabilities of most design firms at present (which is why historical data is difficult to find and analyze, as it relates to productivity). These models are not just the electronic drafting to ols that firms now think of as digital practice, nor are they three-dimens ional renderings with separate construction documentation (Seaman 2006). These are object ba sed digital models which the program itself constructs the appropriate plans, details, and sections from. A ny change in one aspect of the drawings, will automatically be accounted for in the other drawings. The BIM process has the potential to remove the guesswork about how the most difficult part s of a building come together, which tend in most cases to be the corners. These models also transcend 3D and can be manifest in 4 th dimension (4D) and 5 th dimension (5D). Projects can digitally be built in the computer environment, showing any possible conflic ts with the schedule; this is an incredible tool to relate information to the owners and show models for future produc tion. If delays arise, they can be input into the model, and BIM will be able to determine any the necessary changes in the schedule. Four D (4D) models link component s in 3D CAD models with activities from the design, procurement, and construction schedules. Resulting 4D models allow project stakeholders to view the planned construction of a facili ty over time on a computer screen and to 17

PAGE 18

review the planned or actual st atus of a project in the contex t of a 3D CAD model for any day, week, or month of the project (Fisher and Kunz 2004). The 5D represents the money aspect of the pr ogram (Figure 2-1). Projects will have the materials for construction estimated, and work up a cost of material proposal. Changing materials for Bid Alternate purposes will be easy to see both the immediate cost impacts, but also a life cycle costing to the owner (AEdgar 2006). Moving to an integrated, parametric, and object-based system should lead to dramatic changes in design and construction as well as, possibly, compensation and risk allo cation. Life cycle cost analys is can project to the owners, cost savings and operational cost s over the lifetime of a building. This information can Figure 2-1. Relationship of a BIM to all facets of the AEC industry. Courtesy of NBIMS AEdgar 2006. 18

PAGE 19

prove to be very important in determining feasibili ty of a project. This information is also very important for determining whether a project m eets Green Building specifications or LEED accreditation. A BIM can be used with distributors for estim ating cost of materials and the ability to control the cost of the building is very captivatin g to the owners. Materi al suppliers can insert their specific data and cost in to the BIM with the appropriate cost factors, and from this information, a hard dollar cost and a solid estim ate can be generated, which will be the actual cost of the building. Changes can then easily be made to any of the specified products, creating new estimates and building costs. When changes are made, they can then be assignable to the architect, engineers, or owners. This can then determine responsibilities for payment on change orders (Seaman 2006). 2.1.1 Increasing Value Through Shared Information Results of this design methodology is not just a creation of the Architects design intentions and spatial relationshi ps shown in 3D, a BIM is a re pository for digital information and data generated by the design process and simulations; it is the design, fabrication information, erection instructi ons, specifications, materials pa lette, schedule, and project management logistics in one database (Schinnerer 2006) Data models will exist for the life of a building, can be used to manage the clients asse t, and will exist as the As-Built documents for future additions, renovations, and upgrades. Because the true benefit of a BIM is to the project owner, the push to use a BIM will most likely be a client-driven de velopment. Many owners see the single point of responsibility in integrated practice as an attractive alternativ e to the over-the-wall method of design and construction in which an architect completes a design and hands it over to a contractor for construction (Elvin 2007). The value is in the significant building efficien cies and initial cost 19

PAGE 20

savings and extends to the operations and mainte nance of the facility (Guidelines for Improving Practice 2007). Speed, accessibil ity, communality, and adaptability are achieved by the use of a common database, early information user input, knowledge representation and information technology, team collocation, and information ex change in small batches (Elvin 2007). Based on expert studies, othe r benefits of BIM include reduced risks, improved productivity, streamlined production, maintenance of design intent, and facilitation of quality control through clear co mmunication and sophisticated anal ytical tools (Guidelines for Improving Practice 2007). All of which will be r ealized from conception, thru construction, to the life cycle analysis of the building. 2.1.2 National Building Information Modeling Standards (NBIMS) Once software had been established for th e new design methodology and development of construction drawings, NBIMS set forth to devel op standards to be followed by those using the software. With the adoption of CAD programs, a set of standards was never initiated, which is why construction drawings from different Architect ure firm can be virtually similar, but have distinct differences in how th ey are shown, drawn, and notated. Early CAD programs were not interoperable with other program s specific to the AEC industry. National Building Information Modeling Standards advocates that BIM is the future of the AEC industry and has been trying to develop a set of universal standards for the industry to follow. This is one of many components that will make using BIM a more productive asset for the AEC industry to use. Knitting together the br oadest and deepest constituency ever assembled for the purpose of addressing the losses and limita tions associated with errors and inefficiencies in the building supply chain is the goal (Davis 2006). These standards are an integral part of ma king interoperability between all phases of a construction projects life from inception onward. Without this, using a BIM would essentially be 20

PAGE 21

pointless. Documents, that set standards for BIM, must overcome the impediments that have begun to be identified so the implementation of BIM, for the entire industry, to be successful. 2.1.3 Collaborative Working The most beneficial aspect of using BIM technology with soft ware like Revit is the way it changes the design process. A BIMs goal is to recognize the pot ential benefits that collaborative working through all stages of design and construction can offer. This happens to be the hardest thing to implement in the design pr ocess being that there ar e complications for the interoperability of the design data. In all likelihood, multiple models will be produced in different disciplinary BIM applications and thes e will have to be combined into one composite model for visualization, clash detection, and other tasks (Figure 2-2). At the same time, the guide emphasizes that it is not ne cessary to create all the models to derive the benefits of using BIM on a project. Contractors can make many "par tial uses" of BIM such as assisting with scoping during bidding and purchasing, reviewing portions of the proj ect scope for analyses such as value engineering, coordina ting construction sequencing (eve n if just for two trades), demonstrating project approaches during mark eting presentations, and so on (Khemlani 2006). Despite the great potential for collaborative wo rking in the design stag e of a project, this has not yet been fully exploited, due to the lack of applicable information exchange standards that can be widely adopted by th e project team. While a great deal of attention has been focused on interoperability of design applications between design disciplines, there has been less focus on the specific information needs and exchange capabilities of the cost consultant (The IT Construction Forum 2006). Cost consultants are integral to collaborative working in determining the costs of construction. This is something that BIM software is programmed to calculate automatically, 21

PAGE 22

from proper input in the digital model, this can save construction management firms time in the estimating process. It has been shown, however that BIMs sometim e miss-calculate the measurements of high level information. Currently, the wider uses of BIMs incorporate the capacity to generate measurements automatically from objects created by designers. This capability is being actively promoted although its application on live projects has been limited (The IT Construction Forum 2006). Forward thinking cost consultants can wo rk collaboratively with design and construction firms that implement BIM into their projects, however they will continue to rely upon the quality Figure 2-2. Combining multiple models into a composite model (Contractors Guide to BIM 2006) 22

PAGE 23

and consistency of design information. Since a BIM is produced by a computer program, it has the same flaws that any other computer program has, it is limited by the ability of the user. Garbage in, garbage out, will be a mantra that will have to be acknowledged and constantly checked for. With the newest technologies and digital design, buildings are becoming more complex, the state of the art HVAC systems (Figure 2-3), and buildings are breaking the mold in a way that was never done before, and this is all a ttributed to computer de sign (Figure 2-4). Cost consultants are developing new wa ys of working in order to pr ovide the best cost estimates possible given complicated designs. Although BIM software is able to keep record of how much material is used, it is not able to determine how much labor and effort are re quired to construct these new and complicated designs, this is a specialty of cost consultants. They will become vital to construction estimators on very complex projects. Additionally, there will be no overnight conversion to collaborative Figure 2-3. A section of the BIM model for One Island East tower in Hong Kong, Gehry Technologies project with st ructural engineers, Arup. The drawing shows several floors of a mechanical zone halfway up the tower. HVAC systems are green; plumbing and electrical are purple and blue, respectively; and steel is gray. (The Architects Newspaper 2006) 23

PAGE 24

Figure 2-4. Frank Gehrys Stata Center located at the Massac husetts Institute of Technology (MIT). The construction documents of this building are impossible to represent totally and accurately in 2D. The use of BIM was essential to the construction of this building. Image courtesy of 2006 http://philip.greenspun.com/copyright/ working, but for those practices which have the opportunity and capability to respond positively, the eventual gains could be substant ial (The IT Construction Forum 2006). 2.2 Productivity Construction has remained unchanged for centuries, being a process where manual labor is used to place building component s to erect structures. This present delivery system, in its current form, consists of: Programming: With the owners input, an architect determines what the owners needs are and what supporting programmatic elements are essential for the building. Schematic design: Architects draw a conceptual spat ial plan on paper. The owner then reviews the drawings and a pproves or suggests changes Designed development: Architect gets feedback from design professionals, i.e. the structural, mechanical and civil engineers. 24

PAGE 25

Construction drawings: Final developed drawings passe d onto owner. Owner then approves the drawings to begin construction. Bidding: Contractors attain the c onstruction drawings and estimat es are prepared to submit back to the owners. Construction: After awarding the job to the co ntractor, construction begins. Adrian (2004) writes that over the years there have been many technological advances in the construction process that have both increased the rate of construction, and supplemented the complexity of the construction processes. Larges t impacts are from the advent of the mechanical crane, which enabled large heavy construction units to be moved quickly over vertical distances. This is widely responsible for the completion of complex designs for Gothic Cathedrals. With technological improvements to the crane, skyscrap ers were able to be erected, something that was previously not attainable. Mechanical cran es have had a tremendous impact on productivity in the construction industry, but the cons truction process has remained unchanged. Another great technological adva nce was with the advent of th e cell phone. Lots of time was wasted, in comparison to todays standards, either waiting for clarifications on information or merely having to be off site to take calls Productivity has dramatically improved, because cell phones receive and place calls, but also co me with personal organizers and phonebooks. Now construction managers can make calls to Engineers and Architects while on the jobsite, being able to maintain supervision on constr uction workers. Supplie rs can contact the job superintendent to confirm delivery appointments. This is perhaps the most recent technological advance to improve productivity in construc tion but what lies on the horizon is BIM. Building Information Modeling has the poten tial to revolutionize the construction industry, although it is not without it s potential drawbacks, and the benefits of BIM have yet to be documented since it is still relatively new to the construction industry. Productivity is the biggest selling point for the utili zation of BIM in the AEC industry; therefore productivity has to 25

PAGE 26

be studied and forecasted since information for BIM on productivity is limited, specifically to the smaller construction firms that make up the majority of the cons truction industry. 2.2.1 Productivity in the Construction Industry Productivity and quality in th e construction industry have been on the decline over the years. In fact, construction produc tivity increases (see Ta ble 2-1) are the lowest out of all listed individual industries accordi ng to the U.S. Department of Commerce (Construction Review 2002). Construction productivity increased was a dismal 0.80% in 2002. Reasons for this dismal amount of increased productivity is because of the high turnover rate in the construction industry, the duration on a project is typically only a year, so th ere is no chance for a learning curve to have an affect for each specific j ob, and the sub-contractor/general contractor relationships are continually ch anging. In one study, a Federal Price Commission concluded that an industrys ability to increase productivity is directly dependen t on the degree to which it can set productivity standards (Adrian 2004). Implem entation of BIM throughout the industry will help set productivity standards to follow. The biggest factor that reduces productiv ity on a construction job is the amount of nonproductive time spent by laborers. Reasons for this can be attributed to a number of factors (see Table 2-2). This study will examine the possibilities of utilizing BIM to increase productivity in the following areas : industry related, labor related, and management related. This is particularly important for small size construc tion firms. As shown in Figure 2-5, the majority of construction firms that make up the constr uction industry are small companies, having less than 15 workers. These firms account for more than 10% of the gross national product annually and are most in need of some measures to im prove productivity; unfort unately therein lays a problem. Small firms are hesitant to invest in research and development (R&D) or optimal 26

PAGE 27

Table 2-1. Productivity increases for various industries (2002) Industry Productivity Increase (%) Agriculture 3.64 Construction 0.80 Government 1.64 Manufacturing 2.60 Mining 3.17 Public Utilities 5.40 Transportation 4.60 Source: Construction Review, U. S. Department of Commerce, Washington D.C., 2002 computer programs to improve productivity. There ar e number of barriers that keep contractors from using the latest technology, in cluding fears (legal/risk fears, fear of change, fear of the unknown, etc.), initial investment co sts, the time to learn how to use the software, and perhaps Table 2-2. Reasons for nonproductive time in the construction industry Industry-related Labor-related Management-related factors factors factors Uniqueness of many projects Locations at which projects are built Adverse weather and climate seasonality Dependence on the economy Small size of firms Lack of R & D Restrictive building codes Government labor and environmental laws High percentage of labor cost Variability of labor productivity Supply-demand characteristics of industry Little potential for labor learning Risk of worker accidents Union work rules Low worker motivation Poor cost systems and control Poor project planning Poor planning for measuring and predicting productivity Source: James J. Adrian, 2004 27

PAGE 28

Figure 2-5. Distribution of construction company size by number of employees, 1996. (Dr. E. Douglas Lucas, 2008) the lack of support from the senior leadership of the company, which may be the biggest barrier for many (Khemlani 2006). Building Information Modeling requires both research and development to implement into a construction comp anies process and a rath er large investment. Software that can manipulate BIMs, like Revit, cost about $6,000 per license. Cost of the software and training make it difficult for small construction companies to justify purchasing and implementing. This study will make a case for small construction firms to invest in a BIM program for their future survival in a changing in dustry. Estimates have also suggested that as much as 30% of project costs are wasted thr ough poor management of the design-construction process (Brown and Beaton 1990). This is repr esented accurately in a study done by Adrian (2004) showing that roughly 50% of a constructi on laborers day is wasted either waiting for materials, or just not performing (Figure 2-6). Changes are an absolute necessity to increase productivity. 2.2.2 Input into Design With the traditional relationship between the architect, owner, and contractor, the contractor has very little, if any, say about the de sign of a project. This gives the Architect the 28

PAGE 29

Figure 2-6. Analysis of producti ve and non productive time during a typical construction project (Adrian 2004) complete freedom to design any type of buildi ng they wish, contingent upon approval by the owner. Next, the drawings are turned over to the owner for competitive bidding by various contractors. Since the relationshi p between the contractor and arch itect starts after the drawings are complete, there is little input that the contractor can offer to improve productivity during the construction process. During the design phase of a project, the archit ect will prepare several levels of estimates on the size, quality, and cost of the building. This is based on their conception of the cost for building the project. Mo st architects base their costs on histor ical construction square foot costs of similar projects and neglect market trends and cost of materials. Small cost increases can have dramatic impacts of the final cost of a bu ilding. There is no doubt th at if the estimates are grossly incorrect, both the quality of the project and the time it takes to complete it suffer (Adrian 2004). 29

PAGE 30

Using a Construction Management (CM) firm early in the design process will result in more accurate preconstruction estimates that will keep the owner more informed for bankroll and cost purposes. Fully integrated BIM design pr ocess links the CM to the architect at the beginning of the design phase. Each of them w ill have input to the design of the building, and the end result will be a more cost effective bu ilding due to the increased productivity from this type of relationship. They enable the explor ation and improvement of the project executing strategy, facilitate improvements in construc tability with corres ponding gains in on-site productivity, and make possible the rapid identif ication and resolution of time-space conflicts (Fisher and Kunz 2004). Although this system offe rs a more complex design process, it allows all participants to input the best possible s cenario for a constructi on project (Figure 2-7). Mechanical Engineer Owner Tenant Construction Manager Interior Designer Electrical Engineer Structural Engineer Civil Engineer Architect Building Information Model Figure 2-7. Reciprocal relationshi ps between various parties invol ved in the design process and the BIM project 30

PAGE 31

2.2.4 Ten Step Program for Improving Productivity The ten step program for improving productivity in the construction industry as written by Adrian (2004) is as follows: 1. Making the project look like a fi rm rather than a job; developing a personnel management program. 2. Improved Communications 3. Planning a Productive Site Layout 4. Challenging the Work Process 5. Developing a scientific work standard versus an accounting based standards 6. Planning and Scheduling 7. Project Control and Pr oductivity Improvement 8. Equipment Management to Enhance Productivity 9. Productivity Improvement through Safety 10. Productivity Through Attention to Quality 2.3 Advantages and Disadvantages of BIM Parametric modeling as the design and construc tion database is a difficult one to examine from practice and insurance-coverage perspectives. Firms will have increasing challenges as they realize that they are moving fr om a physical modeland hard-copy plans and specificationsto the primary information generators for a digital database ( Guidelines for Improving Practice 2007). Some problems with BIM will be related to liability. With the op en access to the model from all aspects, (anyone involved in the construction project) how can engineers or architects be expected to sign a set of drawi ngs, placing their liabil ity on the line? This major issue could have potentially huge detrim ental effects on productivity. 31

PAGE 32

As A/E firms move from an analog system, where original construction documents are easy to identify and monitor, through our presen t semi-integrated system, to what could be called a super-integrated future, those firms will have to deal with new business rules and possibly unknown liability exposures. This happens because owners, CM, sub-contractors, and suppliers are supplying information to the BIM; and has all been done in a collaborative effort to streamline the design and construction process. Desired results are focused on a project that takes less time, is more economical, and less costly. The driving theory behind BIM is the elimina tion of change orders and RFIs that occur because of missing information in the constructi on documents since all th e parties involved in creating the completed BIM will check for all possi ble conflicts and problems. Problems exist, not in the coordination of the BIM, but in the coordination of all partie s involved with access to the BIM. Typically, design elements consist of (but are not limited to): surveying, architecture, civil engineering, electrical engineering, mech anical engineering, st ructural engineering, landscape architecture, fire/alarm engineering, communica tions, interior designs, owners, tenants, construction managers, commissioning, etc. These professionals will have input to the BIM before, up until, and after, construction begins. Once construction begins a secondary group of people are necessary, thes e are (but are not limited to): general trades, site/excavation, steel construction, mechanical c onstruction, electrical constructi on, fire sprinkler construction, concrete construction, ro ofing, masonry, glazing, elevator controls, finishes, technology, and landscaping. This is a large group of people to get together and coordinate to use a BIM model for all construction information. Combine that with the fact that, the rela tionships between the involved parties are all connected to the model and they ar e also connected to each other. With such a complicated relationship, the bi ggest problem will be how to control who puts what into the system, and what kind of problems will that generate (Seaman 2006. 32

PAGE 33

2.3.1 Proponents of BIM Building Information Modeling software is uni que and advanced in its ability provide architects, engineers, and constr uction managers the necessary inte roperable program for all their needs. Proponents of BIM indicate that the only limitations to using BIM are the abilities of the users and list the following benefits of using BIM: Conflict Resolution conflicts will be identified ahead of time so changes to the drawings can be made before construction begins. Adjusts costs as changes occur determine changes in projects as time progresses. The costs for specific objects can be input into th e BIM. Merely changi ng the objects will not only coordinate with the drawings, but will update the schedules and estimates. Speeds up Design/Construction process BIM will speed up: programming, preliminary design development, preplanning for constructio n, but it still is beholden to the speed at which the architect produces drawings. Intelligent desi gn takes time, and cannot be compressed. The program can speed up the development of construction drawings. Reduces Ultimate Cost by compressing time for construction, genera ting specific costs for changes, and handling changes up front. Single Entry Input only needs to happen once. When something is put into the plan view of a drawing, it will be shown in the door schedu le, interior elevations, exterior elevations, and sections. Upon modification, when an objec t is changed, all instan ces of it in the BIM change as well, along with all accompanying notations. The same can be said of estimating. Changes in the estimate will tric kle down throughout the BIM. It will even help you coordinate anything that changes from substitutions of objects, i.e. electrical demands on panels after changing lighting for the building. Alternates Since substitutions are easy to in terchange in a BIM, this will give owners the opportunity to request many more alternates to see how cost can be influenced. Design optimization important for addressing LEED issues. Conflict Identification and Resolu tion Is great for clarifying locations for running of the mechanical/electrical/communication/fire. The only limitation is that the contractor must run their system in the specified location, or ot her trades will face problems, especially in tight spaces. Constructability Details can be developed to show how building components come together 33

PAGE 34

Construction Sequencing/Scheduling the mode l will be sequenced and scheduled so you can see the approximate progress. Viewing th e BIM in 4D will help keep the construction project schedule. Life Cycle Evaluations Energy calculations can be run using solar heating to determine the cost of running the HVAC for a building. Useful for budgeting cost over time. Operational simulations animate the model to show activity, how the building would be used i.e. a medical facility. Show how the patient would be moved from surgery or an industrial plant, see how the plant operates and make sure that you will have all the necessary clearances during operations. (Seaman 2006; Autodesk 2007; Sheldon 2007) Interoperability is a huge component of BIM software. Manufacturing software will be able to access a BIM and derive all their applicab le data. Idea being that this transfer of information will be seamless. GSA use in Phase I Government Service Administra tion (GSA) is requiring that BIM be used during Phase I of construction which me ans up to and including the schematic phase of the construction process. This is just the first step, and BIM will be adopted and moved forward in the construction process systematically. All GSA projects are encouraged to deploy mature 3D-4D-BIM technologies, spatial program validat ion and beyond. Contra ctual language has to be developed for this to take root. This is the same way in which LEED Accreditation came to the forefront in current government jobs. Typically, once government enacts something, the private industry will follow suit. Green building is leading BIM to a certain extent because of its ability to do Cost analysis and Life cycle analysis over the lifetime of a bu ilding. Typically when doing the cost analysis now, it is an energy saving analysis (see Figures 2-8 and 2-9). In Green Buildings it is just applied to the Energy and recyclabil ity side of it. A BIM allows th e user to do cost analysis over the entire construction process as well. Most of what is being seen in Green building and LEED is a precursor for what is going to be seen from the implementation of BIM. United States Green 34

PAGE 35

Figure 2-8. Computer modeling to analyze air temperature distribution to determine the benefits of displacement ventilation in the courtroom lobby, halfway up the tower, indicated with a green stripe on the drawing. (Google image 2007) Figure 2-9. The Pearl River Tower includes integr ated wind turbines and photovoltaic panels to offset its energy use. Inset is an Ecotect model showing the amount of solar radiation on the towers various surfaces. (Fortmeyer 2008) 35

PAGE 36

Building Council (USGBC) and Autodesk will e xplore opportunities to integrate Autodesks technology with the USGBCs Leadership in Energy and Environmental Design (LEED) Green Building Rating System, to help the building indu stry more easily and rapidly meet goals for reduced carbon dioxide emissions (Cole 2006). Commissioning is a requirement in a LEED or green building. A BIM would allow the commissi oning administrator to be involved from the beginning of the construction proce ss to ensure that certain crite ria are certified and a building will truly meet the specified commission rating. 2.3.2 Disadvantages of BIM Below is a list of items that have to be considered before changing to a BIM methodology. The question being, whether or not the problems with implementing BIM are too big to overcome. Garbage in-Garbage out when suppliers ente r data into the model, will they be held responsible when things do not work, or w ill they blame the engineers for not checking over the drawings. No Standard BIM Contract Documents if a set of standards is not developed, interoperability of BIM will not be efficient. Electronic Data Transfer Engineers and archite cts are reluctant to pr oviding digital data to suppliers and contractors because the data can be modified. A/E want to protect their data and work for liability and copyright purposes so pdf files are used. BIM gives access of the model to suppliers for doing takeoffs. Interoperability How well will programs relate and talk to each other. BIM cannot interface with other programs (yet). When a different program takes a BIM and opens it with another program, who will check to make sure that all the engineered data is still correct from the transfer into another program. (Seaman 2006) Will the Architect remain the representative of the owner in charge of overseeing the entire project, or will their role change, making the ar chitect merely a supplier; the supplier of the design. International Building Code dictates that Arch itects are responsible and have to sign and seal documents, they will be the ones responsible for ADA and all code differences from state to state, country to country. Architects could po ssibly take over constr uction management duties 36

PAGE 37

since the software provides a lo t of the specialized products that construction managers provide i.e. scheduling and estimating. From this reasoning, BIM should be a great asset for a design/build company, but currently this is not the case, as observed from my interview with a large design/build company that is utilizing BIM. Who is going to have copyright of data wh en it is done, (processes cannot be copy written), will the architect be able to copyright drawings when the program actually makes changes to the drawings? In the current process, when changes need to be made to a set of dr awings, the responsible party annotates the drawings w ith a revision date, and a revisi on number. Then the part of the drawing that is changed is marked with a cloud and the corres ponding revision number, making it very easy for anyone who looks at th e drawings to determine what has been changed. With BIM, revisions can still be made to the drawings, but instead of getting an accurate account of what has been changed, a whole new set of drawings is issued, and since the program has dynamic input, a cha nge in one location is made throughout the drawings. These will not be marked with revision clouds, so findi ng changes on a set of drawings could be very difficult. Plus, who ma kes the change and why? This needs to be carefully considered when using BIM (Seaman 2006). Polygonal modeling is what arch itects currently use to show the owner what spaces and buildings look like, this is a vi ew of what exists, what is drawn on the paper. Parametric modeling creates the design from the input you use. If the user wanted to put in a specific window or door, product information could be re trieved from the manufacturers database, inserted in the wall, and the program can gene rate details provided by the manufacturers specifications. But who will be responsible for ma king sure that details are up to date, and who will be held accountable? 37

PAGE 38

CHAPTER 3 METHODOLOGY Objective of this thesis is to study the potential use of BIM in the AEC industry and how it can improve productivity for construction ma nagers. A BIM is a design methodology that breaches the gap between the design intentions of architects and engineers, and the implementation of design by construction managers. It is a computer model that fulfills the needs of all parties involved in the AEC indus try, offering CAD servi ces, cost calculations, energy simulations, building code checking, life cycle analysis, and it is formatted to be interoperable with other programs that are specific to the AEC industry. Productivity improvements for the constructi on industry were researched by reading various books and articles to understand the worki ngs of a very labor inte nsive industry. History of BIM was researched to determine the purpose of the program and the limitations that it may have. The BIM program used for this study wa s Autodesk Revit because Autodesk is the biggest software provider for the A/E industry. The author has over 10 years experience with AutoCAD and 5 years of experience with cons truction documents. Using this experience, the author was able to test the pe rformance of the program, helping to discover more limitations. Interviews with two small construction compan ies, one large design-build company, and one design firm were also conducted to gage BI M acceptance by well esta blished companies. 3.1 Productivity Knowledge about productivity was attained from readi ng Construction Productivity: Measurement and Improvement written by James J. Adrian (2004) along with other various journals/articles. Specifics that were especi ally considered in determining BIMs impact on productivity were Adrians ten step program for improving producti vity. Other various concepts for improving productivity were also considered during the research i.e. labor productivity for a 38

PAGE 39

typical day of construction, va lue engineering, the effect of information technologies on construction, and human factors. 3.2 Advantages and Disadvantages Positive and negative effects of BIM and how it relates to the construction industry have to be considered when a construction company is deciding to implement BIM into their basic operations. It is easy to find out all the positive effects that BIM can have on the construction industry, but the negative effects have to be addr essed as well. Drew Seaman, Esquire conducted a professional development semi nar at a combined meeting of the A/E ProNet membership, the American Institute of Architects risk mana gement committee, The National Society of Professional Engineers' insurance committee, representatives of the Am erican Institute of Architects trust and representatives of The Amer ican Consulting Engineering Companies. This seminar provided an in-depth analysis of the issues that affect the de ployment of BIM on the AEC industry. These are issues that need to be resolved and precedence that needs to be set for BIM to be successful in changi ng the construction industry. 3.3 Interviews Interviews were conducted with small cons truction management companies (Company 1 and Company 2), a large design build company (Company 3), and a large and innovative design firm (Company 4). Representatives of construc tion Companies 1 and 2 interviewed about their current working operations and were informed about the BIM process. Questions were asked to evaluate their responses towards implementing su ch a system into their current operations. Representatives at Company 2 were interviewed about perceived benefits from utilizing BIM on some of their projects. Objective being: to attain knowledge from their first hand experience about how BIM is being accepted in the workplac e and their perceived benefits or perceived drawbacks. Company 4 only utilized BIM for their operations because of the complexity of their 39

PAGE 40

designs. It is essential for them to use BIM b ecause conventional drawings are not adequate to convey design intentions. These interviews alon g with the other studie s conducted will provide good insight on both, how BIM is being received in the construction industry and what the barriers are for implementing BIM into small construction management firms. Questions about issues related to productivity on the jobsite and issu es about BIM in the marketplace that have been determined to be essential to this research are as follows: How much time is spent analyzing constr uction documents prior to the construction process? How long does it take to prepare a bid using a traditional set of construction documents? Approximately how many RFIs are subm itted for a typical construction job? What is the average time spent wa iting for a return on an RFI? How much time is spent conversing with the Architect/Engineers a bout the construction job? Are you currently using Building Info rmation Modeling at your office? If not, do you foresee changing over to some ki nd of a BIM system at your construction company? If so, what problems have you encountered using the BIM process? Do you implement any productivity improvement practices with your construction crews and if so, what? It should also be noted that using BIM may provide all of these bene fits, but designing and development of the construction documents will be more costly than the traditional way of creating construction documents. 3.4 Process of BIM This research also involved learning the pr ocess of BIM first hand from continued use, information seminars, and tutorials. Autodesk Re vit seems to be the program of choice for the A/E industry with their drafting program, AutoCAD therefore; the program that was used for 40

PAGE 41

this experience was Autodesks Revit. The aut hors personal experience in architecture has given him ample experience with AutoCAD and how construction documents are created. Revit gives the user an interface that is not very similar to AutoCAD. This is one of the first drawbacks to changing from a drafting program to a BIM approach. Most of the A/E industry utilizes AutoCAD in their operations. It is easier to learn BIM having no computer drafting experience at all than it is with 10+ year s of computer draftin g experience (Imaging Technologies, Autodesk Revit product representative 2007). 41

PAGE 42

CHAPTER 4 INTERVIEW RESULTS From the interview process, a good perspectiv e of real world app lication was attained from construction Companies 1, 2, and 3. Comp any 1 and Company 2 were a small general contractor firm and a roofing sub-contractor, respectively. Company 3 was part of a large design/build firm. A conference wa s also held with a large desi gn firm (Company 4) that uses BIM on their projects. Questions asked and answers provided are found in Appendix B. The interviews and meetings we re conducted in December 2007. 4.1 Small Construction Companies 4.1.1 Construction Company 1 General Contractors (GC) typically will have between three to four weeks to compose a bid, and if awarded the contract, they have about two weeks to get finances and arrangements in order before construction begins. Representative s do most of their estimates using hand written notes. Although, thorough in reviewing the construction documents prior to bidding, (asking many questions for addendum prior to the bid date ) little coordination errors go unnoticed, which become causes for change orders later on durin g construction. During the construction phase, typical wait times are between two to three weeks before receiving an answer to an RFI which, for the most part, does not impede progress on the job, but if something gets delayed because of an RFI, another change order gets added to the job. During the construction process, both formal and informal meetings are held with the Arch itects/Engineers to disc uss progress on the job, change orders that have been requested, and pos sible conflicts and futu re progress on the job. This typically amounts to around three to four hours a week. From a small construction companys perspective, there is no real advantage in acquiring BIM. Up front costs, in both time and money, are more than can be justified. 42

PAGE 43

From the interview, it is apparent that the amount of time used for all aspects of construction and the amount of change orders th at get issued for a job are detrimental to productivity for Company 1. 4.1.1 Construction Company 2 This roofing sub-contractor has between two weeks and a month to compose a bid for construction. Their scope of work is very lim ited and specific. Jobs are typically performed with little coordination problems and few RFIs. They distribute the construction drawings to the steel fabricator or truss fabricat or to obtain the necessary shop dr awings. Since their time on the job is limited, they do not converse much with th e architects and engineer s until inspections are required. Any RFIs are typically issued from the shop drawings to th e engineers for approval with the roofing sub-contractor acting as the middle man. This roofing sub-contractor is opposed to the implementation of BIM for their construction operation. Although 3D models make it easier to visualize space productivity advancements are not realized. This owner has been in the construction in dustry for more that 25 years. He is not prejudice against informati on technologies; but is un willing to recognize the advantages of utilizing LEED practices in construction. The author beliefs that implementing BIM in to normal operations would give small or medium sized construction firms, a distinct advantage in the areas of: lost time and money and increasing productivity. Obstacle to implementation would be tr aining in this area, but the current crop of building construc tion graduates will have a gene ral knowledge of this program and its assets for a company, and will not be able to ignore the possible be nefits. In addition, the new construction managers and job superintende nts will be more computers savvy and will be able to learn this program with relative ease. 43

PAGE 44

4.2 Company 3: Large Design / Build Firm Data acquired from representativ es at a large design build firm generated mixed feelings. One representative touted BIM as being the r eason why construction on the new performing arts center in Miami, Florida was completed. Before a BIM was constructed, the steel fabricator had over 200 RFIs within the first th ree months because of the difficult angles and form of the building. Putting the drawings into BIM cleared up virtually all questions involved with the steel structure of the building. This design/build firm has been implementing BIM on projects they are familiar and comfortable with, that have owne rs willing to try using a new delivery system, so projects are performing slower than their trad itional method because of the lear ning curve. Most benefits of using BIM are attained when the design is too complicat ed to portray in 2D. Unfortunately, the pilot projects for BIM are very easy to attain through traditional means and this firm has an office full of extremely proficient users of Auto CAD. It will take a wh ile for the market to switch to a more BIM centric approach, and this will be enabled with its implementation during design and construction education in University curricula. A nother representative has mixed reviews with the benefits that can be acquired. Since this company is a design/build firm, they fast track most of their projects, meaning that construction begins before construction documents are completed. A BIM is most beneficial in th e 3D, 4D, and 5D realms when the building has been completely designed. Using BIM for fa st track construction has not provided any significant advancem ent in productivity. 4.3 Company 4: Architectural Design Firm A conference was held with a representative of a large design firm. This firm is one of the global innovators in BIM methodologies. Duri ng the conference, the be nefits of a BIM were 44

PAGE 45

discussed against the added cost of utilization. Benefits this fi rm uses to promote using BIM included: A 40% elimination of unbudgeted changes (change orders) Cost estimate accuracy of 3% Less than 1% cost growth Bids within 2.5% of act ual construction costs 60% less Requests For Information (RFIs) 80% reduction in time to generate a cost estimate Overall savings of 10% of contract su m through clash detection (coordination) 7% schedule cost reduction 10 to 20 times the return on investment though its life cycle analysis. This provides convincing data for the implementation of BIM to owners. Inherent complexity of their projects make it essentia l to use BIM, because 2D drawings cannot accurately represent design intentions. Their project s have been very successful and they are one of the few firms that have historical data on th e benefits of using BIM, however the problem is that results are subjective to interpretation by the design firm re porting them. It should also be noted that using a BIM will be a more expensive process than the traditional method of construction in up-front costs. 45

PAGE 46

CHAPTER 5 CONCLUSIONS AND RECOMMENDATIONS A BIM is, in its most basic form, the move from analog to digital design and construction. It is a model-based, dynamically linked, technology with a database of project information for coordination that has a real time, dynamic aspect associated with it; and is poised to fundamentally change the way projects are built and how project stakeholders communicate with each other through the unlimited transfer of information between the project stakeholders, Architects, Engineers and a ll construction personnel. A BIM is designed to be the mediating progr am between the specific programs used by architects, engineers, contractors and suppliers/venders. It move s towards a completely universal and interoperable program working with computer based models in 3D, 4D and 5D. From the 3D model, plans and sections can be developed (Figure 5-1). The 3D capabilities of the program will visually solve any questions about material and spatial relationships. This makes conflict resolution easier to detect as well. Engineers can design their respective systems (i.e. plumbing, HVAC and fire sprinkler) and coordinate with each other. Once the model is composed, Figure 5-1. A 3D polygon model and 2D lines and te xt compose a set of integrated construction documents. Images courtesy FacilityGenetics, LLC and Ghafari Associates (NIBS 2006). 46

PAGE 47

Figure 5-2. Virtual construction documents and installation photograph. Images courtesy FacilityGenetics, LLC and Ghafari Associates (NIBS 2006). installers can follow the BIM to prevent any c onflicts in future construction (Figure 5-2). Models can then be created in 4D so contractor s can both visualize construction before it actually takes place, and predict the best locations for construction equipment and lay down areas. Progress can also be monitored to ensure that pr oductivity levels are being maintained (Figure 53). With 50% of a typical construction day bein g non-productive, BIM applications can be used to gain a 33% increase by addressing: late or inaccurate info, waiting on resources, multiple material handling, waiting on instructions and rewo rk. This will have a dramatic increase in productivity for the construction industry, making it more compatible with productivity increases in other industries li ke agriculture, manufactur ing, transportation, etc. Figure 5-3. Installation process and equipment requirement. Accurate steel sizes, members, weight and cost. Images courtesy Kling (NIBS 2006). 47

PAGE 48

Negative aspects of BIM have to be addres sed for the technology to be successfully integrated into the AEC industry. There are a lot of specific requireme nts with structure, inspections, etc. that relate to the Internati onal Building Code. A BIM has to be capable of recognizing project locations to m eet regional building codes, esp ecially for overseas projects. All the input from users accessing the drawings ma y become problematic. Sealing of drawings may prove to be difficult if 30 different people have input to the drawings, how will professionals be able to verify that they witnessed what work had been done on the BIM model. This also applies to the actual program, BIM is supposed to make changes for the user as well when structures are changed, columns are inserted or removed. How will the engineers be able to identify all the changes that the program its elf can make to the model and would they be willing to sign and seal the draw ings not knowing what changes may have taken place from their original intent or design. Who will be held accountable for Coordination? Architects and engineers are the professionals responsible for coordination. Since this new program is supposed to manage coordination for you, who will be at fault and who will make the changes wh en things conflict. Plus, the engineers and architects are going to have to learn a new program that is more expensive, and their fees are not going to increase. This could cause some hesitation for the AEC industry to change. Future of BIM in the construction industry will be just as important as traditional computer aided drafting (CAD) programs. It will require many years of gathering data and compiling a databases, both from the Architecture/ Engineering side with traditional construction details, and the construction side from gath ering actual productivity data. Once a solid database has been formed, productivity will begin to improve and through continuing education, more opportunities for improvement will be gin to reveal themselves. Perhaps the most important issue 48

PAGE 49

to remember is the program can only be as helpful and the information that is input to it. The old adage garbage in, garbage out could have a significant impact on productivity using this program. 5.1 Increasing Productivity with BIM Using Adrians Model Adrians 10 step model can be used to increa se productivity in the c onstruction industry. Results of this study suggest that using Adrians model BIM can be used to improve productivity. 5.1.1 Making the Project Look Like a Firm Rather Than a Job: Developing a Personnel Management Program This helps to encourage construction worker s to take pride in their work, and sets precedence for performance and appearance. Use of BIM during the planning phase can predict the best location for lay down of materials through the animated c onstruction process. This can be relayed to all trades doing wo rk long before they even get to the site. Having this knowledge gets the job started imme diately and without delay. 5.1.2 Improved Communications Poor communication at a jobsite leads to low productivity, and redo work. A BIM will be able to increase communications between the Architect/Engineers and the jobsite superintendent. There needs to be knowledge of BIM on both sides so communications is through the program. A BIM can also be used to document a job and to keep all involved parties free from problems, delays, and increases progress and achievements. 5.1.3 Planning a Productive Site Layout Building information modeling can be used to determine proper locations for the construction lay down of materials and the delive ry times of materials because of the dynamic scheduling ability that BIM has to offer. C oordination becomes easier, and as-built drawings become more accurate. Construction site layout enta ils things such as trailer locations, materials, 49

PAGE 50

equipment, and storage areas, signs and lavatory locations, break areas, etc. Proper jobsite layout can stem equipment theft. All of these th ings are critical for increases in productivity. 5.1.4 Challenging the Work Process Questions like why are we doing it the same wa y, where is the best place to do it, when is the best time to do it, etc. need to be asked to find ways of improving the construction process. Object being, to improve the work pr ocess, which will increase jobsite productivity. BIM methodology is a new and inve ntive way to construct a building, and shall not be dismissed because it is difficult. 5.1.5 Developing a Scientific Work Standard Versus an Accounting Based Standards Utilization of BIM will, hopefully, introduce a new, more standard way to develop drawings from multiple/different design firms. This new standard will increase the knowledge of persons preparing bids and reading drawings because of the simila r/typical styles to compose a set of drawings, promoting a more cohesive work environment. 5.1.6 Planning and Scheduling This was discussed earlier because of the 4D and 5D opportunities that BIM offers as part of its database. Ability to render time lapse studi es into a project will he lp in predicting better more efficient ways to utilize time and improve scheduling. 5.1.7 Project Control and Productivity Improvement One needs to know what problems are if they are to correct them and improve productivity. Information needs to be recorded regularly to determine the productivity of the current crew on a jobsite. This information could be cataloged and studies will determine what needs to be done to find increases in worker productivity. This will also set a precedence on which BIM projects can be judged, and compared to previous projects that used the traditional construction method. 50

PAGE 51

5.1.8 Equipment Management to Enhance Productivity This is not relevant to BIM, it relates to the issues of renting rather than owning equipment and worrying about maintenance. It is focuse d on using new and not outdated equipment to improve productivity on a jobsite. 5.1.9 Productivity Improvement through Safety It is clear that a safe jobsite is a more pr oductive jobsite, helping to increase worker moral and keep workers motivated (knowing that their employer is concerned about their safety). A BIM can give early clues about potentia l hazards that may occur on the jobsite. 5.1.10 Productivity through Attention to Quality Quality products are a necessity to improve productivity; it gives the workers something to take pride in. With BIM, buildings will be able to be estimated and bid more accurately. Cutbacks will not be necessary to bring a proj ect back within budget. Through the use of conflict resolution, more attention can be set on construction detailing. 5.2 Conclusion True benefits of BIM will be realized when architects, engineers, and contractors use the software seamlessly between each other. Although this is a great program for the industry, it is not the end all program. It is a program that has to be used in conjunction with the already used programs of the various trades, i.e. the details that it generates are not suitable for construction, and a separate CAD program is necessary for detailing construction elements correctly (Figure 5-4). 5.3 Recommendations For future analysis of BIM and productivity in the construction i ndustry, a set of design and interoperability standards has to be adopted, and a shift from CAD to BIM needs to happen. 51

PAGE 52

Figure 5-4. Section details from Revit Tutorial (Revit 2008). Once this takes place, historical data will become more readily available, and surveys can be conducted to compare the traditi onal method of construction agai nst the BIM methodology. This kind of information will be essential in figuring out the future of the industry, instead of just relying on projections. Future research needs to be done on interoperability with the various programs that are essential to the AEC industry to see how well BIM can be integrated into daily use. Surveys should be conducted to determine how well BIM is improving productivity, and how productivity levels compare against other U.S. industries. This will become more readily available once more historical data is gathered from construction and design firms that have implemented the program. 52

PAGE 53

APPENDIX A LIST OF TERMINOLO GY AND ABBREVIATIONS 2D. A drawing that exists in only the X and Y planes 3D. A drawing that exists in the X, Y, and Z planes 4D. A BIM that can also be shown in a time stamp sequence, to show progress 5D. A BIM that can forecast cost anal ysis over the lifespan of the building A/E. Architects and Engineers AEC. Architecture / Engi neering / Construction AIA. American Institute of Architects BIM. Building Information Modeling CAD. Computer Aided Drafting CM. Construction Management Firm IAI. The International Alliance for Interoperability IFC. Industry Foundation Classes INFORMATION. The Information / data that is obtained from the building. LEED Leadership in Energy in Environmental Design LIFECYCLE. Describes all the phases of the building process: de sign, construction documents, procurement, construction, mainte nance, additions, and demolition. MODELING. The model that houses, maintains, and controls the flow of information needed to manage the building NBIMS. National Building Information Model Standards NIST. National Institute of Standards and Technology R&D. Research and Development RFI. Request for Information 53

PAGE 54

APPENDIX B INTERVIEW QUESTIONS AND ANSWERS 1. Company 1 (small general contractor) 2. Company 2 (small roofing contractor) 3. Company 3 (large design/build firm) How much time is spent analyzing construction documents prior to the construction process? 1. Typically have three weeks to a m onth to prepare bids for a project. 2. Between two weeks and a month. 3. Since most jobs are fast-track, we start building as soon as we get the drawings. How long does it take to prepare a bid using a traditional set of construction documents? 1. It takes the entire time we have the cons truction documents for review. Typically we get our sub contractors bids th e day before the base bid is due. 2. Typically between one or two weeks 3. Approximately how many RFIs are submitted for a typical construction job? 1. This is dependent upon the architect and the owner, they range from 0 to 35, depending on the complexity of the job. 2. Typically roofing jobs do not have many RFIs, but when substituting materials or adding a roof penetration, there can be as high as 10 3. Projects that are fast-track typically have a lot of RFIs numbering into the hundreds on a single project What is the average time spent waiting for a return on an RFI? 1. the average time is around two weeks to three weeks 2. two weeks 3. It depends on how difficult the question is, but typically they ar e answered within a week, and sometimes the same day. How much time is spent conversing wi th the Architect/Engineers about the construction job? 1. Before the construction begins, very lit tle during construc tion, regular monthly progress meetings are held, and correspondence continually occurs 2. not much at all, both before and during construction 3. There is an open dialogue between th e architects/engineers and contractors throughout the entire project. Are you currently using Building Info rmation Modeling at your office? 1. No 2. No 3. Yes, we are implementing BIM on project s that lack complexity, but use 3d design regularly in the construction process. If not, do you foresee changing over to some kind of a BIM system at your construction company? 1. No, it would be to large an investment and change for our company 2. No 3. 54

PAGE 55

If so, what problems have you encountered using the BIM process? 1. 2. 3. BIM is a great concept, problems occur b ecause fast-track jobs are started with 50% completion of construction drawings. The problem with BIM is that the drawings have to be complete to gain any benefit from estimating the job and developing the drawings. Do you implement any productivity improve ment practices with your construction crews and if so, what? 1. No 2. No 3. ______________________________________________________________________________ 4. Company 4 (Design Firm) What BIM software do you use? a. Digital Project When did you start utilized BIM in the design process at Ghery Technologies? a. I was a co-founder of Ghery Technologies with Frank Gehry and Jim Glymph. Ghery Technologies was established in 2002. How would you compare Digital Project with Autodesks Revit ? a. They similar in scope and are used to create BIMs, but Digital Project is a more complicated and advanced system. What are the benefits of using BIM th at Ghery Technologies has observed? a. The benefits that we have been experiencing with BIM are: A 40% elimination of unbudgeted changes (change orders) Cost estimate accuracy of 3% Less than 1% cost growth Bids within 2.5% of act ual construction costs 60% less Requests For Information (RFIs) 80% reduction in time to generate a cost estimate Overall savings of 10% of contract sum through clash detection (coordination) 7% schedule cost reduction 10 to 20 times the return on investment though its life cycle analysis 55

PAGE 56

How many projects have you used BIM on? a. There have been 32 major projects accomplished using BIM How long before you expect the majority of AEC to convert over to a BIM system? a. It will probably take around seven years 56

PAGE 57

LIST OF REFERENCES Adrian, James. (2004). Construction Productiv ity: Measurement and Improvement, Stipes Publishing L.L.C., Champaign, IL. The American Institute of Ar chitects. (2007). Preparing for Building Information Modeling. < http://www.aia.org/nwsltr_pm.cfm?pagename=pm_a_20050722_bim > (Nov. 12, 2007). Originally published in Guidelines for Improving Practice, Vol. XXXV No. 2. Reprinted with permission of Victor O. Schinnerer & Company Inc. Bedrick, James R, AIA. (2006) The Architects Handbook of Professional Practice. John Wiley & Sons, New York, N.Y. Cole, Noah. (2006). Autodesk and U.S. Gr een Building Council Partner on Technology Initiatives to Move Building I ndustry Toward Greener Future. < http://www.usgbc.org/News/PressReleaseDetails.aspx?ID=2749 > (Jan. 23, 2007). Eastman, Charles M. (1999). Building Product Models: Computer Environments, Supporting Design and Construction, CRC Pr ess LLC, Boca Raton, FL. Elvin, George. (2003). Tablet and Wearable Computers for Integrated Design and construction.(Oct. 8, 2007). Elvin, George. (2007). Integrated practice in architecture: master ing design-build, fast-track, and building information modeling / George El vin, John Wiley & Sons, Hoboken, N.J. Fischer, Martin and Kunz, John. (2004). The Scope and Role of Information Technology in Construction. < http://cife.stanford.edu/online.publications/TR156.pdf > (Jan. 12, 2008). Fortmeyer, Russell. (2008). SOMs Pearl River Tower. < http://www.archrecord.construction.com/featur es/digital/archives/0612casestudy-1.asp > (Mar. 22, 2007). Fukai, Dennis. (2006). Building Simple: Building an Information Model, Insitebuilders, Archer, FL. Gehry Technologies. (2004). Jim Glymph to Pr esent at Conference on Building Information Modeling. < http://www.gehrytechnologies.com/company-press-04-08-2005.html > (Nov. 12, 2007). Ho, Cathy Lang and Menking, William. (2006). Super Modeling. < http://www.archpaper.com/features/2006_20_super_modeling.htm > (Sep. 15, 2007). Howard, Rob. (1998). Computing in Construction: Pioneers a nd the Future, ButterworthHeinemann, Woburn, MA. 57

PAGE 58

Keller, Chris. (2004). Interoperability at Dow Jones & Company. < http://www.archibus.com/asset/0407/assetframeset.cfm?rightlink=asset/0407/interopera bility.pdf&vid=13676&CF ID=627806&CFTOKEN=45406879 > (Feb. 8, 2008). Khemlani, Lachmi. (2006). The AGC's BIM Initiatives and the Contractor's Guide to BIM < http://www.aecbytes.com/buildingthefuture/2006/AGC_BIM.html > (Jan. 22, 2008). Mosca, Peter L. (2007). Building Informa tion Modeling Adoption Accelerating, CMAA/FMI Owners Survey Finds. < http://realtytimes.com/rtp ages/20071224_modeladopt.htm > (Jan. 13, 2008). National Institute of Standards and Technology (N IST). (2007). General Buildings Information Handover Guide: Principles, Me thodology and Case Studies. (Feb. 3, 2008). Office of the Chief Architect. (2006). GSA Building Information Modeling Guide, 1st Series, Washington, D.C. U.S. General Services Administration. (2006). D-4D Building Information Modeling. U.S. General Services Administrati on. (Aug. 28, 2007) 58

PAGE 59

BIOGRAPHICAL SKETCH Joseph C. Kuehmeier earned his masters (MSBC) degree from the M.E. Rinker, Sr. School of Building Construction at the University of Florida. During his studies he worked as an associate architect for CRG Architects / Palatka Inc. where he dealt with all phases of the design and construction process. Pr ior to earning his MSBC he earned a bachelor of design in architecture from the University of Florida, graduating cum laude, and earned a Master of Architecture (MArch) from the University of Florida. He is currently working on achieving his architectural license in conjunction with his contractors license. Josephs research interest are related to how the design and construction processes can communicate together seamlessly using a common digital language. He has five years experience in the design industry and looks forw ard to future endeavors in the design/build environment. 59