|
UFL/COEL-95/003
IMPACT OF LONGBOAT KEY BEACH NOURISHMENT
ON HARD BOTTOM SEDIMENTATION RATES
by
Darwin C. Stubbs
Thesis
1995
IMPACT OF LONGBOAT KEY BEACH NOURISHMENT ON HARD BOTTOM
SEDIMENTATION RATES
By
DARWIN C. STUBBS
A THESIS PRESENTED TO THE GRADUATE SCHOOL
OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT
OF THE REQUIREMENTS FOR THE DEGREE OF
MASTER OF ENGINEERING
UNIVERSITY OF FLORIDA
1995
ACKNOWLEDGMENTS
I would like to express my gratitude to my advisor and supervisory committee
chairman, Dr. Daniel M. Hanes, and the members of my supervisory committee, Dr.
Robert G. Dean and Dr. J. Ashish Mehta.
I must also thank the indispensable staff of the Coastal Engineering Laboratory
for meeting and exceeding the many demands of my research work. Thanks go to
Vernon Sparkman and Daniel Brown for the construction of my sediment traps.
Thanks also go to Viktor Adams, Don Mueller and Mark Sutherland for their tireless
effort and humor in the field.
I am also very appreciative of the assistance I received in the analysis of my
data. Thanks go to Konstantin Marusin for developing the wave analysis software
and Ani Akarjalian for analyzing my sediment samples.
My parents deserve special thanks for their constant support and
encouragement.
I owe a large debt of gratitude to my friends, especially Tim, Thermo, Choad,
Tweety, Slick, Robcindyandbud, Mr. and Mrs. Man and Dave. They deserve thanks
for listening to me, pretending to listen to me, laughing with me, laughing at me,
surfing with me and surfing on me.
Miscellaneous thanks go to Negra, Avellanas, Little Hawaii, Grande, Langosta,
Roca Bruja, Dominical, Poof, Reggie, Scooter, Slugwood, barley, malt, hops, MSP,
Orifice, P-a-B Lounge, Chim Chim, Cindy Loftgreen, Holly Golightly, Brett Ashley
and Jake Barnes for keeping it all in perspective.
TABLE OF CONTENTS
page
A CK N O W LED G M EN TS .................................................................................... ii
LIST OF FIGURES ............................................................. vi
LIST O F TA BLES ............................................................ ........................... vii
A B ST R A C T ...................................................................................................... ix
CHAPTERS
1 INTRODUCTION
1.1 Introduction to Sedimentation
1.1.1 D definition ..................................................... ........................... 1
1.1.2 Environmental Impact .............................. .............. ............... 2
1.1.3 Study Objectives ............................................ ................................... 3
1.2 The Longboat Key Nourishment Project
1.2.1 Project Location ............................ .. ..................... 5
1.2.2 Project Specifications .......................................... 5
1.2.3 Project Schedule ............................................ 7
1.2.4 Monitoring Station Sites .................... ................... 8
2 METHODS
2.1 Introduction ........................................................................................ 11
2.2 Wave and Turbidity Packages
2.2.1 Peripheral Sensors .................... .... ................. 12
2.2.2 Sam pling Schem e ............................................... ....................... 14
2.2.3 Field C configuration ............................................. ........................ 15
2.3 Sediment Traps
2.3.1 Sedim ent Trap D esign Criterion ................................................... ... 17
2.3.2 O original Trap D esign ........................................ ........................ 19
2.3.3 Second Trap Design ..................... .......................................... 21
2.3.4 Final Trap Design ............................................. 24
2.3.5 Sediment Sample Analysis Procedure ............................................ 29
3 RESULTS
3.1 Introduction ........................................................................................... 31
3.2 Manual Turbidity Monitoring
3.2.1 Method ................... .. ............................ 31
3.2.2 M annual Turbidity Data ....................................... ....................... 32
3.3 Sensor Data
3.3.1 Sensor Deployment Schedule ..................................... ........... .. 36
3.3.2 O B S D ata ....................................................... ............................ 40
3.3.3 W ave D ata ...................................................... ............................ 42
3.4 Sedimentation Data
3.4.1 Sediment Trap Sampling Schedule ................................................. 47
3.4.2 Sedim entation Data ................................................................... 47
4 DISCUSSION
4.1 Introduction ........................ ......... .. ............................................ 56
4.2 Trendline and R-Squared Value Equations ............................................. 58
4.3 Significant Wave Height
4.3.1 Significant Wave Height Data ........................... ....... ............ 59
4.3.2 Significant Wave Height Sedimentation Relationship ................ 60
4.4 Maximum Horizontal Velocity
4.4.1 Maximum Horizontal Velocity Calculations ................................. 62
4.4.2 Maximum Horizontal Velocity Sedimentation Relationship .......... 64
4 .5 Sum m ary .................................................... ............... ................................ 68
5 SUMMARY AND CONCLUSIONS
5.1 Introduction ...................................................... .............................. 69
5.2 Summary
5.2.1 Monitoring Methods ......................... ................... 70
5.2.2 Monitoring Results ........................................... 70
5.2.3 Wave Force and Sedimentation Analysis ....................................... 72
5.3 Sediment Monitoring Requirements Recommendations ........................ 72
5.3.1 Standardized Sedimentation Monitoring ........................................ 73
5.3.2 Am ended Sam pling Schedule .................................... .... ....... .... 73
5.4 Suggestions for Further Investigation ............................ ........... 74
APPENDIX A: W AVE DATA PLOTS ......................................................... ... 76
APPENDIX B: SEDIMENTATION DATA ..................................... .... 111
R E F E R E N C E S ........................................ ............ ........................................ 146
BIOGRAPHICAL SKETCH ....................................................... 148
LIST OF FIGURES
Figure page
1.1 Nourishment location map ................... ........................................... 6
1.2 Time line of nourishment and monitoring activities ...................................... 8
1.3 M monitoring project location map ............................................... ............ 10
2.1 System I package field configuration ...................................... . ............ .. 16
2.2 System II package field configuration ...................... ................. .. 16
2.3 Original sediment station configuration .......................... .............. ........... 21
2.4 Sedim ent trap stand ............................................................. .................... 22
2.5 Second sediment station configuration .......................... ........ ........... .. 23
2.6 Final sedim ent trap design ................................. .... ........................ 25
2.7 Final sediment stand design ......................... ........ ................ 26
2.8 Final sediment station configuration .................... ................... .. 27
3.1 Time line of wave data coverage ....................................... .... 39
3.2 Average sand sedimentation rates, hard bottom vs. control ........................ 52
3.3 Average fines sedimentation rates, hard bottom vs. control ........................ 54
4.1 Sand sedimentation rate versus significant wave height ............................. 61
4.2 Fines sedimentation rate versus significant wave height ............................. 62
4.3 Sand sedimentation rate versus maximum horizontal velocity ................... 65
4.4 Fines sedimentation rate versus maximum horizontal velocity ................... 66
LIST OF TABLES
Tables p
1.1 Sedim ent characteristics ............................................................................ 7
1.2 M monitoring locations ...................................................... .......................... 9
2.1 Performance of sediment trap designs ............................................. ........... .. 29
3.1 Manual turbidity readings, during nourishment ............................................ 32
3.2a Manual turbidity readings, after nourishment ............................................ 33
3.2b Manual turbidity readings, after nourishment ............................................... 34
3.3 Average manual turbidity readings, during and after nourishment ................. 35
3.4 Summary of deployment activities .......................................... ... 37
3.5 W ave data availability summary ................................. ..... .... ....... ..... 38
3.6 Average wave data characteristics ........................................ .... 44
3.7 Average wave data characteristics .................................... .... 45
3.8 Maximum height and period for five storm events ...................................... 46
3.9 Sediment sampling deployment/retrieval schedule ...................................... 49
3.10 Average sand sedimentation rates ........................................................ 49
3.11 Average fines sedimentation rates .................................. ...... .............. 50
3.12 Average sand sedimentation rates, hard bottom vs. control ....................... 51
3.13 Average fines sedimentation rates, hard bottom vs. control ....................... 53
3.14 Average sedimentation rates before, during and after nourishment ............. 54
4.1 Significant wave height and sedimentation rates ...................................... 60
4.2 Maximum horizontal velocity and sedimentation rates ............................... 64
4.3 Trendline and r-squared values for sand sedimentation data ....................... 67
4.4 Trendline and r-squared values for fines sedimentation data ...................... 68
Abstract of Thesis Presented to the Graduate School
of the University of Florida in Partial Fulfillment of the
Requirements for the Degree of Master of Engineering
IMPACT OF LONGBOAT KEY NOURISHMENT ON HARD BOTTOM
SEDIMENTATION RATES
By
Darwin C. Stubbs
May 1995
Chairman: Daniel M. Hanes
Major Department: Coastal and Oceanographic Engineering
A sedimentation, wave climate and turbidity monitoring project was conducted
before, during, and after construction of the nourishment of Longboat Key, Florida.
This study attempts to evaluate the effects of the Longboat Key beach nourishment
on hard bottom sedimentation rates. The second objective of this study is to analyze
and evaluate the sedimentation monitoring methods employed at Longboat Key and
to propose a standard sedimentation monitoring procedure. This study describes the
monitoring methods, monitoring results, and analyzes the interaction between wave
activity and sedimentation.
Three sediment trap designs were employed and evaluated during the course of
this study. The final trap design and field configuration proved very effective. The
sturdy construction allowed for a 99% sediment sample retrieval rate. In addition, a
low relative standard deviation between the field replicates at each site indicates
representative sampling.
The results of the monitoring data shows two important facts. First of all, the
hard bottom sites of Longboat Key experienced larger wave conditions than the
control sites. Secondly, the hard bottom sites showed significantly larger sand
sedimentation rates than the control sites.
The analysis of the relationship between the wave parameters of significant
wave height and maximum horizontal water particle velocity and sedimentation rates
as measured by the sediment traps point out several interesting facts. Apparently, the
relationship between fines sedimentation and wave activity is fairly linear. However,
sand sedimentation seems to related to a power of wave activity. This analysis also
indicates that the wave parameter of maximum horizontal water particle velocity
offers the best correlation to both fines and sand sedimentation.
Finally, this study offers four recommendations. First of all, it is proposed that
the final sediment trap design and configuration employed in this study be adopted as
the standard wherever feasible. Secondly, it is recommended that in conjunction
with sedimentation, relative bed level measurements be obtained with the use of a
ruled post jetted at each monitoring site. Thirdly, the sedimentation monitoring
schedule should be amended so that sedimentation and wave climate monitoring
begins at least six months prior to nourishment and monthly sediment sampling
periods be maintained throughout the study. Finally, it is recommended that flow
studies be conducted on the existing trap configuration as well as a trap configuration
featuring staggered replicate heights.
CHAPTER 1
INTRODUCTION
1.1 Introduction to Sedimentation
1.1.1 Definition
Sedimentation can be defined as the precipitation of sediment in the water
column. The significant portion of the sediment in suspension is locally eroded from
the sea bed. As the sea bed is agitated by the hydraulic forces of waves and currents,
the sediment is entrained into the water column where it may be transported by these
same forces. Deposition occurs when these mobilized particles settle out of the
water column and back into the sea bed. The sedimentation rate as measured by a
sediment trap is the quantity of sediment per unit area that precipitates into a trap
over time. It may be important to point out that, in the context of this study, the
sedimentation rate is not a measure of accretion or net sediment accumulation but of
sediment flux. It accounts only for the sediment that settles onto an area, not the
subsequent transport of sediment away from an area.
One important byproduct of sedimentation is increased turbidity or the reduced
clarity of water due to the scattering and absorption of light by the suspended
particles. This is especially true of sediment with a high concentration of fine
material (Dompe, 1993).
1.1.2 Environmental Impact
Sedimentation directly affects the growth and survival of marine communities,
particularly the benthic organisms associated with reefs, such as the stony corals
prevalent in Florida. First of all, the activity of sediment removal greatly taxes
energies that are usually reserved for growth and reproduction. In extreme cases,
excessive sedimentation can smother and ultimately destroy the coral tissue.
Secondly, sedimentation increases turbidity which can greatly reduce the amount of
light that penetrates to the photosynthetic coral community. This light is vital to the
zooxanthellae plant cells that reside within the living tissue of the coral. These plant
cells provide the coral colony with nutrients and assist in the removal of waste. This
symbiotic relationship promotes rapid growth and the accretion the limestone
skeleton that support the coral polyps and serve as the foundation of the reef
environment (Dodge, 1987).
The rate of sedimentation is a result of both natural and human activities. The
most common natural events that may increase sedimentation are storms. The
intensified wave action associated with storms tends to suspend sediment into the
water column where it can be transported. Coral communities can contend with
these relatively short-lived, natural events. However, the long-term increase in
sedimentation associated with beach nourishment dredging projects may be far more
detrimental.
Beach nourishment activities involves dredging sand from a borrow site,
transporting and discharging the material to the nourishment site. Sediment
suspension and subsequent increases in turbidity are induced at the borrow site
3
where the sand is dredged by excavation and suction, and at the nourishment site
where the slurry is discharged. In some cases, there is substantial leakage of the
dredge pipeline that contributes to sedimentation as well. Studies have shown
reduced growth rates and mortality of coral communities as a result of beach
nourishment activities (Dodge 1987; Goldberg, 1988). In addition, there can be a
long term increase in sedimentation associated with beach nourishment projects.
Elevated levels of sediment activity are experienced until the nourished beach
eventually achieves an equilibrium profile.
1.1.3 Study Objective
In order to evaluate the environmental effects of beach nourishment projects,
the former Florida Department of Environmental Regulation (now the Department of
Environmental Protection) has established wave, turbidity and sedimentation
monitoring requirements. The results presented in this study represent a component
of the monitoring program for Longboat Key Florida. This program includes the
measurement of sedimentation of four offshore study sites along the nourishment
project and at three adjacent control sites. In addition, wave and turbidity
measurements have been monitored at two of the study sites and two of the control
sites. In accordance with the Department of Environmental Regulation nourishment
permit, sedimentation monitoring was conducted before, during and after
nourishment. Construction began in March, 1993 and concluded in August, 1993
and the monitoring program began in November, 1992 and concluded in August,
1994.
4
The environmental impacts of sedimentation associated with beach
nourishments is a relatively new consideration and monitoring has taken place only
since the past decade (Goldberg, 1988). Thus, the monitoring process is still in an
evolutionary state; as new knowledge of environmental impact becomes available,
monitoring requirements are amended or broadened. Currently, this requirement is a
very general provision.
The sedimentation monitoring schedule, collection methodology, analysis
methodology, and results presentation is outlined in the second section of the
monitoring requirement of the Longboat Key nourishment permit. This section lists
four stipulations. First of all, sedimentation in milligrams (dry weight) per square
centimeter per day are to be measured every 30 days for a 90 day period prior to
construction and every 30 days during construction and every 60 days for one year
after construction. Secondly, these dry weight measurements are to be stratified
according to the fines portion and the sand portion. Thirdly, three replicates shall be
sampled at each site. Finally, "the methods used to collect and analyze the
sedimentation rates can be any scientifically viable procedure" (Department of
Environmental Regulation, 1992, p. 12) subject to approval from the Bureau of
Wetland Resource Management prior to monitoring. It is apparent that the required
method of sediment collection and analysis lacks specific instruction.
The focus of this study is to analyze the sedimentation monitoring of the
Longboat Key nourishment project and to evaluate the existing Department of
Environmental Regulation monitoring guidelines. This will include an examination
of the performance of the of the sediment trap design, the sediment analysis
5
procedure, and the resulting data analysis methodology incorporated in the Longboat
Key monitoring project. These findings will be utilized to judge the feasibility of the
requirements of the Department of Environmental Regulation. Finally,
sedimentation monitoring recommendations will be presented. This evaluation may
lead to a standardized method to obtain and analyze sedimentation rates.
1.2 The Longboat Key Nourishment Project
1.2.1 Project Location
The DER issued permit number 41 & 581938039 June 18, 1992, to nourish the
coastline of Longboat Key, Florida. The nourishment construction contract was
granted to Applied Technology and Management, Inc. The entire length of the Gulf
Coast town of Longboat Key, Florida, was nourished in the Spring and Summer of
1993. Longboat Key is a barrier island on the Gulf of Mexico that stretches
approximately ten miles along the west coast of Florida. It is located south of St.
Petersburg and Tampa Bay as shown on the following page in figure 1.1.
1.2.2 Project Specifications
The nourishment permit was issued on June 18, 1992, construction began on
February 28, 1993, and construction ended on August 12, 1993. One million, one
hundred and sixty thousand cubic yards of material from the New Pass ebb-tidal
shoal at the south end of Longboat Key nourished the south beach, from DNR
monument R-13 south to R-29B, near the terminal groin at the southern tip of the
6
island. One million, six hundred and fiflty thousand cubic yards of material from the
Longboat Pass ebb-tidal shoal at the northern end of Longboat Key was
hydraulically excavated for the nourishment of the north beach, from monument R-
47 south to R-13. These DNR monuments are marked on figure 1.1. This represents
9.28 miles of beach front nourishment (ATM, 1994).
Longboat Pass
R-47
Longboat
R-12
R-29B -6-
New Pass
Figure 1.1: Nourishment location map
7
The New Pass borrow site consisted of material with a mean grain size of .22
mm which was placed on the south beach with a native mean grain size of .19 mm.
The Longboat Pass borrow site consisted of material with a mean grain size of .19
mm which was placed on the north beach with a native mean grain size of .21 mm.
This is summarized in table 1.1 (ATM, 1994).
Table 1.1: Sediment characteristics
Location Mean Sorting,
Diameter (mm) )
Longboat Pass Borrow Site 0.19 0.78
Native North Beach 0.21 0.57
New Pass Borrow Site 0.22 1.52
Native South Beach 0.19 1.20
1.2.3 Project Schedule
The nourishment project was completed in two stages. The first stage
consisted of the nourishment of the southern portion of the island from DNR
monument R-29B, beginning on February 28, moving north and ending at monument
R-12 on May 2, 1993. The second stage consisted of the nourishment of the northern
portion from DNR monument R-47, beginning on May 3, moving south and ending
at monument R-12 on July 12, 1993. This was followed by spot refills which ended
on August 12, 1993.
In accordance with the nourishment permit, a sedimentation and turbidity
monitoring project was implemented at the end of October of 1992, coinciding with
the subsequent nourishment of Longboat Key in March of 1993. Sedimentation and
manual turbidity monitoring began 90 days prior to nourishment and continued for
one year after the completion of nourishment. Turbidity and wave climate
monitoring began after the completion of nourishment and continued for one year
thereafter. Figure 1.2 is a time line of these activities.
10/25/92 2/28/93 8/12/93 1/1/94 8/12/94
Nourishment
Sedimentation Monitoring
Manual Turbidict Monitoring
Wave and Turbidity Monitoring
4/7/93 8/25/93
Figure 1.2: Time line of nourishment and monitoring activities
1.2.4 Monitoring Station Sites
The monitoring locations include four stations at hard bottom sites along
Longboat Key and control stations on adjacent Siesta Key, Anna Maria Island and
Long Key. Presented below in Table 1.2 are the names, locations and mean lower
low water depths of each site.
Sedimentation is monitored at all seven of these locations through the use of
sediment traps mounted to the ocean bottom. Turbidity and wave climate are
monitored at the Long Key and Siesta Key control sites and the Longboat Key #34
and Longboat Key #2 hard bottom sites. This is accomplished through the use of
electronic instrument packages mounted to the ocean bottom. Figure 1.3, on the
9
following page, is a map of the monitoring sites and the equipment deployed at the
respective sites.
Table 1.2: Monitoring locations
Site NAD System Latitude Longitude Depth
Siesta Key SK 1064582 N, 476646 E 27"15'40" N 82033'09" W 4.6 m
Longboat Key #6, LBK6 1111215 N, 446697 E 27023'21" N 82o38'43" W 4.5 m
Longboat Key #2, LBK2 1112927 N, 445498 E 27023'38" N 82038'57" W 5.6 m
Longboat Key #43, LBK43 1123050 N, 436808 E 27025'28" N 82040'34" W 4.6 m
Longboat Key #34, LBK34 1123256 N, 436055 E 27025'19" N 82040'42" W 5.3 m
Anna Maria Island, AM 1156367 N, 420896 E 27030'47" N 82043'33" W 4.6 m
Long Key, LK 1227089 N, 415328 E 27042'27" N 82044'39" W 4.5 m
NORTH Long Key
NORTH Lo
LK O0
Tampa Bay
6?
Anna Maria
Figure 1.3: Monitoring project location map
* Sediment Station
0 Instrument Package
CHAPTER 2
METHODS
2.1 Introduction
This chapter will focus on the measurement methodologies incorporated in
obtaining the wave climate, turbidity and the sedimentation data. The wave climate
and turbidity measurements were collected through the use of self-contained, in-situ
electronic packages. These packages were equipped with a nephelometer, a pressure
transducer, and in some cases, a current meter. Sediment traps were employed to
obtain the sedimentation measurements.
A description of the wave and turbidity packages and the sediment traps will
be presented in this chapter. The wave and turbidity package will be examined first.
This examination will include an explanation of the package sensors, sampling
scheme and field configuration. This will be followed by a detailed description of
the sediment trap design, field configuration and sediment sample analysis. As
previously stated, sedimentation monitoring is a relatively new nourishment permit
requirement and there are no standardized collection or analysis procedures. Thus,
the sediment trap utilized in this project was a new design and will be emphasized.
2.2 Wave and Turbidity Packages
The wave and turbidity packages are based on a previous design that has been
successfully utilized in past projects, specifically the 1991 Hollywood renourishment
(Dompe, 1993). The instrument package consists of a watertight PVC body and the
peripheral sensors. The body houses the battery pack, sensor circuitry, and the data
logger, which controls the sampling scheme and data storage. Two instrument
package designs were employed in the turbidity and wave climate monitoring, the
system I and system II. The peripheral sensors of the system I consist of two
nephelometers, a pressure transducer, and a current meter. The peripherals of the
system II package consists of one nephelometer and a pressure transducer. These
peripherals, as well as the package sampling scheme and field configuration will be
described in this section.
2.2.1 Peripheral Sensors
The peripheral sensors will be described in this section. This will include only
a brief explanation of the physical measurement principles of the instruments and
calibration methods. The analog voltage signals of these instruments are converted
to a digital bit signal and saved on an Onset Computer Corporation Tattletale data
logger.
The two system I nephelometers used to measure turbidity are OBS-1 Optical
Backscatterance Sensors manufactured by Downing and Associates. The system II
nephelometer is the OBS-3 Optical Backscatterance Sensors manufactured by
Downing and Associates as well. The OBS-1 and OBS-3 models operate under the
same principles which will be briefly discussed. These instruments will be
collectively referred to as OBS. OBS is an optical sensor that measures turbidity by
detecting infrared radiation scattered from suspended matter in the water column (D
& A Instrument Company, 1991). A diode in the center of the OBS face emits
infrared light and photo diodes, which comprise the remaining portion of the OBS
face, and detect the infrared light that is reflected or backscattered from the particles
in the water. The use of infrared light prevents significant signal degradation due to
the interference of sunlight (Dompe, 1993).
Calibration of the OBS is performed by relating the signal outputs of a sensor
in formazin solution samples to the known turbidity levels of the samples. The
turbidities of the formazin solution samples, measured in nephelometric transmission
units (NTU), are determined through the use of a portable nephelometer
manufactured by H-F Scientific, model DRT-15C. The relationship between the
OBS signal and the NTU turbidity level is linear and easily derived.
Wave climate is measured through the use of a Transmetrics P-21 pressure
transducer. The transducer measures total pressure through the varying resistance of
a strain gauge. Incorporating linear wave theory, this pressure data yields wave
amplitude, wave period, and tidal oscillations. Calibrations are performed by
comparing the transducer signal to known values of pressure by using a compressed
air source and by immersing the packages in a cylinder of water at varying depths.
This is a simple linear relationship as well.
Currents are measured using a Marsh McBimey electromagnetic current meter
which operates on the Faraday principle of electromagnetic induction. The
movement of seawater, a conductor, in the magnetic field induced by the current
meter produces a voltage which is proportional to the velocity of the sea water.
Calibration of the current meter is performed periodically by Marsh McBirney.
2.2.2 Sampling Scheme
The system I package was programmed to sample at one hertz for 1024
seconds every two hours. Data files generated by the four sensors are downloaded to
the data logger every twenty-four hours. These packages are equipped with the
Onset Computer Corporation model TT6 data logger with a 20 megabyte hard drive.
With this sampling scheme, the TT6 data logger is capable of storing one hundred
days of data. However, the 12V power source which drives the system I must be
renewed approximately every six weeks.
The system II package sampled at one hertz for 512 seconds every two hours.
These packages utilized the model TT4 data logger which is equipped with over one
megabyte of RAM. This represents a storage capacity of almost 60 days. The
system II was also powered by a 12 V battery pack but only required to be renewed
approximately every three months.
Field visits to download the data and change batteries, if necessary, were
scheduled every four to six weeks.
2.2.3 Field Configuration
As stated earlier, the wave and turbidity packages were deployed at four of the
seven monitoring sites. System II packages were employed at the Long Key and
Siesta Key control sites and at the Longboat Key #34 study site. A system I package
was primarily used at the Longboat Key #2 study site. In cases when the system I
was not available, due to maintenance requirements or field damage, a system II was
deployed at Longboat Key #2. The packages at these four monitoring sites were
supplied from a pool of four system II packages and two system I packages. This
allowed for a spare system II and a spare system I package.
These packages are mounted to steel frames which are secured to the sea bed.
This frame consists of two pipes which are jetted vertically, approximately eight feet,
into the sea bed and connected by a horizontal cross bar at the surface of the bed.
Mounting collars secure the package to the cross bar. The sensors are attached to the
jetted pipe that extends approximately five feet out of the sea bed.
In the system I configuration, the two OBS face opposite each other,
approximately five feet from the sea floor. The pressure transducer and current
meter is mounted approximately three feet and five feet from the sea floor,
respectively. Figure 2.1 illustrates the system I configuration.
In the system II configuration the OBS is mounted approximately five feet
from the sea floor and the pressure transducer is mounted to the lid of the package
body, approximately 2 feet from the sea floor. The exact heights are recorded during
each deployment. Figure 2.2 illustrates the system II configuration.
PVC body
current meter
OBS -
pressure transducer
support frame
Figure 2.1: System I package field configuration
OBS
pressure
transducer
support frame
PVC body
Figure 2.2: System II package field configuration
2.3 Sediment Traps
Sediment traps were used to collect suspended sediments at a fixed point in
space over a period of time. The use of sediment traps as a permit requirement is a
relatively new development. Thus standardized sample collection or analysis
methods have yet been formulated. However, sediment traps have been used in the
natural science fields since the turn of the century and, in limited cases, in
engineering applications. In the case of the natural sciences, these time integrated
samplers, also referred to as settling chambers, are employed primarily to sample
settling or suspended particulate matter (SPM) which includes bioseston as well as
sediment (Rosa et al., 1991). In the limited cases of engineering applications,
sediment traps have been utilized in sediment transport studies, predominantly in
streams and reservoirs. Due to their prevalence, many studies have been conducted
to test the performance of sediment trap design (Rosa et al., 1991). The design of our
sediment traps are based on the results of these studies. The design process and
various sediment trap designs as well as the sediment sample analysis method will be
presented in the following sections.
2.3.1 Sediment Trap Design Criterion
The objective of a sediment trap is to obtain a representative sample of
downward settling sediment. The downward sediment flux can be calculated from
this sample. Two conditions are required to accurately measure settling flux using a
sediment trap. First of all, the sediment concentration at the mouth of the trap must
be identical to that outside of the trap mouth. In other words, the trap design should
not induce flow dynamics that would alter the sediment concentration at the mouth
of the trap. This can lead to a increased or decreased probability that sediment will
be trapped. Secondly, sediment that has collected in the trap must not be
resuspended by turbulent flow conditions at the mouth and expelled. Simply stated,
sediment that accumulates in the trap must be retained.
Extensive testing has indicated that traps which meet these two requirements
most effectively are cylindrical traps with an appropriate aspect ratio
(length:diameter). In flowing, turbulent waters the aspect ratio must be at least 5:1
(Bale, 1993). Another important criteria is a trap diameter of at least five
centimeters. Traps with a smaller diameter may undertrap small dense particles and
overtrap large, less dense particles (Rosa, 1991). Finally, in the case of replicate
traps, the field configuration must not cause significant flow interference between the
traps at a given site. This interference can cause the sediment concentration at the
mouth of one or more of the replicates to differ from local sedimentation conditions.
We imposed two other design requirements to meet the demands of the field
conditions encountered in beach nourishment projects. The first requirement is a
design that facilitates efficient and timely installation and removal as divers are often
subject to adverse weather conditions and low visibility. The second requirement is
a design of sturdy construction to withstand storm-induced wave forces in shallow
waters.
In summary, four important sediment trap design criteria must be met to
facilitate representative replicate sampling: 1) the trap tube must be cylindrical, 2)
the aspect ratio of the trap tube must be at least 5:1, 3) the trap mouth must have a
diameter greater or equal to 5 cm, and 4) the field configuration of the replicates
must not cause concentration interference between the traps. In addition, the field
configuration of the sediment traps should comply with two general requirements:
1) the field configuration must allow for easy trap retrieval and replacement and 2)
be of sturdy construction. An evaluation of the two interim trap designs and the final
trap design, based on the criteria outlined above, will be presented in the following
sections.
2.3.2 Original Trap Design
The original sediment traps, designed by Applied Technology and
Management, Inc., were deployed in the end of October of 1992. This design
consists of a 1.5 inch (3.81 cm) inner diameter, schedule 40 PVC trap tube attached
to a 1000 ml nalgene sample bottle. The length of the trap tube is approximately
30.5 cm and is fastened to the mouth of the sample bottle with a rubber coupling
equipped with stainless steel hose clamps. Three of these traps rest on a flat,
triangular PVC stand which is secured to a 2 inch ( 5.08 cm) inner diameter
aluminum post. The aluminum mounting post is hydraulically jetted approximately
eight feet into the sea bed. The traps sit on the PVC stand and are fastened to the
post with tie-wraps around each of the sample bottles. The mouth of the trap tube is
between three and four feet from the sea bed. Figure 2.3 illustrates the configuration
of this sediment station.
A sediment trap is replaced in the following manner: 1) the tie-wraps around
the sample bottle are cut, 2) the hose clamp on the rubber coupling which fit over the
mouth of the sample bottle is loosened, 3) the sample bottle is carefully detached
from the trap tube and rubber coupling and the sample bottle is immediately capped,
4) the trap tube and rubber coupling is fitted over the mouth of a new sample bottle
and the hose clamp is tightened, and 5) the new trap is resecured to the mounting
post with tie-wraps.
This design and field configuration presents four problems. First of all, the
trap tube diameter violates the minimum diameter criteria. Secondly, the close
proximity of the replicate traps to each other and the mounting post is sure to
significantly disrupt the flow pattern. Thus, this configuration may cause
interference between the samples. Thirdly, the sample retrieval and replacement
process is far to complicated. Field reports show that it requires two divers up to
twenty minutes to perform the replacement. Finally, this configuration is far too
unstable. Often sediment traps would be lost in the field and, in fact, the entire
samples for one sampling period were lost. This design experienced a sediment
sample retrieval rate of only 59% over three deployments. The remaining samples
were lost in the field. At the start of the fourth sampling period, March 6, 1993, a
new design was implemented.
nalgene
sample bottle
PVC stand
E- PVC trap tube
rubber coupling
tie-wrap
. mounting post
_____ I I
Figure 2.3: Original sediment station configuration
2.3.3 Second Trap Design
The second trap design features two new changes to the original. The trap
tubes are 2 inch (5.08 cm ) outer diameter copper tubing and the traps rest on an
aluminum stand which is fastened to the mounting post. This stand design is
illustrated in figure 2.4.
The sediment trap stand consists of a flat circular platform welded to one end
of a section of 2.5 inch (6.35 cm) inner diameter pipe which acts as a shaft. A flat
circular plate with three 2.5 inch (6.35 cm) diameter circles cut out acts as the trap
tube guides and is welded to the other end of the shaft.
trap guide
platform
set bolt '
Figure 2.4: Sediment trap stand
The samples bottles sit on the platform and are secured to the shaft with tie-
wraps. The trap tubes extend through the guide holes on the top plate. The shaft fits
over the mounting post and is secured by two set bolts on each end of the sediment
trap stand. This configuration is illustrated in figure 2.5.
This configuration offers two improvements to the original design. The trap
tube diameter is larger and the traps are far more secure. This design was utilized for
only one sampling period, from March 6 to April 7, 1993, during which time Florida
experienced a hundred year storm. Despite these harsh conditions, fifteen of the
twenty-one samples were retrieved. This represents a 71% retrieval rate.
set bolt
=---
nalgene
sample bottle
trap stand
copper tube
Rubber coupling
- -- tie-wrap
- -1 mI -
- mounting post
Figure 2.5: Second sediment station configuration
However, despite the improvements, two original shortcomings remain. The
trap tubes are still in close proximity to each other, potentially interfering with the
sampling within a sediment station. In fact, the presence of the sediment stand may
contribute to this as well. In addition, the sediment trap retrieval and replacement
steps are identical to the original configuration. Thus, this process still requires
substantial diver down time. By the fifth deployment beginning April 7, 1993, the
final sediment station was designed and implemented.
2.3.4 Final Trap Design
The final sediment trap and configuration is drastically different from the
previous two designs. The sediment trap is composed entirely of two inch (5.08
cm)inner diameter, schedule 40 PVC. The trap consists of two parts, the tube and the
canister as illustrated in figure 2.6. The suspended sediment travels down the tube
and settles in the canister. The trap tube is 46 cm in length and equipped with a
female adapter on one end. This connects to the male adapter on top of the trap
canister. The canister is 15 cm in length and is sealed with and end cap at the
bottom.
In the field, the canister is attached to the trap tube. During replacement the
entire trap is removed and a new trap is installed. The canister is unscrewed from the
tube at the lab when the sediment sample is to be analyzed.
trap tube
46 cm
!-- female adapter
-- male adapter
canister 15c
15 cm
S -- end cap
Figure 2.6: Final sediment trap design
The final sediment trap stand consists of four, six inch sections of 2.5 inch
inner diameter, aluminum pipes arranged in a tripod configuration. This design is
illustrated in figure 2.7.
The center pipe section acts as the shaft which fits over the mounting post and
is secured by two set bolts. Three aluminum plates extend the remaining pipe
sections 11.4 centimeters from the shaft. These sections act as trap holders. The
sediment trap slides into the holder and is secured with two set bolts. This final field
configuration is illustrated in figure 2.8.
K trap holder
11.4 cm
O 6.35 cm
Asset bolt
top view
20.3 cm 15.2 cm
side view
Figure 2.7: Final sediment stand design
Two trap replacement procedures were considered for this new design. The
first alternative was to replace the canisters in the field. This would entail
unscrewing the canisters from the trap tube and screwing on a new canister. The
second alternative was to simply replace the entire trap, the tube and canister, as one
piece. The latter procedure was adopted for two reasons. First of all, the biofouling
in the study area was much more severe than anticipated. Thus, to prevent growth on
the traps, particularly the inside of the tubes, the traps were painted with anti-fouling
paint after each sampling period. If the trap tubes were to remain in the field for
extended periods the fouling would significantly decrease the effective diameter.
Secondly, the act of unscrewing the canisters would resuspend the sediment sample
and increase the chances of sediment loss during the replacement. Therefore, sample
replacement was performed in the following steps: 1) the set bolts on the holder are
loosened and the entire trap is pulled out and immediately capped with a PVC end
cap and 2) the new trap is inserted into the holder and the set bolts are tightened.
aluminum
stand
set bolt
PVC tube
--- PVC canister
mounting post
Figure 2.8: Final sediment station configuration
It is evident that this final configuration meets all four design criteria. The
inner diameter of the trap tube is two inches or 5.04 centimeters and the aspect ratio
is 9:1. The potential of sample interference is reduced due to the greater distance
between the replicate traps. In addition, the two field requirements are met.
Replacement of the sediment traps in this new configuration is much simpler than the
former designs. It can be executed by two divers in almost five minutes. This
configuration also proved far more sturdy than the previous designs. A 99% retrieval
rate was accomplished with this new design.
Table 2.1 summarizes the performance of the three sediment trap designs. For
each design the average relative standard deviation between replicates and sample
retrieval rates are given as well as the number of sampling periods in which these
statistics were calculated.
The relative standard deviation is calculated by taking the standard deviations
of the replicates at a site and dividing by the average rate of sedimentation. This can
be seen as a measurement of the flow interference between replicates. For instance,
large values of standard deviations suggest that the flow induced by the sediment trap
configuration may be interfering with the sediment concentration at the mouth of
adjacent replicates.
It is evident from table 2.1 that the final trap design and configuration
performed the best.
Table 2.1: Performance of sediment trap designs
Relative Standard Deviation Retrieval Sampling
Design Sand Fines Rate Periods
Original 0.28 0.27 59% 2
Second 0.13 0.15 71% 1
Final 0.13 0.15 99% 14
2.3.5 Sediment Sample Analysis Procedure
Once the samples are retrieved they are sterilized with mercurium (HgC12) to
prevent biological growth during transport to the lab. The sample is analyzed in a
lab to determine dry weight of the sand portion, dry weight of the fines portion, and
organic weight. This method follows accepted sediment testing guidelines (Mudroch
et al., 1991) and is outlined below:
1) The cap is removed from the trap tube and the water above the canister is
carefully removed using a vacuum pump. The trap tube is unscrewed from
the canister.
2) All of the contents of the canister is washed onto a 63 micron sieve for wet
sieving. The sieve is seated onto the lid of a receptacle so that the water and
fines that pass is retained.
3) The sample in the sieve is gently brushed until the mixture of fines and
water passes through the sieve.
4) The remaining sand contents of the sieve is carefully washed into a labeled
and tared drying tin.
5) The sand sample is dried in an oven at 110' C.
6) The weight of the dried sand sample is recorded. This represents the dry
weight of the sand sediment and organic of the sand portion of the sample.
7) The remaining portion of fines and water that passed through the sieve is
washed into a labeled container and allowed to settle for 24 hours.
8) Once the fines have settled, the excess water in the container is removed
using a vacuum pump.
9) The fines portion is carefully washed into a labeled and tared drying tin and
dried in an oven at 1100 C.
10) The weight of the dried fines sample is recorded. This represents the
dry weight of the fines sediment and organic of the fines portion of the
sample.
11) The dried sand sample is ashed in and oven at 5000 C for two hours.
12) The ashed weight of the sand sample is recorded. This represents the
dry weight of the sand sediment portion of the sample.
13) The dried fines sample is ashed in an oven at 5000 C for two hours.
14) The ashed weight of the fines sample is recorded. This represents the
dry weight of the fines sediment portion of the sample.
CHAPTER 3
RESULTS
3.1 Introduction
The results of the manual turbidity measurements, electronic sensor
instrumentation, and sediment trap data will be presented in this chapter. The
manual turbidity readings will be presented first. This will be followed by a
discussion of the sensor data. This will include the package deployment schedule,
data processing methods, and a presentation of the processed data. A similar
treatment of the sediment data will follow. This examination will include the
sediment sampling schedule and the presentation of the sediment data.
This chapter serves to present all of the data collected from the Longboat Key
monitoring project. These results will be evaluated to determine the effects of the
nourishment on hard bottom sedimentation rates.
3.2 Manual Turbidity Monitoring
3.2.1 Method
Manual measurements of turbidity were obtained during each field trip. Divers
obtained a water sample near the surface, mid-depth, and near the bottom of the
water column. The surface and bottom samples were obtained approximately two
feet from the surface or bottom. The water samples were then sub-sampled on board
the boat and inserted into an H-F Scientific Model DRT-15C portable turbidometer
for measurement.
3.2.2 Manual Turbidity Data
Table 3.1 provides the results of the manual turbidity readings obtained during
nourishment. These turbidity values are all well within the critical 29 NTU criterion.
These values seem reasonably low for the nourishment activity that was ongoing
during this period. It should be noted however, that this table represents only three
separate sampling dates.
Table 3.1: Manual turbidity readings (NTU), during nourishment
DATE level SK LBK6 LBK2 LBK43 LBK34 AM LK AVG
4/7/93 bot. 8 3.2 10.5 10.5 6.8 3.6 7.5 7.2
5/1/93 surf. 5.0 4.9 2.5 3.0 2.1 3.5
..m .......... . . ..................4 .................. .. ................. .... ................. .......... ....................... ....................... ..... .. ...
mid 4.9 4 2.9 1.6 1.3 2.9
bot. 3.6 3.4 1.9 2.2 1.9 2.6
7/14/93 surf. 1.9 5.2 9.1 4.7 5.4 2.5 2.8 4.5
.............. ....................... ....................... ....................... ....................... ....................... ........................ ....................... ........... ....
mid 3.4 9.7 15.3 5.4 5.8 2.4 5.6 6.8
bot. 6.5 9.3 16 5.5 9.3 2.3 7.2 8.0
surf. 3.5 5.0 5.8 3.9 3.8 2.5 2.8 4.0
Mean mid 4.2 6.9 9.1 3.5 3.6 2.4 5.6 5.0
bot.. ... 5. ......5 6.1 6.0 3.0 7...............2. ......... ........
______bo. 60 .3 .5 6.1 &6. 30 7.4 6.2
Tables 3.2a and 3.2b show the manual turbidity readings after completion of
the nourishment. In most cases, these turbidity samplings were obtained over the
course of several days so the dates given in Tables 3.1, 3.2a and 3.2b are the first day
of each of the samplings. Table 3.2a presents the manual turbidity readings after
completion of the nourishment from 9/29/93 to 3/22/94.
Table 3.2a: Manual turbidity readings (NTU), after nourishment
(9/29/93 3/22/94)
DATE level SK LBK6 LBK2 LBK43 LBK34 AM LK AVG
9/29/93 surf. 4.9 1.8 4.1 5.1 3.8 4.0
mid 4.8 2.4 1.6 5.7 5.8 4.0
bot. 4.8 2.5 2.7 13.3 8.5 6.4
10/23/93 surf. 2.8 1.8 8.7 4.5
...... ... ........... ......... ................................. ....... ............................... .... .......... ......... .... .................... ....................... ....... ................
mid 3.2 3.3 8.8 5.1
___bot. 3.1 3.0 .. 8.1 .......4.7
11/10/93 surf. 14.1 3.3 3.7 3.9 4.0 9.2 8.9 6.7
mid 15.3 4.2 4.1 5.9 22.2 19.0 15.6 12.3
___ bot. 24.9 5.7 8.3 6.3 5.5 33.8 23.1 15.4
11/30/93 surf. 5.3 2.0 2.7 12.0 5.5
mid 5.9 2.0 2.3 13.0 5.8
bot. 6.0 3.2 2.8 15.5 6.9
12/22/93 surf. 22.9 5.5 16.3 14.9
... .......... .............................................................................................................. ....... ........ .................................... ....... .... .. .. ...
mid 23.2 5.8 27.9 19.0
___ bot. 30.9 17.2 60.3 36.1
12/29/93 surf. 2.1 3.4 3.8 3.0 3.5 3.2
mid 2.2 3.0 2.7 2.9 4.3 3.0
bot. 2.6 3.1 4.7 3.8 5.2 3.9
1/11/94 surf. 5.3 2.4 3.9
mid 4.3 4.3 4.3
... ....................... ....................... .......I.4. 5.......... ....................... ....................... ....................... ........I. 4. .. ....... ...... ............
bot. 14.5 __ 14.5 14.5
2/16/94 surf. 2.7 2.1 1.6 1.2 2.0 4.1 2.8 2.4
mid 3.5 2.1 3.0 2.1 1.4 4.2 7.2 3.4
..b .. ........ ... ................ ............. 9" ........ ........ ...... .... ........... ........ 5.......... ......... .... ........ ...
bot. """10.4 3.1 9.6 2.5 29.6 5.1 10.8 10.2
3/22/94 surf 1.1 4.2 0.7 1.8 1.7 3.0 3.1 2.2
mid 1.9 3.2 1.9 2.5 1.0 4.5 2.0 2.4
bot. 3.4 3.5 7.5 3.2 1.3 1.9 13 4.8
The remainder of the post nourishment turbidity measurements are presented in
table 3.2b, the manual turbidity readings from 4/16/94 to 8/13/94. The last row in
table 3.2b represents the averages of the entire set of post nourishment turbidity
readings from 9/29/93 to 8/13/94.
Table 3.2b: Manual turbidity readings (NTU), after nourishment
(4/16/94- 8/13/94)
DATE level SK LBK6 LBK2 LBK43 LBK34 AM LK AVG
4/16/94 surf. 1.9 2.5 1.1 1.6 1.2 3.7 2.5 2.1
mid 1.5 2.2 1.4 2.5 1.9 5.8 3.1 2.6
bot. 2.6 2.9 4.9 2.7 2.1 8.0 3.7 3.8
4/30/94 surf. 1.5 1.2 1.4
mid 3.1 1.8 1.3 1.9 1.5 1.2 2.2 1.9
bot. 3.4 2.1 1.3 6.3 1.8 4.1 9.8 4.1
5/14/94 surf. 1.2 0.7 0.9 0.8 0.7 8.7 2.5 2.2
........ ........ .... .......... ......... .... ......... ............. .......... ............. .......... ........ ..... .................... ....... .. ............................ ......
mid 3.5 0.8 0.9 0.9 1.3 1.2 3.3 1.7
bot. 6.2 1.1 1.2 1.8 1.1 1.1 4.7 2.5
6/11/94 surf. 11.2 3.1 7.5 3.5 4.2 5.0 3.7 5.5
mid 12.0 4.2 9.2 4.9 3.9 5.1 3.7 6.1
bot. 12.0 7.3 1.4 5.3 7.0 6.5 4.6 6.3
6/29/94 surf. 5.4 0.9 1.2 1.4 1.6 2.1 3.1 2.2
............. ....................... ....... .... ....................... ........ .... ........... ........ .... ........... ....................... ............... ..... .. .....
mid 6.5 1.0 1.6 1.5 1.7 2.3 3.1 2.5
bot. 7.1 1.9 1.6 1.5 2.6 4.1 9.8 4.0
7/16/94 surf. 1.3 1.8 2.2 1.4 1.1 2.5 3.1 1.9
mid 1.2 1.7 2.2 1.5 1.5 2.7 3.6 2.1
__ bot. 1.8 2.1 2.7 1.7 1.9 3.4 4.6 2.6
8/4/94 surf. 1.2 0.8 1.6 1.3 1.4 1.4 3.7 1.6
mid 1.1 0.7 1.2 1.8 1.7 2.3 4.1 1.8
bot. 1.5 1.4 1.5 2.0 1.9 2.6 8.5 2.8
8/13/94 surf. 1.7 1.2 1.3 1.7 1.5 4.4 1.5 1.9
... ........... .... ................. ... ...............3^ ................. ... .... .............. ..... ..-.. ........ 8... ... .............. .... ... .......... .. ......
mid 1.8 1.2 1.5 1.2 1.2 8.1 1.5 2.4
bot. 1... 9 ....... ..... 4 1... 5 ....... ... 3 .....4 ...... 8.3 2.0 ............. ...
surf. 3.4 1.4 2.2 1.3 3.6 3.3 4.2 3.9
AVG mid 4.0 1.5 2.5 1.7 4.7 4.0 5.9 4.7
bot. 5.4 2.1 4.1 2.3 6.2 6.4 11.4 7.7
The data in tables 3.2a and 3.2b indicate that, on the whole, the manual
turbidity readings are relatively low compared to the 29 NTU standard. It must be
noted here that these turbidity values represent discrete measurements and that this
sampling cannot be considered random. These manual turbidity samples were taken
only when weather permitted. Obviously weather is a very significant forcing
mechanism for turbidity. Thus, in all likelihood, these values underestimate actual
time-average turbidity levels.
Table 3.3 shows the average manual turbidity readings for hard bottom and
control sites and presents the ratio of hard bottom to control turbidities (HB/Con) for
the nourishment and post nourishment periods.
Table 3.3: Manual turbidity readings (NTU), during and after nourishment
level Hard Bottom Control HB/Con
During surf. 4.6 2.9 1.6
Nourishment mid 5.8 4.0 1.5
bot. 7.5 5.5 1.4
After surf. 2.8 4.4 .64
Nourishment mid 3.2 5.5 .58
bot. 4.4 9.2 .48
Table 3.3 clearly illustrates three facts. First, the turbidity at the hard bottom
sites was larger than at the control sites during nourishment. Secondly, the turbidity
at the hard bottom sites decreased significantly after nourishment. Finally, the
turbidity of the hard bottom sites was significantly less than the control sites after the
nourishment. These average values are based on seventeen sampling dates.
3.3 Sensor Data
3.3.1 Sensor Deployment Schedule
The field servicing schedule for the instrument packages is dependent
primarily on their battery and data storage capacities. In the case of the system I
packages, servicing entails removing the original package for data offloading, battery
replacement, recalibration, general cleaning, and installing the spare system I
package. Due to the battery limitations of the system I, this rotation must be
performed every four to six weeks. However, the batteries of the system II package
require renewal only every three months. The limiting factor of the system II is the
memory capacity, which is filled approximately every six weeks. Data offload can
be performed in the field via a communications cable. Thus, in the case of the
system II packages, servicing would include general cleaning and data offloading in
the field approximately each month. Removal for battery replacement and
recalibration was required every third month.
The initial instrument package deployment began August 25, 1993. The
preliminary plan was to schedule field servicing every month thereafter. However,
due to severe biofouling and unforeseen package damage, the deployments were
interspersed as conditions demanded. This is illustrated in Table 3.4, a summary of
the instrument package deployments. The biofouling on the face of the OBS was
especially troublesome. It served to block out the OBS signal in a matter of days in
some cases. This problem will be discussed in greater detail in section 3.3.2.
Table 3.4: Summary of deployment activities
DATE SK LBK2 LBK34 LK
8/25/93 installed installed installed installed
9/29/93 offloaded replaced offloaded offloaded
10/23/93 offloaded replaced offloaded replaced
11/10/93 removed replaced removed removed
11/30/93 installed replaced installed installed
12/22/93 cleaned cleaned cleaned cleaned
1/11/94 replaced removed removed removed
2/16/94 replaced installed installed installed
3/22/94 removed replaced replaced replaced
4/15/94 cleaned cleaned cleaned cleaned
4/30/94 replaced replaced offloaded offloaded
5/14/94 cleaned replaced cleaned cleaned
6/11/94 offloaded replaced offloaded replaced
6/29/94 cleaned cleaned cleaned cleaned
7/16/94 replaced offloaded offloaded removed
8/4/94 cleaned cleaned cleaned
8/13/94 removed removed removed
Fortunately, the performance of the pressure transducers was very consistent.
The wave climate characteristics of average depth, significant wave height and peak
period are calculated from the pressure data. Thus, the wave climate coverage was
relatively complete. The dates of valid pressure data coverage for each deployment
are given in Table 3.5.
Table 3.5: Wave data availability summary
DEP# DATE SK LBK2 LBK34 LK
1 from 8/25/93 8/25/93 8/26/93 8/26/93
to 9/30/93 9/30/93 9/30/93 9/29/93
2 from 9/30/93 9/30/93 9/30/93 9/29/93
to 10/23/93 10/23/93 10/23/93 10/23/93
3 from 10/23/93 10/23/93 10/24/93
to 11/11/93 11/1/93 11/1/93
4 from 11/11/93
.......................... ................................. ................................. ........................... .................................
to 11/20/93
5,6 from 12/1/93 12/1/93 12/1/94 11/30/94
to 1/11/94 1/11/94 1/11/94 1/12/94
7 from 1/11/94
.......................... ................................. ................................ ................................. .................................
to 1/15/94
8 from 2/16/94 2/17/94 2/16/94
. .. .. . . .. . .. .. .. .. . ... 7 ..... ... ..... .... .. ......... ......
to 3/22/94 3/22/94 3/24/94
9 from 3/23/94 3/23/94 3/22/94
to 4/30/94 4/30/94 4/25/94
10,11 from 5/1/94 5/1/94 5/1/94 4/30/94
to 6/12/94 5/14/94 6/11/94 6/11/94
12 from 6/12/94 6/12/94 6/12/94 6/11/94
___to 7/16/94 7/16/94 7/16/94 7/12/94
13 from 7/16/94 7/17/94 7/17/94
____to 8/25/94 8/25/94 8/24/94 ....
A graphical representation of table 3.5 is given in figure 3.1, a time line of the
wave data coverage for the monitoring project. Lapses in coverage were largely due
to equipment damage and maintenance. These interruptions occurred from 11/1/93
to 12/1/93 and from 1/11/94 to 2/16/94. The first incident was due to the unexpected
severity of the biofouling of the OBS sensors. The packages were taken back to the
coastal lab for maintenance, data offload and recalibration.
9/1/93 11/1/93 1/1/94 3/1/94 5/1/94 7/1/94 9/1/94
I I II I I I I I !
SK
LBK2
LBK34
LK |
10/1/94 12/1/94 2/1/94 4/1/94 6/1/94 8/1/94
Figure 3.1: Time line of wave data coverage
The second interruption was due to extensive field damage incurred during the
sampling period beginning on 12/1/93. In this case, crab traps and their buoy lines
collected around the system I instrument package at LBK #2. Damage was inflicted
as the crab fishermen attempted to retrieve the traps and lines which were tangled
around the package. The package was damaged beyond repair. Each of the sensors
on the package was sheared off. Remarkably, the package housing was intact and we
were able to access the data for the sampling period. The second system I was not
installed at this time due to damage to the support frame. In addition, the package
sampling program for the system II packages malfunctioned and prevented data
offload. Therefore, all packages were removed from the field.
Once again, during the 2/16 to 3/22/94 sampling period, the second system I
package suffered significant damage due to crab traps. The current meter and both
OBS were damaged and the communications port was cracked. Unfortunately, the
data was lost for the deployment. The repairs required almost two months of work
and consequently the spare system II package was utilized at the Longboat Key #2
site. Furthermore, even after the repairs to the system I package, the current meter
was no longer functioning and much of the OBS signal was unsatisfactory for the
remainder of the monitoring.
3.3.2 OBS Data
As mentioned previously, the performance of the OBS sensors was dismal and
painstaking efforts to correct the problem were generally ineffective. Biofouling was
anticipated before the initial package deployment and the OBS face was painted with
tributal, an optical grade anti-biofoulant. The OBS were subsequently painted
whenever the packages were removed from the field.
It was evident that the severity of the fouling was grossly underestimated. As a
result, caustic hoods, manufactured by Oceanographic Industries, were attached to
the OBS sensors. Although this decreased the amount of fouling, the effect of the
hoods did not improve the OBS signal. The next plan of attack was to simply
remove the packages from the field more frequently to repaint and recalibrate the
OBS on location. The system II packages were eventually removed monthly for this
purpose. Unfortunately, this provided disappointing results as well. Eventually, in
addition to the monthly tributal paintings, the OBS face were subjected to
underwater field cleaning biweekly. Despite these efforts, the OBS collected valid
turbidity data for less than seven days after the OBS faces were painted with anti-
biofoulant and less than three days after cleaning with a nonscouring pad in the field.
By the eighth deployment, an 'OBS wipe' instrument was designed and
implemented. It was mounted to the OBS and mechanically cleaned the face of the
OBS every hour. Once again, this proved ineffective. The final decision was to
continue with monthly removal to repaint the OBS of the system II packages and
biweekly field cleaning and to concentrate efforts on manual turbidity readings and
maintaining our wave data coverage.
For obvious reasons, the OBS sensor data was subjected to a quality check to
assess the validity of the readings. Quality factors of one, two or three were assigned
to each burst. A quality factor of one is assigned to invalid data, two is assigned to
data of reduced accuracy and three is assigned to valid data. These assignments are
determined based on inspection of the burst turbidity mean, standard deviation,
minimum and maximum values. Invalid data is very easily determined. This data is
predominantly either a saturated or a noise signal. Thus, quality assignment of
invalid data is very objective. However, the assignment of reduced accuracy or valid
data is far more subjective and therefore prone to error. These two categories are
judged primarily by the standard deviation and secondarily by the mean value. The
nature of biofouling is such that it inflates the mean background turbidity with time
but, to some extent, relative values are not effected. Thus, before the biofouling
reaches the signal-saturation level the OBS signal may still exhibit valid standard
deviation characteristics although the mean value is actually inflated. Based on this
reasoning we believe that the data that is considered valid and reduced accuracy may
actually be inflated values.
As a result of the severe biofouling and lack of confidence in the validity of the
OBS signal, this turbidity data is deemed inconclusive. It is not appropriate to use
this data for assessment of turbidity variations in the field and will not be included in
this study.
3.3.3 Wave Data Results
The wave characteristics of average depth, significant wave height and peak
period are calculated using linear wave theory and are based solely on the pressure
signal. The pressure signal is calibrated at pounds per square inch and converted to
meters of sea water. At this point, average depth is calculated for each burst. A
spectral analysis of the pressure time series produces a wave energy spectrum which
yields significant wave height and the corresponding peak period. The influence of
high frequency surface chop and low frequency infragravity waves are eliminated by
filtering out frequencies of three seconds or less and twenty seconds or more.
A quality check of the wave data was also performed. Due to the consistent
performance of the pressure transducer, the wave data is nearly one hundred percent
valid when deployed in the field. Unfortunately, the same cannot be said for the
performance of the current meter. The reason for this is two fold. First of all the
calibration of the current meter could not be performed at our facilities. Thus, all
calibrations were done by the vendor. In addition, the field configuration of the
current meter and the field conditions encountered served to expose the sensor to
harm. When the current meter was not operating properly we were faced with the
time consuming prospect of vendor repair and recalibration. More often than not, we
opted to redeploy the package with the malfunctioning current meter rather than to
suspend wave data coverage to wait for repairs. Secondly, the current meters
suffered severe damage due to the crap traps during deployments five and eight. The
damage incurred to the system I package during deployment five was irreparable.
All sensors were sheared from the package lid and not recovered, including the
current meter. The damage inflicted during deployment eight left the remaining
current meter beyond repair. These current meter problems are reflected by the poor
coverage in the directional current data.
The plots of the wave characteristics of the complete set of valid wave data
statistics of each data burst is given in Appendix A. Each page represents the data
collected for one deployment at a given site. The characteristics plotted in each page
include average depth, significant wave height and peak period. In the calculation of
significant wave height, any value below 5 cm is considered to be zero.
The average values of the wave characteristics of average depth (Dav),
significant wave height (Hmo) and peak period (Tp), as well as, days of wave data
coverage within the period are summarized in table 3.6.
For purposes of comparison, the values in table 3.6 were calculated to
correspond to the sedimentation data periods. These values represent the averages of
the available wave data within these periods. The average values in the last row and
column are weighted to reflect the varying days of coverage within periods and
monitoring sites.
Table 3.6: Average wave data characteristics
Date Site Weighted
Start End LK LBK34 LBK2 SK Average
8/25/93 9/29/93 Dav, m 4.27 5.55 5.60 4.59 5.00
Hmo, m 0.16 0.26 0.26 0.21 0.22
Tp, s 5.65 4.97 5.02 5.27 5.23
Days 35 34 36 36 35
9/29/93 11/10/93 Dav, m 4.53 5.38 5.52 4.65 5.08
Hmo, m 0.21 0.30 0.30 0.19 0.26
Tp, s 5.02 5.47 5.59 5.44 5.39
........................ .............................................. ................................................ ................ .........
Days 32 32 40 23 32
11/10/93 12/22/93 Dav, m 4.51 5.29 5.89 5.00 5.23
Hmo, m 0.26 0.35 0.32 0.29 0.31
Tp,s 5.13 5.92 6.02 5.83 5.75
Days 22 21 30 21 24
12/22/93 2/16/94 Dav, m 4.38 5.02 5.84 4.87 5.02
Hmo, m 0.32 0.40 0.49 0.34 0.39
Tp, s 6.47 6.55 6.33 6.74 6.53
Days 21 20 20 24 21
2/16/94 3/22/94 Day, m 4.67 5.64 4.47 4.92
Hmo, m 0.26 0.32 0.26 0.28
Tp, s 5.46 5.73 6.10 5.76
....... s ...... ... .... ....... ......... 3....... ........ ....................... ........3....... ........ ........3....... ........
Days 36 33 34 34
3/22/94 4/30/94 Dav, m 5.16 5.75 4.59 5.19
Hmo, m 0.24 0.25 0.21 0.23
...... p................. ....................... .... 2 o............. .... .. .... .............. ...... ............ .... ......... ..........
Tp,s 5.20 5.02 5.11 5.11
Days 38 38 34 37
4/30/94 6/12/94 Dav, m 4.41 5.17 5.35 4.67 4.80
Hmo, m 0.15 0.18 0.15 0.16 0.16
Tp, s 3.84 4.50 3.03 4.32 4.11
Days 42 41 13 42 35
6/12/94 7/18/94 Dav, m 4.85 5.23 5.44 4.80 5.09
Hmo, m 0.21 0.27 0.28 0.25 0.25
....................... ....................... ......................................................................... ........................
Tp, s 4.70 4.34 4.18 4.03 4.30
Days 31 34 34 34 33
7/18/94 8/25/94 Dav, m 5.36 5.54 4.28 5.05
........ . . *....... ..... .... ... ... ............. ... ...... ....... ......... ........
Hmo, m 0.30 0.33 0.23 0.29
Days 38 39 40 39
Weighted
Average
Day, m
4.52
5.32
5.62
4.63
Hmo, m .21 .28 .30 .23
..... .T p..:. ............. :0 ...... ......... f ^..... .. ....... .. ........ ......
Tp,s 5.07 5.19 5.14 5.27
Days 33 34 34 34
__ __ _ __ _I __ _ L J
This time averaged data clearly shows that the hard bottom sites experience
larger significant wave heights. This trend of disproportionate wave conditions
between hard bottom and control sites is highlighted in table 3.7. Table 3.7 is a
comparison of the wave characteristics between the hard bottom (H.B.) and control
(Con) sites.
Table 3.7: Average wave data characteristics
Characteristic H.B. Con H.B./Con
Average Depth, Dav 5.47 m 4.58 m 1.19
Significant Wave Height., Hmo .29 m .22 m 1.32
Peak Period, Tp 5.17 s 5.17 s 1.0
It is evident from this table that the hard bottom sites have experienced larger
waves than the control sites while the peak period remained constant. This 32%
difference in average wave height is significant in two respects. First of all, the
average significant wave height at the hard bottom sites is larger despite the fact that
the average depth is 19% deeper than the control site. Secondly, this difference in
average significant wave heights translates to dramatic disparity when calculating
wave energy. These two ramifications will be further examined in the following
chapter.
An inspection of discrete storm events confirms the results of the time average
data. The five largest storm events recorded by our packages were examined and
these results are presented in table 3.8.
Table 3.8: Maximum wave height and period for five storm events
Event Date SK LBK2 LBK34 LK
10/29/93 to Hmo(max) 1.78 m 1.99 m 1.42 m
11/1/93 Tp(max) 10.7 s 10.7 s 10.7 s
12/14/93 to Hmo(max) 1.28 m 1.40 m 1.43 m 1.11 m
12/17/93 Tp(max) 9.1 s 9.8 s 9.1 s 9.1 s
1/03/94 to Hmo(max) 1.84 m 2.23 m 2.15 m 1.62 m
1/05/94 Tp(,ax) 10.7 s 11.6 s 12.8 s 10.7 s
3/1/94 to Hmo(max) 1.43 m 1.63 m 1.61 m
3/5/94 Tp(max) 10.7 s 10.7 s 10.7 s
8/13/94 to Hmo(max) 1.26 m 1.51 m 1.72 m
8/18/94 Tp(max) 8.0 s 7.5 s 8.0 s
Average Hmo(max) 1.45 m 1.73 m 1.77 m 1.44 m
Tp(max) 9.6 s 9.9 s 10.3 s 10.3 s
The maximum significant wave height (Hmo(max)) and maximum peak period
(Tp(max) ) for the storm events are given for each of the sites. The largest waves of the
monitoring project was recorded at LBK2 and LBK34 from 1/3/94 to 1/5/94. The
most recent storm event beginning on 8/13/94 and subsiding on 8/18/94 was tropical
storm Beryl.
Table 3.8 clearly illustrates that once again, the hard bottom sites experience
larger maximum significant wave heights in discrete storm events. This data shows
that in every case, larger maximum significant wave heights were recorded at the
hard bottom sites. In addition, the average peak period were longer at the control
sites during the storms.
3.4 Sedimentation Data
3.4.1 Sediment Trap Sampling Schedule
The sediment trap retrieval/deployment schedule is summarized in Table 3.9.
After the initial deployment in October, 1992, field trips to retrieve the samples were
scheduled for the first week of January, 1993, and approximately every four weeks
thereafter during nourishment. After the completion of nourishment, field trips were
scheduled at a maximum of every six weeks, well within the eight week retrieval
interval specified in the permit.
3.4.2 Sedimentation Data
Presented in Table 3.10 are the average sand sedimentation rates for each
sampling period. Sedimentation rates, given in milligrams per centimeters squared
per day, were calculated by dividing mass by the area of trap entrance and Julian
days in the sampling period.
Table 3.9: Deployment/Retrieval schedule
DATE SK LBK6 LBK2 LBK43 LBK34 AM LK
10/26/92 15:00 14:00 13:00 12:00
10/27/92 12:00 10:00 11:00
1/2/93 15:00 14:00
1/3/93 09:30 10:30 11:00 11:30 12:00
2/6/93 11:00 11:45 12:15 13:30 14:00 15:00 16:10
February 28, 93 Start of Nourishment
3/6/93 09:30 10:11 10:50 11:15 12:30 13:30 15:00
4/7/93 10:00
4/8/93 10:00 12:35 11:30 13:15 14:15 15:40
5/1/93 09:56 11:24 11:45 12:10 12:35 13:07 14:15
5/29/93 10:02 10:58 11:22 11:55 12:24 13:05 14:11
6/26/93 10:00 10:45 12:15 13:15 13:55 14:30 15:25
7/14/93 12:15
7/15/93 9:51
7/16/93 13:15 14:55 15:25
7/21/93 10:45 9:45 11:51
August 12, 1993 End of Nourishment
8/25/93 13:35 18:45 18:00
8/26/93 9:15 8:10 10:00 13:30
9/29/93 13:15
9/30/93 8:30 14:30 13:00 15:05 15:30 15:55
11/10/93 17:00
11/11/93 8:30 13:25 12:20 14:15 13:52 10:50
12/22/93 16:30 15:00
12/23/93
12/29/93 11:15 10:30 9:50 9:20 8:50
2/16/94 15:31 11:40
2/17/94 9:00 9:57 11:24 11:40 12:55
3/22/94 10:30 13:20 14:52 16:12 16:30
3/23/94 11:03
3/24/94 11:20
4/30/94 12:00 13:30 14:05 14:40 15:30 8:45 10:55
6/11/94 14:00 13:05 12:00 11:15 9:34
6/12/94 12:55 12:20
7/16/94 13:14 11:48 14:32 11:08 9:42
7/17/94 9:56 10:36
8/13/94 9:11
8/24/94 16:49 16:18 14:26
8/25/94 9:03 10:03 10:21 __
Table 3.10: Average sand sedimentation rates (mg/cm2/day)
Sample Period Site
Start End LBK6 LBK2 LBK43 LBK34 SK AM LK
10/26/92 1/2/93 4.64 2.87 4.28 3.26 1.53 1.23 2.65
1/2/93 2/6/93 1.49 0.36 1.10 2.11 0.09 0.97 1.89
2/6/93 3/6/93
3/6/93 4/7/93 814.37 456.51 184.63 241.15 165.85 38.31
4/7/93 5/1/93 7.89 5.18 14.67 6.44 9.44 7.65 1.59
5/1/93 5/29/93 3.29 0.72 0.47 0.71 0.79 1.00 0.92
5/29/93 6/26/93 0.91 0.41 23.12 0.87 1.43 1.04 1.09
6/26/93 7/14/93 1.01 1.07 24.97 1.01 1.84 1.75 2.96
7/14/93 8/25/93 1.08 0.98 1.39 2.75 2.48 2.55 4.02
8/25/93 9/29/93 3.34 1.28 0.90 1.34 1.12 2.17 1.95
9/29/93 11/10/93 45.00 20.55 133.40 69.56 32.41 100.36 8.29
11/10/93 12/22/93 11.69 8.34 50.10 6.44 24.93 12.58 3.70
12/22/93 2/16/94 158.04 192.22 44.01 126.27 35.16 14.02
2/16/94 3/22/94 201.40 275.02 92.22 112.86 30.85 7.54
3/22/94 4/30/94 3.94 6.33 9.94 7.94 1.06 3.07 3.14
4/30/94 6/12/94 0.98 1.25 0.75 0.98 0.65 0.98 2.83
6/12/94 7/18/94 0.89 1.35 6.35 5.54 2.78 3.86 1.79
7/18/94 8/25/94 12.08 12.95 78.42 50.57 7.47 1.96 4.67
The data presented in table 3.10 is punctuated by high sedimentation rates for
the sampling periods with ending dates of 4/7/93, 11/10/93, 12/22/93, 2/16/94,
3/22/94 and 8/25/94. This coincides to corresponding periods of high seas, presented
in the wave data results.
Presented in Table 3.11 are the average fines sedimentation rate for each
deployment/retrieval.
Table 3.11: Average fines sedimentation rates (mg/cm2/day)
Sample Period Site
Start End LBK6 LBK2 LBK43 LBK34 SK AM LK
10/26/92 1/2/93 18.19 16.30 15.03 14.71 12.44 20.08 22.44
1/2/93 2/6/93 22.90 11.50 31.20 27.02 3.58 81.26 20.43
2/6/93 3/6/93
3/6/93 4/7/93 80.72 65.35 53.65 43.72 62.20 70.74
4/7/93 5/1/93 24.06 24.00 30.63 30.40 27.66 29.99 24.21
5/1/93 5/29/93 20.47 18.86 19.10 15.92 10.13 10.79 11.04
5/29/93 6/26/93 10.20 6.81 11.19 5.90 5.04 6.80 5.26
6/26/93 7/14/93 12.17 13.42 14.19 8.44 7.21 6.39 14.72
7/14/93 8/25/93 8.09 10.04 12.20 7.45 7.12 5.86 10.78
8/25/93 9/29/93 8.58 10.22 7.93 6.57 5.44 8.08 9.42
9/29/93 11/10/94 26.02 29.91 36.49 30.73 24.33 18.87 25.11
11/10/94 12/22/93 29.70 30.09 41.58 35.20 26.02 36.75 32.22
12/22/93 2/16/94 41.41 42.95 39.34 39.02 28.75 27.61
2/16/94 3/22/94 50.41 43.50 36.58 30.08 24.78 36.68
3/22/94 4/30/94 15.06 18.87 17.35 16.02 10.42 11.32 27.35
4/30/94 6/12/94 6.64 7.50 6.87 6.35 9.02 7.41 20.92
6/12/94 7/18/94 1.52 9.52 10.54 10.04 8.81 11.85 13.60
7/18/94 8/25/94 10.74 12.35 20.58 15.44 8.82 7.64 18.66
It is evident from table 3.11 that high sedimentation values were recorded for
the sampling retrieval dates of 4/7/93, 11/10/93, 12/22/93, 2/16/94, 3/22/94 and
4/30/94. However, the values are not as dramatic as those for sand sedimentation.
This may indicate that fines sedimentation is not as sensitive to wave climate as sand
sedimentation.
Table 3.12 shows the average sand sedimentation rates of the four hard bottom
sites of Longboat Key and the average rates of the three control sites for each
deployment.
Table 3.12: Average sand sedimentation rates (mg/cm2/day)
hard bottom sites vs. control sites
Sample Period SITE
Start End H.B. Control
10/26/92 1/2/93 3.76 1.81
1/2/93 2/6/93 1.27 .99
3/6/93 4/7/93 485.17 148.44
4/7/93 5/1/93 8.55 6.23
5/1/93 5/29/93 1.30 0.91
5/29/93 6/26/93 6.33 1.19
6/26/93 7/14/93 7.02 2.19
7/14/93 8/25/93 1.55 3.02
8/25/93 9/29/93 1.71 1.75
9/29/93 11/10/94 67.13 47.02
11/10/94 12/22/93 19.14 13.74
12/22/93 2/16/94 131.42 58.48
2/16/94 3/22/94 189.55 50.41
3/22/94 4/30/94 7.04 2.42
4/30/94 6/12/94 0.99 1.49
6/12/94 7/18/94 3.53 2.81
7/18/94 8/25/94 38.50 4.7
AVERAGE 57.29 20.45
There is a very significant difference in sand sedimentation between the hard
bottom and the control sites. It seems evident that the sedimentation rate is much
higher for the sites at Longboat Key. This is illustrated in figure 3.2, a plot of this
data. It is important to note that the y-axis is this plot is in log scale.
Average Sand Sedimentation Rates
485 I Hard Bottom
190 0 Control
148 131
S47 58 50
l C7 N ON O C, 1 ON OC7S Cl Cm CR Ce Cv 00 (t
, t- l - - Cl- -l -
S T 0edm ON CR l N ca 'C N 00 W
Sediment Retrieval Date
Figure 3.2: Average sand sedimentation rates, hard bottom vs. control
In contrast, the difference in fines sedimentation rates between hard bottom
and control sites is not very pronounced. This can be seen in table 3.13. the average
fines sedimentation rates of the hard bottom and control sites for each sampling
period.
1000.00
100.00
10.00
1.00
0.10
Table 3.13: Average fines sedimentation rates (mg/cm2/day)
hard bottom sites vs. control sites
DATE SITE
Start End H.B. Control
10/26/92 1/2/93 16.06 18.32
1/2/93 2/6/93 23.15 35.09
3/6/93 4/7/93 66.57 58.89
4/7/93 5/1/93 27.27 27.29
5/1/93 5/29/93 18.59 10.65
5/29/93 6/26/93 8.53 5.70
6/26/93 7/14/93 12.06 9.44
7/14/93 8/25/93 9.44 7.92
8/25/93 9/29/93 8.32 7.65
9/29/93 11/10/94 30.79 22.77
11/10/94 12/22/93 34.14 31.66
12/22/93 2/16/94 41.24 31.80
2/16/94 3/22/94 43.50 30.51
3/22/94 4/30/94 16.82 16.36
4/30/94 6/12/94 6.84 12.45
6/12/94 7/18/94 7.91 11.42
7/18/94 8/25/94 14.78 11.71
AVERAGE 22.71 20.57
A graphical representation of table 3.13 is given in Figure 3.3. It is evident
that the temporal fluctuations in fines sedimentation are not as extreme as that for
sand and there is a less dramatic difference between the hard bottom and control
sites.
Average Fines Sedimentation Rates
70.00
60.00
50.00
< 40.00
E
S30.00
E
' 20.00
10.00
0.00
[ Hard Bottom
n Control
~No ON ^o N N ON 0 c"N N. CN- o Cl 00 ti
O' .0 1- C\ o\ C C- 00 N Cl Cl C 0----
Sediment Retrieval Date
Figure 3.3: Average fines sedimentation rates, hard bottom vs. control
Given in table 3.14 is the average sand and fines sedimentation rates of hard
bottom (HB) and control sites before, during and after nourishment. These values
are given in mg/cm2/day. The ratio of sedimentation rates of the hard bottom to
control sites (HB/Con) is also given.
Table 3.14: Average sedimentation rates before, during and after nourishment
Sand Sedimentation Rates Fines Sedimentation Rates
Control HB/Con HB
Control HB/Con
Before 2.51 1.40 1.80 19.61 26.71 0.73
During 84.94 26.99 3.15 23.74 19.98 1.19
After 51.00 20.31 2.51 22.70 19.59 1.16
The cursory analysis presented here seems to suggest three important facts.
First of all, the study period was characterized by moderate sedimentation through
the first nine months with the notable exception of the hundred year storm in March
of 1993. In contrast, sedimentation in the Fall/Winter of 1993/1994 and again in
Summer of 1994 were marked by significant activity, especially at the hard bottom
sites. Secondly, the data shows that fines sedimentation is less volatile than sand
sedimentation. Finally, there is notably greater sand sedimentation at the hard
bottom sites. However, this does not necessarily indicate that the higher rate of hard
bottom sand sedimentation is due to the nourishment. The analysis of the wave data
revealed greater wave activity for the hard bottom sites. Thus, until the relationship
between wave activity and sedimentation is understood, it is very difficult to make
any conclusions. In summary, a more thorough analysis of the sedimentation data in
conjunction with the wave data is necessary to obtain a true picture of the sediment
dynamics in Longboat Key and the adjacent control sites. This is performed in the
next chapter.
The complete set of sedimentation data is presented in Appendix B. This data
includes the dry weight of sand and the organic component of sand, the dry weight of
fines and the organic component of fines, sand and fines sedimentation rates, and the
related statistics of each site.
CHAPTER 4
DISCUSSION
4.1 Introduction
This chapter serves to determine if a general relationship exists between wave
activity and sedimentation rate as measured by the sediment traps. Specifically, this
analysis will propose a general model between sedimentation rate and wave activity.
In addition, two wave parameters will be analyzed to determine which offers the
strongest correlation to sedimentation rates.
The two wave parameters that will be examined in this analysis are significant
wave height and maximum water particle velocities. Significant wave heights have
been calculated and presented in the previous chapter. The maximum horizontal
water velocity calculations will be based on the significant wave height, as well as
the average depth and the peak period data presented in the third chapter. These
parameters will be formulated using linear wave theory and are limited to it's
assumptions. In each case, the equations used to determine the wave parameter will
be presented. This will be followed by a comparison of the wave parameter and the
sand and fines sedimentation rate for the corresponding sampling period. Finally, a
summary of the results will be presented.
A preliminary review of the wave and sedimentation data shows increasing
sedimentation with increasing wave conditions. A more detailed examination of the
monitoring data reveals two facts. First of all, the sand sedimentation, which
experience extreme temporal fluctuations, are related to a power of the wave activity.
In contrast, the fines sedimentation, which exhibit moderate temporal fluctuations are
related to wave activity linearly.
It is evident from the significant wave height and sand sedimentation data, that
sand sedimentation is related to significant wave height exponentially. Two
exponential relationships were tested. The first, the exponential power model, relates
sand sedimentation to an exponential power of the significant wave height as
follows:
bx
y = ce
where y is the sand sedimentation rate, x is the significant wave height and b and c
are constants. The second, the power model, relates sand sedimentation to a power
of significant wave height as follows:
b
y = cx
where y is the sand sedimentation rate, x is the significant wave height and b and c
are constants. The sand sedimentation rate data was plotted against the significant
wave height. The exponential power and power model trendline was formulated
and corresponding R-squared values were calculated for this data. The power
trendline showed better agreement, based on higher R-squared values. In fact, in the
case of sand sedimentation, the power trendline showed better agreement for
maximum horizontal velocity as well. Additionally, the fines sedimentation data
consistently showed the best agreement with a linear trendline for all three wave
parameters. Thus, a power relationship has been adopted for the sand sedimentation
data and a linear relationship has been adopted for the fines sedimentation data for
the significant wave height and maximum horizontal velocity analysis.
The following sections will determine which wave parameter shows the
strongest correlation to sedimentation. This chapter will evaluate the wave
parameter that exhibits the strongest correlation to sedimentation rates measured by
the sediment traps and formulate a general expression for this relationship.
4.2 Trendline and R-Squared Value Equations
The power trendline is calculated by the least squares fit of the data points
using the equation:
b
y = cx
where c and b are constants. The linear trendline is calculated by the least squares fit
of the data points using the equation:
y = mx + b
where m is the slope and b is the intercept. The R-squared value is calculated using
the equation:
R2 SSE
SST
where the error sum of squares,
2
SSE = (y, y,')
and total sum of squares,
SST= Y Yi
=l n
where y, is the wave data and yi' is the expected value of the wave data (Hines,
Montgomery, 1980).
4.3 Significant Wave Height
4.3.1 Significant Wave Height Data
The hard bottom (H.B.) and control (Con) site significant wave heights (Hmo),
sand and fines sedimentation rates for each sampling period are presented in table
4.1. In addition, the hard bottom to control site ratios (HB/Con) are presented. It is
apparent from this table that the sand increases nonlinearly with significant wave
height while the fines sedimentation exhibits a far more linear relationship.
Table 4.1: Significant wave heights and sedimentation rates
Date Hmo (m) Sand Fines
(mg/cm2/day) (mg/cm2/day)
Start End H.B. Control H.B. Control H.B. Control
8/25/93 9/29/93 .26 .19 1.71 1.75 8.32 7.65
9/29/93 11/10/93 .30 .20 67.13 47.02 30.79 22.77
11/10/93 12/22/93 .34 .28 19.14 13.74 34.14 31.66
12/22/93 2/16/94 .45 .33 131.42 58.48 41.24 31.80
2/16/94 3/22/94 .32 .26 189.55 50.41 43.50 30.51
3/22/94 4/30/94 .25 .21 7.04 2.42 16.82 16.36
4/30/94 6/12/94 .17 .16 0.99 1.49 6.84 12.45
6/12/94 7/18/94 .28 .23 3.53 2.81 7.91 11.42
7/18/94 8/25/94 .32 .23 38.50 4.70 14.78 11.71
Averages .30 .23 50.00 20.31 22.70 19.59
Ratios HB/Con 1.30 HB/Con 2.46 HB/Con 1.16
4.3.2 Significant Wave Height Sedimentation Relationship
The data from table 4.1 is presented in figure 4.1, a plot of the significant wave
height and sand sedimentation for hard bottom and control sites. The power
trendlines, equations of the trendlines, and corresponding R-squared values are
included in the plot.
This plot illustrates two interesting facts. First of all, the relatively high R-
squared values indicate agreement with the power model of sand sedimentation and
wave climate. Secondly, the trendline of the control site data lies higher than the
hard bottom sites. This is in apparent contrast with the sand sedimentation data that
showed much larger sedimentation rates at the hard bottom sites as indicated by the
hard bottom to control site ratio. This is explained partially by the fact that the wave
heights were generally larger at the hard bottom sites relative to the control sites.
Sand Sedimentation vs Significant Wave Height
0 Hard Bottom
A Control
-- Hard Bottom
- - Control
0 y= 19000x57
R2 = 0.65 A
A
A A -
y = 8900x4.7
R2 = 0.48 C
200.00
180.00 4
160.00
140.00 -
120.00
100.00
80.00 +
60.00.
40.00
20.00
0.00
0.00
0.30 0.35 0.40 0.45
Figure 4.1: Sand sedimentation rate versus significant wave height
Figure 4.2 is a plot of fines sedimentation versus significant wave heights.
Included in this figure are the linear trend lines, equations of the trendlines and
corresponding R-squared values. Figure 4.2 illustrates good agreement of the linear
relationship of significant wave height to fines sedimentation. Once again, based on
the trend lines, the control sites are predicted to experience larger rates of fines
sedimentation for a given wave size. However, the ratio of hard bottom to control
data of fines sedimentation shows slightly higher sedimentation at the hard bottom
sites due to the relatively larger waves.
0.05 0.10 0.15 0.20 0.25
Hmo (m)
Fines Sedimentation vs Significant Wave Height
45.00 Hard Bottom i
40.00 A Control /
S-- Hard Bottom
S35.00
E i - Control
S30.00 y= 140x-13 A 0 /
SR2 059 y= 150x 21
S25.00 R2 = 0.57
20.00 + /
15.00 1 o
S10.00
9i '=- -21
00 5.00 = 0
0
0.00 _-
0.00 0.10 0.20 0.30 0.40 0.50
Hmo (m)
Figure 4.2: Fines sedimentation rate versus significant wave height
4.4 Maximum Horizontal Velocity
4.4.1 Maximum Horizontal Velocity Calculations
The final wave parameter to be analyzed is maximum horizontal velocity. It
should be noted here that this represents the maximum horizontal component of
water particle velocity under a progressive wave at the depth of the mouth of the
sediment trap. Due to the sparse coverage of the current meters, this analysis does
not take into account current velocities.
The wave data were converted to horizontal velocity, u, using the following
equation:
H,,,, cosh k(h + z) c
u = "( cos(kx oat)
2 sinh kh
(Dean, Dalrymple, 1991). Thus the maximum horizontal velocity, Umax, is given
simply as:
H,,, coshk(h + z)
ma 2 sinh kh
2FI 21I
where frequency, a = -, is based on and peak period, T,; wave number, k = -,
T L
is calculated using the dispersion relation; depth, h, is equivalent to average depth,
Da,; and the height to the mouth of the sediment trap, z, is approximately 1.07 m (z is
a negative value).
The results of this conversion are given in table 4.2. The maximum horizontal
velocity and sand and fines sedimentation are given for the hard bottom and control
sites.
Table 4.2: Maximum horizontal velocity and sedimentation rates
Date Max. U-Velocity Sand Fines
(m/s) (mg/cm^2/day) (mg/cm^2/day)
Start End H.B. Control H.B Control H.B Control
8/25/93 9/29/93 .123 .111 1.71 1.75 8.32 7.65
9/29/93 11/10/93 .155 .116 67.13 47.02 30.79 22.77
11/10/93 12/22/93 .177 .158 19.14 13.74 34.14 31.66
12/22/93 2/16/94 .248 .209 131.42 58.48 41.24 31.80
2/16/94 3/22/94 .164 .158 189.55 50.41 43.50 30.51
3/22/94 4/30/94 .120 .120 7.04 2.42 16.82 16.36
4/30/94 6/12/94 .058 .075 0.99 1.49 6.84 12.45
6/12/94 7/18/94 .117 .110 3.53 2.81 7.91 11.42
7/18/94 8/25/94 .155 .144 38.50 4.70 14.78 11.71
Averages .146 .133 50.00 20.31 22.70 19.59
Ratios HB/Con 1.10 HB/Con 2.46 HB/Con 1.16
4.4.2 Maximum Horizontal Sedimentation Velocity Relationship
Presented in figure 4.3 is the plot of the sand sedimentation data and the
maximum horizontal velocity. This plot illustrates two important facts. First of all,
of the three wave parameters analyzed, the maximum horizontal velocity gives the
best correlation to sand sedimentation rate. The high R-squared values attest to this
point. Although the R-squared value for the hard bottom data shows only modest
improvement, the control data shows significant improvement. Perhaps more
importantly, however, is the fact that the hard bottom trendline predicts larger rates
of sand sedimentation than the control trendline. This supports the conclusions of
the sand sedimentation data. In addition, the values of the exponents of the hard
bottom and control trendline are much closer.
The threshold velocity for the initiation of sand grain motion, assuming a .2
millimeter diameter sand grain, and a density of 2.65 g/cm3, is approximately .15 m/s
(Bagnold, 1946). This compares favorably with the maximum horizontal velocity
values in figure 4.3. Although we find sand sedimentation occurring below .15 m/s,
it must be noted that these are average velocities over a sampling period.
Sand Sedimentation vs Maximun U-Velocity
200.00
180.00
160.00
140.00 _
120.00
100.00
80.00
60.00 -
40.00 _
20.00
0.00
0.000
o Hard Bottom
A Control
- Hard Bottom
- - Control
0.050
y= 38000x39
R2 = 0.68 /
0.100 0.1
Maximum Velocity (
A
A -
'y 19000x38
0A " R2 = 0.52
50 0.200
m/s)
0.250
Figure 4.3: Sand sedimentation rate versus maximum horizontal velocity
Figure 4.4 is a plot of the fines sedimentation data versus the maximum
horizontal velocity. In contrast, the fines data illustrates a marked improvement in
the hard bottom R-squared value and a slight drop in control R-squared values.
However, the maximum horizontal velocity data shows the greatest similarity
between the hard bottom and the control trendlines. This corresponds to the
sedimentation data that shows very little difference between hard bottom and control
fines sedimentation rates.
Fines Sedimentation vs Maximum
0 Hard Bottom
A Control
Hard Bottom
- - Control
U-Velocity
y =230x- 11
R2 = 0.65
y= 190x-6
R2 = 0.57
AO
A'O
50.00
45.00
40.00
35.00
30.00
25.00
20.00
15.00 .
10.00
5.00
0.00
0.000
0.100 0.150
Maximum Velocity (m/s)
0.200
Figure 4.4: Fines sedimentation rate versus maximum horizontal velocity
4.5 Summary
This analysis established two important facts concerning the relationship
between the two wave parameters of significant wave height and maximum
horizontal velocity and sedimentation as measured by the sediment traps. First of all,
the data indicates that a power model and a linear model best describes the
relationship between wave climate and sand sedimentation and wave climate and
fines sedimentation, respectively. Secondly, the maximum horizontal water particle
0.050
0.250
velocity at the mouth of the trap seems to offer the best correlation to sedimentation
rate.
Table 4.3 is a summary of the results of the wave parameter analysis for the
sand sedimentation data. The trendline equation and corresponding R-squared value
are given for both hard bottom and control data. This table shows that the maximum
horizontal velocity (max u-vel) parameter offers the highest R-squared value for both
hard bottom and control sites. In addition, the maximum horizontal velocity
trendline is the only one that predicts higher sedimentation rates at the hard bottom
sites for the range of data collected. This coincides with the results of the sand
sedimentation data conclusions.
Table 4.3: Trendline and R-squared Values for Sand Sedimentation Data
Parameter Site Equation R
Hmo H.B. y= 19000x57 0.65
(m) Con y = 8900x47 0.48
Max U-Vel H.B. y = 38000x3.9 0.68
(m/s) Con y = 19000x38 0.52
Table 4.4 presents the same information for fines sedimentation data. This
table shows that the maximum horizontal velocity wave parameter offers a
significantly higher R-squared value for the hard bottom trendline and an average R-
squared value for the control trendline.
Table 4.4: Trendline and R-squared values for fines sedimentation data
Parameter Site Equation R
Hmo H.B. y = 150x -21 0.57
............ .............. ... .- ............. .. .. ... .................................. .0....... ...................
(m) Con y = 140x 13 0.59
Max U-Vel H.B. y = 230x 11 0.65
(m s) Con y 1 90x 6 0..................... ...........
(ms)- Co-n y 19 0x -6 0.57
Two important facts concerning this analysis must be noted. First of all, the
relationships suggested in this analysis are simply data curve fits. These empirical
equations are not developed from sedimentation theory. Perhaps more important
than the actual equations is the fact that the trendlines are similar for both control and
hard bottom data, as would be expected. Secondly, this analysis is based on
sedimentation rates measured by the sediment traps. The equation developed in this
analysis simply relates wave forces to sedimentation rates obtained by the sediment
traps. A more sophisticated analysis must be performed to relate wave climate to
true sedimentation rates.
CHAPTER 5
SUMMARY AND CONCLUSIONS
5.1 Introduction
The focus of this study is to analyze the sedimentation monitoring of the
Longboat Key nourishment project and to evaluate the existing monitoring
guidelines. In conjunction with sedimentation, wave climate and turbidity
monitoring was conducted. This study presents the methods of monitoring with
emphasis on the new sediment trap configuration implemented for this study and the
design process. This is followed by a presentation of the results of the
sedimentation, wave climate and turbidity monitoring. Finally, an evaluation of the
relationship between wave climate and sedimentation is conducted.
A brief summary of each chapter of this study will be presented in the
following section. This will be followed by recommendations concerning the
sedimentation monitoring requirement. Finally, suggestions for further investigation
will be presented.
5.2 Summary
5.2.1 Monitoring Methods
The wave climate and turbidity monitoring was performed through the use of
in-situ instrument packages. These packages are equipped with pressure transducers,
current meters and optical backscatter sensors. The turbidity measurements were
augmented by manual turbidity readings, using a portable nephelometer. Sediment
traps were employed to obtain the sedimentation measurements.
Sedimentation monitoring is a relatively new requirement and there are no
standardized collection or analysis procedures. Thus, the design of the sediment
traps is stressed in this study. The final sediment trap configuration design consists
of two inch PVC sediment traps secured in an aluminum sediment stand which is
mounted to an aluminum post jetted into the sea bed. It has been shown that this
configuration facilitates accurate sediment sampling and reduces replicate
interference. In addition, this design proves to be sturdy and allows for effortless
trap replacement.
5.2.2 Monitoring Results
Maintaining the instrument packages proved to be a challenging task. Severe
biofouling served to undermine the integrity of all of the package turbidity data. In
addition, the packages incurred substantial damage due to crab traps, rendering the
current meters defective. However, frequent manual turbidity readings were taken in
the course of the many field trips to maintain the packages. Additionally, the
packages managed to collect consistent pressure data. Thus, a comprehensive record
of average depth, significant wave height and peak period was obtained. In contrast,
the sediment traps performed very well. In particular, the final sediment trap
configuration allowed for remarkable sedimentation coverage.
The manual turbidity readings were relatively low compared to the 29 NTU
standard. The turbidity measurements at the hard bottom sites proved to be higher
than the control sites during nourishment but were lower afterwards. On the whole,
the manual turbidity measurements seem to suggest that the nourishment did not
affect the turbidity level at Longboat Key. It is important to note that these are
discrete measurements and cannot be considered random. In reality, these values
probably underestimate actual turbidity conditions.
The results of the wave climate monitoring demonstrate that the hard bottom
sites experienced average significant wave heights 32% larger than the control sites.
An investigation of discrete storm events confirm this trend. In addition, the hard
bottom sites experienced waves with longer peak periods for these storm events.
Two important facts are evident in the results of sedimentation data. Fist of all,
the data shows that sand sedimentation experience extreme temporal fluctuations
while fines sedimentation is characterized by moderate temporal fluctuations.
Secondly, there is a significantly larger rate of sand sedimentation for the hard
bottom sites in comparison to the control sites.
5.2.3 Wave Force and Sedimentation Analysis
An analysis of the manner in which wave forces determine sedimentation as
sampled by the sediment trap is conducted in the fourth chapter of this study. This
analysis seems to establish two important facts. First of all, the data suggests that
sand sedimentation is related to a power of wave activity. In contrast, the fines
sedimentation seems to be linearly related to wave activity. Secondly, the wave
parameter of maximum horizontal water particle velocity seems to offer the best
correlation to sedimentation rate.
5.3 Sediment Monitoring Requirement Recommendations
Due to the novelty of sedimentation monitoring, present permit requirements
allows for much flexibility in sediment sample collection and analysis. In fact, the
monitoring requirement portion of the Longboat Key nourishment permit states that
"any scientifically viable procedure" can be used in the collection and analysis
methods to determine sedimentation rate (State of Florida Department of
Environmental Regulation, 1992). However, the information gained from this
monitoring project suggests that specific methods to obtain sedimentation rates can
now be defined.
Two primary recommendations are proposed here. The first recommendation
is to establish a standardized sediment trap design and field configuration. The
second recommendation is to amend the sediment sampling schedule.
5.3.1 Standardized Sedimentation Monitoring
There are two primary reasons a standardized sediment sampling method must
be specified. A tested, standardized method of sediment sampling eliminates the
start up time associated with designing, implementing and evaluating a new design.
The data collected during this start up period or before a viable method is established
may be invalid. In addition, measured sedimentation rates are dependent to some
extent on the sampling method employed. Thus, cross nourishment sedimentation
comparisons cannot be made unless a standardized method is utilized.
It is proposed that the final sediment trap configuration designed in this study
be adopted as the standard design. It performed very well over the course of the
monitoring project and has been tested and analyzed in this study. In conjunction
with this, it is recommended that the monitoring requirements be expanded to
include measurements of relative bed level at the sampling sites. This measurement
is to be taken during each sediment trap replacement using a ruled post that is jetted
into the sea floor. This not only allows for an accretional or erosional
characterization of the sedimentation rate obtained by the traps but it also would
provide valuable information on net sedimentation. Furthermore, the cost and effort
to obtain this useful data is minimal.
5.3.2 Amended Sampling Schedule
The second recommendation proposed in this study involves a minor change to
the sediment sampling schedule. Sedimentation sampling should begin at least six
months prior to nourishment and continue for a year after construction. Wave
climate monitoring should coincide with this sediment sampling schedule. In
addition, samples should be replaced monthly throughout the entire duration of the
monitoring.
The reason for this extended monitoring period before construction is to
establish a statistically significant wave climate and sedimentation baseline prior to
nourishment. An analysis of the relationship between wave forces and
sedimentation, similar to the analysis performed in chapter five of this study, can be
established for the period before and after nourishment. Thus, sedimentation rates
for a given wave condition before and after nourishment can be compared. This
would allow for a more accurate and comprehensive assessment of the nourishment
impact on sedimentation.
The increased frequency in sample replacement offers two benefits. First of
all, it will increase data points which will serve to increase statistical significance.
Secondly, the shorter sampling period will allow for a more thorough analysis of the
relationship between wave forces and sedimentation.
5.4 Suggestions for Further Investigation
The two suggestion for further investigation involves lab tests on sediment trap
designs. Important information may be gained from a comprehensive investigation
of the flow dynamics around the proposed standard sediment trap design. These
experiments may determine if the trap design facilitates representative sampling. For
example, it may determine if there is significant flow interference between the
replicates. This information can lead to improved trap designs if necessary. In
addition, a relationship between true sedimentation rates and measured sedimentation
rates may be established. This ultimately may lead to valuable insights into the
complicated dynamics of sedimentation.
Lab tests on a variation of the proposed sediment trap configuration also merits
investigation. Although current monitoring requirements specifies replicate
sampling at one height, the alternative of staggering the three replicates at different
heights from the sea floor should be analyzed. This would provide much more useful
sedimentation data. Perhaps a sedimentation profile can be interpolated from the
three sampling heights of this configuration. The replicates in this current
configuration show very little standard deviation, thus replicate sampling at one
height seems redundant. An examination of the flow dynamics around this
alternative sediment trap design may determine if representative sampling is possible
for this staggered configuration.
APPENDIX A
WAVE DATA PLOTS
LONG KEY WAVE DATA SUMMARY DEPLOYMENT #1
Sampling Period:
8/26/93@15:40:6 9/29/93@11:40:6 {bursts:12 418}
Deployment Averages:
Depth = 4.27m Significant Wave Height = 0.16m Peak Period = 5.65s
Average Depth
240.82 244.99 249.15 253.32 257.49 261.65 265.82 269.99
Significant Wave Height
240.82 244.99 249.15 253.32 257.49 261.65 265.82 269.99
Peak Period
240.82 244.99 249.15 253.32 257.49 261.65 265.82 269.99
Julian Day
-0.3
o 0.2
E
" 0.1
LONGBOAT KEY 34 WAVE DATA SUMMARY DEPLOYMENT #1
Sampling Period:
8/26/93 @ 10:43:54 9/30/93@ 12:43:54 {bursts:11 432}
Deployment Averages:
Depth = 5.55m Significant Wave Height = 0.26m Peak Period = 4.97s
Average Depth
240.70 244.86 249.03 253.20 257.36 261.53 265.70 269.86
Significant Wave Height
240.70 244.86 249.03 253.20 257.36 261.53 265.70 269.86
Peak Period
240.70 244.86
249.03 253.20 257.36
Julian Day
261.53
265.70 269.86
-5.8
S5.6
5.4
5.2
0.6
S0.4
E
0.2
LONGBOAT KEY 2 WAVE DATA SUMMARY DEPLOYMENT #1
Sampling Period:
8/25/93@18:0:15 9/30/93@12:0:15 {bursts:2 431}
Deployment Averages:
Depth = 5.47m Significant Wave Height = 0.25m Peak Period = 5.06s
Average Depth
240.75 244.92 249.08 253.25 257.42 261.58 265.75 269.92
Significant Wave Height
240.75 244.92 249.08 253.25 257.42 261.58 265.75 269.92
Peak Period
240.75 244:92 249.08 253.25 257.42 261.58 265.75 269.92
Julian Day
0.5
0.4
E0.3
0.2
SIESTA KEY WAVE DATA SUMMARY DEPLOYMENT #1
Sampling Period:
8/25/93@14:41:51 9/30/93@6:41:51 {bursts:1 429}
Deployment Averages:
Depth = 4.59m Significant Wave Height = 0.21m Peak Period = 5.27s
Average Depth
-4.8
> 4.6
4.4
240.70 244.86 249.03 253.20 257.36 261.53 265.70 269.86
Significant Wave Height
240.70 244.86 249.03 253.20 257.36 261.53 265.70 269.86
Peak Period
240.70 244.86 249.03 253.20 257.36 261.53 265.70 269.86
Julian Day
0.5
-0.4
o 0.3
E
10.2
0.1
10
g 8
S6
LONG KEY WAVE DATA SUMMARY DEPLOYMENT #2
Sampling Period:
9/29/93@16:44:45 10/23/93@14:44:45 (bursts:1 288}
Deployment Averages:
Depth = 4.5m Significant Wave Height = 0.15m Peak Period = 4.73s
Average Depth
275.78 279.95 284.11 288.28 292.45
Significant Wave Height
275.78 279.95 284.11 288.28 292.45
Peak Period
6-
4
2
275.78
279.95
284.11
Julian Day
288.28
292.45
-0.4
E
o
E 0.2
-1
LONGBOAT KEY 34 WAVE DATA SUMMARY DEPLOYMENT #2
Sampling Period:
9/30/93@ 18:0:39 10/23/93@6:0:39 {bursts:1 271}
Deployment Averages:
Depth = 5.38m Significant Wave Height = 0.23m Peak Period = 5.11s
Average Depth
276.83 281.00 285.17 289.33 293.50
Significant Wave Height
276.83
281.00
285.17
289.33
293.50
Peak Period
276.83 281.00 285.17 289.33 293.50
Julian Day
5.8
--5.6
E
d5.4
o 5.2
- 1
E
o
E 0.5
"1
n
LONGBOAT KEY 2 WAVE DATA SUMMARY DEPLOYMENT #2
Sampling Period:
9/30/93@18:0:15 10/23/93@8:0:15 {bursts:1 252}
Deployment Averages:
Depth = 5.86m Significant Wave Height = 0.24m Peak Period = 4.89s
Average Depth
622!
6
E 5.8
5.6
276.83 281.92 286.83 291.00 295.17
Significant Wave Height
1-
E 0.5 Hmo
I.
276.83
281.92
286.83
291.00
295.17
Peak Period
276.83 281.92 286.83 291.00 295.17
Julian Day
SIESTA KEY WAVE DATA SUMMARY DEPLOYMENT #2
Sampling Period:
9/30/93@10:58:59 10/23/93@8:58:59 {bursts:1 276}
Deployment Averages:
Depth = 4.65m Significant Wave Height = 0.19m Peak Period = 5.44s
Average Depth
276.54 280.71 284.87 289.04 293.21
Significant Wave Height
276.54 280.71 284.87 289.04 293.21
Peak Period
-4.8
>4.6
M
E
o0.5
E
"1
276.54 280.71 284.87 289.04 293.21
Julian Day
LONG KEY WAVE DATA SUMMARY DEPLOYMENT #3
Sampling Period:
10/24/93@10:0:55 11/1/93@18:0:55 {bursts:1 101)
Deployment Averages:
Depth = 4.62m Significant Wave Height = 0.38m Peak Period = 5.85s
Average Depth
297.17 298.00 298.83 299.67 300.50 301.33 302.17 303.00 303.83 304.67
Significant Wave Height
297.17 298.00 298.83 299.67 300.50 301.33 302.17 303.00 303.83 304.67
Peak Period
~. t n / / \
297.17 298.00 298.83 299.67 300.50 301.33 302.17 303.00
Julian Day
303.83 304.67
E 4.
>4.
O 4.
1.4
1.2
0 0.8
E 0.6
0.4
0.2
86
LONGBOAT KEY 34 WAVE DATA SUMMARY DEPLOYMENT #3
Sampling Period:
10/23/93@10:1:2- 11/1/93@18:1:2 {bursts:1 113}
Deployment Averages:
Depth = 5.39m Significant Wave Height = 0.48m Peak Period = 6.34s
Average Depth
296.17 297.00 297.83 298.67 299.50 300.33 301.17 302.00 302.83 303.67 304.50
Significant Wave Height
- ------T- -- ------
296.17 297.00 297.83 298.67 299.50 300.33 301.17 302.00 302.83 303.67 304.50
Peak Period
296.17 297.00 297.83 298.67 299.50 300.33 301.17 302.00 302.83 303.67 304.50
Julian Day
-1.5
E
o 1
E
1 0.5
u
LONGBOAT KEY 2 WAVE DATA SUMMARY DEPLOYMENT #3
Sampling Period:
10/23/93@ 12:0:15 11/11/93@ 12:0:15 {bursts:1 229}
Deployment Averages:
Depth = 5.01m Significant Wave Height = 0.35m Peak Period = 6.4s
Average Depth
297.08 298.75 300.42 302.08 303.75 305.42 307.08 308.75 310.42 312.08 313.75
Significant Wave Height
297.08 298.75 300.42 302.08 303.75 305.42 307.08 308.75 310.42 312.08 313.75
Peak Period
297.08 298.75 300.42 302.08 303.75 305.42 307.08 308.75 310.42 312.08 313.75
Julian Day
LONGBOAT KEY 2 WAVE DATA SUMMARY DEPLOYMENT #4
Sampling Period:
11/11/93@14:0:48 11/20/93@20:0:48 (bursts:2 113}
Deployment Averages:
Depth = 5.71m Significant Wave Height = 0.2m Peak Period = 7.07s
Average Depth
I -II
-
315.25 316.08 316.92 317.75 318.58 319.42 320.25 321.08
321.92 322.75 323.58
Significant Wave Height
315.25 316.08 316.92 317.75 318.58 319.42 320.25 321.08 321.92 322.75 323.58
Peak Period
315.25 316.08 316.92 317.75 318.58 319.42 320.25 321.08 321.92 322.75 323.58
Julian Day
6.2
6
E
S5.8
S5.6
5.4
5.2
8
C'3
46
4-
4
LONG KEY WAVE DATA SUMMARY DEPLOYMENT #5
Sampling Period:
11/30/93@ 16:0:52 1/12/94@4:0:52 {bursts:1 -511)
Deployment Averages:
Depth = 4.45m Significant Wave Height = 0.29m Peak Period = 5.78s
Average Depth
E4.5
0 .
337.75 341.92 346.08 350.25 354.42 358.58 362.75 1.92 6.08 10.25
Significant Wave Height
5-
15
g:-----------------------r -----
337.75 341.92 346.08 350.25 354.42 358.58 362.75 1.92
337.75 341.92 346.08 350.25 354.42 358.58 362.75 1.92
6.08 10.25
Peak Period
10
5
0
337.75 341.92 346.08 350.25 354.42 358.58 362.75 1.92 6.08 10.25
Julian Day
|