Multi-Resource Allocation across Multi Projects by Subcontractor

xml version 1.0 encoding UTF-8
REPORT xmlns http:www.fcla.edudlsmddaitss xmlns:xsi http:www.w3.org2001XMLSchema-instance xsi:schemaLocation http:www.fcla.edudlsmddaitssdaitssReport.xsd
INGEST IEID E20101123_AAAAAX INGEST_TIME 2010-11-23T07:54:03Z PACKAGE UFE0011878_00001
AGREEMENT_INFO ACCOUNT UF PROJECT UFDC
FILES
FILE SIZE 1053954 DFID F20101123_AAANKV ORIGIN DEPOSITOR PATH song_c_Page_76.tif GLOBAL false PRESERVATION BIT MESSAGE_DIGEST ALGORITHM MD5
d1e461a583c90c3a289fa74dbd2f196c
SHA-1
50e0ec3ddcd5f6143f55db4abfd25939f2305344
20002 F20101123_AAANFY song_c_Page_73.QC.jpg
f0a80e99b466888f184a6bdde87f99ea
e96af151e85943180df722b3494e7eb039484cf5
29178 F20101123_AAAMWC song_c_Page_57.QC.jpg
28e09f7cc96658637392b3b3b086aca2
dabc88dd5828616b349f1846b3ca8634964a5f39
F20101123_AAANKW song_c_Page_78.tif
462205c63211dddf3c3fb3a7b9fbf2ac
46b01da6e1240929540aaa13fbfc00d0d635ebf2
50211 F20101123_AAANDA song_c_Page_35.pro
2dd58ef4264ebb882edae20001982487
f428dd67bbaa2f1838c6b86fe3ab6a14db5db8fe
91229 F20101123_AAANFZ song_c_Page_41.jpg
c2462c04e43d40c0695319c550c511a9
f8b2f724b6d027e4e5f86958cb41188676a8b3b4
5715 F20101123_AAAMWD song_c_Page_63thm.jpg
f4bc61baee33bd8d056868472806c3b1
0bd09e519b69707d976d040d4c5acbd6503b5b54
8198 F20101123_AAANKX song_c_Page_01.pro
a644be86d379d92427752b28184225a9
3a48513e3ff4dfe960b9187fd2cea6f98bc65cb7
99861 F20101123_AAANDB song_c_Page_16.jp2
5c40e4e57064b4e0f5ad5e213662e49b
27ed77eac42917fe3fe2f6da516da8acff005b53
2199 F20101123_AAAMWE song_c_Page_79thm.jpg
1e079b0218233ac339ce08b0b1a6ed1a
4ffe807c847ee3d1a8845efb4476b810ab790c32
4094 F20101123_AAANKY song_c_Page_03.pro
67f024e64ed1e4932584184306985d48
b8eb8fcc3f1f012056133a8e64f7e6004c9944c5
28091 F20101123_AAANDC song_c_Page_16.QC.jpg
735be4f13802dfd2cce2c3aac18f4dbb
cbd88ed61a88687ea964ab3b77677c7b6250de69
2014 F20101123_AAAMWF song_c_Page_16.txt
26c140be961de028c489e3289e0671b1
dac387bad2f1b8c2cb2156167f2413fe4013f1e1
53788 F20101123_AAANKZ song_c_Page_06.pro
23f808b4ba3c279965c0c9ca3f61ef4b
6841fc8ddfefaf12a6c0b0b3c574fddde5697164
23548 F20101123_AAANIA song_c_Page_48.QC.jpg
f9ce4f7c5b78084378f9e849f0730286
2ec79ac10d64d003002b7aa0699391a5798ecd71
1833 F20101123_AAANDD song_c_Page_44.txt
9e24e415a3405d8c28802fd905dd6357
b8143102fb14a9a2f4367351cc2a4776f1219505
1968 F20101123_AAAMWG song_c_Page_24.txt
2404ed3a223a98b61416886178e955e0
eb938d7ecdbd8b8a5f11aaea210103740734208c
78350 F20101123_AAANIB song_c_Page_59.jpg
8f3b0a090a127b58e2bbd161cdcfb8b3
23ddaa98d78db311cec77c4580c49fb022c01862
107734 F20101123_AAANDE song_c_Page_56.jp2
21e10a2056ccf4cf140f27d83a1e79d4
b11fa80f14a1a17e652968c6e3aef83b1150e835
99520 F20101123_AAAMWH song_c_Page_24.jpg
16a26fdb1f77be3fcb72c505fe3f003d
9a8d8b51ccd580b830922325c04c7c850c45735c
214 F20101123_AAANNA song_c_Page_76.txt
a5bac5fcdc5a3edc65c623ffb2d3dccb
28268b7825c097adbdc55e08c1bfa65fa904b6e5
801179 F20101123_AAANIC song_c_Page_62.jp2
ebda3bb957b1916fc032e09cc7713b6f
7f627c737ad2b4e3030147e53ea55124e948d262
25271604 F20101123_AAANDF song_c_Page_69.tif
95e4d9b04a9891018ec430398bea279c
098d76c151017845cb884459b20d505e6b65314f
F20101123_AAAMWI song_c_Page_24.tif
bd288eb0e67e4bb8d8906533e0763a1b
aecf5ccf9173c0e44d8e8d6b8f51df1566c17ee0
1876 F20101123_AAANNB song_c_Page_77.txt
ab3591e6fc6fe7d69c8d0dc0ae3d1a08
a43a747d899b95d06522ae05a0c1853d03793d18
5629 F20101123_AAANID song_c_Page_43thm.jpg
ea212c230ddf364444cbc5a14657bc00
7b8606472fd3b5cd568758b7465a1493a0d75b48
32688 F20101123_AAANDG song_c_Page_18.QC.jpg
ff10d9f5a60e463385d522c850a9abd8
8721ab62f01b2170865c3fca1f4bc52384c62bea
6389 F20101123_AAAMWJ song_c_Page_47thm.jpg
e0465318ffd1d0559158ba6f767f0814
5f7167a55f23052b836aa6332f7d8eeaa3dd84b0
472 F20101123_AAANNC song_c_Page_79.txt
65adf84b4e0b8c08cb1c21ac22822ba7
d2a1ff8ac33801cd2c30e373aac8d72c2514edf5
118452 F20101123_AAANIE UFE0011878_00001.xml FULL
7371d227247e5b27b6d137c17275d1d7
4c65f1d7b289d1e6ee132a600099e8908935ec97
1617 F20101123_AAANDH song_c_Page_68.txt
aaeddc2638f5d14aeb38ea35be71d1d4
351261aefd88e5c5762b76862f3c27f49ebb2b60
5274 F20101123_AAAMWK song_c_Page_05thm.jpg
d16dfd6dd086755b1d1f86315f084761
1f1525d4e416aca79f8ce417847c8bbb23c3ad91
7977 F20101123_AAANND song_c_Page_01.QC.jpg
7e2b4d71e54b3bbf0e868231d87bb561
82491eee89101d0eb946d95ea470943617a48cdc
28914 F20101123_AAANDI song_c_Page_73.pro
bb212d2e10f1a58477b0f3d1d1529e0d
61bb03b22e5782ac63e9f485fda449698379064d
7014 F20101123_AAAMWL song_c_Page_68thm.jpg
72896ce2f070c29dd42311d947a6dc38
c11f909b4bf62b8c6e4f8c40fc6a6ee5c4611b39
9184 F20101123_AAANNE song_c_Page_04.QC.jpg
99e0715a6edc77cad21293345b8b891b
78ef8e185fa16a93e13eae310fbd4aa537e13567
7937 F20101123_AAANDJ song_c_Page_14thm.jpg
06a8a399b9fc2b2cb5c32a475c467b52
20188288479914cf604eebf60a5a61cb3db8c3c5
1743 F20101123_AAAMWM song_c_Page_40.txt
5afaff8c1e78665bc05271f617e40738
965aa670f8c1289f74c227862cbf6b04daed8e4f
4444 F20101123_AAANIH song_c_Page_02.jpg
59ef353bc4f504b3ccdf5f5b50aa9609
78f5ad7530329c65175f08f2403b44bdc259a6d4
68635 F20101123_AAANDK song_c_Page_70.jpg
48e36d067b70d03972470b9521ff11d0
407d6ee5bb61aebc47a8b0aa85ef8a80b6f19528
F20101123_AAAMWN song_c_Page_55.tif
b7e5cb05a18aac2bbebba80a18a7e810
c7778d723fb2b3e818bbdb35b23f2ae74f5a5a28
21902 F20101123_AAANNF song_c_Page_05.QC.jpg
c542e943fa13f3424c83beea99d83a2c
2f5ffbdd028407a96a22beeccd872e7fbf187bb9
27458 F20101123_AAANII song_c_Page_04.jpg
ce3801fd0e606e685785ceab1f4dd7b3
c790f58fe7a85ff0ac89ca83796f5323aa6e69b8
41043 F20101123_AAANDL song_c_Page_26.pro
87068aef33a8ccf3bd2724834ce7773f
cb794a2a58a78cc38869693b56a243f9343b5ff5
26531 F20101123_AAAMWO song_c_Page_55.QC.jpg
0cca7781c78f79ef65e86ade69d9d11f
504e8ac8c19d82be911425e457f100129da4c98c
1572 F20101123_AAANNG song_c_Page_07thm.jpg
c0c483d369d0b2a1281c3a66e57f0393
ce8e91b1639bfe11c1287080ddb69420114cc69c
93219 F20101123_AAANIJ song_c_Page_08.jpg
3454c0cae5ddd929ec1048348740960f
dc4a4251216a0472612f63bdf77ff3110ce99474
F20101123_AAANDM song_c_Page_43.tif
ceb77c413a101e66c4665e77d103a427
f076f9ec5a6a9ba6af9f637e34cc65dc10c0954b
4577 F20101123_AAANNH song_c_Page_07.QC.jpg
bca8a449b7199e1434cd353d1946d61b
7caf76e57ba3b478218a0975a07fa5f477fc6f2c
8958 F20101123_AAANIK song_c_Page_09.jpg
cb6e1689478a677908a77481b7012c63
3792b82cfd1c6f2b03a3e2f06d86708bce2bf967
89694 F20101123_AAANDN song_c_Page_11.jpg
9656bf483bc40f960de8db51fc803500
09e5b99195e3e2df7197870acd58e4a5191891c6
1861 F20101123_AAAMWP song_c_Page_66.txt
ce59b6f4aa5e0ccdcd061ae8960f0856
799647af079e553ce944c1566b25166a7194f986
6731 F20101123_AAANNI song_c_Page_08thm.jpg
090f5bdc5d9f1037a97df9b55b24a1a2
1881791440fc181acfa095a2486d23820fcbb7d0
67862 F20101123_AAANIL song_c_Page_10.jpg
aaff3d3dd675555f5c0e3fe4449ee0ce
615651a2e5341e9525d8e3a710e541c2758215a8
6605 F20101123_AAANDO song_c_Page_58thm.jpg
55fe628e8bf73533241994655aa38f19
4ff9df55e584cfa63bc4ad9afa5709179886e986
27652 F20101123_AAAMWQ song_c_Page_79.jp2
cb7bbc042b2d87b8bfb1d04a8e1e1dac
099331b23eb9f2806240279cd83fe8c55f2f3963
5866 F20101123_AAANNJ song_c_Page_10thm.jpg
58c680fff3dead4153a744d2b7544d14
0c8bea101519d306ac12021a3100507d1ce84cf3
94733 F20101123_AAANIM song_c_Page_29.jpg
72c8f886037fa96a8fb07d616983832d
a53a9733fd0f9461587cca8b2b77e27bad176291
24500 F20101123_AAANDP song_c_Page_71.QC.jpg
c29afba9b64d950b50e79bac825179c7
55f99e9b0b0c901e1c2d5d7fbc91c13ee59bfa5a
27688 F20101123_AAAMWR song_c_Page_75.QC.jpg
4a98de99b8ae62ec0ef653796cb789a1
cf566453e43e7ca9848b2acd95fd8756ba2e9d98
7950 F20101123_AAANNK song_c_Page_12thm.jpg
c7e88881cde387e22b76976c8c55e85b
bb4af28b4f50e4762366bec2c7eb17b33d030ac5
50576 F20101123_AAANIN song_c_Page_33.jpg
9bd7b01c8f35dd1091391247c353dbc3
48b5c5d6de1ef8b4b9eda3dc7aecd7d7692817e7
872220 F20101123_AAANDQ song_c_Page_21.jp2
6c9ee68952e4b9a8d207b12002b63fdb
d1920f1c6e952240d774742a83d2f7b2c8f24b18
F20101123_AAAMWS song_c_Page_11.tif
018e5ec53d058e7bc31c32e2ef50ac55
38ec3a32bf42c1a0877865f71e8c01370ab6c520
31436 F20101123_AAANNL song_c_Page_12.QC.jpg
a888b505fa92435bebe267c5bae5a6c5
a9de6881dda2882b8fdbd392493ac8c1373b6370
62582 F20101123_AAANIO song_c_Page_43.jpg
b877fcde34f255d439010f6df800d2fc
4e5417df24af4a09658d7a06d4b7ca8ef792d799
F20101123_AAANDR song_c_Page_02.tif
c525dc968962be3ab4781a638a7db979
c93006355e3910ce3a8b7b218a38c8ee2be82112
7144 F20101123_AAAMWT song_c_Page_21thm.jpg
aaaa1df92aab4d29c8705dd4c2a74a8b
f1e5e6139b9e59bebe3d1512418a2da7801b0f66
7785 F20101123_AAANNM song_c_Page_13thm.jpg
23277b0241816ec5f7f6f8e5d3dd95a0
c43883b66bd1cc8b9a806248869f83b1879e0b24
76483 F20101123_AAANIP song_c_Page_45.jpg
64b73db56352ce3fff0562bcc9f84aa2
6fb677f8a9506588018329ae2dc843209e1386fc
1745 F20101123_AAANDS song_c_Page_17.txt
9d12c65829468231681b15bcd7679ae0
e6a0415f86327fcf2d10f632a6e878e92bb6ac4a
2018 F20101123_AAAMWU song_c_Page_30.txt
a0c5c0c74ec293cc22b98ed1c4394615
eb621dd3f61b9cd8664f40207323cee7c2a31938
32889 F20101123_AAANNN song_c_Page_13.QC.jpg
72a5628ec0c44bd1b21e3d56778d219c
d338213891d1d891669cde6086545b80a8c6451e
F20101123_AAANDT song_c_Page_57.tif
032f923fce62d49043cc51310e931d5a
5c2e72e443a088de9d604a079bf3b8980128bb18
33668 F20101123_AAAMWV song_c_Page_48.pro
fa4cd29de5584d02ca84234b1fc36142
a9c539a77df22c1103d93aef953558fbb385ef03
71729 F20101123_AAANIQ song_c_Page_48.jpg
bc2fdc6f4074f5f0060e4ef9f3267479
15086037ae92ac13c41d37e1dd9ebcbd47eb6b37
28486 F20101123_AAANNO song_c_Page_15.QC.jpg
1c942849bef140c3253ec77b28d3861b
d919be1111af98779a9f69097b22ea1fc39e4fc8
105999 F20101123_AAANDU song_c_Page_28.jp2
8129580b326136d5afbb1bd26dc296aa
6e3b3ae7ef8a3ea679dd78af0f6542cc4d32313c
103039 F20101123_AAAMWW song_c_Page_34.jp2
18935eb7fc1be89607505e49e3b2e6f0
ab4cebb347e7ee9041507e4f67c1bd4ae8e1434a
99934 F20101123_AAANIR song_c_Page_52.jpg
e8d831732c880244c4d49dc5e506edc3
4d46c5b85354a857849b6f37c43a67e469ea5750
6561 F20101123_AAANNP song_c_Page_17thm.jpg
945cdae7cf1bc971ed5e191041a62ef0
553e1f50269e33730d0c279248ecfabfa0afb659
F20101123_AAANDV song_c_Page_40.tif
12356bdc9fd3f1891220fff16660ff92
af4041cb5437bf7f09abce2f6b964990b68faac3
8199 F20101123_AAAMWX song_c_Page_39thm.jpg
f3a7c92a648caf7c51abc1250e119ccb
878f7cc0ffb4c1b8d4ab87698cad031d43a106e0
91110 F20101123_AAANIS song_c_Page_57.jpg
55f663669820ee249bf4d643225899ff
0eff5e6a79232e7cf7dc5fec0c759c2d8f97c9e8
8022 F20101123_AAANNQ song_c_Page_20thm.jpg
bf5c338e2961786501f6fdf7e0df5898
404e48e605cc056dd134631bdd897212a73ed8f2
1095 F20101123_AAANDW song_c_Page_33.txt
bb185392f13aefa9e7aad2846ca9bac4
3dcccc4213ba4eb20fedaffd0f8b8486889a9917
97081 F20101123_AAAMUA song_c_Page_57.jp2
de48a72c3137ffc8ad5f8637cf666ae9
815234c0a028e4ba7bc68dde2d2afb5a5828db6f
46052 F20101123_AAAMWY song_c_Page_77.pro
b58b3a9864368760c886c640c58541b3
9735b5782c2fbf89decac7deebb5d08e9470ae1c
97175 F20101123_AAANIT song_c_Page_60.jpg
1c06ddeca02d36da535880546285c6a4
867928a73023d8a155643f502c0f1a0643a14a22
26120 F20101123_AAANNR song_c_Page_21.QC.jpg
ac0444ea2f03b8ab4a1ebb74d73fe3f0
1037fd5cc6096c35777d82418dd51f1bef04078c
48289 F20101123_AAANDX song_c_Page_60.pro
9aa2433d24f09f922be5926d4ff7d1bb
124b4101b03b583baa59c554398ba454e5e0d4b8
45023 F20101123_AAAMUB song_c_Page_15.pro
b16e916124fd8203c378e77e261caff1
bbbaa1035e9f598f9019e56598be7ee2bd2dfb01
111227 F20101123_AAAMWZ song_c_Page_18.jp2
fbbb22debb93e5bdd312601075e19380
d4b5f59cb7bd2311f6db4afd3f25f73905ae69bb
105929 F20101123_AAANIU song_c_Page_61.jpg
28558a058ce3f041991716fdb428db74
b7ca35c4bf74bdb45b5ac757c9501eaa2c5bd58e
8016 F20101123_AAANNS song_c_Page_22thm.jpg
e915c632fb6daf6086d5c7ae9cddd72e
cb22f32064f0e3f0b5cf8fd7ed9c37c3a6d1d373
751724 F20101123_AAANDY song_c_Page_48.jp2
b41a958f1a89537feb0bfd446f83621f
a62782a744a5886f2c4c34d3c457a8552b60dda0
50680 F20101123_AAAMUC song_c_Page_64.jpg
a7a7c7f83b014ac952c0e0311e759c0a
23f77e60525ad9a779f79d47242e8540da77ddcf
60504 F20101123_AAANIV song_c_Page_63.jpg
899a69e204d61139044524e7d2c65861
9a99dcdbd3ee3b2fb3699a1c9ea3249bd5a3466e
31798 F20101123_AAANNT song_c_Page_22.QC.jpg
0b10e4ccc78c119b38c5f4ba2d547614
2a95b526ef30e04779c23107a7af6ff1c71febdb
2141 F20101123_AAANBA song_c_Page_61.txt
184981a3a1e5eba8df5701c65afc282f
1ac1de0e29fd8856773864c822c92e08336ed87c
F20101123_AAANDZ song_c_Page_44.tif
60ce378b14339ed0336feb2250fe1bb7
bcf999b08c0a1f82dc82a6e373a63ee8ed89bd97
11256 F20101123_AAAMUD song_c_Page_03.jpg
008bf254c884dec0874f92ef6e3daca9
d76d8828f5419f592ea9d7a3f2d1fd79d226dd40
80055 F20101123_AAANIW song_c_Page_68.jpg
5e0eebac1af4efe7ce00b3c79026a6c2
d22d6a2584137b6ed262541c792b77e0ea2065f0
3067 F20101123_AAAMZA song_c_Page_09.QC.jpg
3dedd25af364c64e814aec352bc85f4c
b2eb197871f1480086a402161f394b33fb567f02
8023 F20101123_AAANNU song_c_Page_24thm.jpg
e5aa756b11da9298f9e041a734753a75
36c6354b4e3daf92b409b8f2c65fb448583135cc
43479 F20101123_AAANBB song_c_Page_11.pro
bb0f7f36dfa4f499c29722041f2ec1b7
d12c7deff9d27a36a090817601ce3fc5805ea2b7
15648 F20101123_AAAMUE song_c_Page_78.pro
f3a0e68898cf96de790d45a238045d15
f4faefba910244215d8fa6645da278807261d5e6
7911 F20101123_AAANIX song_c_Page_74.jpg
d323df4c8731ec592feb657c88c0f5ba
481a96d6b921d3367a1acb55d9bbfbb4db92b62c
29669 F20101123_AAAMZB song_c_Page_41.QC.jpg
755cede1759dc82d6dcf1bff030e967b
9840c20c95cbd3a9acde426121b89926a5185cde
7946 F20101123_AAANNV song_c_Page_28thm.jpg
3875b0f08c95fe5b930901c7f0f4ab21
7e390c0e220603396341ea4f76bf033dcbde61b7
F20101123_AAANBC song_c_Page_12.tif
d41b44ffffc8e0d16bcd6a0f4feb1261
4d20fd49339ae82b659441e3c9af61fb6784ae3b
F20101123_AAAMUF song_c_Page_75.tif
99efe6293f9c55026537bf6fbc219f1a
67e60607a66fdd0e10b2d1e396b50956af522d0d
85487 F20101123_AAANIY song_c_Page_75.jpg
ff3c77cb5d55c1230e4e5d1305a14d95
72b7319696ed92032926f82d670bd1a55494cb22
F20101123_AAAMZC song_c_Page_74.tif
00b06161bc968f1292a3862863232eff
6f235289c6c2023b1e9f5dddf365518471c44f59
32488 F20101123_AAANNW song_c_Page_30.QC.jpg
ae4bc675f136c14a292926d08d46eeb3
be7cf5b953ba2b8bea1a43dd7fdaa5824f987d0d
92056 F20101123_AAAMUG song_c_Page_66.jp2
58aa468fc7a738e9cf18e83e7f9d5853
6e11f661ed9b0e919b24b1561d9a395618d621c3
1051949 F20101123_AAANGA song_c_Page_77.jp2
5495f99f8f8df385601724f935fb9a26
12d9bc685228757c7ee1fe243e34848f3c978548
100591 F20101123_AAANIZ song_c_Page_77.jpg
4936e5155aa69b4a53f0a5ea6ea1a2b9
3cbc444b9ff84979c59c80f21258df12976db966
7351 F20101123_AAAMZD song_c_Page_38thm.jpg
6623eb6432d6ac26c103bbab42cdb1b4
2607a572dac1aeada629ff9172a9b73bfeee4d2a
25314 F20101123_AAANBD song_c_Page_01.jpg
29d8b7987ae3a8b064ac16d61a472660
8daae36738ad614e5bc2bfba274c12cc4c35e128
31038 F20101123_AAANNX song_c_Page_32.QC.jpg
0f7b9b89064835191d9127ab8f22d394
bcac5e335b0508e83ed09abfe5242c99fb3f912b
34152 F20101123_AAAMUH song_c_Page_19.QC.jpg
8d5e86efa2fb60f093b374262d11a072
2802b4e3b5fe0560c4386954b949cfcc424ce418
305 F20101123_AAANGB song_c_Page_36.txt
b7e6fc3d08f56ac937a74c8f9bff10a3
ff3e64cfffedfe6a0f52f6d755e8f90d9509bd4a
82318 F20101123_AAAMZE song_c_Page_42.jpg
984bfa69c5b7419e0612345db587616b
d4a320b934d168e52d3aa0b0c76dd8185bc823c6
104449 F20101123_AAANBE song_c_Page_60.jp2
6b83ba1f175e1a6cd64109545cb24fe6
0ebe96c086b9afbd28ed1338b3fd0855393c0d72
8208 F20101123_AAANNY song_c_Page_34thm.jpg
f28c0b361a789447dd8223d88225b753
acc2d5631ed2edca94116d8cf93ed4932aa846ec
7272 F20101123_AAANLA song_c_Page_07.pro
3e530e993ecf1ab926cbd845aec612cb
7695cfb4e1b959814ed65eaa65229f3882b6a262
31764 F20101123_AAAMUI song_c_Page_43.pro
5f0ac0ed8bd900156ab3c5e305664c5c
59370b02ad9b4229677c0de2201a25ad2e2a05fe
49765 F20101123_AAANGC song_c_Page_24.pro
d55cd2ea7646dc6a2357c2a50b88a83e
e9c01ad68b866faf156c6022b3079a3e3e24c6d1
9396 F20101123_AAAMZF song_c_Page_74.jp2
73859abf19720627427045837dffa9c4
c13354674f9a1e2018af2be1e2997b44deaa8da2
45802 F20101123_AAANBF song_c_Page_27.pro
70bfee768be45734d26aae0e8fe8c8d4
8afefb180cb9bd9bd06fcb8e68ea4fa0bed7d924
8040 F20101123_AAANNZ song_c_Page_35thm.jpg
085557be0ddc654dc413acac9907087b
a527035a16430b42adb09c33950b90d7db847ed3
54243 F20101123_AAANLB song_c_Page_08.pro
510c10c2fc3f6e36a967e57ab6230974
0da848631fe9fc790967d3a686e65e4454ee2ef0
F20101123_AAAMUJ song_c_Page_21.tif
d3a54456b41dc20d088b2c190683eb79
0c61eb1c3494d998a8f48df021b467d6cdd34ad8
F20101123_AAANGD song_c_Page_33.tif
bc2d992bd933d0e0083ef86ae31b03b8
39cafc63dac3f6f8813cf43de225a75ee91619dc
75436 F20101123_AAAMZG song_c_Page_05.pro
02ad6c5871dc962418b35ec3039f86c0
86c202aa5757bf14e06d9b5228533ef5d6b7ca81
1082 F20101123_AAANBG song_c_Page_03thm.jpg
22485f6de5d77aeba724c4c2ab114abf
6a26551a3a5aa973af7ea75a944b084856689679
51529 F20101123_AAANLC song_c_Page_18.pro
e6434359b167415ba32262a5ed9a1c99
a1392415b46d6163b540e7996014d26f589170dd
108895 F20101123_AAAMUK song_c_Page_30.jp2
0528888914d3c5c65e78545ddeb07f50
a4226f067bbf3b789e997b5a5a3be8cc15cf203e
F20101123_AAANGE song_c_Page_45.tif
9e6e778262ef0c0bc4e394904c6fdd00
9b782f3b9b5608768a9c952bb81d4de674429d0f
F20101123_AAAMZH song_c_Page_64.tif
c039415d991fe7402f922516ddaeff9d
8f2d70175e56e6ced31070ef2dda277214b0bfe9
930328 F20101123_AAANBH song_c_Page_26.jp2
920beb9c1ab82cd29691c9ffd18d6059
485148f1b087ce880eb7b8a001ca1b4ac1978a9a
1716 F20101123_AAAMUL song_c_Page_31.txt
40e7cb13bb43e788a48620a26d50cdc3
1b2c5a9eec8ad32aba07ee2d61bd645b0fec12c0
98016 F20101123_AAANGF song_c_Page_22.jpg
fdef84901e394b4ac2cf7af46edaa318
d861d40aa2b037534c56e1d59a5cbb8a821e8c13
501 F20101123_AAAMZI song_c_Page_04.txt
5752aedd8416cb4f6af3b804a8f4bd90
8a7d7a8ebd3737390ac03a7744553ccf22e575cb
70712 F20101123_AAANBI song_c_Page_47.jpg
b349053dab87514400fe303e8c8576ad
0e47b61d1d252ae2811f2a30ebc42be04e5b0a1c
53047 F20101123_AAANLD song_c_Page_19.pro
fec684171597ea2f85f41e6920943463
c9589113840f42079a7dbef70a533ade7f00998c
92938 F20101123_AAAMUM song_c_Page_75.jp2
3ecb55ba5f91b840572d9e14cc697469
5518fa4a5ec09c2b27f5a2f88ec6c297d74f7d3a
14675 F20101123_AAANGG song_c_Page_07.jpg
deebd0532e92fde80069ba4e6ac5590d
6b200844877ff5003db25107a92d6c5a5439b869
106207 F20101123_AAAMZJ song_c_Page_12.jp2
aebbcac1b99177e670058a3ce811dd62
f73afd2fefce449982be8772a279c04baa35d748
F20101123_AAANBJ song_c_Page_67.tif
b15c5e4da6f22b85ba3983f1f8cab197
6ee5d994285aed762f0248d3028e003eb97667fb
50013 F20101123_AAANLE song_c_Page_20.pro
547665af62cf8a661ff10e2ef8309874
2639fc4c66e4a318b2749e32a8bb36a1d8e08bb3
99694 F20101123_AAANGH song_c_Page_32.jp2
c275dd96b6e8a869dace888e2b9e7747
dec0791ce1c7164faafe5bd375ef8a968944b77f
565 F20101123_AAAMZK song_c_Page_02thm.jpg
7d25d88b6717ebae0092953657fd7019
f6130bc1c1e9f9de050a5e38add8c76d3cf81c91
28429 F20101123_AAANBK song_c_Page_04.jp2
8d29687ec77d4dffabd80533b29f3fa7
6f8d4877420230496beb8f85c53de2a4215e0afa
46406 F20101123_AAANLF song_c_Page_29.pro
9a3374027d6a78a1630b9107cce288b5
9cd5b54c564c19c839e67c496e173766e9b76e6f
96530 F20101123_AAAMUN song_c_Page_41.jp2
820eb892076eb82ea6634a86c2d23c38
987fbc2bd3bf793a5c83edf14560e9c19693a529
84356 F20101123_AAANGI song_c_Page_38.jpg
35aeab5dbc861fdd13a818ce87784605
4828c637f799919682b93f3ee62f4318e7069e47
4515 F20101123_AAAMZL song_c_Page_46thm.jpg
a836cfa4996dcbe5ac03f379984d3e72
b5ff8ded307401173d755bd9432cf82f81df00e5
1966 F20101123_AAANBL song_c_Page_22.txt
ea3d69cceb3255b2517f805cac7b51f0
f40337f931884afc7056a8430a280a6e92a9dcb6
33614 F20101123_AAANLG song_c_Page_31.pro
1932f5d33ff3810a3b7ee3c59929ae2c
8bbdd54cea597881d9bc9c05d19f6edd508fd877
100558 F20101123_AAAMUO song_c_Page_27.jp2
f6daca129af83889eac864463d49d194
8f2fcd1a225d2397d54ece4f8eca3948f0bf1b27
1598 F20101123_AAANGJ song_c_Page_63.txt
ba59bf460c9f1390612cf8ce0981c0f6
eb7fb6b07e79cf9d06bc529db788fd0834c2ad71
1984 F20101123_AAAMZM song_c_Page_35.txt
bc6c7048ac89a374b67b5b747b1039e1
ef0e593d2f5e0377bfcb1ea391bb575363a1ca7f
64435 F20101123_AAANBM song_c_Page_73.jp2
b76b52e4d4f851f68309db7af7168cf5
989f209b83eff428cb419519204e1c3c02c84869
43096 F20101123_AAANLH song_c_Page_37.pro
cda0c393a73948a749e8bce123e49226
a2e5288dd07ade3013c5e65ef8429f9d7313bc5a
41311 F20101123_AAAMUP song_c_Page_23.pro
1619c3e874a0477873fcec46bbfc9049
ab3079f3ab022f4e6d2eb15bb3613799ae1599e4
1565 F20101123_AAANGK song_c_Page_47.txt
80c6daeebad546941ba6567e01388709
1d0b71cd58068ac2e64c0b75610dbc11c1e656b2
51342 F20101123_AAAMZN song_c_Page_52.pro
982618883a4577071349ab21a4f041ad
bc00c5fe4e14cd032ebbcda34599f5c55ed4369d
11382 F20101123_AAANBN song_c_Page_04.pro
1a29eec56a8ac966bf18e5880032c1c6
f968462c78c86ce4e11c63a357d9b2f9cfc13cb8
38630 F20101123_AAANLI song_c_Page_38.pro
905b5cef43e1d6b7b2431556f22441a8
28b5d5cf2d07f043406aa29e525e43ab532c3518
F20101123_AAAMUQ song_c_Page_71.tif
8151ed9ad79e97cb75aa63f1927bf3dc
fe161fca1e148d8ef97baaeeaed2b160077d9628
98634 F20101123_AAANGL song_c_Page_25.jpg
f17f4480d3d09b0deb2812675d846d07
61ed8be72fe4ffc74ab4cbc138300bd794b065fc
88678 F20101123_AAAMZO song_c_Page_51.jpg
16800c95797de4391e720104ef5c6e40
25b767245a0112444fe3310d7cf2bc29819ee84c
8342 F20101123_AAANBO song_c_Page_53thm.jpg
0c76a3eaf03a57d2dde6374fe2315f44
458e6399b93a044c2d0ce420867535e6470ae199
50942 F20101123_AAANLJ song_c_Page_39.pro
669d3a522e0957a3803102dc78072734
f4893ca5db4694f83409ffe4e6070c09c762fdd2
93716 F20101123_AAAMUR song_c_Page_16.jpg
f81c74199ca5704e402706f4885b844d
4a23daec46d1c4901ec9bbbdffc4fbb7a99373dc
7461 F20101123_AAANGM song_c_Page_32thm.jpg
03f04a0b7146b632f63c678691bea3ac
17ef3b537b4d9f65db5bcc851f6e2d9826df954e
83859 F20101123_AAAMZP song_c_Page_72.jp2
13a45f30b1ecb1fc684e02a97ff19362
422459140aa19ccd62df327b06e0d28070f849de
7564 F20101123_AAANBP song_c_Page_23thm.jpg
0c0b305483a165e91b5c4ed0d18ea5be
5a0cff2a03d82f67cb609a875aed7afccc4aff58
36000 F20101123_AAANLK song_c_Page_40.pro
b7a599238ce090387f9bc353775a647f
bcd9e9e730d04a9f00f18e97633fff751d2c7e6e
862371 F20101123_AAAMUS song_c_Page_68.jp2
610b7895ff97c51393a28edd7bca3e66
6b83b48a8e6eb8cba8ef1aec5ee33a05090d9a07
87538 F20101123_AAANGN song_c_Page_42.jp2
169a9850103f33e44fd7584a27f6e9c2
1d339e6ebb6b0f6ac1653d5c9c04856cbfe7bf16
7576 F20101123_AAAMZQ song_c_Page_41thm.jpg
8cf472b3e32018db42cb91ab2e0a638f
c620b9b63ce35e5844073319c4b8233e7c471e15
19051 F20101123_AAANBQ song_c_Page_06.QC.jpg
b5f3c85a2860776353067868444b7b15
27fe29409189c66f253d4fdc6ae07c44928393a3
42925 F20101123_AAANLL song_c_Page_42.pro
738a0a2b1dec4d312e6d40557f98c81a
c724414acc3caf039d649fc38747fcba932eb76c
F20101123_AAAMUT song_c_Page_27.tif
29fa386f6bcdd4a7f73444e91ecb041e
509f35583538f00aee6a428d83d8e8d7f565062f
93258 F20101123_AAANGO song_c_Page_51.jp2
16b37786399fb05712f3913d1ae7d0e1
ba5f2edd12ffe07de18b2dfeda4c8075167a795b
F20101123_AAAMZR song_c_Page_66.tif
b5cf6776f4250ba2fb74a0873b36ec32
d42c11e45532f3f983b47f0230db9c88e71012a6
22151 F20101123_AAANBR song_c_Page_65.QC.jpg
790df698ffa7c8efeaef74b2579e8628
ae7eeb56b768b6ccf86710ce9357639af95c7f72
36745 F20101123_AAANLM song_c_Page_45.pro
61de60926990886d05314648312159cf
3fc8cbfdc9df005a6498b97a6f73e1a77ea365ec
F20101123_AAAMUU song_c_Page_68.tif
bb3bb5be1748fc00f8206e67baeb1387
74d0f8d8b29766713bea5ac7c37090a747cc69a8
17016 F20101123_AAANGP song_c_Page_64.QC.jpg
08715261c00fe2400fffe95e1ba4de09
3fbebe82479f0359138cf7b466ccc6994dfa676d
25346 F20101123_AAANBS song_c_Page_31.QC.jpg
b7835361d19e27c36703cf5b7d8f097a
781ffcbbf072ba37e480f7383066239f71762de6
34080 F20101123_AAANLN song_c_Page_47.pro
49e7e727fcb8883eafdbdff78d7408a3
433f7f82f26590e6d3a731089108c51a077e5d99
21797 F20101123_AAAMUV song_c_Page_33.pro
25f83eba2ed51ffe22ae12f5fe3ed66c
19337719e8a7983d2fddcc100e442d72fa4f982f
1516 F20101123_AAANGQ song_c_Page_70.txt
4ca3daf941017cb06459e1c21217ccac
5149539f9ddbbf1182794f114b0e6ed6936eee29
F20101123_AAAMZS song_c_Page_09.tif
bee3aeef18db82c3a69876b3544dc6fc
2812c7807b72f40105c51dd5e102e4dd5855bf84
79589 F20101123_AAANBT song_c_Page_06.jpg
406571a6cd9f4711c4de66f5c8b872ff
d3fd03c1f857221593f32756502c8b8560156389
50792 F20101123_AAANLO song_c_Page_56.pro
e0db9431dbf04b2af61175d4fcec0210
5903c5075f9ccb73e11e4e22f84adca86c5741d0
F20101123_AAAMUW song_c_Page_36.pro
22dbf192bd87cd2d8e112bdbf60290de
f830d8c6023b7ee61383393039eb1642cd85bfe2
4570 F20101123_AAANGR song_c_Page_06thm.jpg
883b6665c49d23099378cc66820a75bd
2d947de22e068b55a162c09181f931ed5ec296ae
7566 F20101123_AAAMZT song_c_Page_50thm.jpg
0b903848e51bb563f836c5914ce03bf3
eff6297dffa2b1265e9b3fa019167e4b3e21ae4b
1827 F20101123_AAANBU song_c_Page_27.txt
e1c7eb7551e08885b3c8fc3e8eca3171
557952779d14e9bc09352cd1e65fea99c0ee02a6
45649 F20101123_AAANLP song_c_Page_57.pro
7f65913c3fb3888421cc123725f4aaa1
cdde0bbb86d680859dca59929ac538ba6f7a3435
370 F20101123_AAAMUX song_c_Page_07.txt
2aeb6d7c78bc42d88ad46eb69c35f881
4e0c1b85e97260dbd2aa6a909c3e7ff631332e24
1867 F20101123_AAANGS song_c_Page_26.txt
4f3a8d5bedf9c79c86843960ff4fe3dc
d46d78c68dcf9f5b064c11205bd62a26a498cea4
1772 F20101123_AAAMZU song_c_Page_75.txt
f0fc2ac25a541ca3d2be9ff83250a096
96d298c22e296d5b74cfe6ecfd6d7b43fdb0b386
31992 F20101123_AAANBV song_c_Page_24.QC.jpg
63ac9541c68f19e12074b9b77cc13b86
72d9bd117bd135d33b3c1a82855c7608836fd34b
38960 F20101123_AAANLQ song_c_Page_59.pro
a853f3fb861eb7b83d21f312dcf75f29
4aaa0931ec88dff34c25380622ce589cb46e70d5
1918 F20101123_AAANGT song_c_Page_60.txt
33f8dda931c98596ad546f3bc2affba6
7c878ec39ebf09924cab4addc56c187d90266088
82871 F20101123_AAAMZV song_c_Page_40.jpg
fcd5235f177801dd390e8ea788441327
91327582ca7e4a85b6668ea0a958e163f9f26135
71093 F20101123_AAANBW song_c_Page_69.jpg
b89c06400a64de670e9c4f6101463a10
9ace925a170a5dde6d67eaa2a9ee0f4f2a4019e8
79012 F20101123_AAAMUY song_c_Page_55.jpg
4ac3ac513a096320e061ceae90feb113
5206091ef39fb94f7fef455b655c09cdd21d37b8
52673 F20101123_AAANLR song_c_Page_61.pro
6d851fee9afaae41c3e77789e8d75fe7
237482ae5e77bdca00da5055a2e80a6a592bd0d3
2880 F20101123_AAANGU song_c_Page_74.pro
036f94bc04e0ede6ba87e6e17c2a04e7
4380e63e064a2e169d57ed5594aeb144fd8ecfb8
48497 F20101123_AAAMZW song_c_Page_34.pro
04d384ea20a4f7c774c91ca9aaf2a067
2bfd7965339a7ddfc1ce7b14d56fcea03c803845
15538 F20101123_AAANBX song_c_Page_36.jpg
2c5416afa9cbaccac3f15d0b5a5b1fd2
195d0921d0efb02eb8e5f50287f4a64e617ab6b4
45573 F20101123_AAAMUZ song_c_Page_46.jpg
2ca3a1653372722c024d3c43097e5467
f1e5ec1af451170a5d153c343d26f9349e17a4fa
23032 F20101123_AAANLS song_c_Page_62.pro
f71734b0020a5b1f5a09ec9e081afbc2
dd3673ff57c878ddeaa23df7f808559db50f8900
F20101123_AAANGV song_c_Page_36.tif
660f1759d0f9d8501b5d0214397c1720
c8765f608cd43c166e7d6baf03b4da8e9cf9368f
95474 F20101123_AAAMZX song_c_Page_34.jpg
a40a4ea09d2b8b50b4ffb0a478187378
080c55cd81d1500b631f35ba215d20c5a1083e10
F20101123_AAANBY song_c_Page_30.tif
b08c965ccc10575fea276d5867ed22ae
9d437ee30424b35cceef7e7c1571f7b7a16e92d5
26226 F20101123_AAANLT song_c_Page_63.pro
fce5580fdfa10c257bef2d5568e5b618
9bdc18572d347b1d4744f84edb609b1e3ef88121
1798 F20101123_AAANGW song_c_Page_37.txt
228a1c4251bc9c6b908cb5fcab4dcc74
0959a96978018b0672ce4dd4e14c3317c9e9dfae
519064 F20101123_AAAMXA song_c_Page_49.jp2
ed9165d09fd9a9de98b79bc3ac6c8e94
0682d760ee04460a72992aa596a09d0166c04531
1041 F20101123_AAAMZY song_c_Page_02.pro
1a9ba2ce76f021c58b219103b8fc91bb
a6c55c096e28923991285f482f3c013ed163dc81
50080 F20101123_AAANLU song_c_Page_67.pro
ed995f5c6edbb362655777ac320bec76
385facb3435ceb7db9ef2ac656b36add09986ec5
66057 F20101123_AAANGX song_c_Page_65.jpg
25393b1d55322ee24323d07a3e66fbbf
04d0553efcc572b30cc63f43c9f6e19b419bd641
2637 F20101123_AAAMXB song_c_Page_09.pro
f0d71239da50e05d96b6a8db0f1d6eaf
805b0dc6ecc1f2fdb1a853e2e2028c9e6da8461c
7211 F20101123_AAAMZZ song_c_Page_55thm.jpg
7fda1cea2ea02712071e9fcbcebeea50
095e3665d917a00c05ccf8f9f2b0b5876a9decbb
F20101123_AAANBZ song_c_Page_01.tif
af81c6574bdf38579c09a4b8ae8eff8e
94c656417f1fa89bd7b53b4a379458b116b14e46
37606 F20101123_AAANLV song_c_Page_68.pro
8fc5ec7b517e27ea9ab964ecdadf2da0
821ab1739295b0a69248d20bb49cb75aef7900dc
5725 F20101123_AAANGY song_c_Page_65thm.jpg
c7762f6f676463ecd0effbb3bcd09ef0
2b3dfb7db1fbd33e68af8ef8ae262de94782b170
99320 F20101123_AAAMXC song_c_Page_53.jpg
a869ad994ad42fd9bc3b5649c0399847
e6e7fb2585a55ad556a27478e0b65328f709cfc9
32719 F20101123_AAANLW song_c_Page_69.pro
47ea82374fdb47e2318b0c054fd2a002
f4b56c15d0f57297882d7614b668cf0541a64245
1059 F20101123_AAANGZ song_c_Page_09thm.jpg
f38f801dfbb6b3bc832aa7b19bbc15a0
0c52aa4a4046239bbde563c9b9d2bb568a3d67c3
32156 F20101123_AAAMXD song_c_Page_56.QC.jpg
64dd718772486e15fcf022bfe6e68374
8e58b45f4bfec9ae8ddb5fb47f1e5296a95369bb
91195 F20101123_AAANEA song_c_Page_26.jpg
2fca1590a0e08dbafd4e3d2d83ea4200
a6b0519950815fc0f98963c3aac2ca2da2a5d5ac
37772 F20101123_AAANLX song_c_Page_72.pro
e049fbd6625466016fa5e1294246fbac
ce7eb52c79b56a11683edf3c1c039f16fb72b68e
1825 F20101123_AAAMXE song_c_Page_11.txt
9072245da0b19cc677630db4817debc8
c6d2fe08b5a1b08ab9c0fb6da0d40e0286f07dcc
2002 F20101123_AAANEB song_c_Page_13.txt
b9ba31b524b45b34d62f072a3d80a42c
367659cd6d97fbff41a5c9ce928b7f37e6c508b5
4284 F20101123_AAANLY song_c_Page_76.pro
317eb51ac0b60153a7f8f7d55d56798b
aa90f19039a03ec4a69901bf2ed2cce0e1cd2a4c
76592 F20101123_AAAMXF song_c_Page_71.jp2
cd980464759f90749eb921c16fa36f8a
f439f3c02ae22e3e99ec04832dfcb40459d8321b
5434 F20101123_AAANJA song_c_Page_02.jp2
52c6ee51198272045f23bdd6e09b61bf
88bfee3724a2d67435e109c2eb111e4d229ddaee
1051973 F20101123_AAANEC song_c_Page_05.jp2
4897d198baa5c2d0891eb90e800e2386
4ae3b2251c937c213e090025481b2034226cc0e5
10654 F20101123_AAANLZ song_c_Page_79.pro
61c544fe87cc4c30796d41797c94d95e
7ee26b38b94c41071e47b18890cd2a19b26819e9
21549 F20101123_AAAMXG song_c_Page_43.QC.jpg
468b703206c6ff4185baf141fb5ec094
29b1d7de634c106bfec09af25a65c39a9375a533
17877 F20101123_AAANED song_c_Page_33.QC.jpg
3b830a4ae8ec8851ffa09f336e7d0fc9
ecf9baecec99ad8b54dc1fe014e45eb330882791
42677 F20101123_AAAMXH song_c_Page_75.pro
b62163dec47d3519b17dbd5f39b50a36
a33f81248d6b20d3e55391991b4dd8c931b8589c
1051959 F20101123_AAANJB song_c_Page_06.jp2
16cbe80d8c8b806b0a2039aa996eefee
5b58e81f828c8ee18b636d2e42309a9068cd4650
1484 F20101123_AAANEE song_c_Page_69.txt
31f67cdcc5a88b9a92e8856844be5237
958cd557c44fb3250112c412b7368687f1fae7ef
33746 F20101123_AAANOA song_c_Page_35.QC.jpg
14e6ae057cee223e3916cfb453503386
b8afb46482091fda1eda68b34efc1f469fd1f53c
27388 F20101123_AAAMXI song_c_Page_42.QC.jpg
019d6928826633534a58924dd44d589f
1bea05d6cd1f2507364e9c77556ab387df2a68a7
202445 F20101123_AAANJC song_c_Page_07.jp2
3bebfaba6e9942fe6a12b0349c73c026
5443d03fa25a1e7cde3df1b53cbeb170f0759524
76034 F20101123_AAANEF song_c_Page_31.jpg
ed7fa79c7b4e950d8d99e9e568ed23f8
da3d7e1e1aa727f6261defbcf6513317a2286199
5683 F20101123_AAANOB song_c_Page_36.QC.jpg
6e095db1b33843886d0e314edb50c370
b5165c3bfe6eaefcfebb680ee60d08f5496f7c7c
114624 F20101123_AAAMXJ song_c_Page_09.jp2
fd0f6b23379c9087d178411d4ec9b9e8
e12d0928c91cf295c912401766347bef4cf959d2
72344 F20101123_AAANJD song_c_Page_10.jp2
42a2e6daf23c51add8bd5060e6eeeb69
ecb510574bc160ea5a47433c02edc7218e7e8fba
16684 F20101123_AAANEG song_c_Page_46.QC.jpg
6e5725961c08bb01e942928fe096d71c
079e0e859cd1208b4340df2eec32ca52af387f37
28575 F20101123_AAANOC song_c_Page_37.QC.jpg
e807785c42e8afc850c1671f35364e3c
e7bf05de165fae5d6f24ea06672f6f441f6e751d
104959 F20101123_AAANJE song_c_Page_14.jp2
6aef836d52a387a9745d73f2d39a526c
9597e9b84c24717f3c9f8af3566e73f547f62415
26184 F20101123_AAAMXK song_c_Page_45.QC.jpg
edbd39fa2cfdce1037cdfe0df04d7e4e
45da874d997f72b528005d8184cd0ee258361244
91655 F20101123_AAANEH song_c_Page_32.jpg
919e7b8e9d880aafda106500a1a5f00b
cc10595027490bd2867334e751fc32b6a735e76a
28363 F20101123_AAANOD song_c_Page_38.QC.jpg
1a0913a8e1e7687f787c8f35706cc908
26a508aa3a840bfc1ce6857bdc3c22d260820dd0
88656 F20101123_AAANJF song_c_Page_17.jp2
d8acaa45847e07b7a1d4104fa22a3a4d
9038bd70e34fa047d674075da84eebb9ff7639de
31847 F20101123_AAAMXL song_c_Page_14.QC.jpg
4ecae68b4a0d74f91ffc6e5424204960
dbdf0d300c1e479b1a7ba4fb8789616ad5abeab7
F20101123_AAANEI song_c_Page_53.tif
23dd913ec3e1f9397572af0ed4b318df
7025569fd3b3f2125159c9b6c7f28744a5af1ec9
32448 F20101123_AAANOE song_c_Page_39.QC.jpg
597a1259e7835e55c149c0a9a009057e
ddda0485dd76e4c9d93978eb56d01c884bb85bd7
107188 F20101123_AAANJG song_c_Page_22.jp2
43d424039670c98c084c27917a5bcc0f
9fb8f6581021575e028e132163a3554be741a2d3
F20101123_AAAMXM song_c_Page_63.tif
5ceda2e46ff25ddddfa8bfb8c9621bd3
f5da9751b3cf8e260a923ece01e7e116dad06029
222 F20101123_AAANEJ song_c_Page_03.txt
6cb852db69c850326a665a42f471040d
922ce080ca1a8131a2ea9a4ba941407d20df1eda
28389 F20101123_AAANOF song_c_Page_40.QC.jpg
be440acc69e2879adc6ed53897845535
829c45807566229bd60ec3f1b9eb1ff8baf07544
104921 F20101123_AAANJH song_c_Page_25.jp2
6015dd5f3b3408634e2916fecd2b9a7d
743400adae49e5beb7d2a50b2663c8c3e5c87379
90741 F20101123_AAAMXN song_c_Page_15.jpg
39f305bc5044a91ad33081b00038eab5
70e0fd6e3cd5ef6d4f4d86774d673dd4b6787788
159 F20101123_AAANEK song_c_Page_74.txt
e498916ddd7dbccd31e99046ed39a91a
d58902fdd54b28f48bf14cedefe4607c0f0f47e4
785688 F20101123_AAANJI song_c_Page_31.jp2
e3d1bfc570d720c7cc6db535a0cddb54
b1fbff4f5917ad33029bbf14e23226920c56c403
53022 F20101123_AAAMXO song_c_Page_54.pro
feb51d0f000da788f2b479eca045be7c
dd827bc06dc3fbcae14877c65f980060a5443bd3
32323 F20101123_AAANEL song_c_Page_10.pro
77c283193bdd46258467f83f7e885dd7
3a5684eac6ed661ad6a5fe9347907b459f436dcd
7244 F20101123_AAANOG song_c_Page_42thm.jpg
b57609b80960daca6709a334cbfe8288
a5e5ba9d6e48725e6f825c9a0252d88b6a24f84d
106967 F20101123_AAANJJ song_c_Page_35.jp2
a75b49f5e9583c96e83fef8948c7caea
52a82440f779b130586ff4c425dea56de947115c
6742 F20101123_AAAMXP song_c_Page_71thm.jpg
8fdfdfe178a431a12d58f27fbb9fad2e
fba65aee8972e452be18d2ff650b26603ea61093
F20101123_AAANEM song_c_Page_72.tif
68c83fc9a513aacb9668797eae15ebfb
d002b23b3c32adc457ccf541a381173d0211d807
6692 F20101123_AAANOH song_c_Page_45thm.jpg
51a450a2d02981c33a6c6cda7877c49d
f4fcb07fea5cdb1abc4f96c63ec117a0c3ac8f2d
93365 F20101123_AAANJK song_c_Page_37.jp2
1ae7e07290ae4c31133ca61ebe41e0e3
8b27d849bd7b98c1ccc0cc90ed194f59ad7cc4e0
98097 F20101123_AAANEN song_c_Page_44.jp2
bc5eb85f81b65cbc496aa1bbc34ffbfc
cce354675f7d76ca1f71f91a6bfb6c6a84676c28
23371 F20101123_AAANOI song_c_Page_47.QC.jpg
eea7a6cd775f1c88e6b8ad2381f8edc3
6dffbb6ead4bb8dde628880312b12d8d7e441a12
887506 F20101123_AAANJL song_c_Page_38.jp2
b2e6a1a091d18857a0b59595c4256224
1e617f1c518e5546a615b71b816b633ffd17871a
1546 F20101123_AAAMXQ song_c_Page_45.txt
a425013d0757e951e78ad9bc39885063
d9e5a876d1676267b189d166ded0ac46e6d045c7
98527 F20101123_AAANEO song_c_Page_28.jpg
ad396bd67aae92aba7254cd8164a0a79
8add576bb6f3cb1e70eb318aa95abcfc59cc2687
17560 F20101123_AAANOJ song_c_Page_49.QC.jpg
74f108cfc733c0caf1213fb3a94076db
9a4f23af92eedc94acb6442603e9392ec6035ab1
107670 F20101123_AAANJM song_c_Page_39.jp2
cdf05988c7a7dfe9e310cceba8f5a4c1
2d1f8d39322d0c4d7f219bbb2e934c5c597abe82
7562 F20101123_AAAMXR song_c_Page_26thm.jpg
859fe18511441d6753dad9ff5a041d49
eb09f24db6d62c0f46b8790e09594e8bda1a67f8
43002 F20101123_AAANEP song_c_Page_66.pro
ce811435a396b7de1f2d2d3fee145951
f6e58234c08b62094593afa3bff97f7f1f91b305
27983 F20101123_AAANOK song_c_Page_50.QC.jpg
9c7a724edf5208a0eed3eb270bd1ac7f
ca5d63e1835148c1acdc214465a6724a14bf8cf7
824477 F20101123_AAANJN song_c_Page_45.jp2
238626d9eef7793d2f0700338fe899fa
833cc1241fa68da89ef0882052397732e2c139db
112967 F20101123_AAAMXS song_c_Page_19.jp2
80f29eec922638d29415f3a2d9ebbb00
75644895c76fda520ca76b9b43b84e2460f783c4
4809 F20101123_AAANEQ song_c_Page_33thm.jpg
e6e1c29f0992b74967727b87252c22c0
96ca92883d1a04e4d1b2cbf9ca00b654475706a9
28135 F20101123_AAANOL song_c_Page_51.QC.jpg
d169ee3f9e11ea88e0e98d2ee5467ccc
566e80e36c53a9cd275d919437eb8b2b7f2d9542
73144 F20101123_AAANJO song_c_Page_47.jp2
b0c83d74166655f5d395c7827ad2ec50
56c183b84db0b1385e30cb31f3747f35a25aa4e6
50340 F20101123_AAAMXT song_c_Page_53.pro
b83bfc3e47ba79127e89635949ee2dfe
08161fb989a1b40779a47b606600ad7a6836ba7b
F20101123_AAANER song_c_Page_34.tif
faa53a3a425a62b2be45b4507a3c0ec4
e3c481a949c40262319d07c17614d4a43bfbc8be
24211 F20101123_AAANOM song_c_Page_58.QC.jpg
ff2988db4363cc5dbbe8fac5327cabed
bd6b4055e1f628d20d1fc104e9d34d2446a78ea4
107243 F20101123_AAANJP song_c_Page_53.jp2
50d659bbdff9479b38a0b17025acfa59
c569b6ed3e352e2360a23249233bb5ff187cff90
98660 F20101123_AAANES song_c_Page_12.jpg
8ebd2f8114fd62d6952dd65d598d881c
571d535eeaf9b6aef5d592de89b29ff86bad7ec4
1934 F20101123_AAAMXU song_c_Page_57.txt
cf07b9a5ef16b99697e76f703b3cff40
54d7bde36ebf06580e85905c842214e4f0f2992b
7743 F20101123_AAANON song_c_Page_60thm.jpg
eeb450581f1234bd32de9b3f195c37e7
59cdfee3d0ca0598bf445bbf7ee99b68a65949a9
113166 F20101123_AAANJQ song_c_Page_54.jp2
a111b277e4c23ce2c54747ca8574c133
9941b2ed05cfe3159064afea4673099ae3dea00f
72967 F20101123_AAANET song_c_Page_71.jpg
5ee9f5692d0ca1b64d9e40cd27041826
a07c9ba159583042429f15aeb6d4362faf5335e3
102243 F20101123_AAAMXV song_c_Page_18.jpg
60f1eed7ad05e816dafa91c4269939a0
8ff2e7db803135cc80c89d1219559606d7351870
31063 F20101123_AAANOO song_c_Page_60.QC.jpg
02ae5cd390855e35474f2f44d9c0d8a4
b2c3856df7b2ec0aa0e1d99a07fe01fec2e8d6a6
76895 F20101123_AAANJR song_c_Page_58.jp2
876bbaa864c97c0e02830e7b1c870b8d
0a31d156739232207245cb9be6c8035505299be7
48660 F20101123_AAANEU song_c_Page_25.pro
ae84d88dd3569febe6a888b02c3327ff
5f72a313b2d4021e5df17f5a33ae09cc55123456
89172 F20101123_AAAMXW song_c_Page_50.jpg
9467ce450eb7959a0501d66d835ad554
cef8398e7fca0f310d4fb883e17dea089a75041a
7931 F20101123_AAANOP song_c_Page_61thm.jpg
86c76d7df0e5ba3403b3b7b9b670f813
1a2286110ae0595fe39083fba5aa626b55980b6a
81567 F20101123_AAANJS song_c_Page_59.jp2
6ef88a804ccb114e4721b360444489a0
59e06e74ebc53dbe468ad15615ca4a477ac190ff
31294 F20101123_AAANEV song_c_Page_27.QC.jpg
dcf34ffee7eaa26fa17f98ce151526db
e014365dc0a9cce8fd1fc5efad948e55f8875ce6
45594 F20101123_AAAMXX song_c_Page_32.pro
eabf75443f18960be8339e07d3a534a6
bb0dd2f8b60e6338b43d37c9638fe2e8d1b5c179
32703 F20101123_AAANOQ song_c_Page_61.QC.jpg
0becc57c0a12334bad080253e03253d9
b50ceefe7864e35f5a0ef9d5395d63b5d593d2fe
71144 F20101123_AAANJT song_c_Page_65.jp2
ab9c18ab681fa23dafeb54ae2e7321eb
cc96a9129092929b61dedd55bf48122685e3c0a2
59545 F20101123_AAANEW song_c_Page_73.jpg
7b99466151e08352c792c02c128a1a81
9451f960f2fdfad00d6e8fd6d705c97342bcb2b9
7951 F20101123_AAAMVA song_c_Page_27thm.jpg
780fdc1af27045d38d762168fe3e560f
53609eee0b4c94e25d480ff5b483b3acc525bd46
F20101123_AAAMXY song_c_Page_62.tif
d2b3ff9984d14f545d2e5c17362164be
e502c425d795eb968215941f957cf0cd66417762
6897 F20101123_AAANOR song_c_Page_62thm.jpg
bcc42a8655e4b8dbbbf04425c11c0eca
372fd855a46c1821146af8ee584e3944df248d1c
741808 F20101123_AAANJU song_c_Page_69.jp2
af3a08b6aef8392d38d80d03b406750c
d40f1911070101e0fee34d2df112b447e72b5991
51117 F20101123_AAANEX song_c_Page_30.pro
eb1c97a91a136c7e3e11123e1a39ec3a
d8de8400f7fadbb34f10350de34f87cc5fa82a11
6539 F20101123_AAAMVB song_c_Page_59thm.jpg
52c20a2f47b55d5cb679b0b83523352a
07b2e89ba765a8bbe1da412e0230a4f88ba6b954
23625 F20101123_AAAMXZ song_c_Page_49.pro
18be6d08b56d9a612f19e6f3db159f8c
6f41b5dc1ad400d4b834cf3be3b213d046db5f54
21762 F20101123_AAANOS song_c_Page_62.QC.jpg
73868608a16400fbc28bb32c5c3af99e
4eb9ce250d559933aebabfd6dfbe1f0e037bc321
72526 F20101123_AAANJV song_c_Page_70.jp2
fe68b1793af7c9aa149f29784a4c7010
0c965fb74a37be8abf4309394a4868aee4b1de1b
103208 F20101123_AAANEY song_c_Page_19.jpg
fb8453cc18173bad4b6190a3783cfc9f
9a9fb295d0c63f19f7167c3e58267f79d6763b8a
97778 F20101123_AAAMVC song_c_Page_14.jpg
c9f6f99cbaf3f184d784e4ec73c00f49
71dceb76ceed843b3913b00e779c165324a3f93d
20134 F20101123_AAANOT song_c_Page_63.QC.jpg
c87eb57b98273a038afb1c7c526bd0e3
8bb2aa8be016d8d972af4c2a6a2514ffa33ba0e8
11967 F20101123_AAANJW song_c_Page_76.jp2
d2a8301c3aa892731387236c1fdf4739
a1b7cffa0aaefa3721bc18a53dd85cf8f411400a
36003 F20101123_AAANCA song_c_Page_78.jpg
b8961b1ed831a8ae017a103902dbbd8a
0b662553f635e31df27f7c6ed1e66f7a819027ce
1475 F20101123_AAANEZ song_c_Page_02.QC.jpg
71939d41a8ea79e45517382420303e54
1ebcb1ce41354df35943ec627b9d71325bb93ab5
99338 F20101123_AAAMVD song_c_Page_39.jpg
c83d3b77215bf7558f3ad8f0c971fb24
5794ea88065187a641450cc3ad21dcde4b1627ae
4856 F20101123_AAANOU song_c_Page_64thm.jpg
b4660c36ad418915c29e0dcaf60a84e2
7e925fc21eea6a0ce3e3dc06a16caa88a8f6b38e
F20101123_AAANJX song_c_Page_03.tif
1d52a085ca0247f2ce383a68dbe98d1c
3a4c8b0f136f6b0e7e17744e8af264e2eeda3c74
7275 F20101123_AAANCB song_c_Page_16thm.jpg
85447dc9dc183cf24edb08692c9830ce
e907c8f6b170636b7accd1a3ee30cce339139187
506517 F20101123_AAAMVE song_c_Page_33.jp2
5915c9681066fe41e81095a55cb41783
361801085e35b84e79ec8050e4d57a7152bcd070
8103 F20101123_AAANOV song_c_Page_67thm.jpg
f564f09bb2cf915fd338a5db7c411900
cfaeaac90c0a325ea1cdc40bfb56a8b58964231a
F20101123_AAANJY song_c_Page_06.tif
034410e0c65c427d8549b23725b4c1fc
5af63c8f7fcdbe01793e279c69bc5eab34e7d2a0
65673 F20101123_AAANCC song_c_Page_43.jp2
87047a85dfff94e05aeb5279c3e2222a
d0b76e2f8ef838bfd04e4db6dcac2828de3d07a4
101200 F20101123_AAAMVF song_c_Page_13.jpg
764d7e68689541403498d530cb152203
c6190b0a06d6ca9abac59e5f790ce6abfb11c83e
22725 F20101123_AAANOW song_c_Page_70.QC.jpg
70da4d3b852f0eb32c00f1583e56dc38
7e0c7b0ac25095a5c6a1bef61d86b6d47024c72d
F20101123_AAANJZ song_c_Page_08.tif
0e4da3dac9514ba33249db4688c9566d
fdc4f044da941875f6576d94e0f48bd2aa58d383
1952 F20101123_AAANCD song_c_Page_12.txt
92f4b7571dacc7d800bebdc430cd03b9
0ecfa0faf26f6ea84159546c8ad678dcac56faf3
463227 F20101123_AAAMVG song_c_Page_46.jp2
23ba9b45662eca4b9c7a9a1acf3d6f88
f2f2207f68bb5d0f5e898b3772f284631055ac56
8228 F20101123_AAANHA song_c_Page_18thm.jpg
ec8125d2a89b5ffdfa06c59ca8ddb4c3
0307d91d66db20a5e2e5a428c270e3d2e885e6d1
6628 F20101123_AAANOX song_c_Page_72thm.jpg
86d34dbd4392cdbb428e083d28e9dde9
0098dd52655be4304048f2ba01a7ec8889d8e96b
108302 F20101123_AAANCE song_c_Page_67.jp2
bfb6c22fe87b8ecd5710af2dca7e30f3
b4612625e21abe5280db7cb00747fc663f9f5a99
31026 F20101123_AAAMVH song_c_Page_34.QC.jpg
3d432f90b3fbe0419d92bf725826bcec
5149588071a6459eadbc98f1179a3eb66482a52f
1869 F20101123_AAANHB song_c_Page_29.txt
75a65e7db78f56b9a1b9d42babfa3a24
55b3436d88b90877d85278c112095ecb7b89f255
26250 F20101123_AAANOY song_c_Page_72.QC.jpg
d942e4e453232174cbee96106eec8524
cbb04cd0baf4622911ea955d42ab07824e13dab7
105 F20101123_AAANMA song_c_Page_02.txt
396c32b8bf194d15d56b8a2912eea81e
a368c404dfd3811faf4df6b6b38a3ebb63a89a46
78475 F20101123_AAANCF song_c_Page_72.jpg
4a1cf6d048996bc393393986ed350535
4f0de51428ee60d4160ddf9b5637a0e33a63b9c2
100375 F20101123_AAAMVI song_c_Page_67.jpg
3cd6238ea31b9a189c633a84c31ea7a9
654c48f5ffcc87c413086c2351fab7d0f892b401
6321 F20101123_AAANHC song_c_Page_69thm.jpg
0a2b64afdf2625cee605456a6c2ce26b
84bee0130eaa7feff191afcde2b92b06b34a289a
5423 F20101123_AAANOZ song_c_Page_73thm.jpg
8167d6e237e386676284c3104dfbc1ce
96eb024287e1e033e0b8bee4f8e70166fc02dae1
3173 F20101123_AAANMB song_c_Page_05.txt
3479ce7cb3dd4df03e64313c271f91ab
cdb90dfdf995544a85e821e8f8800769f70bbb57
428 F20101123_AAANCG song_c_Page_01.txt
3bf3194f5c42ba7daa3472a648c4343b
de00d012b4e0a1eec6e83f25b227426e24d45597
1922 F20101123_AAAMVJ song_c_Page_28.txt
566dd6603a5f72f757e1073e08e10fa2
51ed349a02a5c21398ef43b9c523fe863a26a799
96133 F20101123_AAANHD song_c_Page_05.jpg
effa7356f635d9d6f646de132fd29120
7e552fbaa017f0b6d8f458153545872549336b7c
2179 F20101123_AAANMC song_c_Page_08.txt
9c08a1245037dbba9f3e431e5f0d8e92
e4087fc574ddf61fcb54c047845569e768e56652
F20101123_AAANCH song_c_Page_20.tif
49eca569053f1e50018536d8fa0b3de8
f30ed9a8481dbeafa57b47a86296d1addc21bb70
7636 F20101123_AAAMVK song_c_Page_15thm.jpg
6ead60070b6ecb576756046df30895b3
d50b9c6c116806108d3b552d8fc83a3a5f98ff2f
81952 F20101123_AAANHE song_c_Page_17.jpg
0ebb2b6f694a40675a92ee6c38d57d99
bd75c097c680402c6a955da08f28122222b2ee0b
1534 F20101123_AAANMD song_c_Page_10.txt
64f424ba589518c0e5384e0ea2b915eb
393821003f5664af539278100e50f851e3533a0f
99426 F20101123_AAANCI song_c_Page_35.jpg
9f1c1423e0cc785fc576ce2df7a5732b
bed7e92ed38fe7285bfe111bda0c8c1b24252e27
F20101123_AAAMVL song_c_Page_07.tif
9b5dc6a2803b71931d191a75f03e3b00
bdb05ddc71c8696d8c864027037293d436824274
41113 F20101123_AAANHF song_c_Page_17.pro
2c599573d537efe240e4d11d010fa315
ab80b6b342c8e25b26da276d2a5019da4c03f695
683 F20101123_AAANCJ song_c_Page_78.txt
85226268ba75d247e2ebfa4a855f74ba
799949d9625ddcf148f5d1b6689558f2acae5488
97146 F20101123_AAAMVM song_c_Page_15.jp2
fb60bba2838d318a03b379d26bf0aedc
f7d7a6d3a5dedce62a6c8b0e0e9a494ad6e6205a
44468 F20101123_AAANHG song_c_Page_50.pro
ce725c7377604fbc43d6a37de2ada25a
4f2decd055f3f58809965b536f98bdbb688892f1
1936 F20101123_AAANME song_c_Page_14.txt
8040ec0f8957b615333114c0ffb35bcb
5fe0f52cf757f8088619a32bbf66c7c79f261c40
7285 F20101123_AAANCK song_c_Page_40thm.jpg
791d91cff8e9623c25bfaa9f75760906
1f10e4078a98821ed06e6e2540f455b336e8859c
1916 F20101123_AAAMVN song_c_Page_50.txt
64cc8f74b4de48cb8240c9e0e3f442dd
12cba1aa1bcce0ec98786e55c18fceab9156b850
F20101123_AAANHH song_c_Page_54.tif
306dff68947c5388aa638f5557e6e65a
ad46f0d5240656fe2c9070997379383adb62d44b
2087 F20101123_AAANMF song_c_Page_19.txt
b204ee2460fa31f247a0782036a2904d
a51f571f15198c989d8e2221b54120052f300af7
8191 F20101123_AAANCL song_c_Page_52thm.jpg
dcfa3bfe672bfd8dd5d14d86c9d49e6a
c27c02e470dea40caf04bbf7d577fa99065deeb0
94528 F20101123_AAANHI song_c_Page_11.jp2
d08b9dacd4b543ab5511205ca14887ac
5d8f29706b129c4fb35561b4bd809115ef51b084
1920 F20101123_AAANMG song_c_Page_25.txt
e8f19117b8555998048c15cc744f4765
45307e397365e94bc29044daa6ccc164b765ad34
50316 F20101123_AAANCM song_c_Page_13.pro
acdd762246909d14dabc0ee2e1f29b66
edc5afd60d1407355f8fb25ccc9f6938952243d4
F20101123_AAAMVO song_c_Page_17.tif
e19af8912bcfad372c31472a0a2c7308
2686d42ce888d4a208c840e5974431dd5ba10aa3
899691 F20101123_AAANHJ song_c_Page_23.jp2
56d85e5e605111cc933ff4d9a42ff813
806280563322b056a15c2b1187f1275455e13cff
1855 F20101123_AAANMH song_c_Page_32.txt
a31975ee2ac610c79b9a39de6d723ad9
973feec047009a18b0ae2f99a9bc78ef99438300
45879 F20101123_AAANCN song_c_Page_41.pro
a6dd0197d7d72976dddaee4501e5dc97
03021b860c08ca7d796add0862ce6da85a7f093a
33059 F20101123_AAAMVP song_c_Page_67.QC.jpg
72e0349b9b869125696981ce19d667e4
ebcb022ba9b95c8150689d7c813d89aae0d0eeeb
28559 F20101123_AAANHK song_c_Page_77.QC.jpg
f96a0a67f3bb86f61318ae66e3c468c6
5f4ea399e4a14f03061b1a60ef5ef89f82518dc9
F20101123_AAANMI song_c_Page_34.txt
970f6d72edc1e33a0c79b4fa5082cf48
0f223eec7258e3a27590dc6674a9b2d273dd5547
2487 F20101123_AAANCO song_c_Page_04thm.jpg
d9ce4da1f9fc0bdb27ab3c49094a9358
b0e9bd16a38d8559c6f1679ce7afb0f382b121d5
49030 F20101123_AAAMVQ song_c_Page_14.pro
c1ed7af7c546c5c989ccd748f16d2936
1978a97814a26ac55fe4e6a225b8db4cd1fac1ba
25888 F20101123_AAANHL song_c_Page_17.QC.jpg
b96f9c56dd455a32f43e47f11b3f8916
bb17eb34caa046961182a173afcc81446ed9b6a8
1697 F20101123_AAANMJ song_c_Page_38.txt
03e03a76745a9bee00ed0aa883fc0bca
cc869db326a93bc0bd780de114aa37e09594d07b
24212 F20101123_AAANCP song_c_Page_69.QC.jpg
775e49702ba8697eb195bc257a690b2c
6e87a5cb76e35d670ea9e06347ca895aa6a60148
26764 F20101123_AAAMVR song_c_Page_79.jpg
47fff5d2192d6356f2b027cc75c4ab4d
3bff8638449ec2900c70ffff69890ac62a84abfb
960629 F20101123_AAANHM song_c_Page_40.jp2
7932fb79effdea4faa8cb89f2d483690
354df43e3dbec7eb2fbce852e73306fa141df23e
2015 F20101123_AAANMK song_c_Page_39.txt
57f35524774adc5ac0057fdcf333c7c0
2a8ef88cc5b247cecc154b32914459ba5cfe4019
7403 F20101123_AAANCQ song_c_Page_66thm.jpg
a93b04e37f8201cdfe1d282ed1155fed
812da8e1a87f1fcbe11e846ba08363cba8622860
F20101123_AAAMVS song_c_Page_16.tif
8ec323cfd50f20261df3089c86cd6f8c
ee1ec7f205934596a22e720dc0b69fe218d9ae92
7486 F20101123_AAANHN song_c_Page_44thm.jpg
9a0b187b829745335b5a7f232f64d646
b67527618ab3a3069502c58c891cf4e5a0f194ef
1872 F20101123_AAANML song_c_Page_41.txt
59de24857ea9fc2d7bb65e676673686b
91d022bdbc12417e0922c582d70b5b3d1680d36a
34813 F20101123_AAANCR song_c_Page_71.pro
c2ab901692212d125f06d5e2e3d9d4d9
0ce2a163d83fd6edaa15d7cfb9cf32fd3a8ac705
32046 F20101123_AAAMVT song_c_Page_25.QC.jpg
759631070704395afe718341c5e0789a
774d9785dca7824b7f4d7f3dc151394fcae05e25
27347 F20101123_AAANHO song_c_Page_26.QC.jpg
ac8d9536ab2cf94f26a3169766b41441
45c8fd3230a3fe22bbb3a313b6c5d6c23c2b6bd1
1879 F20101123_AAANMM song_c_Page_42.txt
64ae9854017a1bc68e402f47ffdaddea
6c48fdcf89588ae0842e8e31674b5a843bc704d8
105231 F20101123_AAANCS song_c_Page_24.jp2
ee150e9d49ad6f3ddea6e358df64558b
28eb882f2e652fd5061b1007af8ab64d2144ab20
23742 F20101123_AAAMVU song_c_Page_01.jp2
8308d9894debdccce2f4e872f5c8fb71
b2721ceecdaab5becc2cfe12990c424bf0db3d40
105402 F20101123_AAANHP song_c_Page_54.jpg
289a21d0da7fe88a4d5df0673ffab39f
90b3c21920b04def155c8212838bb93b319b9b9c
1552 F20101123_AAANMN song_c_Page_43.txt
679bd4b8ec3f69e5cce6840efe96e46c
eb76043610692647b944a833f1cac6df7670b056
74021 F20101123_AAANCT song_c_Page_58.jpg
84e867da4ba89b6d33d74c2ba3affc64
cbcfa072d95dc6a0eb027417c36826b63390d3fb
2086 F20101123_AAAMVV song_c_Page_54.txt
ccb84ae40be61961662d81243753ef00
9c311a061d5b52f3ec15f8d1c2936533adce21df
1975 F20101123_AAANHQ song_c_Page_20.txt
bed59d340efea759d16f1d8e048dbf24
5f039029ee1d2b4868ca22e502c8abc5142fb42f
1039 F20101123_AAANMO song_c_Page_46.txt
a4ffa7f38701adfed7af8c3614280313
db283af105c402381836be4e7250b5224a0cadec
32761 F20101123_AAANCU song_c_Page_20.QC.jpg
00fcd61b88e9294ce2afa3876d761e8f
6ab97a26d77c9654a847a5fadb769a287f3eaafa
F20101123_AAAMVW song_c_Page_73.tif
a1846776cffd552d31efc288f4d58146
a445e00cdc8fe6baf906406fbe5216c526ae8968
F20101123_AAANHR song_c_Page_38.tif
16dcbe53fa6946848b35de7fe03c7a88
832492b78190ccc5c5fa1999ec32c7a877363a7f
1448 F20101123_AAANMP song_c_Page_48.txt
ede83318df65d14e7d8d14dafa6ca38e
a308ef022f3c0a1e0f7c4430f706295a811cfbdc
1732 F20101123_AAANCV song_c_Page_21.txt
2a6d02e57798bf29451717acbdac823b
f786481cc1dfaac8b9cbaead957617b6b0e76f36
20864 F20101123_AAAMVX song_c_Page_46.pro
5ba2070a7c6d6c59b7e4c33feef7c0a6
7d48855206bc8d9e8ab70a2d694342fff3f578f9
51303 F20101123_AAANHS song_c_Page_49.jpg
2d282041944f86a6acd819082a2f661d
293aaa42c446b3e42d71174496dd218904afe7fd
1227 F20101123_AAANMQ song_c_Page_49.txt
1b05273b12567f29cdf5a951bd2a117d
bb7179aadb04a92a6107b94a3905075a20db68e7
31304 F20101123_AAANCW song_c_Page_28.QC.jpg
f22346d21af6992ec00fee44071d95f5
0cc677f0d8201fee7e8b3631eadb834346c3fa88
F20101123_AAAMVY song_c_Page_04.tif
e808ffe91c855aca8fbb6b5f64134292
9785fa931597e209b4b69f36857596c56644d45d
F20101123_AAANHT song_c_Page_79.tif
2cd118755c7ee8412430589f6c769b2f
3718f46ba11b3f7978ad8ccb2a5298a248cc48e2
1766 F20101123_AAANMR song_c_Page_51.txt
76d4aeefc440b4dfee1f1a3873d0811c
d1250e82624590164e3452bf36096009dd1ed14c
F20101123_AAANCX song_c_Page_77.tif
7d44467173859159f0183c50a5f9fc24
b7eec20925bdfd1a3d053d75f7de4e4653a36f47
F20101123_AAAMVZ song_c_Page_18.tif
9a2c0b0812413da2953c9e2bc9be1363
42f41f392553b6041e5f77be5704d37b72b41d5b
23941 F20101123_AAANHU song_c_Page_64.pro
490bd26b6551b1543393f7d992a54747
28bebb854b65c49224a0be90e021b69328371be5
1956 F20101123_AAANMS song_c_Page_55.txt
4d3235feee281be056adb292e4f2cdb8
e70bc089bc3498b68304e8bf9b1b44ba1827198f
36622 F20101123_AAANHV song_c_Page_55.pro
1b3207cacf730c54594e7c485784d4e4
9eb94832d47dfc1cc7379982b88806a7ec24b27b
32052 F20101123_AAANCY song_c_Page_65.pro
9e6b040000dd049b6983ed4546321593
fbeb66751f4b79d144028375d2d04dd25d9947c4
2007 F20101123_AAANMT song_c_Page_56.txt
faebe57c810c9b4d2ebbcd36ea85cb82
d1d2724a08f7c2ad4b3a942e66b8c7975bddb392
8335 F20101123_AAANHW song_c_Page_54thm.jpg
52fdbc3ad661c499eaf23e4891724ad9
c255fb81d4089d5585628fdaf0b83c27255bcc32
78894 F20101123_AAAMYA song_c_Page_21.jpg
3162f57aa477bc94386ecc1a859426c5
a4624c8d26d8cdce2af09f4d8cae0bd4f727def6
1542 F20101123_AAANAA song_c_Page_36thm.jpg
78a8e32a578aca4e774b85d6a41e4f9c
7e83a8f6852529b6364b480562d2969510dc0c72
2090 F20101123_AAANCZ song_c_Page_01thm.jpg
99bdf8c785d5b604887c0d34ddce83e0
9c01639a0686f59363f6758e8c6482502008889f
1970 F20101123_AAANMU song_c_Page_58.txt
911e30ca6b194d859e9ab01e9a3eefd4
c0995966ffda26e09a7372ef513b92cf06661fb9
2552 F20101123_AAANHX song_c_Page_78thm.jpg
8e46f919bd24734faaf297157e1b5c25
391aeb0f95ff47cade682caf12097160816ebeed
31975 F20101123_AAAMYB song_c_Page_52.QC.jpg
6e2ca74202f4c18bf19d9593861568b1
b517a9db1317e9fe8dd0e0b59778293575fc385a
8352 F20101123_AAANAB song_c_Page_30thm.jpg
a7b83bfcd6db04ebff9a6a5bbac0ac89
dcf7f541bf12616f15ba88cb9b2d7ef80bc37ac7
1731 F20101123_AAANMV song_c_Page_59.txt
73c0b219f262b2ddc9fdaffa7b362cca
010b45ee471220d2926ea3df8ed61d072f863422
F20101123_AAANHY song_c_Page_22.tif
b384205408c60ae9293d693a9c6e61bb
213a39e088bc13974c2b6cd1b8cc908c9adf5b0f
56203 F20101123_AAAMYC song_c_Page_64.jp2
2d387843c1b7e88713872c0f9ad3308b
ae2b3314a3c887dbbbef38615e95469e0b6fda84
26507 F20101123_AAANAC song_c_Page_68.QC.jpg
b6040712fbce9dd5be828141fe22bfc6
af525fa51f35334792dcf42cfb7d57803d802eb3
1474 F20101123_AAANMW song_c_Page_62.txt
88a580587dce15236af1c9a87b2babcd
6606ca2072bfa2b93e174bd07c14138eb1c65645
28469 F20101123_AAANFA song_c_Page_66.QC.jpg
8422516e3e3b80c13e582e71cf8f0e5c
a54e359df8ab37520a51ea8ccf579c5e1449a8bc
F20101123_AAANHZ song_c_Page_46.tif
ef0079e80106e222c0918afbd36e0ab2
75cf5b98812a0686397f12e58ad7284f68863a0b
8118 F20101123_AAAMYD song_c_Page_25thm.jpg
d4ff242e571fa77c0294d86b714f05ef
5092268f52d193c79d06a7bf25556c2f68527b44
F20101123_AAANAD song_c_Page_08.jp2
af68040c03b30e9a265a4d6f63192593
6e72f9579e0f3de48930fd747e8104f2f9852906
1399 F20101123_AAANMX song_c_Page_64.txt
72824a3624b09472cfb18d17e92820a4
fea2306ab05eda70fa8a9111849a6819ef80692b
7569 F20101123_AAANFB song_c_Page_57thm.jpg
d3e884f8998f117729fb4a47e2a5b2c6
7730a33ff9ae17313a7f0d288c60db4c9697b6a3
8113 F20101123_AAAMYE song_c_Page_56thm.jpg
25c181c8518a942cc472e8d090a43b0e
1875af330be92a31f60e33e517c7db2c0169652d
37037 F20101123_AAANAE song_c_Page_21.pro
e4391ede66d93587e86160de6cc266aa
ef1f22176f9fcd31cedfce9cdae9e4f98dd0ee6a
1781 F20101123_AAANMY song_c_Page_65.txt
f48eaf1426656f748d56e265bb7c519d
408def25894ab45ce8b6c1933e7d53e174616714
F20101123_AAANKA song_c_Page_10.tif
b30a7a38a8d4b55afb2a459a72cb9482
66cf2355c1dd1257bdc8de98b92a02e13e70e720
45736 F20101123_AAANFC song_c_Page_44.pro
6f84e8a3025a5c0a452ede679f350acb
c25a54996d22ba31f5fdcb94c7c4ca306103de5a
100936 F20101123_AAAMYF song_c_Page_30.jpg
56bc19899ca0fe6e46def0abaf10c794
202bd4405b36906017b2385afba1aebe1163def3
1156 F20101123_AAANAF song_c_Page_76thm.jpg
1abb2221aa4c01c7f2da1fd117754c8f
2e18137321a00d9fcda7718216cbe8448570ea5b
1584 F20101123_AAANMZ song_c_Page_71.txt
7ae496920184ede7bbcb9a075e5cdd9b
8e26dbfc09e78c1aae2a3a1bfd346a833c166635
F20101123_AAANKB song_c_Page_13.tif
a80e0e672bd59e8888ec074d60127cef
f740621fafc6ff007b7de03a75e018d359e908d3
31844 F20101123_AAANFD song_c_Page_53.QC.jpg
b07259c6765da50b28db5a0a03332917
b52d0f455689abbef5d765b51c092332b0dbd28f
7337 F20101123_AAAMYG song_c_Page_77thm.jpg
48b166b8967993943e0610d1ecd6cba6
9e72afc8fa500f65e3e68edf36b4943f9758c6ba
86963 F20101123_AAANAG song_c_Page_66.jpg
8dc430348327d7e2eab1143385c1f3ec
bc0fe1d5da7f73372416e81cb7c973565a84c4aa
89438 F20101123_AAANFE song_c_Page_37.jpg
9af2aeb1f609d518fe66123b8796ed55
91fa7236973d731fd6d3f7a954c310002b1a1476
6971 F20101123_AAAMYH song_c_Page_51thm.jpg
416d2371cb61f495c880945c3903c80d
e7023b48f6b2c9b4e0ee34712d28cb121b960a4b
8589 F20101123_AAANAH song_c_Page_79.QC.jpg
9c63e1f366b0996750717ec6e03ab116
6708981b8d4684ef906fc05ea48bf6962372f881
2990 F20101123_AAANPA song_c_Page_74.QC.jpg
7e085718a56f2598a3b68e2df651e7a6
6198cbb68b03cb8382004ce7419ebb2f221279f3
F20101123_AAANKC song_c_Page_14.tif
4d37243cb23cc7567bc53a9c5a9504f5
f753cf959b4a118a6fc3a474634a4386358ae082
1974 F20101123_AAANFF song_c_Page_67.txt
a409bd1015f1c274a3e9f2e8f750c0d7
dfaf80fd62777cf2c9a89f191eecbef8d00df550
106372 F20101123_AAAMYI song_c_Page_20.jp2
5d82b278e7f9d4a88f2e50a82b638592
85e3e0109382a12c3550f6cfe58244ba48d94bbf
98186 F20101123_AAANAI song_c_Page_20.jpg
90e1c3dff7357d9f6646dc5763995d9b
cca493555c129a73ac5568bb9d739825f52f5913
6861 F20101123_AAANPB song_c_Page_75thm.jpg
1769b2120b2a0f5f1400e64d3ec8dfbd
6c6949f60f14c403d93ee27b6db67cad3b838a05
F20101123_AAANKD song_c_Page_15.tif
5ae4f3c6963de8e52503810f273f19af
91f236d40d0439a17f58e3904b2b49effb868e85
865866 F20101123_AAANFG song_c_Page_55.jp2
deaf6ce6437941e474db79f5a30c00df
6ede8a19af5675f3318e7f4b67748a885678f79e
F20101123_AAAMYJ song_c_Page_05.tif
61960eba0c28f9a326f2b5922a4c900c
2e36de322bc94ebda9683dd2831bb35f11daef15
F20101123_AAANAJ song_c_Page_59.tif
333c480142ef4a2c155df098ed2adb46
2155fd2c4c61a3e6b75418164065f1597bba761b
4241 F20101123_AAANPC song_c_Page_76.QC.jpg
b7a193d37a19b75b746484389a757d1e
7aa03234d4b47f9ecf6599428b1714b3d6401c96
F20101123_AAANKE song_c_Page_19.tif
f4f349319421e00545e66bef76765d73
97d28cef386789058bee0823b308646cb613167c
28089 F20101123_AAANFH song_c_Page_23.QC.jpg
c3eba2f02c66494364e5be1e901c101a
124216a99ae1ce1508636fc89e14eb4dd3ecee0c
93252 F20101123_AAAMYK song_c_Page_50.jp2
6e275042b20577405fe67d125b48250e
82f96e39a4f17f27ac74b80ff123fc643ac981ff
11503 F20101123_AAANAK song_c_Page_03.jp2
04d06d80d150c7048d26616aaed5794b
390e2656a986e29c18bf3b3f438e626da0e096ac
91780 F20101123_AAANPD UFE0011878_00001.mets
c5522fb25db75f550b8209f92923f022
f17333baab5d6b6053ac1786194fff99eeae64da
F20101123_AAANKF song_c_Page_25.tif
475227c24b5b9d0098db9c4145d366e9
791e4d0ec9e3cf5b51487d4e5300011b97330ab7
25373 F20101123_AAANFI song_c_Page_59.QC.jpg
ab4438ef3c978b25d8648d9684666b2a
ddd8de5d2124f6e693832f857aa5006afe7383cf
2027 F20101123_AAAMYL song_c_Page_18.txt
2ffc43274dedb3b015bfd7b06fb0f8ff
0e8da063d42e2f32f6b5a5586d51f92693caac05
7150 F20101123_AAANAL song_c_Page_11thm.jpg
a6d596cbd0dbe521f881a748124be2c8
7e4df160a94b0b65770c80bdcbc84abf95bce541
F20101123_AAANKG song_c_Page_26.tif
191bc0230cccdbf2f41486b8861912d8
e7e0051983468c87299aae48728cf32ab8d96d9c
409025 F20101123_AAANFJ song_c.pdf
d7202e3e034911653148c1418cebe6f8
f5b1781d7a13713b01b480fe82d2d763cedd75bb
11207 F20101123_AAAMYM song_c_Page_76.jpg
434b4df3030729b0fcdd3cb6393a96f4
159c0f1a42121cee6aa69901a65eb7762bc80dc1
F20101123_AAANAM song_c_Page_29.tif
9f7590186ec5f4f60f7a52e8a2fe878a
cb9b46a4e203de84f18e24f6c969bf3c85051edf
F20101123_AAANKH song_c_Page_28.tif
c4d6b704702aec6970f92ace4e273149
7f3af4e29655cfd7b5db65e4ea59761d096e5615
F20101123_AAANFK song_c_Page_48.tif
a8ff97fe4b96d288d95079aba31c4fd0
e8117ca7cd57e92e9b7bfdc46e5c5a2081c43fc1
47933 F20101123_AAAMYN song_c_Page_16.pro
d126855ac3334b3eb962a62c739b21db
09be1329f3a3c365be322d421eb065a99c7acd71
1582 F20101123_AAANAN song_c_Page_73.txt
31b1053cf0810b037bca29d080d02884
611cdf8c24c7929e2f4f11761844a8449078ab14
F20101123_AAANKI song_c_Page_31.tif
25a2459ef5cc0daa979f8ee52bf6905d
5a3dd748063563637bfb6a00ec3693d8fd39bc10
1793 F20101123_AAANFL song_c_Page_23.txt
1b11b78fcd39f39a139120e386fd4998
13cfd5cb1de03b8d5c567ad514d2f1cbdc1e3a11
85430 F20101123_AAAMYO song_c_Page_23.jpg
5cfd0eb0b885bbfd06e9b368558b4d9b
4edfd5ab82dc08d32828982410766693355f4b25
49929 F20101123_AAANAO song_c_Page_22.pro
2abab13285fa3fede3f31152dfeb8817
383528653e153a8d8c713b518d5c125af76f691a
F20101123_AAANKJ song_c_Page_32.tif
03d8d8ad3453a72184bcfc3dca709605
5119501cd8339a49c73afa9fdccc4fa844c72c71
2768 F20101123_AAANFM song_c_Page_03.QC.jpg
c22dfa4fd97ac9082a74518b3759f967
63b3a5bfc6dbb4717ee6d1a38c842428a162a265
102721 F20101123_AAAMYP song_c_Page_29.jp2
70eaed4ff4d9fab72991976248b215bb
a2807ed2941ed2b219657d79ded2e47f0bde0657
10483 F20101123_AAANAP song_c_Page_78.QC.jpg
c682a253da8089c00000ba6814c0caca
5d0aa8d8307a39d09142d3b2ce640768a20f966c
F20101123_AAANKK song_c_Page_37.tif
7def7d21f358d60d18d812cb9837bae3
ad58e2953fea71c653dc03aa0c1669d5fc1ada03
1636 F20101123_AAANFN song_c_Page_72.txt
853dc87411c76b00bd734cdc202ac88b
aba56ca385f0a62b159f6df3bb63b64684b14908
28425 F20101123_AAAMYQ song_c_Page_11.QC.jpg
d4a0cbd7d45a25ece086e734c3c4ba6e
791267b9ec988cf22f1d7a728b91f85f2d1479bd
5997 F20101123_AAANAQ song_c_Page_70thm.jpg
3e8f1a6c1a494d468cd7200c754019b8
417291b661d42c53d6351bea5d19d87172ca5933
100073 F20101123_AAAMTS song_c_Page_56.jpg
2579c29c76ae4978e641c5ecae1badb1
69ae4076a4c3d63be6bce65b137e34a445989915
F20101123_AAANKL song_c_Page_39.tif
bc2ca219d47314045249e797524a545b
afcf0e59a25ac86edccef3f390ea1d1d67f675dd
17020 F20101123_AAANFO song_c_Page_36.jp2
588043f96a124773819953b8a3d1a57d
b6515c6fe7f2fb2214730a1e0f24532c100ae399
F20101123_AAANAR song_c_Page_52.tif
c421a9b5b45a31afcd8f852f54c0baf4
01e305de25219ce1c72b3fb7a7f7a96920dd222a
43176 F20101123_AAAMTT song_c_Page_51.pro
1d6a204eb778da91aeb056fdd9dac1eb
57984fc3a00d1ca146d61826385d65a9bc61369e
F20101123_AAANKM song_c_Page_41.tif
e2d6cde23e00dd7453c30cbc83dee82e
77615b3eee7c6794290ef68036112762b5e23453
2205 F20101123_AAANFP song_c_Page_06.txt
213c0a17cb96b7a52a387c41a6e6180a
97d3c4098b3f39292c7256d1717f738ff3ab521d
F20101123_AAAMYR song_c_Page_35.tif
3105fd620b3613b996c273537ec0d064
d6aa037d34674bdc1601e43fc29a0ab043f7f4e0
F20101123_AAANAS song_c_Page_70.tif
9f4cb2569dd1fbcc5d2ef116008b93c5
76fc485c6d7e9d7854ead5eb11e7ab9209204183
1988 F20101123_AAAMTU song_c_Page_53.txt
a32aaecadb46bde683f83713bb6d147e
e442bd399502459148d6b5bc4e5f4d4f907b31c1
F20101123_AAANKN song_c_Page_42.tif
c11e2ae75ed4cacd4e4d5cc65cd87cf8
53dc8391cb77671e43243f35cfbe5bd9a18bdfc2
30587 F20101123_AAANFQ song_c_Page_29.QC.jpg
b5fbcdf34a8f02e2f9dd73dc82aba322
bff15100d367a0b77a38a9c6ccf70444fb73c004
108524 F20101123_AAAMYS song_c_Page_13.jp2
9d448684f1ff23174e513ac2925c272e
79e83272825eacbafc6ba5be014dc2a7cf4d0ed0
94331 F20101123_AAANAT song_c_Page_27.jpg
d67e7489cb4423b24766cfa4db67e7a9
6ad8c6e176a901d48c8912209061e9a26472c2f9
888 F20101123_AAAMTV song_c_Page_74thm.jpg
5deef4952e4bc9a00e9f2a6c67270f05
2089476e613e90a0e7114063d8581cc28852b5c3
F20101123_AAANKO song_c_Page_47.tif
455d7cf28e0fe5596ce5a04e13247667
b59a62079d0f7a47c47e82a9555b6ec1e39cb585
48576 F20101123_AAANFR song_c_Page_28.pro
25590ab4c3429e8a0c3192badb52ab5b
757c2544656d229046cc939b4c0ed2e03cb65251
108 F20101123_AAAMYT song_c_Page_09.txt
ec9731a3d25c059895b7fbbbab4519ee
72c6cad10eb80adb33284ce65548a5f3debf6c7b
7994 F20101123_AAANAU song_c_Page_29thm.jpg
3df3eab37c14431331fb697976e88b22
e8a42555e197c1c7dee9abfce2ef5fd36b6033c9
6096 F20101123_AAAMTW song_c_Page_48thm.jpg
a823bd9eb8e9d08629f62b467c3ef627
bb05670a74b286cc6e63cbad7ede4395e3ded9b9
F20101123_AAANKP song_c_Page_49.tif
bf1b6987ff105488c6db0b3bc657c643
a6dcd750c9343aa36a647540527bd3210abae470
30176 F20101123_AAANFS song_c_Page_44.QC.jpg
3e1ee2b9e2df7aefe4d818a85690990f
df0f78e7780dadc83f9a355370c209e4b911b8f6
5137 F20101123_AAAMYU song_c_Page_49thm.jpg
4aefe66eb68fea3f33885b4c9939ed12
3e1fa52ffe4d730ef6ffba1428ffa5826da07474
49461 F20101123_AAANAV song_c_Page_12.pro
50e076ce7af435d6c9bce62f60bd454c
533d19ac6f15e0a118a08055530324e23d147b48
6920 F20101123_AAAMTX song_c_Page_31thm.jpg
9c91b332a444768d49d8ecec3b541e1f
16d90dafeecbf3402b61d8d0d88a32349dd934ab
F20101123_AAANKQ song_c_Page_50.tif
3ee574021658da55b206d6a7906362db
ad28f084fc664e223bb61304c49abf5f1673c1d4
63612 F20101123_AAANFT song_c_Page_62.jpg
f814af96667f58481621cabaa0788cd7
bd8456bc0d7a3a1313ff82eeae16ca7b2546b398
F20101123_AAAMYV song_c_Page_56.tif
a0a24362a5bfcd702827f74e186c4b2d
68004a37247ad3029065b1998b19e2058220cc8a
34026 F20101123_AAANAW song_c_Page_54.QC.jpg
d70929f5476b9f7ea501c85be46ad213
9f0054fd9d22c4961ad5390d4d3a8012b24ee3f8
108139 F20101123_AAAMTY song_c_Page_52.jp2
f8436f6f59d6225e465894e2cbdfd969
4781b9f171ec345e06e31745e140099fd075e117
F20101123_AAANKR song_c_Page_51.tif
cd98b84147d3a836d376db74df491d61
c9b18f5404e0254698f83d73dbd49c3ff85e3f1a
1787 F20101123_AAAMYW song_c_Page_15.txt
a24fb578937d2b3286ef5422282af707
66006d7a020659c7197f5eb34e49413c88d01ba3
19989 F20101123_AAANAX song_c_Page_10.QC.jpg
b9104e44288a2a8739c68f272e96f0b7
035822c22da178cfb4ba59edd71b7efe0e10b21b
26868 F20101123_AAAMTZ song_c_Page_08.QC.jpg
96ac95bf4d6b927b7dd9af734bf5aa41
08c1df3bd45b5712820b0698a616b17674e1c294
113187 F20101123_AAANFU song_c_Page_61.jp2
dee2b8178ff745dd8ff02cf35cd43730
ce3b09ff7a0d2479b3183d5004a6d6128a686ee0
F20101123_AAANKS song_c_Page_58.tif
800a2205da47df086a09e16254420af6
599d3062521f17ceff2456442bdf83b187d24e5d
32393 F20101123_AAAMYX song_c_Page_70.pro
a8888cf3bc9f8d6963006ef523954bd6
ac023e43762a5c35e44ac69526cbe0b7f3165da4
F20101123_AAANFV song_c_Page_23.tif
42351917e0ba298b2513253cf4fde7ef
1734ad00acca9e2be840ae1fa17d1c38f4eeab70
F20101123_AAANKT song_c_Page_61.tif
e8c2b97f19ac4dab66800d78b815488d
04c13f36cf3be4bf7261a0e6ecf3ca275fa3d2c2
621347 F20101123_AAAMYY song_c_Page_63.jp2
9496e3fd784b5dff15a366182617c2f4
4c469e1d655d1e5da92da2463c9c71b9239aa73d
F20101123_AAANAY song_c_Page_60.tif
a462fa00a71d1b33e07589d4f9c3542d
2692e9cdacaa65f523f7679a7897f0967a038234
92963 F20101123_AAANFW song_c_Page_44.jpg
388a8accbbeea2cc8d8e548a013f3183
a65a49ac2281c5ba9e7ec92d085b37152df6b477
36627 F20101123_AAAMWA song_c_Page_78.jp2
32d10905821ad09f396f588b9a935bfe
bfb5493a6e0c771dc162a76e26e5e1a26251eeb9
F20101123_AAANKU song_c_Page_65.tif
6522998304b093d87d544442a4f07736
538e3917c694ccf2be9cea140d0358477c08ae74
8153 F20101123_AAAMYZ song_c_Page_19thm.jpg
8866783cf7790fd901c3ba0d9ddaa1fd
d3bd831f70ca851d6be88222c6de130a3818f026
7178 F20101123_AAANAZ song_c_Page_37thm.jpg
e185847e05d153756b33d5fabca92a28
78d97e1bf01ecbc697c7daa8ffddc8d1521d8491
38810 F20101123_AAANFX song_c_Page_58.pro
0424ce501a582ff2f5aaadc4158801b0
d127feaedacd083aa365738d905b66c4bdb6d59b
2020 F20101123_AAAMWB song_c_Page_52.txt
47f72bb7a3f49997aabef49f9712dd98
3263f0713ecf0bc8ff5839f980b74b502182d954



PAGE 1

MULTI-RESOURCE ALLOCATION ACROSS MULTI PROJECTS BY SUBCONTRACTOR By CHUAN SONG A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLOR IDA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN BUILDING CONSTRUCTION UNIVERSITY OF FLORIDA 2005

PAGE 2

Copyright 2005 by Chuan Song

PAGE 3

This document is dedicated to my lovely grandparents in the remote country. And it is also dedicated to my family for their unconditional support.

PAGE 4

ACKNOWLEDGMENTS I would like to thank Dr. William OBrien as my committee chair for his help to me during the preparation of this thesis. I would like to thank Dr. Rayment Issa as my committee co-chair for his help on the case studies. Also I would like to express acknowledgement to my committee members for reviewing my thesis. Special thanks also go to professionals from the companies that responded to my questionnaire. iv

PAGE 5

TABLE OF CONTENTS page ACKNOWLEDGMENTS.................................................................................................iv LIST OF TABLES............................................................................................................vii LIST OF FIGURES.........................................................................................................viii ABSTRACT........................................................................................................................x CHAPTER 1 INTRODUCTION.......................................................................................................1 General..........................................................................................................................1 Introduction of Scheduling Optimization Concepts.....................................................3 Problem Statement........................................................................................................6 Scope and Limitations..................................................................................................6 2 LITERATURE REVIEW............................................................................................7 Basic Concepts..............................................................................................................7 Resource Constraints.............................................................................................7 Resource Allocation..............................................................................................9 Construction Costs...............................................................................................10 Independent Subset..............................................................................................12 Perspectives of Application to Multi Projects By Subcontractor...............................16 Why Multi Projects..............................................................................................16 Why Subcontractor..............................................................................................17 Other Literature...................................................................................................18 Models of Subcontractors Construction Costs..........................................................19 Tardiness and Overtime Cost Model...................................................................19 Parametric Influence Model................................................................................22 Summary.....................................................................................................................23 Critique and Current State of Literature..............................................................23 Research Needs...................................................................................................25 3 SINGLE RESOURCE ALLOCATION ACROSS PROJECTS................................27 Presumption................................................................................................................27 v

PAGE 6

Resource Shifting Within Independent Subset....................................................27 Total Construction Costs.....................................................................................29 Parametric Models of Single Resource Allocation.....................................................31 Indirect Cost and Direct Cost..............................................................................31 Other Costs..........................................................................................................34 Case Study...........................................................................................................34 Model 1 Labor (crew) allocation...............................................................34 Model 2 Equipment (flexible resource) allocation....................................38 Summary.....................................................................................................................40 4 MULTI-RESOURCE ALLOCATION ACROSS MULTIPLE PROJECTS............41 Environment for Multi-resource Allocation Across Multi Projects...........................41 Significance of Independence Subset in Multi-Resource Allocation.........................44 Multi-Resource Allocation Parametric Model............................................................47 Multi-Resource Allocation Case Study......................................................................51 Case Study on Multi-Resource Allocation.................................................................56 Introduction.........................................................................................................56 B&G Painting, Inc...............................................................................................57 BCH Mechanical Inc...........................................................................................61 5 CONCLUSIONS.......................................................................................................65 LIST OF REFERENCES..................................................................................................67 BIOGRAPHICAL SKETCH............................................................................................69 vi

PAGE 7

LIST OF TABLES Table page 3-1 Resource allocation comparison in Case 1...............................................................37 3-2 Resource allocation comparison in Case 2...............................................................40 vii

PAGE 8

LIST OF FIGURES Figure page 2-1 Construction costs composition...............................................................................11 2-2 Graphic illustration of property of independent subset............................................13 2-3 Graphic illustration of formation of a new independent subset from two consecutive independent subsets..............................................................................16 2-4 Total cost curve as a function of overtime utilization under the compact and relax procedure.........................................................................................................21 2-5 Complementarity (flexible/fixed resources ratio) modifier curve............................23 2-6 Work area modifier curve........................................................................................23 3-1 Illustration of resources shift in the independent subset..........................................28 3-2 Construction costs in independent subset i..............................................................30 3-3 Complementarity modifier C in Model 1.................................................................35 3-4 Work area productivity modifier W in Model l.......................................................36 3-5 Complementarity modifier C in Model 2.................................................................38 3-6 Work area modifier W in Model 2...........................................................................39 4-1 Illustration of multi-resource allocation across projects..........................................45 4-2 Two resources applications on two projects.............................................................52 4-3 Complementarity modifier C in multi-resource allocation case study.....................52 4-4 Working area productivity modifier W in multi-resource allocation case study.....53 4-5 Complementarity modifier C for wall covering.......................................................58 4-6 Working area productivity modifier W for painting................................................59 viii

PAGE 9

4-7 Working area productivity modifier W for wall covering.......................................59 ix

PAGE 10

Abstract of Thesis Presented to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Degree of Master of Science in Building Construction MULTI-RESOURCE ALLOCATION ACROSS MULTI PROJECTS BY SUBCONTRACTOR By Chuan Song August 2005 Chair: William OBrien Cochair: Raymond Issa Major Department: Building Construction Due to the limitation of resources on construction projects, the subcontractor will shift multi resources fluidly within projects or across projects to meet resource demands. During the multi-resource allocation procedure, some factors influencing the cost have to be considered such as the change to existing conditions and the collaboration across projects. The research has been conducted in this area. Some influence factors are identified to establish a model to figure out productivity change and help allocate various resources. Then the original resource allocation schedule can be improved so as to reduce the subcontractors total construction cost. The objectives of this thesis are to discuss the effects of multi-resource allocation and determine how to reach a better multi-resource allocation approach by a mathematical model. x

PAGE 11

CHAPTER 1 INTRODUCTION General The construction industry is one of the driving industries in the economy. Through the first ten months of 2004, the total construction on an unadjusted basis came to $495.3 billion, up 9% from the same period in 2003. The 9% increase for the total construction during the January-October period of 2004, compared to 2003, was due to this performance by sector residential building, up 16%; non-residential building, up 3%. By geography, the total construction in the first ten months of 2004 was the following the South Atlantic, up 13%; the West, up 12%; the Northeast and South Central, each up 7%; and the Midwest, up 4% (Dodge, 2005). Recognizing the economy growth rate in 2004 has settled to 4.4 percent that is above the historical trend, a booming construction market is expected in the year 2005. Residential improvements are forecast to remain strong, fueled by higher new home prices, and a scarcity of buildable land in many markets. The nonresidential segment will accelerate to a growth rate of 6.0 percent in 2005, equaling the growth rate in the residential markets. On the other hand, inflation is back on the radar screens of both the central bank and the financial markets. The Consumer Price Index (CPI) jumped up 2.0 percent toward the end of 2004, the highest reading of the year. Prices for construction products and materials became a major issue throughout 2004. The cost of certain steel products and wood panel products rose by 150 percent or more, with limited availability. Gypsum, structural lumber, cement, copper, and PVC all showed major increase. In the 1

PAGE 12

2 case of steel, a strong foreign demand (e.g., from China), limited domestic capacity, coke shortages, and a limited number of available ships will keep up price pressures. Similarly, a shortage of cement is expected to result in the price going even higher (Giggard, 2005). So for the subcontractors, construction resource allocation optimization has a significant impact on the ability to achieve success in the implementation of construction projects. Although research in construction management and practitioners in the construction industry realize the importance of resource allocation across construction projects, there is still a divergence of opinion on how much effort should actually be invested in construction resource allocation activities to obtain a better performance during the construction period, and how much benefit the subcontractor may obtain through these reallocated resource activities. Moreover, even now some subcontractors are indeed reallocating resources at some degree in construction, they just make decisions with their experiences, without a systematic method that can take into account the actual external conditions as much as possible, and then can assist subcontractors to adjudge the situation impersonally. The objective of construction resource allocation is to find a way that is consistent with specified resource limits, as well as profiting subcontractors the furthest and matches up with the schedule. It is necessary for the subcontractor to plan overall plans for multi projects and take all factors into consideration to obtain the maximum profits. Sometimes they would have to change the existing resource allocation plan. The result of planning as a whole is that some projects may not have the shortest construction duration; meanwhile other projects may take too much resource than the average level. The

PAGE 13

3 subcontractors ultimate objective however is to lower construction costs, and improve profit margin, with a fixed total amount of resources. In this thesis, an attempt is made to develop a practical approach that presents a near-optimum solution to allocating finite construction resources among projects in the standpoint of the subcontractor. The thesis starts with a brief description of the resource allocation problem. The impact of resource allocation on construction cost is then proposed, approaching consequent tardiness and overtime costs. Followed by optimization applications in both single project and multi-projects, parametric models are addressed to figure out the productivity change and the corresponding results in different costs and profits, taking into consideration the resource situations. The multi-resource projects guideline is evolved by the optimization implementation. The performance of the proposed approach is then evaluated, and recommendations made. Introduction of Scheduling Optimization Concepts As we know, scheduling is a matter of great concern in construction. Resource allocation is one of the scheduling optimization methods. Optimization problems in construction scheduling are traditionally classified into the following categories depending on the objectives: (1) time-cost tradeoff; (2) resource leveling; and (3) resource allocation (Hegazy, 1999). What is the difference? What specific characters for resource allocation? Time-cost tradeoff is concerned with minimizing the project cost while maintaining the desired project duration. Resource leveling is concerned with minimizing peak resource requirements and period-to-period fluctuations in resource assignment while maintaining the desired project duration. Resource allocation is concerned about minimizing project duration without exceeding the available resource limits.

PAGE 14

4 Normally the subcontractor has more than one project to work ongoing. Each construction project is composed of a network of activities. Each activity in a project has a corresponding duration. The project duration is usually measured in integral increments of time called independent subsets (that will be elaborated in Chapter 2 Literature Review) each of which consist of certain activities. The normal duration of an activity refers to the time required to complete that activity under normal circumstances. Meanwhile the construction cost of an activity or a project is somewhat associated with its construction duration. Normally, corresponding to the reduction in activity/project duration is an increase in direct cost, and in contrast a decrease in indirect cost. For some activities and projects, it is possible to reduce their duration below the normal duration. This is done through some measures called crashing. Some ways by which crashing is achieved include overtime, additional manpower, equipment and/or other resources, and the use of better skilled men and/or improved technology. Crashing with resource allocation is done as a tradeoff between resource, duration, and cost. But on the basis of limited resources, considering both the direct cost and the indirect cost in construction, the comprehensive total cost maybe maintained at the same level, perhaps even lower, with shorter activity duration. This study is to determine the best one during the period of optimizing resources. On the other hand, resource allocation attempts to reschedule the project tasks so that the existing resources can be efficiently utilized while keeping the modified construction schedule does not exceed the required construction duration. At present few companies can remain competent in todays highly competitive construction industry

PAGE 15

5 environment without effectively managing their resources, particularly the allowable adjusted resources. Concerning the resource allocation, the basic PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) scheduling techniques in practice have proven to be helpful only when the project deadline is not fixed and the resources are not constrained by either availability or time, assuming that the resources are neither able to flow from one activity to another activity, nor flow among different projects. As this is not practical even for smaller sized projects, the resources in construction are basically fixed in quantity, and resource allocation has been used to achieve a near-optimum result in relation to practical considerations, allowing the resources to shift among activities and projects. An activity or a project can have any duration between the normal and crash duration. However, one subcontractor normally has a cluster of ongoing activities or projects. The subcontractor needs to comprehensively analyze the different resource allocation schemes, then find a most profitable one and work out the lowest construction cost accordingly. Due to the complexity of construction projects, time-cost tradeoff and resources allocation have been dealt with as two distinct sub-problems that cannot guarantee optimum solutions. In this thesis, a proposal is addressed to time-cost tradeoff and resource allocation, considering both aspects simultaneously. In other words, resource allocation is used to adjust the schedule and solicit the optimal tradeoff between the duration and the cost, so that the final objective is to find the schedule by which the

PAGE 16

6 contractor is able to supply the project in demand as well as reach the maximum profit at a lower cost. Problem Statement The goals of this study include the following: Presenting a thorough literature review on the effect of resource allocation on the schedule duration and the construction cost. Identifying the relevant external influence factors. Presenting some hypothetic models and conduct case studies to demonstrate validity of the models. Outlining the future extensions. Scope and Limitations Due to limited time and access of information, the initial study focused particularly on some major kinds of resources. The other resources are not mentioned in this thesis. Also the case studies only happened to subcontractors with labor allocation. Since resource allocation may follow different development steps and patterns in other countries, the literature review focused on scheduling the development and application of methods in the United States. Responding to the above-mentioned restrictions, the scope of this study has been set as the following: The literature review reflects construction resource allocation characteristics and its applications in the United States. Other possible characteristics that may seem evident in other countries are not included. Because of a variety of resources depending on the specific fields, this thesis only addresses the problem of some sorts of major resources often encountered in construction projects. The other possible resources are not analyzed in detail. The hypothetical model is established on the basis of these major resources. The case study was only done to subcontractor located in Florida and Arizona. The viewpoints will be more applicable if more subcontractors are investigated.

PAGE 17

CHAPTER 2 LITERATURE REVIEW The objective of this literature review is to define the basic concepts in this thesis, and introduce methods and models proposed in earlier literature that would be a starting point for this research about resource allocation. This chapter will also try to collect information on the application and development of resource allocation in both single-resource and multi-resource projects in reviewing the relevant application of optimization by the methods in kinds of resource allocation. At the end of this literature review, research needs will be generalized to start the research methodology design, data analysis, and conclusion in a later chapter. Basic Concepts The research in the past decades supplied a large number of publications about the resource allocation and the construction cost change as a consequence of resource allocation. Some basic concepts resulting from this past research are relevant to the study in this thesis. It is necessary to discuss them first. Resource Constraints Typical resources that have appeared in construction include a rented piece of equipment that needs to be returned early, a number of skilled workers or crews who need to be hired for the job, some amount of material that needs to be used in the project, and proper working spaces where the project can be operated, and so on. For complexity reasons, construction scheduling is a critical process of assigning activities to resources in time. However, a variety of constraints affect this process, so 7

PAGE 18

8 that scheduling actually is a decision-making processthe process of determining a schedule. Normally a project construction is affected by constraints as follows: activity durations, release dates and due dates, precedence constraints, transfer and set-up times, resource availability constraints (shifts, down-time, site conditions, working spaces, etc.), and resource sharing. These constraints define the space of admissible solutions. It has been acknowledged that the use of constraint-based techniques and tools enables the implementation of precise, flexible, efficient, and extensible scheduling systems: precise and flexible as the system can take into account any constraint. Critical Path Method (CPM) is the basic scheduling solution and widely applied to the construction field. But CPM scheduling computations do not take into consideration resource constraints. However we can see that in most practical situations the availability of resources is limited. The assumption of unlimited resources is unrealistic and may result in unfeasible solutions. In addition to the CPM approach, the Time-Cost Trade-off (TCT) approach is criticized for being incapable of representing the capacity costs and constraints of subcontractors and suppliers to resolving changes in schedule. Capacity constraints and poor site conditions cause subcontractors and suppliers real costs, which managers should take action to mitigate, and also suggested incorporate site conditions and capacity constraints into construction planning and scheduling techniques (OBrien and Fischer, 2000). Other scheduling methods such as resource leveling, overtime, etc. also have this shortcoming mentioned above. As a matter of fact, resources are flexible and allowed to shift in a reallocating method. If resources are superfluous at some time period, slack resources can be shifted to other activities or projects where more resources are needed so

PAGE 19

9 as to save money for the subcontractor as well as speed up the lagging projects. Actually even when resources are not excessive, they still may be allocated to critical activities or projects where time can be bought cheapest while maintaining resource feasibility. Efficient reallocation of resources for construction planning activities possibly may reduce the duration of activities below the normal duration even in a lower cost. Resource Allocation Resource allocation is one of the new scheduling approaches developed in the past decades. It constitutes another important class of scheduling methods. Through mobilization and shift of constrained resources across activities in construction projects, even across different projects, it is an attempt to seek a more realistic scheduling method, having the minimization of both project duration and total project cost as its goals. In the practical construction environment that subcontractors operate within, resources must be allocated to multiple jobs in activities, even to multiple projects because of limited resources. Very often resources must be allocated in conditions of competing demand and uncertainty about project schedule. Subcontractors will shift resources fluidly among the jobs, activities, or across projects to meet demands, trying to find low cost allocations within a project or across projects. Because resource allocation is supposed to solve a more practical schedule, incurring a substantial portion of the cost of the project and significantly affecting its duration, it has therefore received a great deal of attention from researchers. So resource allocation is becoming a very popular measure to control total construction costs, especially preferred by subcontractors. Many scholars mentioned resource allocation as a scheduling optimization method in the huge volume of literature over the years. Birrell (1980) was the first author to consider the implication for project uncertainty and change

PAGE 20

10 on the cost and resource allocation of subcontractors and suppliers and the need for consideration of resource constraints when coordinating schedule alternatives. Subsequent empirical work has demonstrated that subcontractors and suppliers routinely reallocate resources among jobs, activities, and projects on a daily basis (OBrien and Fischer, 2000). Hegazy (2000) developed solutions that mathematically illustrate scheduling with certain constrained resources. Construction Costs The final objective of scheduling and resource research is to determine which resource allocation will give the best overall economical solution. Then what are the compositions of project costs? The costs caused by construction activities are easily understood as the direct cost, which may be expected to dominate each operation in the form of material costs, labor costs, equipment costs, etc. Especially with the contract system, direct cost is critical when the work may be completed at the lowest total cost. However, the project direct cost does not represent the full cost of the work. Besides direct cost, the total cost must be added to all the other indirect costs of the project such as overhead charges, payment to office staff, etc. Because both direct cost and indirect cost are associated with the complete execution of the work, and proportional to time, they jointly elaborate the derivation of the total project cost curve. The solution to the cost problem is: all costs vary with duration and direct costs tend to decrease if more time is available for an operation, but indirect costs will increase with time (Antill and Woodhead, 1982). See Fig. 2-1 for an illustration of this point. For the direct cost, the least duration will result in the highest cost while the lowest costs will be spent with the available longest project duration. Moreover, the direct cost

PAGE 21

11 curve is concave and the magnitude of its slope decreases monotonically with increased project duration (Chaker, 1973). Any project schedule is feasible between the least time duration and the normal duration, even the duration with tardiness. Figure 2-1. Construction costs composition. Total construction cost consists of direct cost and indirect cost. Indirect cost is basically linear proportional to project duration. Extremely short or excessively long project durations make direct cost higher. The indirect costs are estimated by the planner in a conventional way and vary with different project completion times. Usually they vary almost directly with project duration. Only making out the needed indirect costs for the normal or tardiness duration solution and for one other duration such as the least time duration solution, a straight line variation will be derived between these two points. In general, the project total cost curve may be figured out by simply adding two cost curves at any desired duration on the diagram. Of course the direct cost curve has a fluctuation range with the different resource conditions and other constraints. Then from Fig.1, a minimum total project cost is immediately found. This is the most economical

PAGE 22

12 solution for the project. In practice, it is unlikely that a subcontractor can always reach this optimal point. If construction cost is within a range adjacent to the minimum point, the projects will be profitable enough. In other words, the objective of allocating resources across projects is to make sure the cost is in such a scope; also, the corresponding durations are acceptable. Independent Subset It was mentioned before that the project duration is usually measured in integral increments of time called independent subsets, each of which consist of certain activities or projects. The notion of independent subset was introduced to effectively avoid the disorder possibly aroused by coincidence of too many activities or projects (Yang et al. 2002). It is necessary to arrange so many activities and projects, which happened on a subcontractor and interlaced to each other, in order of time. They proposed an approach that assumed that all activities or projects carried out by a subcontractor are not absolutely available for processing effectively at time zero. They took into account the project planning and activities sequences controlling. A subcontractor generally has several ongoing projects, and a practical construction project consists of dozens or even hundreds of activities. Every activity or project has its duration, resources needed in construction, and costs used to guarantee the processing of this activity/project. Considering the possibility of processing many activities, even many projects at the same time, everything will be interlocked if activities are assumed to be available along the scheduling horizon. It will become too complicated and desultory to allocate resources across activities or projects, and further to work out the resulting duration and costs. So the tone is set for the basic research entityIndependent Subset.

PAGE 23

13 For any schedule of projects, an independent subset of project satisfies three definitions: (1) the release date of the first job in the subset is strictly greater than the completion date of the jobs immediate predecessor; (2) the completion date of the last job in the subset is strictly less than the release date of its immediate successor; (3) no unscheduled regular time exists between the start of the first job in the subset and the completion of the last job in the subset. (Yang et al. 2002). See Fig. 2-2 for property of the independent subset. Figure 2-2. Graphic illustration of property of independent subset (Yang et al. 2002). In Fig.2-2, the time horizon length represents the schedule time for a specific resource. Independent subsets on this time horizon actually are a series of activities or projects applicable to one kind of resources. Once the duration and costs of every independent subsetactivity or projectare obtained, the necessary duration and construction costs with this specific resource will consequently be received. Each independent subset, i.e., the block along the time horizon, is composed of several activities or projects. All of them are processed in accordance with a predetermined sequence. For example, we have scheduled the first project in an independent subset to complete on day t1, and the next job in the sequence, i.e., the second project, has a release

PAGE 24

14 date of t2, with t2 = t1 + k, where k is a nonnegative integer greater than 1, then no jobs are scheduled on days t1 + 1, t1 + 2, t1 + (k-1) in the original schedule, and so on. After reallocating the resource within the independent subset, several adjustments must be made. Some jobs have longer durations, but some of them have shorter construction durations. Accordingly the independent subsets durations and costs will change for the whole project as well. It is important to note that the definition of an independent subset does not preclude an independent subset consisting of a single job or an independent subset consisting of all jobs to be scheduled, which occurs, for example, when all release time equals zero. For instance in the case illustrated in Fig. 2-2, there is only one activity/project in Independent Subset 1. But Independent Subset 2 comprises 4 activities/projects, and 3 activities/projects in Independent Subset 3. In Fig.2-2, R represents regular processing time, and represents overtime. These two notations may be regarded as a form of construction resource in this thesis. They are shifted across activities or projects so as to optimize the original schedule and make more profits. The problem is to schedule a finite set of activities or projects with a single resource during some finite time horizon of length T. Here the processing time is used to elaborate the concept of independent subset. Each activity or project has an available processing time of R during regular time, plus an additional amount of time for overtime. Both of them are period independent. So the total amount of processing time available in a given period can be expressed as R+. Assuming that the resource is set available in each period R+, the original schedule consists of m independent subsets, where m is a positive integer. Suppose index

PAGE 25

15 these subsets in order of increasing start time (i = 1, 2, m). If m = 1, then simply apply resource allocation among jobs within this subset. If m > 1, then apply resource allocation individually to jobs of each independent subset, then apply to all independent subsets to one another from 1 to m. Some independent subsets are flexible. They are possibly combined into a new independent subset under a certain condition. This procedure may be realized through two phasescompacting phase and relaxing phase. Firstly compacting phase is to fully utilize all available overtime in any period to make out a corresponding schedule. Then in relaxing phase, the total amount of overtime used in every period (beginning with the latest scheduled job that uses overtime and working backwards in time) is sequentially decreased. Except subset m, other independent subsets may become blocked in applying the relaxing phase to an independent subset, when the completion time of the last job in the subset reaches the period immediately before the starting period of the next independent subset, and also exhausts all regular time in the period. If independent subset i does become blocked by subset i +1, then the two subsets i and i + 1 merge into a single new subset. The new merged subset must satisfy the conditions required in the definition of an independent subset. Figure 2-3 below provides an example of one independent subset blocking another in the resource allocation phase, producing a new independent subset. The above figure provides an example of one independent subset blocking another in the phase of reducing overtime, producing a new independent subset. The utilization of other kinds of construction resources such as materials, labors, etc. is somewhat analogous to that of processing time expatiated above.

PAGE 26

16 Figure 2-3. Graphic illustration of formation of a new independent subset from two consecutive independent subsets. Independent subset 2 is blocked by independent subset 3, and then merged with independent 3 into a new bigger independent subset. Perspectives of Application to Multi Projects By Subcontractor The study of this thesis focuses on the resource allocation application to multi projects constructed by subcontractor. It is believed that the resource allocation is exerting markedly on multi projects, particularly by subcontractor. Why Multi Projects Because of the resources finites, subcontractors need to maintain a resource demand balance across many projects. The environments and projects require the allocation of materials, labor, equipment, and other resources to complete a set of construction projects that change over time. Subcontractors will shift resources fluidly across projects to meet demand, seeking to optimize productivity across projects. Choices about resource allocation are perhaps the most important operational decision that subcontractors make. The ability to shift resources across projects is a key component of flexibility. Subcontractors, unlike suppliers, have limited ability to buffer production by producing ahead of schedule and respond to changes on projects by reallocating resources (OBrien, 2000). A parametric

PAGE 27

17 model relating productivity, site conditions, and resource allocation to a work package was described, and implications of the model were discussed when considering multi-project resource allocation. Due to increasingly intense international competition, construction firms are constantly undertaking multiple projects while they might leverage their resource investments in order to achieve economical benefits. Accordingly, the perspective of multiple projects scheduling has become a critical issue for competition. Regardless of the number of projects, the final objectives for all projects are to strive for minimum total completion time, minimum total costs, and maximum resource usage efficiency. Generally speaking, multiple project scheduling is an area where traditional methods and techniques appear to be less adequate. Why Subcontractor Subcontracting has become prevalent in the construction industry, and presented as an organizational alternative for some economic activities. Construction firms are dispersing their jobs more and more, as subcontracting becomes a basic part of the work organization. The reasons why subcontracting prevails may be summarized as follows: increasing sophistication and specialization of trades, which requires long-term investment in personnel and equipment; increasing prefabrication off site, which similarly requires large-scale investment in fixed facilities; fluctuating demand for services of general construction contractors, which demands agility in adjusting capacity (Sacks, 2003). Nowadays, in order to reduce costs, construction firms do not need to have control of all the value string. By subcontracting, they are able to externalize non-strategic

PAGE 28

18 activities, realizing the aim of costs reducing. Building firms are organized into a consistent operating core based on their individual capabilities. More and more construction companies are becoming construction managers or contractor managers after transferring construction jobs to specialists. Meanwhile, subcontractors are specialists in the execution of a specific task. They may supply manpower, materials, and equipment as well as designs and techniques. In the United States, currently in many projects, it is common for 80-90% of the construction work to be performed by subcontractors. They perform construction work that requires skilled labor from one or at most a few specific trades and for which they have acquired both special-purpose resources and process know-how. Other Literature The project scheduling literature contains a variety of work dealing with multi-project and subcontractors problems. Not meant to be exhaustive, this review is limited to some relevant technologies about resource allocation. While some research considers only one type of resource, some models are only with stated resource constraints, some with single resource, and some with multi resources, and the diversity reflects the complexity of the reality. This chapter tries to tie together widely scattered ideas and to assess a resource allocation model in a simple and generalized form. Sacks (2003) proposed a model of a multi-project and multi-subcontracting paradigm. He tried to identify ways to align a subcontractors benefit and better understand workflow from the subcontractors point of view. Adopting the subcontracting, and researching problems faced by subcontractors, the ultimate goal is the total amount of benefit achievable by both general contractors and subcontractors across multiple projects.

PAGE 29

19 OBrien (2000) presented a model associated with site conditions, resource allocation and productivity, allowing quantitative assessment of the impact of shifting resources across projects. Use of the model for multi-projects resource allocation decision was discussed, and several implications for subcontractor and site management were developed. Hegzy (2000) addressed the algorithm for scheduling with multi-skilled constrained resources. Hegzy (2001) also presented Subcontractor Information System that supports the estimating and project control functions of subcontractors. Models of Subcontractors Construction Costs Tardiness and Overtime Cost Model Flexible preference constraints characterize the quality of scheduling decisions. These preferences are related to due dates, productivity, frequency of changes, inventory levels, overtime, etc. Since preference constraints may conflict with one another, the resolution of a scheduling problem also consists in deciding which preferences should be satisfied and to what extent others should be relaxed. In practice, however, preference constraints are often either combined into a unique evaluation or cost function to maximize or minimize, or compiled into evaluation heuristics to favor candidate solutions that satisfy the preferences. A heuristic approach was tried to minimize weighted tardiness and overtime costs in single resource scheduling. The tardiness costs and overtime costs, as the constraints, are collaborative and considered to satisfy while the scheduling solutions are eventually gained (Yang et al. 2002). A solution to the scheduling problem is a set of compatible scheduling decisions (such as performing the project as soon as possible after tardiness

PAGE 30

20 and overtime costs are generated), which guarantee the satisfaction of the constraints, i.e., minimizing the sum costs of both constraints. The previous literature normally assumed each job took a certain fixed amount of time on the resource, and that both processing times and resource usage can be measured in some continuous time increments, also an assumption exists that the cost of processing activities is the same no matter when the activities are processed, the amount of available processing time in each processing period is fixed. In the paper mentioned above, Yang, Geunes, and OBrien thought the primary method the contractors employ to meet due dates of the project was through the use of overtime. So they tried to overcome the defects in the previous research to direct the construction with a tradeoff of tardiness cost versus the use of overtime (Yang et al. 2002). A model was made to simulate the overtime-tardiness problem. In the model, compacting was the first step that made out a corresponding schedule by fully utilizing all available overtime in any period. The created schedule guarantees the minimum total tardiness costs under the fixed sequence, but with a high overtime costs. Then a relaxing phase was carried outsequentially decreasing the total amount of overtime used in that very period (beginning with the latest scheduled job that uses overtime and working backwards in time). The total amount of relaxed overtime is a function of whether the relax phase produces a lower total cost schedule, so that the optimal sequence of jobs, the start date, finish date, and overtime usage for each job were able to be determined. Basically the overtime cost is the increment with a fixed amount every overtime unit (hour, day, week, month). So it can be seen that the overtime cost is linear in overtime resources utilization. For the tardiness cost, it keeps stable within one time

PAGE 31

21 interval, e.g., the daily penalty or the weekly penalty is a fixed amount within one day/week. The construction term of the project will not be reduced by one day or one week unless the accumulated overtime utilization reaches a certain amount. That means the tardiness cost decrease is a stepwise decrease to total overtime usage instead of a linear relationship to the overtime usage. Therefore, the total cost function is the sum of a linear function and a stepwise decreasing total tardiness cost function. The resulting total cost curve is shown as the saw-tooth curve in the following Fig. 2-4. Figure 2-4. Total cost curve as a function of overtime utilization under the compact and relax procedure. (Yang et al. 2002) The tardiness cost for an activity determines the amount of cost decrease at each of the steps in the curve, while the overtime cost per unit time, cO, determines the rate of increase after each step. The compact and relax algorithm evaluates the cost at the bottom of each spike on the saw-tooth curve, then finally a minimum total cost for the predefined sequence of jobs might be obtained.

PAGE 32

22 Overtime and due date were presented for the representation of constraints and subsequently a solution was figured out to satisfy these constraints, by resource allocation, proper usage of overtime, and tardiness (Yang et al. 2002). Parametric Influence Model When subcontractors make resource allocation choices, they have to take into account some influence factors. OBrien (2000) addressed these considerations in his literature Multi-project Resources Allocation: Parametric Models and Managerial Implications. He proposed a productivity model with which subcontractors allocate resources. He stated that subcontractors must consider the switching and logistics costs of moving resources across projects, the affect of altering the balance of different classes of resources, and the ability of a project to absorb and loan resources with regard to productivity and completion dates. The parametric model was defined as: Pi = (aj T y)CW The productivity model was described as an ideal productivity with complementarity. For the construction method j, the rate per unit of flexible resources (such as labor, small tools and equipment that are often used by single workers), a, multiplied by the number of flexible resources, y, gives the ideal productivity rate. Complemented by flexible-fixed resources ratio (fixed resources were defined as heavier equipment that serves crews rather than individuals) C and work area productivity modifier W, the final actual productivity rate was gained. When there is an ideal ration of flexible to fixed resources, complementarity modifier C reaches a maximum value of 1. As the ratio varies, the value of C will decrease towards zero as shown in the Fig.2-5.

PAGE 33

23 Figure 2-5. Complementarity (flexible/fixed resources ratio) modifier curve Figure 2-6. Work area modifier curve Work area modifier W is a function of the size of work area w. W is zero when there is no available work area. That means there is no possible production. As work area increases, productivity increases too. OBriens model provides the subcontractor with insight as to how to allocate the resource. Such a model may become the criteria for subcontractors in determining project operating decisions, making contracts and developing schedules. Summary Critique and Current State of Literature In the above-mentioned literature about tardiness and overtime cost, there was a presumption of solution approach that job preemption on the resource was not allowed,

PAGE 34

24 i.e., once a job is started it must proceed to completion before any other job can be started (Yang et al. 2000). In a practical construction project, the original construction schedule is allowed to adjust and change in order to match the time schedule well and ensure the financial situation in the budget. Sometimes activities would be started in advance and at other times postponed a little. Consequently one resource might be preempted by another job instead of the scheduled job. Moreover, many projects keep changing even in the process of construction, particularly in the design-build projects that become more and more popular in this industry. The designer, the owner, and the contractor need to cooperate closely, and frequently change their plans and timetable in accordance with the requirements. Furthermore, compacting phase is to set the resource availability to the hard time, i.e., the regular time plus overtime. For the algorithm proposed in this paper, the relaxing phase is to begin with the last scheduled job after the compact phase of the algorithm. This relaxing procedure is repeated backwards till the first scheduled job. In this phase, the overtime costs are going down to zero while the decrease of working time possibly results in the tardiness costs. In practice, few contractors will complete the project later than the project due date requested by the owner. It is about not only the cost problem, but also the reputation of the contractors. So the contractors are unlikely to make out a schedule longer than the required completion days. The contractor has to keep the record and reputation good in order to get more projects. They definitely would rather increase the investment such as increase the overtime to ensure the completion date than consider if the tardiness costs

PAGE 35

25 are lower than the overtime costs. Normally subcontractors will try their best to prevent tardiness from happening. So it is significant to study projects with presumption of normal durations. Research Needs The final target of a subcontractors multi-project resource allocation research is to complete the project in time and in demand desired, meanwhile with possibly lower comprehensive total costs. The project duration may be adjusted to be shorter or longer within an allowed scope through resource allocation. Considering indirect cost, a fluctuation in total cost curve can be achieved. The lowest point of this fluctuation curve is the optimum solution to subcontractors (to be explained in chapter 4). However, due to the complexity of construction, the total cost and project duration vary by complicated situation such as the disturbance caused by relevant activities to one another. So the case studies with calculations of both cost and duration will focus on a single resource project in this thesis. However, the implications of project uncertainty and change on the cost and resource allocation of subcontractors in multi-project will also be discussed. Through the literature review, the relevant information and basic concepts necessary for resource allocation resolution in my thesis are collected and explained. Different from overtime usage or other time-cost tradeoff methods, resource allocation is absorbing more attention in the construction field because of its property of being flexible and being prone to construction cost reduction, constructability improvement, and better project quality. Starting from the basic entityindependent subset in a single resource project, resource allocation optimization will be analyzed and extended to further prospect. In my study I will seek the cost curve related to resource allocation, and create some models

PAGE 36

26 that relate to site conditions, resource allocation, productivity, and other influence factors. In view of the perspectives of resource allocation application in multi-project, the project scheduling problems will be discussed in detail.

PAGE 37

CHAPTER 3 SINGLE RESOURCE ALLOCATION ACROSS PROJECTS This chapter discusses the basic concepts on which a model for resource allocation in a single-resource project is built. Components of construction cost are explained and a parametric model used to optimize the resource allocation is introduced as well. Two case studies are used to help understand the application of single resource allocation that establishes the base for development of multi-resource allocation. Presumption Resource Shifting Within Independent Subset According to the concepts of independent subsets elaborated in chapter 2, the project duration is measured in integral increments of time of independent subsets. Independent subsets are accrual units that chronicle along the time horizon. The allowed adjustable resource such as labors, materials, equipment, etc. can be shifted among the activities or projects within one independent subset. After obtaining the durations and corresponding costs of affected activities or projects, they may evolve into data of a series of independent subsets. Then the subcontractors total project costs associated with this specific kind of resource may be evaluated. In practice, activities or projects within one independent subset occur simultaneously. These activities or projects are using the resources at the same time. They integrate together to form a complete independent subset. Within an independent subset, every activity or project is allowed to adjust respectively, i.e., with resource reallocation across these activities or projects. All of the subcontractors work is divided 27

PAGE 38

28 into many independent subsets in the time order of activities or projects. On the basis of Fig. 2-2, we can illustrate the resource reallocation within an independent subset as shown in Fig.3-1. Figure 3-1. Illustration of resources shift in the independent subset In Fig.3-1 above, the first activityindependent subset i consists of 4 jobs, numbered from 1 to 4. Independent i+1 includes several jobs, and independent i+2 has 3 jobs, and so on. Every independent subset has a fixed construction period that has been decided in the schedule. In independent subset i, job 1, 2, and 3 fully utilize the available processing time, the sum of overtime and regular time R. Job 4 just utilizes a part of regular time. Under this situation, we assume the construction cost is X that includes the indirect cost and direct cost (refer to Literature Review). Indirect cost is fixed because it basically is positively proportional to construction period time. Direct cost should cover the expenses that have occurred in both overtime and regular time. Through resource allocation, we may reach another situation. The work time for job 1, 2, and 3 may fall down to a level lower than the regular time, and in contrast the working time of job 4 increases. The new situation will result in a new construction cost Y, and the composition

PAGE 39

29 of Y is the same as that of X. Comparing X with Y, the contractor certainly prefers a lower one, and meanwhile the activity completion due time will still be guaranteed. So we may create a series of different situations through different resource allocation methods. Finally the lump sum of every shortest activity construction period time is the construction term most beneficial to subcontractors. Total Construction Costs As described in the Literature Review section of this thesis, the total construction cost is the lump sum of direct construction cost and indirect construction cost. The direct cost curve in the Literature Review shows that the solution for direct cost must be somewhere between the two extremes of the least-cost solution and the least-time solution, and the direct cost tends to decrease if more time is available. In contrast, the indirect cost varies almost positive directly with project duration. The blend of direct cost curve and indirect cost line presents the change fluctuation of the total project construction cost, and also supplies the information for determination of lower cost and corresponding project duration. We now move from the study vision to the independent subsetthe epitome of activities or projects performed by a subcontractor. The whole construction cost and project duration are accruements of all independent subsets. Each independent subset has a series of activities/projects. The data are required for every possible method of carrying out each activity or project. How much resources allocated for each job, how much time scheduled, and so on, are all related to resource allocation, so it becomes the only influence factor to generate different total construction curve. Since the indirect cost just has a simple relationship with the activity period, we pay attention to the direct cost. Direct cost curve is pivotal because it can have any

PAGE 40

30 duration between different normal and least duration, then a range of possible durations and corresponding costs based on its utility data is available for each activity. Accordingly, different combinations of possible durations for the activities can be associated with the project. Because all individual activities are assumed to have valid continuous cost curves, the curve in Fig. 3-2 implies that any project schedule is feasible between the least-time duration and the all-normal duration. Figure 3-2. Construction costs in independent subset i The data such as construction schedule and resource allocation scheme set the limits of the cost and duration of an activity. Usually the contractor determines these data before starting the activities. It is to indicate that a different method of performing the same activity may define a different set of data. Consequently, it may have a different utility curve, such as the two direct cost curves caused by different resource allocations. The indirect cost curve is plotted on the same graph as the direct cost curve and then summed up to give the total cost curve so as to determine the final cost curve. The

PAGE 41

31 project total cost curve is plotted by simple addition of the two other costs at any desired duration on the graph. Then it is immediately clear that a minimum total project cost exists. This is the most economical solution for the project, i.e., the duration for the least total cost. In practice, contractors wish to pursue this most economical solution if they possibly can. Even they cannot always achieve the idealistic point. Also contractors will have the intrinsic property of construction cost as a helpful reference. By different construction methods through adjusting resource allocation, contractors then will work out a feasible cost solution that is most profitable to them. Parametric Models of Single Resource Allocation We just focus on one independent subset to analyze the single resource allocation influence on activity construction cost. In the independent subset i, the construction cost is composed of two portionsdirect cost and indirect cost. The parametric models in this thesis try to find a way to determine the cost of loaning or absorbing resources on a particular work area, meanwhile only single resource is allowed to separately allocate in the models, no matter what resource it is, labor or material. Indirect Cost and Direct Cost As explained in Literature Review, a productivity function formula has been developed as follows: Pi = (aj T y)CW (OBrien, 2000) Equation 3-1 In Equation 3-1, Pi is the actual productivity rate for all resources applied, aj is ideal productivity rate per unit of flexible resource for construction method j, y is units of flexible resources applied, C is complementarity productivity modifier, and W is work area productivity modifier.

PAGE 42

32 Equation 3-1 allows us to calculate activity duration. Ti = Qi/Pi Equation 3-2 Where Qi is the construction quantities of activity i, and Ti is the deduced activity duration of activity i. With computation of activity duration through Equation 3-2, we will easily access the construction costs by multiplying duration by unit cost. Indirect cost includes the overhead, project management expense, and so on. It is basically a linear relationship along the activity construction time. So we may figure out the indirect cost by the following Equation 3-3. Cind = mTi + n (m>0, n0) Equation 3-3 Here Cind represents the indirect cost of activity i; m represents the unit indirect cost; and n represents the start-up cost at the beginning of activity i. Direct cost is the money invested directly to the activitys construction. Its change curve depends on the different source allocation ways as described in section of total costs analysis. Under a certain resource allocation situation, the direct cost Cd can be divided into regular part and overtime part. Two parts have different unit cost. The direct cost of the overtime part does not exist in case the activity may be completed within the time without any overwork. In addition, we ignore the possible rewards for early completion and the possible penalties for tardiness. Either in regular time or in overtime, we have to take into account costs caused by both applied flexible resources and applied fixed resources. Cr = SryyR + SxxR Equation 3-4 Co = Sryy + Sxx Equation 3-5

PAGE 43

33 where Cr direct cost occurred in regular time Co direct cost occurred in overtime Sry unit cost in regular time for one certain flexible resource Sx unit cost for one certain fixed resource Sry unit cost in overtime for one certain flexible resource y units of flexible resources in regular time x units of fixed resource in regular time R regular time overtime Addition of Cr and Co will result in the equation for direct cost Cd: Cd = Cr + Co = SryyR + SxxR + Sryy + Sxx = SryyR + Sryy + Sxx(R + ) Equation 3-6 The lump sum of R and is the maximum available processing time Ti for the activity i that is deduced by Equation 3-2. In case the working time Ti is less than the regular time R with productivity rate Pi, there is no over time Otherwise, a certain amount of overtime will be used in activity i. The quantities of flexible resource y and fixed resource x will be determined by the concrete resource allocations. Therefore, the total construction cost CT is: CT = Cind + Cd Equation 3-7 Different resource allocations result in different cost point. Connecting all points, the total cost curve can be plotted.

PAGE 44

34 Other Costs When building the picture of total cost of resource allocation, there are other considerations needed to be included. Shifting cost for moving flexible or fixed resources from site-to-site, training expenses for new added unskilled labors, the cost for being familiar with the new equipment, etc. will happen in the resource allocation periods. Those costs are likely to be different for each resource allocation, and for each activity. They vary depending on the conditions environments supplied by the sites. The tougher terrain conditions or longer distance may increase the shifting costs. Few numbers of new added workers will keep the training costs lower. In this thesis, we will not discuss those costs due to the variety of activity individuality. Furthermore, it is not difficult for contractors to respectively estimate those costs according to concrete situations. As for the material cost, because the quantities needed to complete the activity basically are constant and can be found in the estimate, they will not be discussed here. Case Study Two cases will be discussed in this section. They respectively study construction cost with labor allocation, and equipment (flexible small tools) allocation. In order to simplify the problem, we assume every activity in the following models has only one job, and the ideal unit productivity remains same no matter how the resources are reallocated. Model 1 Labor (crew) allocation For a 12,000 sq. ft. plastic roofing work, the construction period is 15 days. One standard crew to do this work includes 2 sheet metal workers and 2 building laborers. Their unit cost is $ 600 per day in regular time, and $ 900 per day in overtime. The ideal

PAGE 45

35 productivity rate of one crew is 600 sq. ft. per day. On the job site, 5,000 sq. ft. of the working area and one PVC machine are supplied for roofing. We assume that the PVC machine requires at least one crew (2 sheet metal workers and 2 building workers) to operate, so the function drops to zero at one. However, the machine is not fully productive with one crew and it can exert all its power with 2 crews. More crews greater than two can affect little on overall productivity. So the complementarity modifier C is illustrated below in Fig.3-3. Figure 3-3. Complementarity modifier C in Model 1 For each crew, they need 5,000 sq. ft. of working area to guarantee the maximum productivity rate. Smaller working area will result in conflicts in construction. On the other hand, they have to spend extra time on mobilization with a too large working area. So the work area productivity modifier may be plotted as in the following Fig.3-4. With these conditions, how many crews do we need to complete this roofing work and yet be most economical? We may work it out by equations set up in section. Firstly we compute the cost with 2 crews. Because 2 crews are using one PVC machine, the complementarity modifier C is 1. The average working area for each crew is only 2,500 sq. ft., so the work area modifier W is only 0.63. The ideal productivity rate

PAGE 46

36 for each crew is 600 sq. ft. per day, and the flexible resource quantity y, i.e., the number of crews is 2. Then the actual productivity rate for this activity comes out. Figure 3-4. Work area productivity modifier W in Model l P = (aj y)CW = 600 x 2 x 1 x 0.63 = 756 sq. ft. /day By Equation 3-2, the working time for this activity is: T = 12,000/756 = 15.87 days Because the project is required to finish within 15 days, the overtime is 0.87 days. R = 15 days = 0.87 days In this case, the indirect costs include management fees, overhead costs, etc. in addition to daily cost $ 100, $ 500 basic cost is needed at the beginning of the activity. That means: m = 100 n = 500 Therefore: Cind = mT + n = 100 x 15 + 500 = 2000 dollars

PAGE 47

37 Using equation 6, we may work out the cost both in regular time and cost in overtime. Because the daily cost for a fixed resource, which is for the PVC machine here, does not change, we just compare the cost for labor. Cd = SryyR + Sryy = 600 x 2 x 15 + 900 x 2 x 0.87 = 19,566 dollars Equation 7 tells us how much the total cost is: CT = 2000 + 19566 = 21,566 dollars Then we consider the situation with only one crew. The complementarity modifier turns to 0.8, but the work area modifier raises to 1. P = (aj y)CW = 600 x 1 x 0.8 x 1 = 480 sq. ft. /day T = 12,000/600 = 25 days R = 15 days = 25 = 10 days Cind = mT + n = 100 x 15 + 500 = 2000 dollars Cd = SryyR + Sryy = 600 x 1 x 15 + 900 x 1 x 10 = 18,000 dollars CT = 2000 + 18,000 = 20,000 dollars So that the comparison results are concluded in the table below: Table 3-1. Resource allocation comparison in Case 1 Duration Overtime Indirect cost Direct cost Total cost 2 crews 15 0.87 2000 19,566 21,566 1 crew 15 10 2000 18,000 20,000 In this model, it shows that decreasing the numbers of the crew from 2 to 1 seems beneficial to contractors. Using one crew comes into better effect, and the contractors should reallocate the superfluous crew to other activities or projects.

PAGE 48

38 Model 2 Equipment (flexible resource) allocation Hydraulic excavators and cranes are used to cooperate to do 1,000 cubic yards trenching activity without exact construction time limitation (8 working hours per day). A total of 3,000 sq. ft. of working area is available. The hydraulic excavators are flexible, but the cranes are fixed resources. With one crane already working on the job site, the contractor cares about how many excavators they should allocate to this activity in order to achieve the most economical effect. The curve of Productivity complementarity C shows 2 excavators working with one crane are fully productive. Although the productivity rate will drop off 30% when only one excavator is used, a crane requires at least one excavator to operate, and thus the function drops to zero. Figure 3-5. Complementarity modifier C in Model 2 One excavator needs 2,000 sq. ft. to become most productive. Smaller or bigger areas all decrease its behavior, shown in Fig. 3-6. The ideal daily output of each excavator is 50 cubic yards, and the hourly cost is $40. The cost for fixed resourcecraneshould be taken into consideration because the construction time is varying. The hourly cost for the crane is $50.

PAGE 49

39 If we use only one excavator, the related parameters are computed according to the processes shown in model 1. Figure 3-6. Work area modifier W in Model 2 P = (aj y)CW = 50 x 1 x 0.7 x 0.9 = 31.5 cubic yard /day T = 1000/31.5 = 31.75 days R = 31.75 days = 0 days Cind = mT + n = 100 x 31.75 + 500 = 3,675 dollars Cd = SryyR + Sxx = 50 x 1 x 37.5 x 8 + 40 x 1 x 37.5 x 8= 22,860 dollars CT = 3675 + 22860 = 26,535 dollars And then if we add one more excavator in this activity, y units of flexible resources becomes 2, and the xunits of fixed resourcestill maintain as 1. The average for each excavator is 1500 sq. ft. Assume that the work area modifier W can be interpolated, W is 0.9 under the situation with 2 excavators. P = (aj y)CW = 50 x 2 x 1 x 0.9 = 90 cubic yard /day T = 1,000/90 = 11.1 days R = 11.1 days = 0 days

PAGE 50

40 Cind = mT + n = 100 x 11.1 + 500 = 1,610 dollars Cd = SryyR + Sxx = 40 x 2 x 11.1 x 8 + 50 x 1 x 11.1 x 8= 11,544 dollars CT = 1610 + 11544 = 13,154 dollars The comparison table is shown as follows: Table 3-2. Resource allocation comparison in Case 2 Duration Overtime Indirect cost Direct cost Total cost 1 crew 31.5 0 3675 22860 26535 2 crews 11.1 0 1610 11544 13154 On the contrary, adding one more excavator to model 1 will accelerate the project greatly, and with less costs. Using the same method, the contractor may compute the costs for 3 excavators, or more, until they find a solution that is sound for them. Summary Although the equations and models are established only within a single resource allocation scope, they still reveal the relationships between construction cost and resource allocation to a certain extent. As a main method to control cost and set down the schedule, resource allocation plays an important role. In accordance with the specific conditions of different activities or projects, it is not difficult to simulate the above analysis and establish models on the computer, and then further electrolyze the data processing. We just discussed two resource allocation methods for each model, but the computer may repeat the same processes to calculate many allocations. With the electrical results, the cost curve, including the direct cost curve and the direct cost curve will be easily plotted. That will be the right-hand guidance to subcontractors. This analysis method can be further developed in multi-resource projects. The possible influence and the perspective will be discussed in chapter 4.

PAGE 51

CHAPTER 4 MULTI-RESOURCE ALLOCATION ACROSS MULTIPLE PROJECTS On the basis of elaboration of single resource allocation, the concept of independent subsets and the parametric cost model are introduced in the application of the subcontractors multi-resource allocation in this chapter. The implementation of multi-resource allocation encompasses consideration of mutual impacts caused by allocation itself to the subcontractor as a whole, of certain combinations of resource utilization. Two examples of subcontractors, taken from an investigation in Florida and Arizona, are presented in this thesis on their resource allocation measures. The evaluation of their allocations is also addressed. Environment for Multi-resource Allocation Across Multi Projects Due to increasing sophistication and specialization of work, which creates a more complex work environment, the subcontractor is likely to grow to encompass more trade, invest more in personnel and equipment, and be able to confront tough work conditions with a tighter schedule. Increasing prefabrication off site and more complicated construction on site require multifarious fixed facilities too. Under this kind of environment, the subcontractor has to consider the deployment of each resource in the meantime other than a schedule with a single resource. Reasonable multi-resource allocation across projects is necessary to take advantage of resources and also complete all projects as required. Multi-resource allocation across multi projects in the context of construction is the assessment of the real inputs for any of the subcontractors projects or 41

PAGE 52

42 programs of construction and the identification of the action necessary to ensure that there is a balance between requirements and availability. With the resource constraints, some of projects will be prioritized and the others not. What are the criteria? Most of the subcontractors normally prioritize their projects with multi-resource on customer priority, stakeholders interest, corporate portfolio, product roadmap, business strategy, and project budget (Faniran et al. 1999). The single most significant factor is the return of investment. Other prominent reasons used to allocate resources across projects are reliant on the subcontractors core business. Utility, construction, and government industry prioritize projects based on regulatory requirements, legislative mandates, emergencies, and political demands in addition to above-mentioned criteria. From the standpoint of a subcontractor, the return of investment, i.e., the construction cost, is the only concern in this thesis. In order to maximize the profits, multi-resource allocation is necessary, on the one hand, to improve the efficiency, and on the other, to plan all projects as a whole so as to reduce the cost as much as the subcontractor can manage to do so. Multi-resource allocation involves much more than merely crunching numbers in a mathematical calculation. In the single resource allocation hypothesis, the resources are allocated in the chronological order based on project priorities. If resources are insufficient then there may well be decreases in the labor productivity, thus possibly prolonging project durations with the risks of project tardiness, and increasing the construction cost as well. Also there may be some kinds of excessive resources at some projects that damage the balance of process causing inability to fully exerting other resources and a rise in price through a change in the correlation. So the resolution is to

PAGE 53

43 shift the extra resources from the projects where fewer resources are required to reach the optimum efficiency to the projects that need more resources to speed up the progress. But in the typical multi-resource allocation, the resources are allocated simultaneously to sets of activities or projects, rather than to individual activities or projects in a sequential manner. With multi-resources allocation across multi projects, the subcontractor possibly does not save money on some projects, and even has to endure the loss to some degree, but meanwhile gain profits from other projects. In other words, some projects are sacrificed to create favorable resource conditions for other prioritized projects, then benefit from them, and eventually profit the subcontractor in the entire plan. The first step in the process of moving to a strategic resource-allocation perspective is to determine where current strengths exist, where the weakness exists, and where the priority will be set to build upon these answers. In some instances, significant construction resources are required to move forward toward strategic objectives. In these instances, the subcontractor must set priorities and balance available resources (Chinowsky and Meredith, 2000). For example, if a subcontractor finds two projects are scrambling for the same kinds of limited resources, then a decision must be made as to which of these gaps requires the greater attention at the current time. Each subcontractor impossibly supplies unconditional resources to their projects. Normally they strive to grab sufficient projects so as to ensure a ready supply of available work. In addition they must tend to make the most of limited resources when they perform work on multiple projects simultaneously. From the subcontractors point of view, the focus is not on any one specific project, but on multiple projects. Each

PAGE 54

44 construction project manager, on the other hand, is highly focused on the project for which they are responsible, so that they would rather utilize resources as much as they possibly can. However, rather than advancing an individual area, the subcontractor must retain an overall perspective acknowledging that each of the projects and each of the resources are equally important to achieving a long-term vision. Moreover, the mutual influence caused by multi-resource allocation must be taken into consideration. Will the subcontractor suffer losing interest in any other projects if the amount of one kind of resource goes down on a project? What is the optimal point of resources arrangement to guarantee a companys profit? Similar to the balancing of resources on a project, the balancing of resources at a subcontractors organization level is required to keep him on a continued path of advancement. This thesis proposes to attempt to understand the behavior of subcontractors in resources allocation on multiple projects that requires looking beyond the boundaries of a single resource/project and taking the subcontractors multi-resource/multi-project viewpoint. Significance of Independence Subset in Multi-Resource Allocation Different from the single-resource allocation elaborated in chapter 3, various resources are in use on a subcontractors projects. Those resources are applied to each project in accordance with the construction processing sequence. And the same project utilizes different resources in different periods, including materials, labor, equipment, working areas, etc. Normally the subcontractor takes care of every resource at the same time. How to help coincide the usage of resources to offset the possible shortage or excess, avoid the possible conflicts and wastage between resources, and finally obtain the maximum financial return is the only problem the subcontractor cares about. Figure 4-1 imitates the situation of multi-resource allocation.

PAGE 55

45 Figure 4-1. Illustration of multi-resource allocation across projects A simple multi-resource allocation sketch is shown in Fig. 4-1. It consists of only resource 1 and resource 2. The subcontractors projects are arranged along the time horizon, represented by blocks with different colors. It can be seen that these projects are processed in different periods with different resources and different regular time R and overtime Also due to the different processing time, those projects are merged into or divided into different independent subsets. As shown in Fig. 4-1, resource 1 is applied to project 1, 2, 3 and 4 at the same time. So project 1, 2, 3, and 4 are integrated into one independent subset. The next project using resource 1, leading the next independent subset, has a time gap with its predecessor. For the application of resource 2, project 1 and 3 are dealt with firstly as an independent subset. Project 2 and 4 do not start immediately after the completion of the first independent subset that is composed of project 1 and 3. So project 2 and 4 form a new separate independent subset. In the

PAGE 56

46 following independent subsets, the construction sequence for other projects might differ from that in the construction with resource 1. Within the independent subset, every activity or project is allowed to adjust the usage of resource. Similar to the single-resource allocation, this kind of resource allocation probably is beneficial to related projects; meanwhile the different resources collaborate or influence each other. Usually the allocation of one kind of resource will result in the ripple effect on other resources. The subcontractor needs to take into consideration all relevant impacts so as to maximize the profits. Efficient allocation of resources for construction activities or projects requires that the determination of resource requirements should be undertaken on a return-adding and cost-effective basis. Too little resource allocation effort possibly results in implementation failures, delays, mediocrity, and inefficiency. Consequently there is a high probability that the project will exceed the subcontractors existing budget. When the correct amount of resource allocation effort is invested, the project implementation time is optimized, the construction costs are decreased, and there is a high probability that the project will save much money for the subcontractor. But additional resource allocation effort beyond the optimal level is essentially wasteful, probably even projects will achieve intended objective, because of the implementation delays that inevitably arise due to the additional time required to complete the allocation and the increasing costs of associated work such as the resource shifting expenses. Since it is hard to work out how much effort should be invested, and it is not possible to readily identify from so many multi-resource allocation options, which projects to assign higher priorities to, and which projects to improve the subcontractors

PAGE 57

47 financial status, a simple repetitive calculation procedure may be used. It is possible, therefore, to introduce a scheduling software system into resource allocation scheduling and consequently monitor the impact on the total yield results. Each project within the independent subset is selected in turn, given the highest priority over all of the others, and the consequent project duration and corresponding construction costs are monitored. Repeat this procedure to figure out costs of all resource-allocation combining possibilities, then the optimal one will be obtained through the comparison of results. The procedure is demonstrated in a case study in the following section. Multi-Resource Allocation Parametric Model On the basis of the productivity function formula discussed in single-resource allocation analysis, a parametric model is presented here to promote the understanding of multi-resource allocation concept by attempting to explain the basic tenet of this concept in the context of the subcontracted construction environment. The basic tenet begins with a statement of the ultimate goal from the subcontractors point of viewto maximize his profit over considered projects. In the single-resource analysis in chapter 3, the overtime cost or tardiness cost are involved in total cost calculation. For the sake of simplicity, both overtime and tardiness cost will be ignored. Assuming that the subcontractor is remunerated only according to quantity of work performed in each project, this model can be stated as follows: I = (AjDj CT) Equation 4-1 nj1 where I subcontractors net income over project 1 through project j Aj total work amount of project j (j = 1, 2, 3n)

PAGE 58

48 Dj unit price for the work on project j (j = 1, 2, 3n) CT total construction cost As discussed in the previous chapters, total construction cost is composed of direct cost Cd that is obtained by multiplying the total quantity of resources on project j with the unit cost of resources, and indirect cost Cind. Using the definitions in chapter 3, the subcontractors net income is: I = (AjDj Cind Cd) = (AjDj Cind qjSj) Equation 4-2 nj1 nj1 Cind subcontractors overall indirect construction cost qj total quantity of resources on project j (j = 1, 2, 3n) Sj unit cost of resources on project j (j = 1, 2, 3n) Because the cost of resources can be separated into material part and labor part, and the material cost may be expressed as the product of actual performed work multiplied with the unit price of the material for the work. In this thesis, the focus is on the subcontractors strategy in allocating resources; the material waste will be omitted. Then assuming the actually performed work is equal to the demanded work that is represented by Aj, So Equation 4-2 will be deduced to as follows: I = (AjDj Cind AjMj TijLijyij) = [Aj(Dj Mj) Cind TijLijyij] nmji,1,1 nmji,1,1 = [Aj(Dj Mj) Cind (Qij/Pij)Lijyij] nmji,1,1 = {Aj(Dj Mj) Cind [Qij/(aijyijCijWij)]Lijyij} nmji,1,1 = {Aj(Dj Mj) Cind [Qij/(aijCijWij)]Lij} Equation 4-3 nmji,1,1

PAGE 59

49 where Mj average unit cost of material on project j Tij work time of resource i on project j Lij cost of unit time for one unit of resource i (other than material) allocated by the subcontractor to project j over period T Qij amount of work with resource i on project j Pij productivity with resource i on project j aij full productivity with resource i on project j yij units of resource i on project j Cij complementarity productivity modifier of resource i on project j Wij work area productivity modifier of resource i on project j (i = 1, 2, 3m; j=1, 2, 3n) The parameters for productivity P are quoted from Equation 3-1 in chapter 3. The parameter on the left side of equation 10 represents the subcontractors profit. The terms on the right hand side of the equation represent income for work performed deducted by cost of materials, indirect cost, and cost of resources except that of materials. For the sake of simplicity, it is assumed that the existing work amount is fixed; material cost and indirect cost are both assumed constant over time period T as well as amount of each resource and cost of unit time for unit resource. Under these assumptions, it can be seen from the equation that the subcontractors challenge in any period T is to set resource units yij that determines complementarity productivity modifier Cij, and work area productivity modifier Wij for each resource on each project to maximize productivity Pij.

PAGE 60

50 The subcontractor will set the quantity of resources applied to each project at each distinct time period. Determination of the correct resource level must take into account not only the expected amount of work that will be made available during the different period and total construction term or schedule, but also the available fixed machine, work area provided by the general contractor, and mutual effects on productivity of resources due to resources allocation to each other. As can be seen, the subcontractors profitability is extremely sensitive to the ratio of the quantity of work that can be performed during the specific period, to the productivity in that period. The subcontractor can reduce this sensitivity by increasing the average productivity across all projects. Sometimes even when some projects are assigned appropriate resources, resource availability on other projects will be diminished by these assignments, so does the productivity. For the subcontractor, the goal is the aggregate benefit with multi-resource across multiple activities in separate projects. From the established model, it is possible to explore the factors that motivate a subcontractor in assigning resources to the various projects. When will a subcontractor increase, decrease, or withdraw resources from any particular project? How do the working conditions influence the behavior of the subcontractor in assigning resources? How does market force affect the ability of a subcontractor to commit appropriate resources to projects? And so on. However, the immediate goal of this thesis should not be able to answer these questions directly. Rather its goal should be to establish an economic and behavioral model of subcontractor decision-making that would enable prediction of the range of decisions that may be made.

PAGE 61

51 Multi-Resource Allocation Case Study Assuming a roofing subcontractor has two projects to build at the same time, one is 6,000 square feet, and the other ones size is 7,500 square feet. Our study focuses on two sorts of crews, membrane crew and insulation crew, working on two projects. The cost for each membrane crew per day is $200, and that for each insulation crew per day is $300. So in this case, membrane crew and insulation crew are two resources needed to reallocate between these two projects. Only one membrane crew and one insulation crew are assigned to Project 1, two membrane crews and 3 insulation crews are assigned to Project 2. As the schedule changes, one membrane crew is shifted from Project 2 to Project 1, and one insulation crew is also moved to Project 1 from Project 2. Due to the interactive affects on construction complementarity and working area on both projects caused by multi-resource reallocation, the change of comprehensive construction costs can be obviously observed. Ignoring the time gap between the two resources applications, both projects are presumed to utilize two different kinds of resources contemporarily. So the multi-resource on these two projects can be described with independent subsets as follows. The resource assignment information is given as follows: Project 1: 6,000 sf to work; 4,000 sf working space; one fixed membrane application machine; one fixed insulation application machine; one membrane crew with an ideal productivity of 1,200 sf/day; one insulation crew with an ideal productivity of 800 sf/day. Project 2: 7,500 sf to work; 5,000 sf working space; one fixed membrane application machine; one fixed insulation application machine; two membrane crews, each of them has an ideal productivity of 1,200sf/day; three insulation crews, each of which has an ideal productivity of 800sf/day. Allocation: respectively moving 1 membrane crew and 1 insulation crew from Project 2 to Project 1.

PAGE 62

52 Figure 4-2. Two resources applications on two projects Meanwhile, influence parameters described in Equation 3-1, i.e., the complementarity modifier and the working space modifier, comply with the following figures. Furthermore, another prerequisite is the ideal unit productivity, for both membrane crew and insulation crew, does not change although crews are reallocated from Project 2 to Project 1. Figure 4-3. Complementarity modifier C in multi-resource allocation case study Before reallocation, the calculation is as follows: For membrane crews: amC1mW1m = 1200x0.8x0.8 = 768 sf/d.each

PAGE 63

53 amC2mW2m = 1200x1x0.4 = 480 sf/d.each Figure 4-4. Working area productivity modifier W in multi-resource allocation case study For insulation crews: aiC1iW1i = 800x0.8x0.8 = 512 sf/d.each aiC2iW2i = 800x0.9x0.4 = 288 sf/d.each am/ai ideal productivity of each membrane crew/insulation crew. C1m/C1i complementarity modifiers of membrane crew/insulation crew on Project 1. It is 0.8 for both membrane crew and insulation crew (respectively 1 crew for the machine) before reallocation. C2m/C2i complementarity modifiers of membrane crew/insulation crew on Project 2. It is 1 for membrane crew (2 crews for the machine) and 0.9 for insulation crew (3 crews for the machine) before reallocation. W1m/W1i working space modifiers of membrane crew/insulation crew on Project 1. It is 0.8 for both membrane crew and insulation crew (respectively 2000 sf space every crew with total 2 crews) before reallocation.

PAGE 64

54 W2m/ W2i working space modifiers of membrane crew/insulation crew on Project 2. It is 0.4 for both membrane crew and insulation crew (respectively 1000 sf space every crew with total 5 crews) before reallocation. So the subcontractors net income before allocation will be: Ibefore = {Aj(Dj Mj) Cind [Qi,j/(ai,jCi,jWi,j)]Lij} 2,21,1ji = {Aj(Dj Mj) Cind [(6000/768 + 7500/480) x 200 + (6000/512 + 7500/288) x 300]} 2,21,1ji = [Aj(Dj Mj) Cind 16200] 2,21,1ji After reallocation: For membrane crews: amC1mW1m = 1200x1x0.4 = 480 sf/d.each amC2mW2m = 1200x0.8x0.75 = 720 sf/d.each For insulation crews: aiC1iW1i = 800x1x0.4 = 320 sf/d.each aiC2iW2i = 800x1x0.75 = 600 sf/d.each C1m/C1i complementarity modifiers of membrane crew/insulation crew on Project 1. It is changed to 1.0 for both membrane crew and insulation crew (respectively 2 crews for the machine) after reallocation.

PAGE 65

55 C2m/C2i complementarity modifiers of membrane crew/insulation crew on Project 2. It is changed to 0.8 for membrane crew (1 crew for the machine) and 1.0 for insulation crew (2 crews for the machine) after reallocation. W1m/W1i working space modifiers of membrane crew/insulation crew on Project 1. It is changed to 0.4 for both membrane crew and insulation crew (respectively 1000 sf space every crew with total 4 crews) after reallocation. W2m/ W2i working space modifiers of membrane crew/insulation crew on Project 2. It is changed to 0.75 for both membrane crew and insulation crew (respectively 1667 sf space every crew with total 3 crews) after reallocation. So the subcontractors net income after allocation will be: Iafter = {Aj(Dj Mj) Cind [Qi,j/(ai,jCi,jWi,j)]Lij} 2,21,1ji = {Aj(Dj Mj) Cind [(6000/480 + 7500/720) x 200 + (6000/320 + 7500/600) x 300]} 2,21,1ji = [Aj(Dj Mj) Cind 14200] 2,21,1ji The subcontractors income from all projects contracts, material cost, and indirect cost are assumed constant no matter which resource allocation way they adopt. Then by comparing net income after reallocation Iafter with net income before reallocation Ibefore,

PAGE 66

56 obviously the fact is the subcontractor will gain more net income than that before reallocation. Iafter Ibefore = [Aj(Dj Mj) Cind 14200] 2,21,1ji [Aj(Dj Mj) Cind 16200] = 2000 2,21,1ji It can be seen that the membrane crew cost on these two projects is $4,600 before crew reallocation. Even after the crew reallocation, the final cost of membrane crews remains at $4,600. The allocation process does not profit the subcontractor on membrane crew cost. However, after crew reallocation, the insulation crew cost on two projects goes up to $11,400 from $9,600. During the two resources allocation, the shift of membrane crew and the insulation crew from Project 2 to Project 1 cuts down the cost of membrane crews, but it indeed lessens the insulation crews competition of utilizing working spaces, and urges them to make the most of construction equipment, and finally shortens the total construction period on these two projects, making further profit for the subcontractor. This impact resulted not only from the allocation of one sort of crew, but also from multi-resource allocation between two projects. Case Study on Multi-Resource Allocation Introduction The multi-resource allocation case study questionnaire was sent out to subcontractors with different disciplines and located in different places. Then the analysis focused on feedback information from those subcontractors that devoted exactly multiple resources to multi different projects. The ultimate target of collecting information from those subcontractors is to see if they adopted multi-resource allocation measures across

PAGE 67

57 their multi-projects, then to evaluate their allocating policies from the subcontractors standpoint if they really adopted some measures on projects. Finally a better allocation method may be found in light of the analysis results. Taken out from feedback information from those subcontractors, two subcontractors are presented here for analysis. One is a painting subcontractor, and the other one is a mechanical subcontractor. The multi-resource allocation case study questionnaire had 3 parts, Part 1 Background Information, Part 2 Questions on Productivity, and Part 3 Evaluation of Resource Allocation. Part 1 asked the recipient to provide background information on its company name, project and resource information, and respective quantities of work with different resources on different projects. Part 2 asked the participant some questions regarding construction productivity. Ten questions were asked for a descriptive response to the possible influence on productivity due to either assigned fixed machine or available working area. This part tried to find affecting factors in the parametric model of resource allocation. Part 3 asked detailed questions about resource allocating criteria, direct cost, and workers shifting information. This part was designed to confirm if the subcontractors actual thinking about the resource allocation complies with the theoretical model discussed in the last two chapters. B&G Painting, Inc. B&G Painting, Inc. was performing painting and wall-covering work on two projects during the same period. It performed 350,000 square feet painting and 7,000 square feet wall covering on project 1; 175,000 square feet painting and 5,000 square feet wall covering on project 2. With sufficient applying of machines and working areas, two kinds of workers might respectively reach the full productivities of 300 square feet per

PAGE 68

58 hour and 15 linear yards per hour, wherever the project is. The painter was paid $40 per hour, and the wall-covering worker could earn $20 per hour. No fixed machine was required to do the painting work, but wall covering workers need pasting machine in the construction process. Each project was provided with a pasting machine. One worker can operate the machine alone, but the productivity would be doubled with two workers. At most four workers could be assigned to use one machine together when the productivity reached the maximum. Each painter needs 10,000 square feet of working space to achieve the full productivity, which would be declined to two-thirds of full productivity with the minimum working space of 1,000 sf. The ideal working space for wall-covering worker is 1,000 sf when they may construct at the fastest speed. At least 500 square feet space is required for each wall-covering worker, but the productivity was only half of full productivity. There were 30,000 sf and 9,000 sf respectively provided for project 1 and 2. The subcontractor does not think too large a work area would de-motivate workers and make them less productive because the company set up daily goals on what should be achieved. In accordance with the situation supplied above, the complementarity figure for the wall covering can be shown: Figure 4-5. Complementarity modifier C for wall covering

PAGE 69

59 Figure 4-6. Working area productivity modifier W for painting Figure 4-7. Working area productivity modifier W for wall covering From the very beginning, B&G Painting, Inc. allocated 5 painters and 3 wall-covering workers on project 1; 3 painters and 2 wall-covering workers on project 2. They did not shift any workers across projects till the completion of both projects. So a total of 8 workers were working on project 1 and 5 workers on project 2. Then the working space for each worker would be 3,750 sf (30,000/8=3,750) on project 1 and 1,800 sf (9,000/5=1,800) on project 2. So the working space modifier W of painting would be deduced to 0.76 and 0.69 for project 1 and project 2 on the basis of Figure 4-7. Every wall-covering workers working area was bigger than 1,000 sf so that the working space modifier of wall covering is 1 for both projects. Because the painter did not need any fixed machine, so the complementarity modifier C for painting is also 1. But it would be 0.75 for wall covering on project 1 with 3 workers and 0.5 on project 2 with 2 wall covering workers. The subcontractors income may be worked out as follow:

PAGE 70

60 For painting: apC1pW1p = 300x1x0.76 = 228 sf/hr.each apC2pW2p = 300x1x0.69 = 207 sf/hr.each For wall covering: awC1wW1w = 15x0.75x1 = 11.25 ly/hr.each awC2wW2w = 15x0.5x1 = 7.5 ly/hr.each I = {Aj(Dj Mj) Cind [Qij/(aijCijWij)]Lij} 2,21,1ji = {Aj(Dj Mj) Cind [(350000/228 + 17500/207) x 40 + (7000/11.25 + 5000/7.5) x 20]} 2,21,1ji = [Aj(Dj Mj) Cind 120998] 2,21,1ji The subcontractor did not reallocate workers between these two projects, so they did not know if their policy of spending $120,998 on labor cost was the best choice or not. Although project 1 was larger than project 2, dense workers on project 1 affected workers productivity. Assuming anther situationreallocate one painter from project 2, also one wall covering worker from project 1 to project 2. Therefore, there would be 4 painters and 2 wall-covering workers on project 1, 4 painters and 3 wall-covering workers on project 2. Correspondingly, the working area modifier W for painting would be changed to 0.81 on project 1 and 0.67 on project 2. Meanwhile, the complementarity modifier C for wall covering also reversed, then there would be 0.5 on project 1 and 0.75 on project 2. What would have happened? For painting:

PAGE 71

61 apC1pW1p = 300x1x0.81 = 243 sf/hr.each apC2pW2p = 300x1x0.67 = 201 sf/hr.each For wall covering: awC1wW1w = 15x0.5x1 = 7.5 ly/hr.each awC2wW2w = 15x0.75x1 = 11.25 ly/hr.each I = {Aj(Dj Mj) Cind [Qij/(aijCijWij)]Lij} 2,21,1ji = {Aj(Dj Mj) Cind [(350000/243 + 17500/201) x 40 + (7000/7.25 + 5000/11.25) x 20]} 2,21,1ji = [Aj(Dj Mj) Cind 119995] 2,21,1ji Comparing two results, it is obvious that the new allocation suggestion would save $1,003 for the subcontractor. With recommended allocating measure, the cost on project 2 would be increased a little. But as the whole plan, the final cost of both projects would be less. Maybe this amount is not a big money resource for the subcontractor in this case, but it might result in a huge loss on the big scale project. With the parametric model as the guideline, allocating 1 painter and 1 wall-covering worker from project 1 to project 2 seems more profitable to the subcontractor. BCH Mechanical Inc. BCH Mechanical Inc. has performed 22,000 linear feet and 34,000 linear feet of pipefitting and plumbing for project 1 and project 2. Both the pipefitting and the plumbing crew need to be equipped with the same welding device to carry out the work. Every set of welding devices can meet the requirements for two crews, either pipefitting

PAGE 72

62 or plumbing. Each worker requires 4000 square feet working space to maximize the productivity, and at least 1500 square feet working space with half of full productivity. The full productivity of the pipefitting crew is 200 linear feet per day, and the plumbing crew can finish at most 100 linear feet per day. These ideal productivities keep same at different projects. Project 1 provided 10,000 sf working area for crews; project 2 provided 20,000 sf. Hourly salaries of crews are $70 for pipe fitters and $50 for plumbers. At the beginning, one pipefitting crew and one plumbing crew with one set of welding device were assigned on project 1, but three pipefitting crews and three plumbing crews with three sets of welding devices on project 2. Being aware of too few crews on project 1, there were one pipefitting crew and one plumbing crew reallocated later from project 2 to project 1, with one set of welding device also shift to project 1. Is this reallocation a good decision? Before allocation: (5000 sf working space for each crew, so the working area modifier is 1 on project 1; 3333 sf working space for each worker on project 2, so the working area modifier W is 0.87.) For pipefitting: apfC1pfW1pf = 200x1x1 = 200 lf/day apfC2pfW2pf = 200x1x0.87 = 174 lf/day For plumbing: apbC1pbW1pb = 100x1x1 = 100 lf/day apbC2pbW2pb = 100x1x0.87 = 87 lf/day Ibefore = {Aj(Dj Mj) Cind [Qij/(aijCijWij)]Lij} 2,21,1ji

PAGE 73

63 = {Aj(Dj Mj) Cind [(22000/200 + 34000/174) x 70 x 8 + (22000/100 + 34000/87) x 50 x 8]} 2,21,1ji = [Aj(Dj Mj) Cind 415344] 2,21,1ji After allocation: (2500 sf working space for each worker, so the working area modifier is 0.7 on project 1; 5000 sf working space for each worker on project 2, so the working area modifier W is 1.) For pipefitting: apfC1pfW1pf = 200x1x0.7 = 140 lf/day apfC2pfW2pf = 200x1x1 = 200 lf/day For plumbing: apfC2pfW2pf = 200x1x1 = 200 lf/day apbC2pbW2pb = 100x1x1 = 100 lf/day Iafter = {Aj(Dj Mj) Cind [Qij/(aijCijWij)]Lij} 2,21,1ji = {Aj(Dj Mj) Cind [(22000/140 + 34000/200) x 70 x 8+ (22000/70 + 34000/100) x 50 x8]} 2,21,1ji = [Aj(Dj Mj) Cind 444912] 2,21,1ji It can be seen that $29,568 more were spent on workers cost. However, the subcontractor just allocated resources according as the superficies of lacking workers on project 1, they did not realize that they would incur more costs. In case they have a parametric model analysis as the guideline, the subcontractor could avoid this kind of

PAGE 74

64 resource allocation across multi projects that might be harmful to the subcontractors benefits.

PAGE 75

CHAPTER 5 CONCLUSIONS This thesis has explored the concept of single-resource allocation across projects for the subcontractor, and derived a concept of multi-resource allocation across projects from a parametric model. The study reported in this thesis focuses on the construction of multi-resource allocation undertaken within a subcontract for the purpose of achieving success in project performance. Based on the results obtained from the study, multi-resource allocation can be defined as an effective scheduling optimization measure. Through rational resources allocation across projects, the whole construction cost can be controlled more effectively with timely completion that satisfies customers. Certainly a great deal of calculation in accordance with the thinking described in this thesis is needed to approach a more optimized solution. Although the applicability of the derived resource allocation model does not take into account all of the influence factors, the analysis has nevertheless demonstrated that appropriately allocating resources across a project increases the probability of perfect project performance and is therefore likely to be cost-effective. This would be of benefit to the top management of subcontracting firms in determining how to achieve cost-effectiveness in resource allocating within the firm. A subcontractor should not be discouraged if he finds one or more areas have significant weakness associated with resource allocation at the present time. The research about multi-resource allocation is still under development, and further research work is 65

PAGE 76

66 being undertaken so that it is hoped that the solution of multi-resource allocation rationality will be more easily refined, evaluated, and implanted.

PAGE 77

LIST OF REFERENCES Antill, J. M., Woodhead, R. W. (1982). Critical Path Methods In Construction Practice. John Wiley & Sons Inc., Sydney, Australia, P157-160. Birrell, G.S. (1980). Construction Planning Beyond the Critical Path. ASCE Journal of the Construction Division, 106(C03), 389-407. Chaker, A. A. (1973). Optimal Scheduling and Resource Allocation in Project Networks. Dissertation for Ph.D., University of Illinois at Urbana-Champaign. Chinowsky, P. S., and Meredith, J. E. (2000). Strategic Management in Construction. ASCE Journal of Construction Engineering and Management, 126(1), P1-9. Dodge, F.W. (2005). Construction Up. Accessed March, 2005. http://www.architecturalwest.com/FW_Dodge/fw_dodge_1_05.htm Faniran, O. O., Love, P. E. D., and Li, H. (1999). Optimal Allocation of Construction Planning Resources. ASCE Journal of Construction and Management, 125(5), P311-319. Giggard, R. (2005). Economy Sputters Toward Recovery. Construction, V72, i2, P4. Hegazy, T. (1999). Optimization of Resource Allocation and Leveling Using Genetic Algorithms. ASCE Journal of Construction Engineering and Management, 125(3), P167-175. Hegazy, T., and Ersahin, T. (2001). Simplified Spreadsheet Solutions I: Subcontractor Information System. ASCE Journal of Construction Engineering and Management, 127(6), P461-468. Hegazy, T., and Ersahin, T. (2001). Simplified Spreadsheet Solutions II: Overall Schedule Optimization. ASCE Journal of Construction Engineering and Management, 127(6), P469-475. Hegazy, T., Shabeeb, K., Elbeltagi, E., and Cheema, T. (2000). Algorithm For Scheduling With Multiskilled Constrained Resources. ASCE Journal of Construction Engineering and Management, 126(6), P414-421. 67

PAGE 78

68 OBrien, W. J. (2000). Multi-Project Resource Allocation: Parametric Models and Managerial Implications. Presented at Eighth Annual Conference of the IGLC, University of Sussex, Brighton, UK, P11. OBrien, W. J, and Fischer, M. A. (2000). Importance of Capacity Constraints To Construction Cost And Schedule. ASCE Journal of Construction Engineering and Management, 126(5), P366-373. Yang, B., Geunes, J., and OBrien, W. J. (2002). A Heuristic Approach for Minimizing Weighted Tardiness and Overtime Costs in Single Resource Scheduling. University of Florida, Gainesville, FL.

PAGE 79

BIOGRAPHICAL SKETCH Chuan Song was born in Beijing, China. He graduated from Beijing University of Technology (formerly named Beijing Polytechnic University) with a bachelors degree in civil engineering. He attended graduate school at the M.E. Rinker, Sr. School of Building Construction at the University of Florida in 2003, graduating with a Master of Science in Building Construction in 2005. 69


Permanent Link: http://ufdc.ufl.edu/UFE0011878/00001

Material Information

Title: Multi-Resource Allocation across Multi Projects by Subcontractor
Physical Description: Mixed Material
Copyright Date: 2008

Record Information

Source Institution: University of Florida
Holding Location: University of Florida
Rights Management: All rights reserved by the source institution and holding location.
System ID: UFE0011878:00001

Permanent Link: http://ufdc.ufl.edu/UFE0011878/00001

Material Information

Title: Multi-Resource Allocation across Multi Projects by Subcontractor
Physical Description: Mixed Material
Copyright Date: 2008

Record Information

Source Institution: University of Florida
Holding Location: University of Florida
Rights Management: All rights reserved by the source institution and holding location.
System ID: UFE0011878:00001


This item has the following downloads:


Full Text












MULTI-RESOURCE ALLOCATION
ACROSS MULTI PROJECTS BY SUBCONTRACTOR

















By

CHUAN SONG


A THESIS PRESENTED TO THE GRADUATE SCHOOL
OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT
OF THE REQUIREMENTS FOR THE DEGREE OF
MASTER OF SCIENCE IN BUILDING CONSTRUCTION

UNIVERSITY OF FLORIDA


2005

































Copyright 2005

by

Chuan Song
































This document is dedicated to my lovely grandparents in the remote country. And it is
also dedicated to my family for their unconditional support.















ACKNOWLEDGMENTS

I would like to thank Dr. William O'Brien as my committee chair for his help to me

during the preparation of this thesis. I would like to thank Dr. Rayment Issa as my

committee co-chair for his help on the case studies. Also I would like to express

acknowledgement to my committee members for reviewing my thesis. Special thanks

also go to professionals from the companies that responded to my questionnaire.
















TABLE OF CONTENTS

page

A C K N O W L E D G M E N T S ................................................................................................. iv

LIST OF TABLES .........._ ......................................... vii

LIST OF FIGURES ................. ....................... .... .................... viii

A B ST R A C T ......... ............................................................................... . x

CHAPTER

1 IN T R O D U C T IO N ............................................................... ................ .... 1

G general .................. ................................... ................ ................ ..... .
Introduction of Scheduling Optimization Concepts ................................................ 3
Problem Statem ent ......................................................................... .. ......... 6
Scope and Lim stations ........................................ ..... ...................6

2 L IT E R A TU R E R E V IE W ......................................................... ............................... 7

B asic C on cepts.............................. ...................................................... ............... 7
R source C onstraints ................................................................. .............. .. 7
R source A location .................... .............................. .. ........ ................ .9
Construction Costs.................... .. ...................... ....... 10
In dep en dent Sub set............. ........... .................................. ...... ..... ....... ... 12
Perspectives of Application to Multi Projects By Subcontractor.............................16
W hy M ulti P rojects....................................................................... ........ 16
W hy Subcontractor .............................................................. ............. ..... 17
O their L literature ............................................. .............. ........... 18
Models of Subcontractor's Construction Costs .....................................................19
Tardiness and Overtime Cost Model ............ ..........................................19
P aram etric Influence M odel ....................................................... ....................22
S u m m ary ......................................................... ............... ................ 2 3
Critique and Current State of Literature ......... ..............................................23
Research N eeds .................................. ... .. ........ ......... ... 25

3 SINGLE RESOURCE ALLOCATION ACROSS PROJECTS................................ 27

Presum option ............................................. 27



v









Resource Shifting Within Independent Subset................ .....................27
T otal C construction C osts ............................................. ............................ 29
Parametric Models of Single Resource Allocation.........................................31
Indirect Cost and Direct Cost .................. .............. .....................31
O th er C o sts ................................................................ 3 4
Case Study ......... ..... ...... .. ............... ........ ..... ...............34
Model 1 Labor (crew) allocation................... .... ..............34
Model 2 Equipment (flexible resource) allocation............................. 38
Su m m ary ......................................................................................... 4 0

4 MULTI-RESOURCE ALLOCATION ACROSS MULTIPLE PROJECTS ........... 41

Environment for Multi-resource Allocation Across Multi Projects .........................41
Significance of Independence Subset in Multi-Resource Allocation......................44
M ulti-Resource Allocation Parametric M odel .................... ..............................47
M ulti-R source A location Case Study ........................................... .....................51
Case Study on M ulti-Resource Allocation ...................................... ............... 56
In tro d u ctio n ................................................................................................... 5 6
B & G Painting, Inc. ...................... ................ ................. ..... ...... 57
B C H M echanical Inc. ................................................... .. ........ ...... ............6 1

5 CON CLU SION S ......... ........................ .... .............. .... ..... .... 65

L IST O F R E FE R E N C E S ...................................................... ...................................... 67

BIO GRAPH ICAL SK ETCH .......................................................... ... .............. 69
















LIST OF TABLES

Table pge

3-1 Resource allocation comparison in Case 1.................................... ............... 37

3-2 Resource allocation comparison in Case 2.................................... ............... 40

















LIST OF FIGURES


Figure pge

2-1 Construction costs com position.. ......................... ............................................. 11

2-2 Graphic illustration of property of independent subset........................................13

2-3 Graphic illustration of formation of a new independent subset from two
consecutive independent subsets............................................ ........ ....... 16

2-4 Total cost curve as a function of overtime utilization under the compact and
relax procedure. ........................................................................2 1

2-5 Complementarity (flexible/fixed resources ratio) modifier curve............................23

2-6 W ork area m odifier curve ............................................... ............................. 23

3-1 Illustration of resources shift in the independent subset............... ..................28

3-2 Construction costs in independent subset i ................................... ............... 30

3-3 Complementarity modifier C in M odel 1 ...................................... ............... 35

3-4 Work area productivity modifier W in Model 1 ................... ............................. 36

3-5 Complementarity modifier C in M odel 2...................................... ............... 38

3-6 Work area modifier W in Model 2 ......................... ............... 39

4-1 Illustration of multi-resource allocation across projects..................................45

4-2 Two resources applications on two projects........................... ...........................52

4-3 Complementarity modifier C in multi-resource allocation case study...................52

4-4 Working area productivity modifier W in multi-resource allocation case study .....53

4-5 Complementarity modifier C for wall covering.....................................................58

4-6 Working area productivity modifier W for painting ............................. 59









4-7 Working area productivity modifier W for wall covering .............................59















Abstract of Thesis
Presented to the Graduate School of the University of Florida
in Partial Fulfillment of the Requirements for the
Degree of Master of Science in Building Construction

MULTI-RESOURCE ALLOCATION
ACROSS MULTI PROJECTS BY SUBCONTRACTOR

By

Chuan Song

August 2005

Chair: William O'Brien
Cochair: Raymond Issa
Major Department: Building Construction

Due to the limitation of resources on construction projects, the subcontractor will

shift multi resources fluidly within projects or across projects to meet resource demands.

During the multi-resource allocation procedure, some factors influencing the cost have to

be considered such as the change to existing conditions and the collaboration across

projects.

The research has been conducted in this area. Some influence factors are identified

to establish a model to figure out productivity change and help allocate various resources.

Then the original resource allocation schedule can be improved so as to reduce the

subcontractor's total construction cost.

The objectives of this thesis are to discuss the effects of multi-resource allocation

and determine how to reach a better multi-resource allocation approach by a

mathematical model.














CHAPTER 1
INTRODUCTION

General

The construction industry is one of the driving industries in the economy. Through

the first ten months of 2004, the total construction on an unadjusted basis came to $495.3

billion, up 9% from the same period in 2003. The 9% increase for the total construction

during the January-October period of 2004, compared to 2003, was due to this

performance by sector residential building, up 16%; non-residential building, up 3%.

By geography, the total construction in the first ten months of 2004 was the following-

the South Atlantic, up 13%; the West, up 12%; the Northeast and South Central, each up

7%; and the Midwest, up 4% (Dodge, 2005).

Recognizing the economy growth rate in 2004 has settled to 4.4 percent that is

above the historical trend, a booming construction market is expected in the year 2005.

Residential improvements are forecast to remain strong, fueled by higher new home

prices, and a scarcity of buildable land in many markets. The nonresidential segment will

accelerate to a growth rate of 6.0 percent in 2005, equaling the growth rate in the

residential markets. On the other hand, inflation is back on the radar screens of both the

central bank and the financial markets. The Consumer Price Index (CPI) jumped up 2.0

percent toward the end of 2004, the highest reading of the year. Prices for construction

products and materials became a major issue throughout 2004. The cost of certain steel

products and wood panel products rose by 150 percent or more, with limited availability.

Gypsum, structural lumber, cement, copper, and PVC all showed major increase. In the









case of steel, a strong foreign demand (e.g., from China), limited domestic capacity, coke

shortages, and a limited number of available ships will keep up price pressures. Similarly,

a shortage of cement is expected to result in the price going even higher (Giggard, 2005).

So for the subcontractors, construction resource allocation optimization has a significant

impact on the ability to achieve success in the implementation of construction projects.

Although research in construction management and practitioners in the construction

industry realize the importance of resource allocation across construction projects, there

is still a divergence of opinion on how much effort should actually be invested in

construction resource allocation activities to obtain a better performance during the

construction period, and how much benefit the subcontractor may obtain through these

reallocated resource activities. Moreover, even now some subcontractors are indeed

reallocating resources at some degree in construction, they just make decisions with their

experiences, without a systematic method that can take into account the actual external

conditions as much as possible, and then can assist subcontractors to adjudge the situation

impersonally.

The objective of construction resource allocation is to find a way that is consistent

with specified resource limits, as well as profiting subcontractors the furthest and

matches up with the schedule. It is necessary for the subcontractor to plan overall plans

for multi projects and take all factors into consideration to obtain the maximum profits.

Sometimes they would have to change the existing resource allocation plan. The result of

planning as a whole is that some projects may not have the shortest construction duration;

meanwhile other projects may take too much resource than the average level. The









subcontractor's ultimate objective however is to lower construction costs, and improve

profit margin, with a fixed total amount of resources.

In this thesis, an attempt is made to develop a practical approach that presents a

near-optimum solution to allocating finite construction resources among projects in the

standpoint of the subcontractor. The thesis starts with a brief description of the resource

allocation problem. The impact of resource allocation on construction cost is then

proposed, approaching consequent tardiness and overtime costs. Followed by

optimization applications in both single project and multi-projects, parametric models are

addressed to figure out the productivity change and the corresponding results in different

costs and profits, taking into consideration the resource situations. The multi-resource

project's guideline is evolved by the optimization implementation. The performance of

the proposed approach is then evaluated, and recommendations made.

Introduction of Scheduling Optimization Concepts

As we know, scheduling is a matter of great concern in construction. Resource

allocation is one of the scheduling optimization methods. Optimization problems in

construction scheduling are traditionally classified into the following categories

depending on the objectives: (1) time-cost tradeoff; (2) resource leveling; and (3)

resource allocation (Hegazy, 1999). What is the difference? What specific characters for

resource allocation?

Time-cost tradeoff is concerned with minimizing the project cost while maintaining

the desired project duration. Resource leveling is concerned with minimizing peak

resource requirements and period-to-period fluctuations in resource assignment while

maintaining the desired project duration. Resource allocation is concerned about

minimizing project duration without exceeding the available resource limits.









Normally the subcontractor has more than one project to work ongoing. Each

construction project is composed of a network of activities. Each activity in a project has

a corresponding duration. The project duration is usually measured in integral increments

of time called independent subsets (that will be elaborated in Chapter 2 Literature

Review) each of which consist of certain activities. The normal duration of an activity

refers to the time required to complete that activity under normal circumstances.

Meanwhile the construction cost of an activity or a project is somewhat associated with

its construction duration. Normally, corresponding to the reduction in activity/project

duration is an increase in direct cost, and in contrast a decrease in indirect cost. For some

activities and projects, it is possible to reduce their duration below the normal duration.

This is done through some measures called crashing. Some ways by which crashing is

achieved include overtime, additional manpower, equipment and/or other resources, and

the use of better skilled men and/or improved technology. Crashing with resource

allocation is done as a tradeoff between resource, duration, and cost. But on the basis of

limited resources, considering both the direct cost and the indirect cost in construction,

the comprehensive total cost maybe maintained at the same level, perhaps even lower,

with shorter activity duration. This study is to determine the best one during the period of

optimizing resources.

On the other hand, resource allocation attempts to reschedule the project tasks so

that the existing resources can be efficiently utilized while keeping the modified

construction schedule does not exceed the required construction duration. At present few

companies can remain competent in today's highly competitive construction industry









environment without effectively managing their resources, particularly the allowable

adjusted resources.

Concerning the resource allocation, the basic PERT (Program Evaluation and

Review Technique) and CPM (Critical Path Method) scheduling techniques in practice

have proven to be helpful only when the project deadline is not fixed and the resources

are not constrained by either availability or time, assuming that the resources are neither

able to flow from one activity to another activity, nor flow among different projects. As

this is not practical even for smaller sized projects, the resources in construction are

basically fixed in quantity, and resource allocation has been used to achieve a near-

optimum result in relation to practical considerations, allowing the resources to shift

among activities and projects.

An activity or a project can have any duration between the normal and crash

duration. However, one subcontractor normally has a cluster of ongoing activities or

projects. The subcontractor needs to comprehensively analyze the different resource

allocation schemes, then find a most profitable one and work out the lowest construction

cost accordingly.

Due to the complexity of construction projects, time-cost tradeoff and resources

allocation have been dealt with as two distinct sub-problems that cannot guarantee

optimum solutions. In this thesis, a proposal is addressed to time-cost tradeoff and

resource allocation, considering both aspects simultaneously. In other words, resource

allocation is used to adjust the schedule and solicit the optimal tradeoff between the

duration and the cost, so that the final objective is to find the schedule by which the









contractor is able to supply the project in demand as well as reach the maximum profit at

a lower cost.

Problem Statement

The goals of this study include the following:

* Presenting a thorough literature review on the effect of resource allocation on the
schedule duration and the construction cost.

* Identifying the relevant external influence factors.

* Presenting some hypothetic models and conduct case studies to demonstrate
validity of the models.

* Outlining the future extensions.

Scope and Limitations

Due to limited time and access of information, the initial study focused particularly

on some major kinds of resources. The other resources are not mentioned in this thesis.

Also the case studies only happened to subcontractors with labor allocation.

Since resource allocation may follow different development steps and patterns in

other countries, the literature review focused on scheduling the development and

application of methods in the United States.

Responding to the above-mentioned restrictions, the scope of this study has been

set as the following:

* The literature review reflects construction resource allocation characteristics and its
applications in the United States. Other possible characteristics that may seem
evident in other countries are not included.

* Because of a variety of resources depending on the specific fields, this thesis only
addresses the problem of some sorts of major resources often encountered in
construction projects. The other possible resources are not analyzed in detail. The
hypothetical model is established on the basis of these major resources.

* The case study was only done to subcontractor located in Florida and Arizona. The
viewpoints will be more applicable if more subcontractors are investigated.














CHAPTER 2
LITERATURE REVIEW

The objective of this literature review is to define the basic concepts in this thesis,

and introduce methods and models proposed in earlier literature that would be a starting

point for this research about resource allocation. This chapter will also try to collect

information on the application and development of resource allocation in both single-

resource and multi-resource projects in reviewing the relevant application of optimization

by the methods in kinds of resource allocation. At the end of this literature review,

research needs will be generalized to start the research methodology design, data analysis,

and conclusion in a later chapter.

Basic Concepts

The research in the past decades supplied a large number of publications about the

resource allocation and the construction cost change as a consequence of resource

allocation. Some basic concepts resulting from this past research are relevant to the study

in this thesis. It is necessary to discuss them first.

Resource Constraints

Typical resources that have appeared in construction include a rented piece of

equipment that needs to be returned early, a number of skilled workers or crews who

need to be hired for the job, some amount of material that needs to be used in the project,

and proper working spaces where the project can be operated, and so on.

For complexity reasons, construction scheduling is a critical process of assigning

activities to resources in time. However, a variety of constraints affect this process, so









that scheduling actually is a decision-making process-the process of determining a

schedule. Normally a project construction is affected by constraints as follows: activity

durations, release dates and due dates, precedence constraints, transfer and set-up times,

resource availability constraints (shifts, down-time, site conditions, working spaces, etc.),

and resource sharing. These constraints define the space of admissible solutions.

It has been acknowledged that the use of constraint-based techniques and tools

enables the implementation of precise, flexible, efficient, and extensible scheduling

systems: precise and flexible as the system can take into account any constraint. Critical

Path Method (CPM) is the basic scheduling solution and widely applied to the

construction field. But CPM scheduling computations do not take into consideration

resource constraints. However we can see that in most practical situations the availability

of resources is limited. The assumption of unlimited resources is unrealistic and may

result in unfeasible solutions. In addition to the CPM approach, the Time-Cost Trade-off

(TCT) approach is criticized for being incapable of representing the capacity costs and

constraints of subcontractors and suppliers to resolving changes in schedule. Capacity

constraints and poor site conditions cause subcontractors and suppliers real costs, which

managers should take action to mitigate, and also suggested incorporate site conditions

and capacity constraints into construction planning and scheduling techniques (O'Brien

and Fischer, 2000).

Other scheduling methods such as resource leveling, overtime, etc. also have this

shortcoming mentioned above. As a matter of fact, resources are flexible and allowed to

shift in a reallocating method. If resources are superfluous at some time period, slack

resources can be shifted to other activities or projects where more resources are needed so









as to save money for the subcontractor as well as speed up the lagging projects. Actually

even when resources are not excessive, they still may be allocated to critical activities or

projects where time can be bought cheapest while maintaining resource feasibility.

Efficient reallocation of resources for construction planning activities possibly may

reduce the duration of activities below the normal duration even in a lower cost.

Resource Allocation

Resource allocation is one of the new scheduling approaches developed in the past

decades. It constitutes another important class of scheduling methods. Through

mobilization and shift of constrained resources across activities in construction projects,

even across different projects, it is an attempt to seek a more realistic scheduling method,

having the minimization of both project duration and total project cost as its goals.

In the practical construction environment that subcontractors operate within,

resources must be allocated to multiple jobs in activities, even to multiple projects

because of limited resources. Very often resources must be allocated in conditions of

competing demand and uncertainty about project schedule. Subcontractors will shift

resources fluidly among the jobs, activities, or across projects to meet demands, trying to

find low cost allocations within a project or across projects.

Because resource allocation is supposed to solve a more practical schedule,

incurring a substantial portion of the cost of the project and significantly affecting its

duration, it has therefore received a great deal of attention from researchers. So resource

allocation is becoming a very popular measure to control total construction costs,

especially preferred by subcontractors. Many scholars mentioned resource allocation as a

scheduling optimization method in the huge volume of literature over the years. Birrell

(1980) was the first author to consider the implication for project uncertainty and change









on the cost and resource allocation of subcontractors and suppliers and the need for

consideration of resource constraints when coordinating schedule alternatives.

Subsequent empirical work has demonstrated that subcontractors and suppliers routinely

reallocate resources among jobs, activities, and projects on a daily basis (O'Brien and

Fischer, 2000). Hegazy (2000) developed solutions that mathematically illustrate

scheduling with certain constrained resources.

Construction Costs

The final objective of scheduling and resource research is to determine which

resource allocation will give the best overall economical solution. Then what are the

compositions of project costs? The costs caused by construction activities are easily

understood as the direct cost, which may be expected to dominate each operation in the

form of material costs, labor costs, equipment costs, etc. Especially with the contract

system, direct cost is critical when the work may be completed at the lowest total cost.

However, the project direct cost does not represent the full cost of the work. Besides

direct cost, the total cost must be added to all the other indirect costs of the project such

as overhead charges, payment to office staff, etc.

Because both direct cost and indirect cost are associated with the complete

execution of the work, and proportional to time, they jointly elaborate the derivation of

the total project cost curve. The solution to the cost problem is: all costs vary with

duration and direct costs tend to decrease if more time is available for an operation, but

indirect costs will increase with time (Antill and Woodhead, 1982). See Fig. 2-1 for an

illustration of this point.

For the direct cost, the least duration will result in the highest cost while the lowest

costs will be spent with the available longest project duration. Moreover, the direct cost









curve is concave and the magnitude of its slope decreases monotonically with increased

project duration (Chaker, 1973). Any project schedule is feasible between the least time

duration and the normal duration, even the duration with tardiness.






Optimal costs amea
t Total project cost


I Direct project cost

SI Indhirect project cost





Project Duration

Figure 2-1. Construction costs composition. Total construction cost consists of direct cost
and indirect cost. Indirect cost is basically linear proportional to project
duration. Extremely short or excessively long project durations make direct
cost higher.

The indirect costs are estimated by the planner in a conventional way and vary with

different project completion times. Usually they vary almost directly with project

duration. Only making out the needed indirect costs for the normal or tardiness duration

solution and for one other duration such as the least time duration solution, a straight line

variation will be derived between these two points.

In general, the project total cost curve may be figured out by simply adding two

cost curves at any desired duration on the diagram. Of course the direct cost curve has a

fluctuation range with the different resource conditions and other constraints. Then from

Fig. 1, a minimum total project cost is immediately found. This is the most economical









solution for the project. In practice, it is unlikely that a subcontractor can always reach

this optimal point. If construction cost is within a range adjacent to the minimum point,

the projects will be profitable enough. In other words, the objective of allocating

resources across projects is to make sure the cost is in such a scope; also, the

corresponding durations are acceptable.

Independent Subset

It was mentioned before that the project duration is usually measured in integral

increments of time called independent subsets, each of which consist of certain activities

or projects. The notion of independent subset was introduced to effectively avoid the

disorder possibly aroused by coincidence of too many activities or projects (Yang et al.

2002). It is necessary to arrange so many activities and projects, which happened on a

subcontractor and interlaced to each other, in order of time.

They proposed an approach that assumed that all activities or projects carried out

by a subcontractor are not absolutely available for processing effectively at time zero.

They took into account the project planning and activities sequences controlling. A

subcontractor generally has several ongoing projects, and a practical construction project

consists of dozens or even hundreds of activities. Every activity or project has its

duration, resources needed in construction, and costs used to guarantee the processing of

this activity/project. Considering the possibility of processing many activities, even many

projects at the same time, everything will be interlocked if activities are assumed to be

available along the scheduling horizon. It will become too complicated and desultory to

allocate resources across activities or projects, and further to work out the resulting

duration and costs. So the tone is set for the basic research entity-Independent Subset.









For any schedule of projects, an independent subset of project satisfies three

definitions: (1) the release date of the first job in the subset is strictly greater than the

completion date of the job's immediate predecessor; (2) the completion date of the last

job in the subset is strictly less than the release date of its immediate successor; (3) no

unscheduled regular time exists between the start of the first job in the subset and the

completion of the last job in the subset. (Yang et al. 2002). See Fig. 2-2 for property of

the independent subset.

Resource Usage


Independent Independent Subset 2 Independent Subset 3
Subset 1

R + .......... .. .. .



Time

Figure 2-2. Graphic illustration of property of independent subset (Yang et al. 2002).

In Fig.2-2, the time horizon length represents the schedule time for a specific

resource. Independent subsets on this time horizon actually are a series of activities or

projects applicable to one kind of resources. Once the duration and costs of every

independent subset-activity or project-are obtained, the necessary duration and

construction costs with this specific resource will consequently be received. Each

independent subset, i.e., the block along the time horizon, is composed of several

activities or projects. All of them are processed in accordance with a predetermined

sequence. For example, we have scheduled the first project in an independent subset to

complete on day ti, and the next job in the sequence, i.e., the second project, has a release









date of t2, with t2 = tl + k, where k is a nonnegative integer greater than 1, then no jobs

are scheduled on days ti + 1, ti + 2, ..., ti + (k-1) in the original schedule, and so on.

After reallocating the resource within the independent subset, several adjustments must

be made. Some jobs have longer durations, but some of them have shorter construction

durations. Accordingly the independent subset's durations and costs will change for the

whole project as well.

It is important to note that the definition of an independent subset does not preclude

an independent subset consisting of a single job or an independent subset consisting of all

jobs to be scheduled, which occurs, for example, when all release time equals zero. For

instance in the case illustrated in Fig. 2-2, there is only one activity/project in

Independent Subset 1. But Independent Subset 2 comprises 4 activities/projects, and 3

activities/projects in Independent Subset 3.

In Fig.2-2, R represents regular processing time, and D represents overtime. These

two notations may be regarded as a form of construction resource in this thesis. They are

shifted across activities or projects so as to optimize the original schedule and make more

profits. The problem is to schedule a finite set of activities or projects with a single

resource during some finite time horizon of length T. Here the processing time is used to

elaborate the concept of independent subset. Each activity or project has an available

processing time of R during regular time, plus an additional amount of time D, for

overtime. Both of them are period independent. So the total amount of processing time

available in a given period can be expressed as R+0.

Assuming that the resource is set available in each period R+1, the original

schedule consists of m independent subsets, where m is a positive integer. Suppose index









these subsets in order of increasing start time (i = 1, 2, ..., m). If m = 1, then simply apply

resource allocation among jobs within this subset. If m > 1, then apply resource allocation

individually to jobs of each independent subset, then apply to all independent subsets to

one another from 1 to m.

Some independent subsets are flexible. They are possibly combined into a new

independent subset under a certain condition. This procedure may be realized through

two phases-compacting phase and relaxing phase. Firstly compacting phase is to fully

utilize all available overtime in any period to make out a corresponding schedule. Then in

relaxing phase, the total amount of overtime used in every period (beginning with the

latest scheduled job that uses overtime and working backwards in time) is sequentially

decreased. Except subset m, other independent subsets may become "blocked" in

applying the relaxing phase to an independent subset, when the completion time of the

last job in the subset reaches the period immediately before the starting period of the next

independent subset, and also exhausts all regular time in the period. If independent subset

i does become blocked by subset i +1, then the two subsets i and i + 1 merge into a single

new subset. The new merged subset must satisfy the conditions required in the definition

of an independent subset. Figure 2-3 below provides an example of one independent

subset blocking another in the resource allocation phase, producing a new independent

subset.

The above figure provides an example of one independent subset blocking another

in the phase of reducing overtime, producing a new independent subset. The utilization of

other kinds of construction resources such as materials, labors, etc. is somewhat

analogous to that of processing time expatiated above.









Resource
Utilization

Independent Subset 2 is "blocked" by 3,
Independent and Independent Subsets 2 and 3 merge
Subset 1 into a new Independent Subset






Time


Figure 2-3. Graphic illustration of formation of a new independent subset from two
consecutive independent subsets. Independent subset 2 is blocked by
independent subset 3, and then merged with independent 3 into a new bigger
independent subset.

Perspectives of Application to Multi Projects By Subcontractor

The study of this thesis focuses on the resource allocation application to multi

projects constructed by subcontractor. It is believed that the resource allocation is

exerting markedly on multi projects, particularly by subcontractor.

Why Multi Projects

Because of the resources finites, subcontractors need to maintain a resource

demand balance across many projects. The environments and projects require the

allocation of materials, labor, equipment, and other resources to complete a set of

construction projects that change over time.

Subcontractors will shift resources fluidly across projects to meet demand, seeking

to optimize productivity across projects. Choices about resource allocation are perhaps

the most important operational decision that subcontractors make. The ability to shift

resources across projects is a key component of flexibility. Subcontractors, unlike

suppliers, have limited ability to buffer production by producing ahead of schedule and

respond to changes on projects by reallocating resources (O'Brien, 2000). A parametric









model relating productivity, site conditions, and resource allocation to a work package

was described, and implications of the model were discussed when considering multi-

project resource allocation.

Due to increasingly intense international competition, construction firms are

constantly undertaking multiple projects while they might leverage their resource

investments in order to achieve economical benefits. Accordingly, the perspective of

multiple projects scheduling has become a critical issue for competition. Regardless of

the number of projects, the final objectives for all projects are to strive for minimum total

completion time, minimum total costs, and maximum resource usage efficiency.

Generally speaking, multiple project scheduling is an area where traditional

methods and techniques appear to be less adequate.

Why Subcontractor

Subcontracting has become prevalent in the construction industry, and presented as

an organizational alternative for some economic activities. Construction firms are

dispersing their jobs more and more, as subcontracting becomes a basic part of the work

organization.

The reasons why subcontracting prevails may be summarized as follows:

increasing sophistication and specialization of trades, which requires long-term

investment in personnel and equipment; increasing prefabrication off site, which

similarly requires large-scale investment in fixed facilities; fluctuating demand for

services of general construction contractors, which demands agility in adjusting capacity

(Sacks, 2003).

Nowadays, in order to reduce costs, construction firms do not need to have control

of all the value string. By subcontracting, they are able to externalize non-strategic









activities, realizing the aim of costs reducing. Building firms are organized into a

consistent operating core based on their individual capabilities. More and more

construction companies are becoming construction managers or contractor managers after

transferring construction jobs to specialists. Meanwhile, subcontractors are specialists in

the execution of a specific task. They may supply manpower, materials, and equipment as

well as designs and techniques.

In the United States, currently in many projects, it is common for 80-90% of the

construction work to be performed by subcontractors. They perform construction work

that requires skilled labor from one or at most a few specific trades and for which they

have acquired both special-purpose resources and process know-how.

Other Literature

The project scheduling literature contains a variety of work dealing with multi-

project and subcontractors' problems. Not meant to be exhaustive, this review is limited

to some relevant technologies about resource allocation. While some research considers

only one type of resource, some models are only with stated resource constraints, some

with single resource, and some with multi resources, and the diversity reflects the

complexity of the reality. This chapter tries to tie together widely scattered ideas and to

assess a resource allocation model in a simple and generalized form.

Sacks (2003) proposed a model of a multi-project and multi-subcontracting

paradigm. He tried to identify ways to align a subcontractor's benefit and better

understand workflow from the subcontractors' point of view. Adopting the

subcontracting, and researching problems faced by subcontractors, the ultimate goal is

the total amount of benefit achievable by both general contractors and subcontractors

across multiple projects.









O'Brien (2000) presented a model associated with site conditions, resource

allocation and productivity, allowing quantitative assessment of the impact of shifting

resources across projects. Use of the model for multi-projects resource allocation decision

was discussed, and several implications for subcontractor and site management were

developed.

Hegzy (2000) addressed the algorithm for scheduling with multi-skilled constrained

resources. Hegzy (2001) also presented Subcontractor Information System that supports

the estimating and project control functions of subcontractors.

Models of Subcontractor's Construction Costs

Tardiness and Overtime Cost Model

Flexible preference constraints characterize the quality of scheduling decisions.

These preferences are related to due dates, productivity, frequency of changes, inventory

levels, overtime, etc. Since preference constraints may conflict with one another, the

resolution of a scheduling problem also consists in deciding which preferences should be

satisfied and to what extent others should be relaxed.

In practice, however, preference constraints are often either combined into a unique

evaluation or cost function to maximize or minimize, or compiled into evaluation

heuristics to favor candidate solutions that satisfy the preferences.

A heuristic approach was tried to minimize weighted tardiness and overtime costs

in single resource scheduling. The tardiness costs and overtime costs, as the constraints,

are collaborative and considered to satisfy while the scheduling solutions are eventually

gained (Yang et al. 2002). A solution to the scheduling problem is a set of compatible

scheduling decisions (such as performing the project as soon as possible after tardiness









and overtime costs are generated), which guarantee the satisfaction of the constraints, i.e.,

minimizing the sum costs of both constraints.

The previous literature normally assumed each job took a certain fixed amount of

time on the resource, and that both processing times and resource usage can be measured

in some continuous time increments, also an assumption exists that the cost of processing

activities is the same no matter when the activities are processed, the amount of available

processing time in each processing period is fixed. In the paper mentioned above, Yang,

Geunes, and O'Brien thought the primary method the contractors employ to meet due

dates of the project was through the use of overtime. So they tried to overcome the

defects in the previous research to direct the construction with a tradeoff of tardiness cost

versus the use of overtime (Yang et al. 2002).

A model was made to simulate the overtime-tardiness problem. In the model,

compacting was the first step that made out a corresponding schedule by fully utilizing all

available overtime in any period. The created schedule guarantees the minimum total

tardiness costs under the fixed sequence, but with a high overtime costs. Then a relaxing

phase was carried out-sequentially decreasing the total amount of overtime used in that

very period (beginning with the latest scheduled job that uses overtime and working

backwards in time). The total amount of relaxed overtime is a function of whether the

relax phase produces a lower total cost schedule, so that the optimal sequence of jobs, the

start date, finish date, and overtime usage for each job were able to be determined.

Basically the overtime cost is the increment with a fixed amount every overtime

unit (hour, day, week, month...). So it can be seen that the overtime cost is linear in

overtime resources utilization. For the tardiness cost, it keeps stable within one time










interval, e.g., the daily penalty or the weekly penalty is a fixed amount within one

day/week. The construction term of the project will not be reduced by one day or one

week unless the accumulated overtime utilization reaches a certain amount. That means

the tardiness cost decrease is a stepwise decrease to total overtime usage instead of a

linear relationship to the overtime usage. Therefore, the total cost function is the sum of a

linear function and a stepwise decreasing total tardiness cost function. The resulting total

cost curve is shown as the saw-tooth curve in the following Fig. 2-4.






Costtal Cost




I |
o Overtime Cost



I i--Tardiness Cost
I I
I ______(1) _
6 (2) Overtin e
M, Utilization
6(3)


Figure 2-4. Total cost curve as a function of overtime utilization under the compact and
relax procedure. (Yang et al. 2002)

The tardiness cost for an activity determines the amount of cost decrease at each of

the steps in the curve, while the overtime cost per unit time, co, determines the rate of

increase after each step. The compact and relax algorithm evaluates the cost at the bottom

of each spike on the saw-tooth curve, then finally a minimum total cost for the predefined

sequence of jobs might be obtained.









Overtime and due date were presented for the representation of constraints and

subsequently a solution was figured out to satisfy these constraints, by resource

allocation, proper usage of overtime, and tardiness (Yang et al. 2002).

Parametric Influence Model

When subcontractors make resource allocation choices, they have to take into

account some influence factors. O'Brien (2000) addressed these considerations in his

literature- "Multi-project Resources Allocation: Parametric Models and Managerial

Implications". He proposed a productivity model with which subcontractors allocate

resources. He stated that subcontractors must consider the switching and logistics costs of

moving resources across projects, the affect of altering the balance of different classes of

resources, and the ability of a project to absorb and loan resources with regard to

productivity and completion dates.

The parametric model was defined as:

Pi = (a T y)CW

The productivity model was described as an ideal productivity with

complementarity. For the construction method j, the rate per unit of flexible resources

(such as labor, small tools and equipment that are often used by single workers), a,

multiplied by the number of flexible resources, y, gives the ideal productivity rate.

Complemented by flexible-fixed resources ratio (fixed resources were defined as heavier

equipment that serves crews rather than individuals) C and work area productivity

modifier W, the final actual productivity rate was gained.

When there is an ideal ration of flexible to fixed resources, complementarity

modifier C reaches a maximum value of 1. As the ratio varies, the value of C will

decrease towards zero as shown in the Fig.2-5.










C



1





i i+1 ly/x


Figure 2-5. Complementarity (flexible/fixed resources ratio) modifier curve


W



1








Figure 2-6. Work area modifier curve

Work area modifier W is a function of the size of work area w. W is zero when

there is no available work area. That means there is no possible production. As work area

increases, productivity increases too.

O'Brien's model provides the subcontractor with insight as to how to allocate the

resource. Such a model may become the criteria for subcontractors in determining project

operating decisions, making contracts and developing schedules.

Summary

Critique and Current State of Literature

In the above-mentioned literature about tardiness and overtime cost, there was a

presumption of solution approach that job preemption on the resource was not allowed,









i.e., once a job is started it must proceed to completion before any other job can be started

(Yang et al. 2000).

In a practical construction project, the original construction schedule is allowed to

adjust and change in order to match the time schedule well and ensure the financial

situation in the budget. Sometimes activities would be started in advance and at other

times postponed a little. Consequently one resource might be preempted by another job

instead of the scheduled job. Moreover, many projects keep changing even in the process

of construction, particularly in the design-build projects that become more and more

popular in this industry. The designer, the owner, and the contractor need to cooperate

closely, and frequently change their plans and timetable in accordance with the

requirements.

Furthermore, compacting phase is to set the resource availability to the hard time,

i.e., the regular time plus overtime. For the algorithm proposed in this paper, the relaxing

phase is to begin with the last scheduled job after the compact phase of the algorithm.

This relaxing procedure is repeated backwards till the first scheduled job. In this phase,

the overtime costs are going down to zero while the decrease of working time possibly

results in the tardiness costs.

In practice, few contractors will complete the project later than the project due date

requested by the owner. It is about not only the cost problem, but also the reputation of

the contractors. So the contractors are unlikely to make out a schedule longer than the

required completion days. The contractor has to keep the record and reputation good in

order to get more projects. They definitely would rather increase the investment such as

increase the overtime to ensure the completion date than consider if the tardiness costs









are lower than the overtime costs. Normally subcontractors will try their best to prevent

tardiness from happening. So it is significant to study projects with presumption of

normal durations.

Research Needs

The final target of a subcontractor's multi-project resource allocation research is to

complete the project in time and in demand desired, meanwhile with possibly lower

comprehensive total costs. The project duration may be adjusted to be shorter or longer

within an allowed scope through resource allocation. Considering indirect cost, a

fluctuation in total cost curve can be achieved. The lowest point of this fluctuation curve

is the optimum solution to subcontractors (to be explained in chapter 4). However, due to

the complexity of construction, the total cost and project duration vary by complicated

situation such as the disturbance caused by relevant activities to one another. So the case

studies with calculations of both cost and duration will focus on a single resource project

in this thesis. However, the implications of project uncertainty and change on the cost and

resource allocation of subcontractors in multi-project will also be discussed.

Through the literature review, the relevant information and basic concepts

necessary for resource allocation resolution in my thesis are collected and explained.

Different from overtime usage or other time-cost tradeoff methods, resource allocation is

absorbing more attention in the construction field because of its property of being flexible

and being prone to construction cost reduction, constructability improvement, and better

project quality.

Starting from the basic entity-independent subset in a single resource project,

resource allocation optimization will be analyzed and extended to further prospect. In my

study I will seek the cost curve related to resource allocation, and create some models






26


that relate to site conditions, resource allocation, productivity, and other influence factors.

In view of the perspectives of resource allocation application in multi-project, the project

scheduling problems will be discussed in detail.














CHAPTER 3
SINGLE RESOURCE ALLOCATION ACROSS PROJECTS

This chapter discusses the basic concepts on which a model for resource allocation

in a single-resource project is built. Components of construction cost are explained and a

parametric model used to optimize the resource allocation is introduced as well. Two case

studies are used to help understand the application of single resource allocation that

establishes the base for development of multi-resource allocation.

Presumption

Resource Shifting Within Independent Subset

According to the concepts of independent subsets elaborated in chapter 2, the

project duration is measured in integral increments of time of independent subsets.

Independent subsets are accrual units that chronicle along the time horizon. The allowed

adjustable resource such as labors, materials, equipment, etc. can be shifted among the

activities or projects within one independent subset. After obtaining the durations and

corresponding costs of affected activities or projects, they may evolve into data of a

series of independent subsets. Then the subcontractor's total project costs associated with

this specific kind of resource may be evaluated.

In practice, activities or projects within one independent subset occur

simultaneously. These activities or projects are using the resources at the same time.

They integrate together to form a complete independent subset. Within an independent

subset, every activity or project is allowed to adjust respectively, i.e., with resource

reallocation across these activities or projects. All of the subcontractor's work is divided










into many independent subsets in the time order of activities or projects. On the basis of

Fig. 2-2, we can illustrate the resource reallocation within an independent subset as

shown in Fig.3-1.

Resource Usage


Independent Subset i Independent Independent
Subset i+1 Subset i+2
Resource Reallocate

+ cD

R


Time

Figure 3-1. Illustration of resources shift in the independent subset

In Fig.3-1 above, the first activity-independent subset i- consists of 4 jobs,

numbered from 1 to 4. Independent i+1 includes several jobs, and independent i+2 has 3

jobs, and so on. Every independent subset has a fixed construction period that has been

decided in the schedule. In independent subset i, job 1, 2, and 3 fully utilize the available

processing time, the sum of overtime D and regular time R. Job 4 just utilizes a part of

regular time. Under this situation, we assume the construction cost is X that includes the

indirect cost and direct cost (refer to Literature Review). Indirect cost is fixed because it

basically is positively proportional to construction period time. Direct cost should cover

the expenses that have occurred in both overtime and regular time. Through resource

allocation, we may reach another situation. The work time for job 1, 2, and 3 may fall

down to a level lower than the regular time, and in contrast the working time of job 4

increases. The new situation will result in a new construction cost Y, and the composition









of Y is the same as that of X. Comparing X with Y, the contractor certainly prefers a

lower one, and meanwhile the activity completion due time will still be guaranteed.

So we may create a series of different situations through different resource

allocation methods. Finally the lump sum of every shortest activity construction period

time is the construction term most beneficial to subcontractors.

Total Construction Costs

As described in the Literature Review section of this thesis, the total construction

cost is the lump sum of direct construction cost and indirect construction cost. The direct

cost curve in the Literature Review shows that the solution for direct cost must be

somewhere between the two extremes of the least-cost solution and the least-time

solution, and the direct cost tends to decrease if more time is available. In contrast, the

indirect cost varies almost positive directly with project duration. The blend of direct cost

curve and indirect cost line presents the change fluctuation of the total project

construction cost, and also supplies the information for determination of lower cost and

corresponding project duration.

We now move from the study vision to the independent subset-the epitome of

activities or projects performed by a subcontractor. The whole construction cost and

project duration are accruements of all independent subsets. Each independent subset has

a series of activities/projects. The data are required for every possible method of carrying

out each activity or project. How much resources allocated for each job, how much time

scheduled, and so on, are all related to resource allocation, so it becomes the only

influence factor to generate different total construction curve.

Since the indirect cost just has a simple relationship with the activity period, we

pay attention to the direct cost. Direct cost curve is pivotal because it can have any









duration between different normal and least duration, then a range of possible durations

and corresponding costs based on its utility data is available for each activity.

Accordingly, different combinations of possible durations for the activities can be

associated with the project.

Because all individual activities are assumed to have valid continuous cost curves,

the curve in Fig. 3-2 implies that any project schedule is feasible between the least-time

duration and the all-normal duration.


SCost

Total cost B
Total cost A

SIndirect cost


R. I Direct cost with allocation B
R+0 I
SI - Direct cost with allocation A

> Period

Figure 3-2. Construction costs in independent subset i

The data such as construction schedule and resource allocation scheme set the

limits of the cost and duration of an activity. Usually the contractor determines these data

before starting the activities. It is to indicate that a different method of performing the

same activity may define a different set of data. Consequently, it may have a different

utility curve, such as the two direct cost curves caused by different resource allocations.

The indirect cost curve is plotted on the same graph as the direct cost curve and

then summed up to give the total cost curve so as to determine the final cost curve. The









project total cost curve is plotted by simple addition of the two other costs at any desired

duration on the graph.

Then it is immediately clear that a minimum total project cost exists. This is the

most economical solution for the project, i.e., the duration for the least total cost. In

practice, contractors wish to pursue this most economical solution if they possibly can.

Even they cannot always achieve the idealistic point. Also contractors will have the

intrinsic property of construction cost as a helpful reference. By different construction

methods through adjusting resource allocation, contractors then will work out a feasible

cost solution that is most profitable to them.

Parametric Models of Single Resource Allocation

We just focus on one independent subset to analyze the single resource allocation

influence on activity construction cost. In the independent subset i, the construction cost

is composed of two portions-direct cost and indirect cost. The parametric models in this

thesis try to find a way to determine the cost of loaning or absorbing resources on a

particular work area, meanwhile only single resource is allowed to separately allocate in

the models, no matter what resource it is, labor or material.

Indirect Cost and Direct Cost

As explained in Literature Review, a productivity function formula has been

developed as follows:

Pi = (a T y)CW (O'Brien, 2000) Equation 3-1

In Equation 3-1, Pi is the actual productivity rate for all resources applied, aj is ideal

productivity rate per unit of flexible resource for construction method j, y is units of

flexible resources applied, C is complementarity productivity modifier, and W is work

area productivity modifier.









Equation 3-1 allows us to calculate activity duration.

Ti = Qi/Pi Equation 3-2

Where Qi is the construction quantities of activity i, and Ti is the deduced activity

duration of activity i.

With computation of activity duration through Equation 3-2, we will easily access

the construction costs by multiplying duration by unit cost.

Indirect cost includes the overhead, project management expense, and so on. It is

basically a linear relationship along the activity construction time. So we may figure out

the indirect cost by the following Equation 3-3.

Cind = mTi + n (m>0, n>0) Equation 3-3

Here Cind represents the indirect cost of activity i; m represents the unit indirect

cost; and n represents the start-up cost at the beginning of activity i.

Direct cost is the money invested directly to the activity's construction. Its change

curve depends on the different source allocation ways as described in section of total

costs analysis. Under a certain resource allocation situation, the direct cost Cd can be

divided into regular part and overtime part. Two parts have different unit cost. The direct

cost of the overtime part does not exist in case the activity may be completed within the

time without any overwork. In addition, we ignore the possible rewards for early

completion and the possible penalties for tardiness.

Either in regular time or in overtime, we have to take into account costs caused by

both applied flexible resources and applied fixed resources.

Cr = SryR + SxxR Equation 3-4

Co = Sr'yO + Sxx( Equation 3-5









where


Cr direct cost occurred in regular time

Co direct cost occurred in overtime

Sry unit cost in regular time for one certain flexible resource

Sx unit cost for one certain fixed resource

Sry' unit cost in overtime for one certain flexible resource

y units of flexible resources in regular time

x units of fixed resource in regular time

R regular time

D overtime

Addition of Cr and Co will result in the equation for direct cost Cd:

Cd = Cr + Co

= SryR + SxxR + Sr'yO + SxxD

= SryR + Sr'yO + Sxx(R + D) Equation 3-6

The lump sum of R and D is the maximum available processing time Ti for the

activity i that is deduced by Equation 3-2. In case the working time Ti is less than the

regular time R with productivity rate Pi, there is no over time D. Otherwise, a certain

amount of overtime will be used in activity i. The quantities of flexible resource y and

fixed resource x will be determined by the concrete resource allocations.

Therefore, the total construction cost CT is:

CT = Cind + Cd Equation 3-7

Different resource allocations result in different cost point. Connecting all points,

the total cost curve can be plotted.









Other Costs

When building the picture of total cost of resource allocation, there are other

considerations needed to be included. Shifting cost for moving flexible or fixed resources

from site-to-site, training expenses for new added unskilled labors, the cost for being

familiar with the new equipment, etc. will happen in the resource allocation periods.

Those costs are likely to be different for each resource allocation, and for each activity.

They vary depending on the conditions environments supplied by the sites. The tougher

terrain conditions or longer distance may increase the shifting costs. Few numbers of new

added workers will keep the training costs lower.

In this thesis, we will not discuss those costs due to the variety of activity

individuality. Furthermore, it is not difficult for contractors to respectively estimate those

costs according to concrete situations.

As for the material cost, because the quantities needed to complete the activity

basically are constant and can be found in the estimate, they will not be discussed here.

Case Study

Two cases will be discussed in this section. They respectively study construction

cost with labor allocation, and equipment (flexible small tools) allocation. In order to

simplify the problem, we assume every activity in the following models has only one job,

and the ideal unit productivity remains same no matter how the resources are reallocated.

Model 1 Labor (crew) allocation

For a 12,000 sq. ft. plastic roofing work, the construction period is 15 days. One

standard crew to do this work includes 2 sheet metal workers and 2 building laborers.

Their unit cost is $ 600 per day in regular time, and $ 900 per day in overtime. The ideal









productivity rate of one crew is 600 sq. ft. per day. On the job site, 5,000 sq. ft. of the

working area and one PVC machine are supplied for roofing.

We assume that the PVC machine requires at least one crew (2 sheet metal workers

and 2 building workers) to operate, so the function drops to zero at one. However, the

machine is not fully productive with one crew and it can exert all its power with 2 crews.

More crews greater than two can affect little on overall productivity. So the

complementarity modifier C is illustrated below in Fig.3-3.

C





0.8




1 2y/


Figure 3-3. Complementarity modifier C in Model 1

For each crew, they need 5,000 sq. ft. of working area to guarantee the maximum

productivity rate. Smaller working area will result in conflicts in construction. On the

other hand, they have to spend extra time on mobilization with a too large working area.

So the work area productivity modifier may be plotted as in the following Fig.3-4.

With these conditions, how many crews do we need to complete this roofing work

and yet be most economical? We may work it out by equations set up in section.

Firstly we compute the cost with 2 crews. Because 2 crews are using one PVC

machine, the complementarity modifier C is 1. The average working area for each crew is

only 2,500 sq. ft., so the work area modifier W is only 0.63. The ideal productivity rate









for each crew is 600 sq. ft. per day, and the flexible resource quantity y, i.e., the number

of crews is 2. Then the actual productivity rate for this activity comes out.


W






0.63 ---



2500 5000 1,

Figure 3-4. Work area productivity modifier W in Model 1

P = (aj y)CW = 600 x 2 x 1 x 0.63 = 756 sq. ft. /day

By Equation 3-2, the working time for this activity is:

T = 12,000/756 = 15.87 days

Because the project is required to finish within 15 days, the overtime is 0.87 days.

R= 15 days

S= 0.87 days

In this case, the indirect costs include management fees, overhead costs, etc. in

addition to daily cost $ 100, $ 500 basic cost is needed at the beginning of the activity.

That means:

m =100 n = 500

Therefore:


Cind = mT + n = 100 x 15 + 500 = 2000 dollars









Using equation 6, we may work out the cost both in regular time and cost in

overtime. Because the daily cost for a fixed resource, which is for the PVC machine here,

does not change, we just compare the cost for labor.

Cd = SryyR + Sr'yO = 600 x 2 x 15 + 900 x 2 x 0.87 = 19,566 dollars

Equation 7 tells us how much the total cost is:

CT = 2000 + 19566 = 21,566 dollars

Then we consider the situation with only one crew. The complementarity modifier

turns to 0.8, but the work area modifier raises to 1.

P = (a, y)CW = 600 x 1 x 0.8 x 1 = 480 sq. ft. /day

T = 12,000/600 = 25 days

R= 15 days

S= 25 -15 = 10 days

Cind = mT + n = 100 x 15 + 500 = 2000 dollars

Cd = SryR + Sr'yO = 600 x 1 x 15 + 900 x 1 x 10 = 18,000 dollars

CT = 2000 + 18,000 = 20,000 dollars

So that the comparison results are concluded in the table below:

Table 3-1. Resource allocation comparison in Case 1
Duration Overtime Indirect cost Direct cost Total cost
2 crews 15 0.87 2000 19,566 21,566
1 crew 15 10 2000 18,000 20,000


In this model, it shows that decreasing the numbers of the crew from 2 to 1 seems

beneficial to contractors. Using one crew comes into better effect, and the contractors

should reallocate the superfluous crew to other activities or projects.









Model 2 Equipment (flexible resource) allocation

Hydraulic excavators and cranes are used to cooperate to do 1,000 cubic yards

trenching activity without exact construction time limitation (8 working hours per day). A

total of 3,000 sq. ft. of working area is available. The hydraulic excavators are flexible,

but the cranes are fixed resources. With one crane already working on the job site, the

contractor cares about how many excavators they should allocate to this activity in order

to achieve the most economical effect.

The curve of Productivity complementarity C shows 2 excavators working with one

crane are fully productive. Although the productivity rate will drop off 30% when only

one excavator is used, a crane requires at least one excavator to operate, and thus the

function drops to zero.

C




0.7




1 2 Ey/x

Figure 3-5. Complementarity modifier C in Model 2

One excavator needs 2,000 sq. ft. to become most productive. Smaller or bigger

areas all decrease its behavior, shown in Fig. 3-6.

The ideal daily output of each excavator is 50 cubic yards, and the hourly cost is

$40. The cost for fixed resource-crane-should be taken into consideration because the

construction time is varying. The hourly cost for the crane is $50.









If we use only one excavator, the related parameters are computed according to the

processes shown in model 1.

W

'1

1 ^ ^ 0.9

0.81



1000 2000 3000

Figure 3-6. Work area modifier W in Model 2

P = (aj y)CW = 50 x 1 x 0.7 x 0.9 = 31.5 cubic yard /day

T = 1000/31.5 = 31.75 days

R = 31.75 days

= 0 days

Cind = mT + n = 100 x 31.75 + 500 = 3,675 dollars

Cd = SryyR + Sxx = 50 x 1 x 37.5 x 8 + 40 x 1 x 37.5 x 8= 22,860 dollars

CT = 3675 + 22860 = 26,535 dollars

And then if we add one more excavator in this activity, y units of flexible resources

becomes 2, and the x-units of fixed resource-still maintain as 1. The average for each

excavator is 1500 sq. ft. Assume that the work area modifier W can be interpolated, W is

0.9 under the situation with 2 excavators.

P = (aj y)CW = 50 x 2 x 1 x 0.9 = 90 cubic yard /day

T = 1,000/90 = 11.1 days

R= 11.1 days

= 0 days









Cind = mT + n = 100 x 11.1 + 500 = 1,610 dollars

Cd = SyR + Sxx = 40 x 2 x 11.1 x 8 + 50x 1 x 11.1 x 8= 11,544 dollars

CT = 1610 + 11544 = 13,154 dollars

The comparison table is shown as follows:

Table 3-2. Resource allocation comparison in Case 2
Duration Overtime Indirect cost Direct cost Total cost
1 crew 31.5 0 3675 22860 26535
2 crews 11.1 0 1610 11544 13154


On the contrary, adding one more excavator to model 1 will accelerate the project

greatly, and with less costs. Using the same method, the contractor may compute the

costs for 3 excavators, or more, until they find a solution that is sound for them.

Summary

Although the equations and models are established only within a single resource

allocation scope, they still reveal the relationships between construction cost and resource

allocation to a certain extent. As a main method to control cost and set down the

schedule, resource allocation plays an important role. In accordance with the specific

conditions of different activities or projects, it is not difficult to simulate the above

analysis and establish models on the computer, and then further electrolyze the data

processing. We just discussed two resource allocation methods for each model, but the

computer may repeat the same processes to calculate many allocations. With the

electrical results, the cost curve, including the direct cost curve and the direct cost curve

will be easily plotted. That will be the right-hand guidance to subcontractors.

This analysis method can be further developed in multi-resource projects. The

possible influence and the perspective will be discussed in chapter 4.














CHAPTER 4
MULTI-RESOURCE ALLOCATION ACROSS MULTIPLE PROJECTS

On the basis of elaboration of single resource allocation, the concept of

independent subsets and the parametric cost model are introduced in the application of

the subcontractor's multi-resource allocation in this chapter. The implementation of

multi-resource allocation encompasses consideration of mutual impacts caused by

allocation itself to the subcontractor as a whole, of certain combinations of resource

utilization. Two examples of subcontractors, taken from an investigation in Florida and

Arizona, are presented in this thesis on their resource allocation measures. The evaluation

of their allocations is also addressed.

Environment for Multi-resource Allocation Across Multi Projects

Due to increasing sophistication and specialization of work, which creates a more

complex work environment, the subcontractor is likely to grow to encompass more trade,

invest more in personnel and equipment, and be able to confront tough work conditions

with a tighter schedule. Increasing prefabrication off site and more complicated

construction on site require multifarious fixed facilities too. Under this kind of

environment, the subcontractor has to consider the deployment of each resource in the

meantime other than a schedule with a single resource. Reasonable multi-resource

allocation across projects is necessary to take advantage of resources and also complete

all projects as required. Multi-resource allocation across multi projects in the context of

construction is the assessment of the real inputs for any of the subcontractor's projects or









programs of construction and the identification of the action necessary to ensure that

there is a balance between requirements and availability.

With the resource constraints, some of projects will be prioritized and the others

not. What are the criteria? Most of the subcontractors normally prioritize their projects

with multi-resource on customer priority, stakeholders' interest, corporate portfolio,

product roadmap, business strategy, and project budget (Faniran et al. 1999). The single

most significant factor is the return of investment. Other prominent reasons used to

allocate resources across projects are reliant on the subcontractor's core business. Utility,

construction, and government industry prioritize projects based on regulatory

requirements, legislative mandates, emergencies, and political demands in addition to

above-mentioned criteria. From the standpoint of a subcontractor, the return of

investment, i.e., the construction cost, is the only concern in this thesis. In order to

maximize the profits, multi-resource allocation is necessary, on the one hand, to improve

the efficiency, and on the other, to plan all projects as a whole so as to reduce the cost as

much as the subcontractor can manage to do so.

Multi-resource allocation involves much more than merely crunching numbers in a

mathematical calculation. In the single resource allocation hypothesis, the resources are

allocated in the chronological order based on project priorities. If resources are

insufficient then there may well be decreases in the labor productivity, thus possibly

prolonging project durations with the risks of project tardiness, and increasing the

construction cost as well. Also there may be some kinds of excessive resources at some

projects that damage the balance of process causing inability to fully exerting other

resources and a rise in price through a change in the correlation. So the resolution is to









shift the extra resources from the projects where fewer resources are required to reach the

optimum efficiency to the projects that need more resources to speed up the progress.

But in the typical multi-resource allocation, the resources are allocated

simultaneously to sets of activities or projects, rather than to individual activities or

projects in a sequential manner. With multi-resources allocation across multi projects, the

subcontractor possibly does not save money on some projects, and even has to endure the

loss to some degree, but meanwhile gain profits from other projects. In other words, some

projects are sacrificed to create favorable resource conditions for other prioritized

projects, then benefit from them, and eventually profit the subcontractor in the entire

plan.

The first step in the process of moving to a strategic resource-allocation perspective

is to determine where current strengths exist, where the weakness exists, and where the

priority will be set to build upon these answers. In some instances, significant

construction resources are required to move forward toward strategic objectives. In these

instances, the subcontractor must set priorities and balance available resources

(Chinowsky and Meredith, 2000). For example, if a subcontractor finds two projects are

scrambling for the same kinds of limited resources, then a decision must be made as to

which of these gaps requires the greater attention at the current time.

Each subcontractor impossibly supplies unconditional resources to their projects.

Normally they strive to grab sufficient projects so as to ensure a ready supply of available

work. In addition they must tend to make the most of limited resources when they

perform work on multiple projects simultaneously. From the subcontractor's point of

view, the focus is not on any one specific project, but on multiple projects. Each









construction project manager, on the other hand, is highly focused on the project for

which they are responsible, so that they would rather utilize resources as much as they

possibly can. However, rather than advancing an individual area, the subcontractor must

retain an overall perspective acknowledging that each of the projects and each of the

resources are equally important to achieving a long-term vision. Moreover, the mutual

influence caused by multi-resource allocation must be taken into consideration. Will the

subcontractor suffer losing interest in any other projects if the amount of one kind of

resource goes down on a project? What is the optimal point of resources arrangement to

guarantee a company's profit? Similar to the balancing of resources on a project, the

balancing of resources at a subcontractor's organization level is required to keep him on a

continued path of advancement. This thesis proposes to attempt to understand the

behavior of subcontractors in resources allocation on multiple projects that requires

looking beyond the boundaries of a single resource/project and taking the subcontractor's

multi-resource/multi-proj ect viewpoint.

Significance of Independence Subset in Multi-Resource Allocation

Different from the single-resource allocation elaborated in chapter 3, various

resources are in use on a subcontractor's projects. Those resources are applied to each

project in accordance with the construction processing sequence. And the same project

utilizes different resources in different periods, including materials, labor, equipment,

working areas, etc. Normally the subcontractor takes care of every resource at the same

time. How to help coincide the usage of resources to offset the possible shortage or

excess, avoid the possible conflicts and wastage between resources, and finally obtain the

maximum financial return is the only problem the subcontractor cares about. Figure 4-1

imitates the situation of multi-resource allocation.










Resource 1
Reallocating
Resource 1

R + .


Time













Time
mId Subset i' mid Subset (i+1)' Tid Subset (i+2)'





Resource 2
Reallocating Reallocating
Resource 2 Resource 2

..



Time
Ind. Subset Ind Subset (i+)" Ind Subset (+2)"

Figure 4-1. Illustration of multi-resource allocation across projects

A simple multi-resource allocation sketch is shown in Fig. 4-1. It consists of only

resource 1 and resource 2. The subcontractor's projects are arranged along the time

horizon, represented by blocks with different colors. It can be seen that these projects are

processed in different periods with different resources and different regular time R and

overtime D. Also due to the different processing time, those projects are merged into or

divided into different independent subsets. As shown in Fig. 4-1, resource 1 is applied to

project 1, 2, 3 and 4 at the same time. So project 1, 2, 3, and 4 are integrated into one

independent subset. The next project using resource 1, leading the next independent

subset, has a time gap with its predecessor. For the application of resource 2, project 1

and 3 are dealt with firstly as an independent subset. Project 2 and 4 do not start

immediately after the completion of the first independent subset that is composed of

project 1 and 3. So project 2 and 4 form a new separate independent subset. In the









following independent subsets, the construction sequence for other projects might differ

from that in the construction with resource 1.

Within the independent subset, every activity or project is allowed to adjust the

usage of resource. Similar to the single-resource allocation, this kind of resource

allocation probably is beneficial to related projects; meanwhile the different resources

collaborate or influence each other. Usually the allocation of one kind of resource will

result in the ripple effect on other resources. The subcontractor needs to take into

consideration all relevant impacts so as to maximize the profits.

Efficient allocation of resources for construction activities or projects requires that

the determination of resource requirements should be undertaken on a return-adding and

cost-effective basis. Too little resource allocation effort possibly results in

implementation failures, delays, mediocrity, and inefficiency. Consequently there is a

high probability that the project will exceed the subcontractor's existing budget. When

the correct amount of resource allocation effort is invested, the project implementation

time is optimized, the construction costs are decreased, and there is a high probability that

the project will save much money for the subcontractor. But additional resource

allocation effort beyond the optimal level is essentially wasteful, probably even projects

will achieve intended objective, because of the implementation delays that inevitably

arise due to the additional time required to complete the allocation and the increasing

costs of associated work such as the resource shifting expenses.

Since it is hard to work out how much effort should be invested, and it is not

possible to readily identify from so many multi-resource allocation options, which

projects to assign higher priorities to, and which projects to improve the subcontractor's









financial status, a simple repetitive calculation procedure may be used. It is possible,

therefore, to introduce a scheduling software system into resource allocation scheduling

and consequently monitor the impact on the total yield results. Each project within the

independent subset is selected in turn, given the highest priority over all of the others, and

the consequent project duration and corresponding construction costs are monitored.

Repeat this procedure to figure out costs of all resource-allocation combining

possibilities, then the optimal one will be obtained through the comparison of results. The

procedure is demonstrated in a case study in the following section.

Multi-Resource Allocation Parametric Model

On the basis of the productivity function formula discussed in single-resource

allocation analysis, a parametric model is presented here to promote the understanding of

multi-resource allocation concept by attempting to explain the basic tenet of this concept

in the context of the subcontracted construction environment. The basic tenet begins with

a statement of the ultimate goal from the subcontractor's point of view-to maximize his

profit over considered projects.

In the single-resource analysis in chapter 3, the overtime cost or tardiness cost are

involved in total cost calculation. For the sake of simplicity, both overtime and tardiness

cost will be ignored. Assuming that the subcontractor is remunerated only according to

quantity of work performed in each project, this model can be stated as follows:


I= Y (ADj CT) Equation 4-1
j=1

where

I subcontractor's net income over project 1 through project j

Aj total work amount of project j (j = 1, 2, 3... n)










Dj unit price for the work on project j (j = 1, 2, 3...n)

CT total construction cost

As discussed in the previous chapters, total construction cost is composed of direct

cost Cd that is obtained by multiplying the total quantity of resources on project j with the

unit cost of resources, and indirect cost Cind. Using the definitions in chapter 3, the

subcontractor's net income is:

n n
I= I (AjDj Cind Cd)= (AjDj Cind qjSj) Equation 4-2
J=1 J=1

Cind subcontractor's overall indirect construction cost

qi total quantity of resources on project j (j = 1, 2, 3...n)

Sj unit cost of resources on project j (j = 1, 2, 3... n)

Because the cost of resources can be separated into material part and labor part, and the

material cost may be expressed as the product of actual performed work multiplied with

the unit price of the material for the work. In this thesis, the focus is on the

subcontractor's strategy in allocating resources; the material waste will be omitted. Then

assuming the actually performed work is equal to the demanded work that is represented

by Aj, So Equation 4-2 will be deduced to as follows:

m,n m,n
I= C (AjDj Cind AjM TijLijYij) [AJ(Dj M- Cind- TijLijYij]
1=1, j=1 =1, =1

m,n
= [Aj(Dj Mj)-Cind-(Qij/Pij)Lijyij]
1=1, =1

m,n
= Z {A(Dj Mj))- Cind [Qij/(aijyijCijWi)]Lijyij
1=1, =1

m,n
= {Aj(Dj Mj) Cind- [Qi/(ajCijWij)]Lij} Equation 4-3
1=1,J=1









where

Mj average unit cost of material on project j

Ti work time of resource i on project j

Li cost of unit time for one unit of resource i (other than material)

allocated by the subcontractor to project j over period T

Qi amount of work with resource i on project j

Pi productivity with resource i on project j

aj full productivity with resource i on project j

yij units of resource i on project j

Cij complementarity productivity modifier of resource i on project j

Wi work area productivity modifier of resource i on project j

(i = 1, 2, 3...m; j=l, 2, 3...n)

The parameters for productivity P are quoted from Equation 3-1 in chapter 3. The

parameter on the left side of equation 10 represents the subcontractor's profit. The terms

on the right hand side of the equation represent income for work performed deducted by

cost of materials, indirect cost, and cost of resources except that of materials.

For the sake of simplicity, it is assumed that the existing work amount is fixed;

material cost and indirect cost are both assumed constant over time period T as well as

amount of each resource and cost of unit time for unit resource. Under these assumptions,

it can be seen from the equation that the subcontractor's challenge in any period T is to

set resource units yij that determines complementarity productivity modifier Ci, and work

area productivity modifier Wi for each resource on each project to maximize productivity

Pi.









The subcontractor will set the quantity of resources applied to each project at each

distinct time period. Determination of the correct resource level must take into account

not only the expected amount of work that will be made available during the different

period and total construction term or schedule, but also the available fixed machine, work

area provided by the general contractor, and mutual effects on productivity of resources

due to resources allocation to each other.

As can be seen, the subcontractor's profitability is extremely sensitive to the ratio

of the quantity of work that can be performed during the specific period, to the

productivity in that period. The subcontractor can reduce this sensitivity by increasing the

average productivity across all projects. Sometimes even when some projects are

assigned appropriate resources, resource availability on other projects will be diminished

by these assignments, so does the productivity. For the subcontractor, the goal is the

aggregate benefit with multi-resource across multiple activities in separate projects.

From the established model, it is possible to explore the factors that motivate a

subcontractor in assigning resources to the various projects. When will a subcontractor

increase, decrease, or withdraw resources from any particular project? How do the

working conditions influence the behavior of the subcontractor in assigning resources?

How does market force affect the ability of a subcontractor to commit appropriate

resources to projects? And so on. However, the immediate goal of this thesis should not

be able to answer these questions directly. Rather its goal should be to establish an

economic and behavioral model of subcontractor decision-making that would enable

prediction of the range of decisions that may be made.









Multi-Resource Allocation Case Study

Assuming a roofing subcontractor has two projects to build at the same time, one is

6,000 square feet, and the other one's size is 7,500 square feet. Our study focuses on two

sorts of crews, membrane crew and insulation crew, working on two projects. The cost

for each membrane crew per day is $200, and that for each insulation crew per day is

$300. So in this case, membrane crew and insulation crew are two resources needed to

reallocate between these two projects. Only one membrane crew and one insulation crew

are assigned to Project 1, two membrane crews and 3 insulation crews are assigned to

Project 2. As the schedule changes, one membrane crew is shifted from Project 2 to

Project 1, and one insulation crew is also moved to Project 1 from Project 2. Due to the

interactive affects on construction complementarity and working area on both projects

caused by multi-resource reallocation, the change of comprehensive construction costs

can be obviously observed.

Ignoring the time gap between the two resources applications, both projects are

presumed to utilize two different kinds of resources contemporarily. So the multi-

resource on these two projects can be described with independent subsets as follows.

The resource assignment information is given as follows:

* Project 1: 6,000 sf to work; 4,000 sf working space; one fixed membrane
application machine; one fixed insulation application machine; one membrane crew
with an ideal productivity of 1,200 sf/day; one insulation crew with an ideal
productivity of 800 sf/day.

* Project 2: 7,500 sf to work; 5,000 sf working space; one fixed membrane
application machine; one fixed insulation application machine; two membrane
crews, each of them has an ideal productivity of 1,200sf/day; three insulation
crews, each of which has an ideal productivity of 800sf/day.

* Allocation: respectively moving 1 membrane crew and 1 insulation crew from
Project 2 to Project 1.











Membrane Crew Usage
Shzft I crew from Project 2
to Project I
R+

Project 2
2 crmws
Time
Independent Subset s
Insulation Crew Usage
Shift 1 crew from Project 2
to Project I



WProject 2
3 c;trws
Time
Independent Subset "


Figure 4-2. Two resources applications on two projects

Meanwhile, influence parameters described in Equation 3-1, i.e., the

complementarity modifier and the working space modifier, comply with the following

figures. Furthermore, another prerequisite is the ideal unit productivity, for both

membrane crew and insulation crew, does not change although crews are reallocated

from Project 2 to Project 1.

C



1
1 ,





1 2 3 Y-/x


Figure 4-3. Complementarity modifier C in multi-resource allocation case study

Before reallocation, the calculation is as follows:

For membrane crews:

amCimWim = 1200x0.8x0.8 = 768 sf/d.each










amC2mW2m = 1200xlx0.4 = 480 sf/d.each

w


1.0 .0
0.9,
0.8,

0.4;


1000 2000 3000 4000 5000

Figure 4-4. Working area productivity modifier W in multi-resource allocation case study

For insulation crews:

aiCliWi = 800x0.8x0.8 = 512 sf/d.each

aiC2iW2i = 800x0.9x0.4 = 288 sf/d.each

am/ai ideal productivity of each membrane crew/insulation crew.

Cim/Cli complementarity modifiers of membrane crew/insulation

crew on Project 1. It is 0.8 for both membrane crew and

insulation crew (respectively 1 crew for the machine)

before reallocation.

C2m/C2i- complementarity modifiers of membrane crew/insulation

crew on Project 2. It is 1 for membrane crew (2 crews for

the machine) and 0.9 for insulation crew (3 crews for the

machine) before reallocation.

Wim/Wli working space modifiers of membrane crew/insulation

crew on Project 1. It is 0.8 for both membrane crew and

insulation crew (respectively 2000 sf space every crew with

total 2 crews) before reallocation.









W2m/ W2i working space modifiers of membrane crew/insulation

crew on Project 2. It is 0.4 for both membrane crew and

insulation crew (respectively 1000 sf space every crew with

total 5 crews) before reallocation.

So the subcontractor's net income before allocation will be:


Before = {Aj(Dj. Mj) Cind [Qi,j(ai,jCijWi)]Lij}


2,2
= {Aj(Dj Mj) Cind [(6000/768 + 7500/480) x 200 +
1=1,j=1

(6000/512 + 7500/288) x 300]}

2,2
= [Aj(Dj.Mj)-Cind 16200]
1=1,y=1

After reallocation:

For membrane crews:

amCimWim = 1200xlx0.4 = 480 sf/d.each

amC2mW2m = 1200x0.8x0.75 = 720 sf/d.each

For insulation crews:

aiCliWi = 800xlx0.4 = 320 sf/d.each

aiC2iW2i = 800xlx0.75 = 600 sf/d.each

Cim/Cli complementarity modifiers of membrane crew/insulation

crew on Project 1. It is changed to 1.0 for both membrane

crew and insulation crew (respectively 2 crews for the

machine) after reallocation.









C2m/C2i- complementarity modifiers of membrane crew/insulation

crew on Project 2. It is changed to 0.8 for membrane crew

(1 crew for the machine) and 1.0 for insulation crew (2

crews for the machine) after reallocation.

Wim/Wli working space modifiers of membrane crew/insulation

crew on Project 1. It is changed to 0.4 for both membrane

crew and insulation crew (respectively 1000 sf space every

crew with total 4 crews) after reallocation.

W2m/ W2i working space modifiers of membrane crew/insulation

crew on Project 2. It is changed to 0.75 for both membrane

crew and insulation crew (respectively 1667 sf space every

crew with total 3 crews) after reallocation.

So the subcontractor's net income after allocation will be:

2,2
after = {Aj(Dj. Mj) Cind- [Qi,j(ai,jCijWi,)]Lij}
l=1,J=1

2, 2
= {Aj(Dj.Mj) Cind [(6000/480 + 7500/720) x 200 +


(6000/320 + 7500/600) x 300]}

2,2
= [Aj(DjMj)-Cind 14200]
1=1,J =1

The subcontractor's income from all projects' contracts, material cost, and indirect

cost are assumed constant no matter which resource allocation way they adopt. Then by

comparing net income after reallocation after with net income before reallocation Ibefore,









obviously the fact is the subcontractor will gain more net income than that before

reallocation.

2,2
after Ibefore = [Aj(Dj Mj) Cind- 14200]


2,2
[Aj(DjMj) Cind 16200] = 2000
1=1,y=1

It can be seen that the membrane crew cost on these two projects is $4,600 before

crew reallocation. Even after the crew reallocation, the final cost of membrane crews

remains at $4,600. The allocation process does not profit the subcontractor on membrane

crew cost. However, after crew reallocation, the insulation crew cost on two projects goes

up to $11,400 from $9,600. During the two resources allocation, the shift of membrane

crew and the insulation crew from Project 2 to Project 1 cuts down the cost of membrane

crews, but it indeed lessens the insulation crews' competition of utilizing working spaces,

and urges them to make the most of construction equipment, and finally shortens the total

construction period on these two projects, making further profit for the subcontractor.

This impact resulted not only from the allocation of one sort of crew, but also from multi-

resource allocation between two projects.

Case Study on Multi-Resource Allocation

Introduction

The multi-resource allocation case study questionnaire was sent out to

subcontractors with different disciplines and located in different places. Then the analysis

focused on feedback information from those subcontractors that devoted exactly multiple

resources to multi different projects. The ultimate target of collecting information from

those subcontractors is to see if they adopted multi-resource allocation measures across









their multi-projects, then to evaluate their allocating policies from the subcontractor's

standpoint if they really adopted some measures on projects. Finally a better allocation

method may be found in light of the analysis results.

Taken out from feedback information from those subcontractors, two

subcontractors are presented here for analysis. One is a painting subcontractor, and the

other one is a mechanical subcontractor. The multi-resource allocation case study

questionnaire had 3 parts, Part 1 Background Information, Part 2 Questions on

Productivity, and Part 3 Evaluation of Resource Allocation.

Part 1 asked the recipient to provide background information on its company name,

project and resource information, and respective quantities of work with different

resources on different projects. Part 2 asked the participant some questions regarding

construction productivity. Ten questions were asked for a descriptive response to the

possible influence on productivity due to either assigned fixed machine or available

working area. This part tried to find affecting factors in the parametric model of resource

allocation. Part 3 asked detailed questions about resource allocating criteria, direct cost,

and workers shifting information. This part was designed to confirm if the

subcontractor's actual thinking about the resource allocation complies with the theoretical

model discussed in the last two chapters.

B&G Painting, Inc.

B&G Painting, Inc. was performing painting and wall-covering work on two

projects during the same period. It performed 350,000 square feet painting and 7,000

square feet wall covering on project 1; 175,000 square feet painting and 5,000 square feet

wall covering on project 2. With sufficient applying of machines and working areas, two

kinds of workers might respectively reach the full productivities of 300 square feet per









hour and 15 linear yards per hour, wherever the project is. The painter was paid $40 per

hour, and the wall-covering worker could earn $20 per hour.

No fixed machine was required to do the painting work, but wall covering

workers need pasting machine in the construction process. Each project was provided

with a pasting machine. One worker can operate the machine alone, but the productivity

would be doubled with two workers. At most four workers could be assigned to use one

machine together when the productivity reached the maximum.

Each painter needs 10,000 square feet of working space to achieve the full

productivity, which would be declined to two-thirds of full productivity with the

minimum working space of 1,000 sf. The ideal working space for wall-covering worker

is 1,000 sf when they may construct at the fastest speed. At least 500 square feet space is

required for each wall-covering worker, but the productivity was only half of full

productivity. There were 30,000 sf and 9,000 sf respectively provided for project 1 and 2.

The subcontractor does not think too large a work area would de-motivate workers and

make them less productive because the company set up daily goals on what should be

achieved.

In accordance with the situation supplied above, the complementarity figure for

the wall covering can be shown:

C





0.25

1 4 Yy/x


Figure 4-5. Complementarity modifier C for wall covering










x'Vpaint





0.66


1,000 10,000 W

Figure 4-6. Working area productivity modifier W for painting

Wwall




0.66



500 1,000 W

Figure 4-7. Working area productivity modifier W for wall covering

From the very beginning, B&G Painting, Inc. allocated 5 painters and 3 wall-

covering workers on project 1; 3 painters and 2 wall-covering workers on project 2. They

did not shift any workers across projects till the completion of both projects. So a total of

8 workers were working on project 1 and 5 workers on project 2. Then the working space

for each worker would be 3,750 sf (30,000/8=3,750) on project 1 and 1,800 sf

(9,000/5=1,800) on project 2. So the working space modifier W of painting would be

deduced to 0.76 and 0.69 for project 1 and project 2 on the basis of Figure 4-7. Every

wall-covering worker's working area was bigger than 1,000 sf so that the working space

modifier of wall covering is 1 for both projects. Because the painter did not need any

fixed machine, so the complementarity modifier C for painting is also 1. But it would be

0.75 for wall covering on project 1 with 3 workers and 0.5 on project 2 with 2 wall

covering workers. The subcontractor's income may be worked out as follow:










For painting:

apC1pWp = 300xlx0.76 = 228 sf/hr.each

apC2pW2p = 300xlx0.69 = 207 sf/hr.each

For wall covering:

awCiwWiw = 15x0.75x1 =11.25 ly/hr.each

awC2wW2w = 15x0.5x1 = 7.5 ly/hr.each

2,2
I= {Aj(DjMj)-Cind [Qij/(ajCijWij)]Lij}
=1 ,j=1

2,2
= ({A(Dj.Mj) Cind [(350000/228 + 17500/207) x 40 +
=1 ,j=1

(7000/11.25 + 5000/7.5) x 20]}


= [Aj(Dj.Mj)-Cind-120998]
=1 ,j=1

The subcontractor did not reallocate workers between these two projects, so they

did not know if their policy of spending $120,998 on labor cost was the best choice or

not. Although project 1 was larger than project 2, dense workers on project 1 affected

worker's productivity. Assuming anther situation-reallocate one painter from project 2,

also one wall covering worker from project 1 to project 2. Therefore, there would be 4

painters and 2 wall-covering workers on project 1, 4 painters and 3 wall-covering

workers on project 2. Correspondingly, the working area modifier W for painting would

be changed to 0.81 on project 1 and 0.67 on project 2. Meanwhile, the complementarity

modifier C for wall covering also reversed, then there would be 0.5 on project 1 and 0.75

on project 2. What would have happened?

For painting:









apC1pWp = 300xlx0.81 = 243 sf/hr.each

apC2pW2p = 300xlx0.67 = 201 sf/hr.each

For wall covering:

awCwWiw = 15x0.5x1 = 7.5 ly/hr.each

awC2wW2w = 15x0.75x1 = 11.25 ly/hr.each


I= {Aj(DjM)- Cind -[Qij/(aijCijWi)]Li}


2,2
= f {Aj(DjMj)- Cind [(350000/243 + 17500/201) x 40 +
1=1,J=1

(7000/7.25 + 5000/11.25) x 20]}

2,2
= [ [Aj(Dj.Mj)-Cind-119995]
1=1,J=1

Comparing two results, it is obvious that the new allocation suggestion would save

$1,003 for the subcontractor. With recommended allocating measure, the cost on project

2 would be increased a little. But as the whole plan, the final cost of both projects would

be less. Maybe this amount is not a big money resource for the subcontractor in this case,

but it might result in a huge loss on the big scale project. With the parametric model as

the guideline, allocating 1 painter and 1 wall-covering worker from project 1 to project 2

seems more profitable to the subcontractor.

BCH Mechanical Inc.

BCH Mechanical Inc. has performed 22,000 linear feet and 34,000 linear feet of

pipefitting and plumbing for project 1 and project 2. Both the pipefitting and the

plumbing crew need to be equipped with the same welding device to carry out the work.

Every set of welding devices can meet the requirements for two crews, either pipefitting









or plumbing. Each worker requires 4000 square feet working space to maximize the

productivity, and at least 1500 square feet working space with half of full productivity.

The full productivity of the pipefitting crew is 200 linear feet per day, and the plumbing

crew can finish at most 100 linear feet per day. These ideal productivities keep same at

different projects. Project 1 provided 10,000 sf working area for crews; project 2

provided 20,000 sf Hourly salaries of crews are $70 for pipe fitters and $50 for

plumbers.

At the beginning, one pipefitting crew and one plumbing crew with one set of

welding device were assigned on project 1, but three pipefitting crews and three

plumbing crews with three sets of welding devices on project 2. Being aware of too few

crews on project 1, there were one pipefitting crew and one plumbing crew reallocated

later from project 2 to project 1, with one set of welding device also shift to project 1. Is

this reallocation a good decision?

Before allocation: (5000 sf working space for each crew, so the working area

modifier is 1 on project 1; 3333 sf working space for each worker on project 2, so the

working area modifier W is 0.87.)

For pipefitting:

apfCipfWpf = 200xlxl = 200 If/day

apfC2pfW2pf = 200xlx0.87 = 174 If/day

For plumbing:

apbClpbWlpb = 100xlxl = 100 If/day

apbC2pbW2pb = 100xlx0.87 = 87 If/day

2,2
Before = {A(DjMj)- Cind- [Qij/(aijCijWij)]Lij}
1=1 ,=1










2,2
= {Aj(Dj Mj) Cind [(22000/200 + 34000/174) x 70 x 8 +
=1,J=1

(22000/100 + 34000/87) x 50 x 8]}

2,2
= C [Aj(Dj.Mj)-Cind-415344]
1=1,j=1

After allocation: (2500 sf working space for each worker, so the working area

modifier is 0.7 on project 1; 5000 sf working space for each worker on project 2, so the

working area modifier W is 1.)

For pipefitting:

apfClpfWpf = 200xlx0.7 = 140 If/day

apfC2pfW2pf = 200xlxl = 200 If/day

For plumbing:

apfC2pfW2pf = 200xlxl = 200 If/day

apbC2pbW2pb = 100xlx1 = 100 If/day

2,2
later = {Aj(Dj Mj) Cind- [Qij/(aijCijWj)]Lij}
l=1,J=1

2,2
= {Aj(Dj -Mj) Cind -[(22000/140 + 34000/200) x 70 x 8+
1=1,j=1

(22000/70 + 34000/100) x 50 x8]}

2,2
= [Aj(DjMj)- Cind- 444912]
1=1,j=1

It can be seen that $29,568 more were spent on workers' cost. However, the

subcontractor just allocated resources according as the superficies of lacking workers on

project 1, they did not realize that they would incur more costs. In case they have a

parametric model analysis as the guideline, the subcontractor could avoid this kind of






64


resource allocation across multi projects that might be harmful to the subcontractor's

benefits.














CHAPTER 5
CONCLUSIONS

This thesis has explored the concept of single-resource allocation across projects

for the subcontractor, and derived a concept of multi-resource allocation across projects

from a parametric model. The study reported in this thesis focuses on the construction of

multi-resource allocation undertaken within a subcontract for the purpose of achieving

success in project performance. Based on the results obtained from the study, multi-

resource allocation can be defined as an effective scheduling optimization measure.

Through rational resources allocation across projects, the whole construction cost can be

controlled more effectively with timely completion that satisfies customers. Certainly a

great deal of calculation in accordance with the thinking described in this thesis is needed

to approach a more optimized solution.

Although the applicability of the derived resource allocation model does not take

into account all of the influence factors, the analysis has nevertheless demonstrated that

appropriately allocating resources across a project increases the probability of perfect

project performance and is therefore likely to be cost-effective. This would be of benefit

to the top management of subcontracting firms in determining how to achieve cost-

effectiveness in resource allocating within the firm.

A subcontractor should not be discouraged if he finds one or more areas have

significant weakness associated with resource allocation at the present time. The research

about multi-resource allocation is still under development, and further research work is






66


being undertaken so that it is hoped that the solution of multi-resource allocation

rationality will be more easily refined, evaluated, and implanted.















LIST OF REFERENCES


Antill, J. M., Woodhead, R. W. (1982). Critical Path Methods In Construction Practice.
John Wiley & Sons Inc., Sydney, Australia, P157-160.

Birrell, G.S. (1980). "Construction Planning Beyond the Critical Path." ASCE Journal
of the Construction Division, 106(C03), 389-407.

Chaker, A. A. (1973). "Optimal Scheduling and Resource Allocation in Project
Networks." Dissertation for Ph.D., University of Illinois at Urbana-Champaign.

Chinowsky, P. S., and Meredith, J. E. (2000). "Strategic Management in Construction."
ASCE Journal of Construction Engineering and Management, 126(1), P1-9.

Dodge, F.W. (2005). "Construction Up." Accessed March, 2005.
http://www.architecturalwest.com/FW Dodge/fw dodge 1 05.htm

Faniran, O. O., Love, P. E. D., and Li, H. (1999). "Optimal Allocation of Construction
Planning Resources." ASCE Journal of Construction and Management, 125(5),
P311-319.

Giggard, R. (2005). "Economy Sputters Toward Recovery." Construction, V72, i2, P4.

Hegazy, T. (1999). "Optimization of Resource Allocation and Leveling Using Genetic
Algorithms." ASCE Journal of Construction Engineering andManagement, 125(3),
P167-175.

Hegazy, T., and Ersahin, T. (2001). "Simplified Spreadsheet Solutions I: Subcontractor
Information System." ASCE Journal of Construction Engineering and Management,
127(6), P461-468.

Hegazy, T., and Ersahin, T. (2001). "Simplified Spreadsheet Solutions II: Overall
Schedule Optimization." ASCE Journal of Construction Engineering and
Management, 127(6), P469-475.

Hegazy, T., Shabeeb, K., Elbeltagi, E., and Cheema, T. (2000). "Algorithm For
Scheduling With Multiskilled Constrained Resources." ASCE Journal of
Construction Engineering and Management, 126(6), P414-421.






68


O'Brien, W. J. (2000). "Multi-Project Resource Allocation: Parametric Models and
Managerial Implications." Presented at Eighth Annual Conference of the IGLC,
University of Sussex, Brighton, UK, P11.

O'Brien, W. J, and Fischer, M. A. (2000). "Importance of Capacity Constraints To
Construction Cost And Schedule." ASCE Journal of Construction Engineering and
Management, 126(5), P366-373.

Yang, B., Geunes, J., and O'Brien, W. J. (2002). "A Heuristic Approach for Minimizing
Weighted Tardiness and Overtime Costs in Single Resource Scheduling."
University of Florida, Gainesville, FL.














BIOGRAPHICAL SKETCH

Chuan Song was born in Beijing, China. He graduated from Beijing University of

Technology (formerly named Beijing Polytechnic University) with a bachelor's degree in

civil engineering. He attended graduate school at the M.E. Rinker, Sr. School of Building

Construction at the University of Florida in 2003, graduating with a Master of Science in

Building Construction in 2005.