• TABLE OF CONTENTS
HIDE
 Front Cover
 Title Page
 Letter to chairman/west Pakistan...
 Table of Contents
 Preface
 General
 Summary
 Project 2: Chaj Doab
 Project 3: Lower Thal Doab
 Project 4: Upper Rechna Doab






Group Title: Ground water and reclamation program. Progress report no. 35
Title: Ground water and reclamation program. Progress report
ALL VOLUMES CITATION PAGE IMAGE ZOOMABLE PAGE TEXT
Full Citation
STANDARD VIEW MARC VIEW
Permanent Link: http://ufdc.ufl.edu/UF00054716/00001
 Material Information
Title: Ground water and reclamation program. Progress report
Series Title: Ground water and reclamation program. Progress report no. 35
Physical Description: Serial
Language: English
Creator: West Pakistan Water and Power Development Authority
Publisher: Tiptton and Kalmbach, Inc.
Publication Date: August 1965
 Subjects
Subject: Farming   ( lcsh )
Agriculture   ( lcsh )
Farm life   ( lcsh )
Spatial Coverage: Asia -- Pakistan -- West Pakistan
 Notes
Funding: Electronic resources created as part of a prototype UF Institutional Repository and Faculty Papers project by the University of Florida.
 Record Information
Bibliographic ID: UF00054716
Volume ID: VID00001
Source Institution: University of Florida
Holding Location: University of Florida
Rights Management: All rights reserved by the source institution and holding location.

Table of Contents
    Front Cover
        Front Cover
    Title Page
        Title Page
    Letter to chairman/west Pakistan water and power development authority
        Unnumbered ( 3 )
    Table of Contents
        Page i
    Preface
        Page 1
    General
        Page 1
    Summary
        Page 2
        Page 3
        Page 3a
        Page 3a
    Project 2: Chaj Doab
        Page 4
        Tubewells
            4a
            Lalian unit
                4a
            Mona unit
                4a
            Khadir unit
                Page 5
            Upper Jhelum subproject
                Page 6
            Lower Jhelum subproject
                Page 7
        Electrification
            Page 7
            Lalian unit
                Page 7
            Mona unit
                Page 8
            Upper Jhelum subproject
                Page 8
                Page 9
            Khadir unit
                Page 10
        Surface drainage
            Page 11
            Chot and Rukan drains
                Page 11
                Page 11a
                Page 11b
                Page 11c
                Page 11d
                Page 11e
                Page 11f
                Page 11g
                Page 11h
                Page 11i
                Page 11j
                Page 11k
                Page 11l
                Page 11m
                Page 11n
                Page 11o
                Page 11p
    Project 3: Lower Thal Doab
        Page 12
        Tubewells
            Page 12a
            Kot Adu unit
                Page 12a
            Alipur unit
                Page 12a
        Surface drainage
            Page 12a
            Kot Adu main drain
                Page 12a
            Budh branch drain
                Page 14
                Page 15
                Page 14a
    Project 4: Upper Rechna Doab
        Page 15
        Tubewells
            Page 15a
            Marala-ravi unit
                Page 15a
Full Text


Dr. P. E. HILDEBRAND
Chief Economist
9Of L9


WEST PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
LAHORE, PAKISTAN


GROUND WATER AND RECLAMATION


PROGRAM


PROGRESS


REPORT


AUGUST 1965

















TIPTON AND KALMBACH, INC.
ENGINEERS


DENVER, COLORADO


NO. 35


LAHORE, PAKISTAN













WEST PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
LAHORE, PAKISTAN







GROUND WATER AND RECLAMATION PROGRAM


PROGRESS


REPORT


AUGUST 1965



















TIPTON AND KALMBACH, INC.

ENGINEERS


DENVER, COLORADO


NO. 35


LAHORE, PAKISTAN










TIPTON AND KALMBACH, INC.
300 INSURANCE BUILDING
831-14TH STREET
DENVER,COLORADO 80202
R.J. TIPTON. PRESIDENT CABLES:
OLIN KALMBACH, VICE-PRES. PHONE 244-2944 ARTIP DENVER
JINCY HUNT, TREASURER
r L. .KIROIS. SECRETARY TIPAK LAHOPR
October 2, 1965







Chairman
West Pakistan Water and Power Development Authority
Sunny View Estate
Kashmir Road
Lahore, Pakistan


Subject: Ground Water and Reclamation Program
Progress Report No. 35

Dear Sir:


There are transmitted herewith two copies of Progress Report No.
35 covering progress on the construction of Ground Water Reclamation
Program works underway during the month of August 1965.


Respectfully submitted,

TIPTON AND KALMBACH, INC.





By
V "ton

Distribution:

Mr. Sayyid Hamid, Chief Engineer, Ground Water and
Reclamation Division 15 cys.
Mr. Ch. A. Hamid, General Manager Power 3 cys.
Harza Engineering Company, International, Chicago 2 cys.
Commonwealth Associates, Inc., Jackson, Michigan 2 cys.
Tipton and Kalmbach, Inc., Lahore 30 cys.









CONTENTS

Page
PREFACE ......... ..... ........... .... ..... ... .... 1

GENERAL *,....................................

SUMMARY ............................Z............. 2
Figure 1 Location Map
Table 1 Project Subdivisions Following 3


PROJECT NO. 2 CHAJ DOAB

Tubewells
Lalian Unit ....................,,..,.,,, 4
Mona Unit .................... .......... 4
Khadir Unit 5.............................. 5
Upper Jhelum Subproject .................. 6
Lower Jhelum Subproject ................ .... 7

Electrification
Lalian Unit ............,............,... 7
Mona Unit ......,&.........,.,........, 8
Upper Jhelum Subproject **.............*... 8
Khadir Unit ..............................

Surface Drainage
Chot and Rukan Drains ..................... 11


PROJECT NO.3 LOWER THAL DOAB

Tubewells
Kot Adu Unit ............................. 12
Alipur Unit ...............................,, 12

Surface Drainage
Kot Adu Main Drain ........1....,....,,,,,. 12
Budh Branch Drain *........,.............,, 1


PROJECT NO. 4 UPPER RECHNA DOAB

Tubewells
Marala-Ravi Unit ...........,........*.., 5


- i









WEST PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
LAHORE, PAKISTAN

GROUND WATER AND RECLAMATION PROGRAM

PROGRESS REPORT NO. 35


August 1965



PREFACE



This report covers progress through the period ending 31 August
1965 on construction and electrification of tubewells and construction
of surface drainage works in the Northern Zone of the Indus Plains.
The works covered in this report are part of the Ground Water and
Reclamation Program of the West Pakistan Water and Power Development
Authority.

Contract preparation and supervision of construction of the
tubewells and surface drainage works is being performed by Tipton and
Kalmbach, Inc., with the assistance of the engineering staff of the
Ground Water and Reclamation Division of the Authority. Administration
and supervision of the electrification of tubewells for the Upper
Jhelum Subproject is being performed by Commonwealth Associates, Inc.
For all other Subprojects and Units presently underway, electrification
supervision is by the Electricity Department of the Authority. The
status of electrification of tubewells reported herein has been excerpted
from information furnished by Commonwealth Associates and the
Electricity Department.

For purposes of planning, the Ground Water and Reclamation
Program is divided into Projects which encompass entire doabs or
major portions thereof. These Projects are further divided into
Subprojects and Units for purposes of construction. The location
of the Projects and their subdivisions are shown on Figure 1.


GENERAL

At the end of August the construction inspection and support
staff of the Engineer and the Authority assigned to field operations
consisted of the following personnel :









WEST PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
LAHORE, PAKISTAN

GROUND WATER AND RECLAMATION PROGRAM

PROGRESS REPORT NO. 35


August 1965



PREFACE



This report covers progress through the period ending 31 August
1965 on construction and electrification of tubewells and construction
of surface drainage works in the Northern Zone of the Indus Plains.
The works covered in this report are part of the Ground Water and
Reclamation Program of the West Pakistan Water and Power Development
Authority.

Contract preparation and supervision of construction of the
tubewells and surface drainage works is being performed by Tipton and
Kalmbach, Inc., with the assistance of the engineering staff of the
Ground Water and Reclamation Division of the Authority. Administration
and supervision of the electrification of tubewells for the Upper
Jhelum Subproject is being performed by Commonwealth Associates, Inc.
For all other Subprojects and Units presently underway, electrification
supervision is by the Electricity Department of the Authority. The
status of electrification of tubewells reported herein has been excerpted
from information furnished by Commonwealth Associates and the
Electricity Department.

For purposes of planning, the Ground Water and Reclamation
Program is divided into Projects which encompass entire doabs or
major portions thereof. These Projects are further divided into
Subprojects and Units for purposes of construction. The location
of the Projects and their subdivisions are shown on Figure 1.


GENERAL

At the end of August the construction inspection and support
staff of the Engineer and the Authority assigned to field operations
consisted of the following personnel :














Engineer WAPDA Pakistani Staff
Expatriate Inspection Support


Lower Thal (Alipur & Drainage)
Mona Unit
Upper Jhelum Subproject
Khadir Unit
Motor Pool
a) Upper Jhelum
b) Khadir


At the end of this report period 58 vehicles were assigned
to field units for transportation. Three of these vehicles were
down for repairs, leaving 94.8 percent of the vehicles assigned to
the field available for use.

The following table indicates temperature and rainfall data
for the cities of Jhelum, Sargodha and Multan during the month of
August. Jhelum is adjacent to the Upper Jhelum Subproject;
Sargodha is the closest major city to the Khadir Unit and Multan
is adjacent to the Lower Thal area of Project No. 3.


Jhelum
Multan
Sargodha


Recorded Temp ,During Month Precipitation During Month
Total Days on Which
Maximum Minimum
Amount Recorded
103 67 3.8 in. 7 days
107 73 0.3 in. 1 day
103 70 2.0 in. 6 days


SUMMARY


Construction of Project No.1 Central Rechna Doab, was
substantially completed in 1962. The status of the construction
of tubewells and surface drainage works in the Subprojects and
Units which have been authorized for construction under Projects
2, 3 and 4 as follows :

Project No. 2 Chaj Doab


Tubewells
Lalian Unit
Mona Unit
Khadir Unit
Upper Jhelum Subproject
Lower Jhelum Subproject

Surface Drains
Chot and Rukan Drains


Gross Area
(Acres)
137,000
112,000
170,000
623,000
673,000
Lengths
(Miles)
19.5


Number of
Tubewells
163
138
205
815
760
Number of
Structures
60


Estimated %
Completion
100%
98.5
19
18
0
Estimated %
Completion
14


-2-














Project No. 3 Lower Thai Doab

Gross Area
Tubewells (Acres)


Kot Adu Unit
Alipur Unit


Surface Drains


400,000
400,000


Length
(Miles)


Kot Adu Main Drain 24,6
Budh Branch Drain 17.2


Project No. 4 Upper Rechna Doab


Number of
Tubewells


475
500


Number of
Structures


Estimated %
Completion


0
0.5


Estimated %
Completion


Gross Area
(Acres)


Tubewells


Number of
Tubewells


Estimated %
Completion


Marala-Ravi Unit


178,000


300


-3 -













LEGEND
'-- PROJECT AND SUBDIVISION BOUNDARIES

PROJECT NO. I CENTRAL RECHNA DOAS

PROJECT NO.2- CHAJ DOAS

J PROJECT NO.3- LOWER THAL DOAB

| J PROJECT NO.4- UPPER RECHNA DOAB

PROJECT NO. LOWER RECHNA DOAB


STATUS OF CONSTRUCTION

MI1 CONTRACT IN PREPARATION

UNDER CONSTRUCTION

COMPLETED


2tALE F ME o
SCALE OF MILES


WEST PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
TIPTON AND KALMBACH, INC. ENGINEERS

GROtIND WATER AND RECLAMATION PROGRAM

LOCATION MAP


I N






TABLE I
GROUND WATER AND RECLAMATION PROGRAM
PROJECT SUBDIVISIONS

COLOR PROJECT SERIAL IDENTIFYING
CODE NUMBER PROJECT TITLE AND SUBDIVISIONS NUMBER NUMBER

I I I CENTRAL RECHNA DOAB
Pindi Bhattian Unit I 01
Chichoki Mallian Unit 2 102
Chuharkana Unit 3 103
Jaranwala Unit 4 I04
Shahkot Unit 5 105
Zafarwal Unit 6 106
Khangah Dogran Unit 7 107
Sangla Hill Unit 8 108
Beranwala Unit 9 109
Harse Sheikh Unit 10 1010
Hafizabad Unit 11 10il
Shadman Unit 12 1012


1 1 2 CHAJ DOAB 2
Lalian Unit I 201
Mona Unit 2 202
Khadir Unit 3 203
Upper Jhelum Sub-Project 21
Sohawa Unit 4 214
Busal Unit 5 215
Phalia Unit 6 216
Lower Jhelum Sub-Project 22
FI Unit 7 227
F2 Unit 8 228
LI Unit 9 229
Gujrat Plain Unit 10 2010


I- I 3 LOWER THAL DOAB 3
Kot Adu Unit I 301
Alipur Unit 2 30.2
Rangpur Unit 3 303
Saline Zone 4 304


I 'I 4 UPPER RECHNA DOAB 4
Maralo-Ravi Unit I 401

S I 5 LOWER RECHNA DOAB 5

































PROJECT 2

CHAJ DOAB










PROJECT NO. 2 CHAJ DOAB


TUBEWELLS


Lalian Unit

The Lalian Unit of Project No. 2 consists of 137,000 acres in
the east-central portion of Chaj Doab in which 163 tubewells have been
constructed.

Construction and electrification of tubewells in the Lalian
Unit by Ingra of Yugoslavia, under a contract whose commencement
date was 27 January 1962, was completed on 1 August 1963. Construction
of the pumphouses for tubewells in this unit by Malik Mohammad Hussain
and Company, under a Contract dated 5 June 1963, was completed in
December 1963.

Mona Unit

The Mona Unit of Project No. 2 consists of 112,000 acres in
the north-central portion of Chaj Doab in which 138 tubewells have
been constructed. Figure 2-102A shows the location and designations
of the tubewells in the Mona Unit,

Construction of the tubewells in the Mona Unit under the
terms and conditions of a contract between the Samad-Vaughn
Construction Corporation and the Authority, dated 21 August 1962
has been completed by their subcontractor Geoistrazivanja,

On 3 April 1965 the Contract for the Construction of
Tubewells in the Mona Unit between the Authority and the Samad-
Vaughn Construction Corporation was cancelled. On this date
performance of the Contract was taken over by the Eastern Federal
Union Insurance Company, who were sureties for the Contractor.
The chief engineer of the surety has taken charge of the work in
the field.

The status of the construction of tubewells in the Mona
Unit is shown in Table 2-102 and figure 2-102B. The surety has
completed the construction of all pumphousos and has completed the
internal wiring and service mast installation. There are about
10 installations which cannot be completed until certain damaged
components of the motor controls are repaired or replaced. The
required components will be salvaged from certain surplus motor
controls held by the Authority.
No payments have been made to the Samad-Vaughn Construction
Corporation, to his surety, the Eastern Federal Union Insurance
Company, nor to the Subcontractor, Geoistrazivanja, during August.
The status of payments under this Contract is shown in Progress
Report No. 25.


-4-










PROJECT NO. 2 CHAJ DOAB


TUBEWELLS


Lalian Unit

The Lalian Unit of Project No. 2 consists of 137,000 acres in
the east-central portion of Chaj Doab in which 163 tubewells have been
constructed.

Construction and electrification of tubewells in the Lalian
Unit by Ingra of Yugoslavia, under a contract whose commencement
date was 27 January 1962, was completed on 1 August 1963. Construction
of the pumphouses for tubewells in this unit by Malik Mohammad Hussain
and Company, under a Contract dated 5 June 1963, was completed in
December 1963.

Mona Unit

The Mona Unit of Project No. 2 consists of 112,000 acres in
the north-central portion of Chaj Doab in which 138 tubewells have
been constructed. Figure 2-102A shows the location and designations
of the tubewells in the Mona Unit,

Construction of the tubewells in the Mona Unit under the
terms and conditions of a contract between the Samad-Vaughn
Construction Corporation and the Authority, dated 21 August 1962
has been completed by their subcontractor Geoistrazivanja,

On 3 April 1965 the Contract for the Construction of
Tubewells in the Mona Unit between the Authority and the Samad-
Vaughn Construction Corporation was cancelled. On this date
performance of the Contract was taken over by the Eastern Federal
Union Insurance Company, who were sureties for the Contractor.
The chief engineer of the surety has taken charge of the work in
the field.

The status of the construction of tubewells in the Mona
Unit is shown in Table 2-102 and figure 2-102B. The surety has
completed the construction of all pumphousos and has completed the
internal wiring and service mast installation. There are about
10 installations which cannot be completed until certain damaged
components of the motor controls are repaired or replaced. The
required components will be salvaged from certain surplus motor
controls held by the Authority.
No payments have been made to the Samad-Vaughn Construction
Corporation, to his surety, the Eastern Federal Union Insurance
Company, nor to the Subcontractor, Geoistrazivanja, during August.
The status of payments under this Contract is shown in Progress
Report No. 25.


-4-










PROJECT NO. 2 CHAJ DOAB


TUBEWELLS


Lalian Unit

The Lalian Unit of Project No. 2 consists of 137,000 acres in
the east-central portion of Chaj Doab in which 163 tubewells have been
constructed.

Construction and electrification of tubewells in the Lalian
Unit by Ingra of Yugoslavia, under a contract whose commencement
date was 27 January 1962, was completed on 1 August 1963. Construction
of the pumphouses for tubewells in this unit by Malik Mohammad Hussain
and Company, under a Contract dated 5 June 1963, was completed in
December 1963.

Mona Unit

The Mona Unit of Project No. 2 consists of 112,000 acres in
the north-central portion of Chaj Doab in which 138 tubewells have
been constructed. Figure 2-102A shows the location and designations
of the tubewells in the Mona Unit,

Construction of the tubewells in the Mona Unit under the
terms and conditions of a contract between the Samad-Vaughn
Construction Corporation and the Authority, dated 21 August 1962
has been completed by their subcontractor Geoistrazivanja,

On 3 April 1965 the Contract for the Construction of
Tubewells in the Mona Unit between the Authority and the Samad-
Vaughn Construction Corporation was cancelled. On this date
performance of the Contract was taken over by the Eastern Federal
Union Insurance Company, who were sureties for the Contractor.
The chief engineer of the surety has taken charge of the work in
the field.

The status of the construction of tubewells in the Mona
Unit is shown in Table 2-102 and figure 2-102B. The surety has
completed the construction of all pumphousos and has completed the
internal wiring and service mast installation. There are about
10 installations which cannot be completed until certain damaged
components of the motor controls are repaired or replaced. The
required components will be salvaged from certain surplus motor
controls held by the Authority.
No payments have been made to the Samad-Vaughn Construction
Corporation, to his surety, the Eastern Federal Union Insurance
Company, nor to the Subcontractor, Geoistrazivanja, during August.
The status of payments under this Contract is shown in Progress
Report No. 25.


-4-









Khadir Unit

The Khadir Unit of Project No.2 consists of 170,000 acres
in the south central portion of Chaj Doab in which 216 tubewells
are being constructed. The contract was awarded on the basis of
205 tubewells, but 11 additional tubewells have been sited to date.
Figure 2-103A shows the locations of tubewells being constructed in
the Khadir Unit.

Construction and electrification of the tubewells in the Khadir
Unit is being carried out under Contract No. 2-103 by Geoistrazivanja
of Zagreb, Yugoslavia. Energoinvest of Sarajevo, Yugoslavia have
subcontracted for the electrification work.

The status of the construction of tubewells in the Khadir Unit
is shown in Table 2-103 and in Figure 2-103B.

During August the Contractor continued construction of tubewells
at a rather slow pace. The slowness of progress was primarily due to
the lack of fiberglass tubewell casing, the reasons for which have been
stated in previous reports. The Contractor has not yet given the
guarantee for the period of 4 years against failure due to use of pipe
having slots other than as specified for tubewells constructed with
Micarta fiberglass pipe having wide slots.

During this report period the Engineer forwarded to the
Authority, Robert W. Hunt Company Inspection Report and Inspection
Certificate No. 3057 MCA. These documents covered the inspection of
3,878.5 linear feet of 8 inch and 10 inch diameter fiberglass pipe
and accessory materials. To date Inspection Reports and Inspection
Certificates covering the inspection of 10,917.50 linear feet of
fiberglass pipe and accessories for use on the Khadir Unit have been
forwarded to the Authority.

During this report period the Engineer supervised the
inspection of 576 linear feet of 15-1/2 inch diameter steel pipe
fabricated by Orient Technical Works of Lahore for Geoistrazivanja
for use as pump housing casing on Khadir Unit Tubewells. To date
8,256 linear feet of 15-1/2 inch diameter pipe has been inspected
and shipped to the project area.

The inspection of Siemens motors scheduled for use on the
Khadir Unit was started at Siemens Karachi works during this report
period. The first group of 88 motors was inspected and full
performance tests were completed on one motor of each type being
furnished by Siemens to Geoistrazivanja for use on Khadir Unit
tubewells. The Engineer has not yet received the tabulated results
of these tests. Upon receipt of this data an Inspection
Certificate covering this work will be issued.

The manufacture of motor control cabinet assemblies scheduled
for use on the Khadir Unit has been started at Siemens Karachi works
but no units had been completed at the end of this report period.

5 -










No payments were made to the Contractor during August. The
status of payments made to the Contractor through the end of August
for tubewell construction work in the Khadir Unit is shown in the
following table :

Portion For Barter Portion In Rupees
Cost In Rupees
This Period To Date This Period To Date
Contract Earnings 0.00 777,970.05 0.00 283,674.62
Deductions Under
Advance of Funds 0.00 777,970.05 0.00 99,286.11
Net Amount Paid 0.00 0.00 0.00 184,388.51



Upper Jhelum Subproject

The Upper Jhelum Subpxoject consists of 623,000 acres in the
upper half of Chaj Doab in which approximately 865 tubewells will be
constructed. The contract was awarded on the basis of 815 tubewells,
but present indications are that the number of tubewells required
may approach 890. Figure 2-104A shows the locations of the tubewella
in the Upper Jhelum Subproject.

Construction of the tubewells in the Upper Jhelum Subproject
is being carried out under Contract No. 2-104 by Southeastern Asia
Drilling Company and their Subcontractor, Harold T. Smith, Inc.

The status of tubewell construction in the Upper Jhelum
Subproject is shown in Table 2-104 and Figure 2-104B.

Tubewell construction continued at a steady pace again this
month. Forty-three tubewells were drilled, cased and shrouded; 43
tubewells were developed and tested; and on 28 tubewells the concrete
pump pedestal and floor slab and footings were poured. All tubewells
constructed during August were constructed using fiberglass tubewell
casing. All phases of construction were delayed at times because of
the rainy weather.

The report on the results of the testing of Siemens motors
and motor control components in Germany was transmitted to the
Authority.

During the month of August electric motors, electric motor
control cabinets and electric meter board assemblies were inspected
at Siemens Karachi works. Eighty-nine motors4 90 motor control
cabinets and 535 meter board assemblies were inspected. The Engineer
has not received the test sheets from Siemens. When these sheets
are received Certificates of Inspection for the material will be
issued.










The Engineer has received from the Robert W. Hunt Company,
and transmitted to the Authority to date, Inspection Report and
Inspection Certificates 352 JJC dated 14 June 1965; 350 JJC-1088AMcK
dated 27 April 19654 1079AMcK dated 5 April 1965; 1071 AMcK dated
10 February 1965; and 1060 AMcK dated 19 and 21 January 1965; and
Inspection Report No. 354 JJC. These certificates and reports cover
120,287.39 linear feet of 8 inch and 10 inch diameter fiberglass
pipe having .18 inch and .20 inch wall thickness and accessories such
as Delrin keys connectors, reducers, adhesive kits, end plates, etc.

Payments made to the Contractor during August are shown in
the following table :

Portion Tn Dollars Portion In Rupees
This Period To Date This Period To Date
Contract Earnings 277,171.30 933,866.43 360,199.34 1,446,716.71

Deductions Under
Advance of Funds 138,585.65 465,172.56 180,099.67 690,001.29

Net Amount Paid 138,585.65 468,693.87 180,099.67 756,715.42


Lower Jhelum Subproject

The Lower Jhelum Subproject of Project No.2 consists of
623,000 acres in the lower half of Chaj Doab in which it is planned
to construct approximately 760 tubewells.

No date has yet been established for calling for tenders on
Contract No. 2-107 for construction of the tubewells in the Lower
Jhelum Subproject. Prequalification of contractors for this contract
has been reopened. The prequalification questionnaire and project
synopsis have been approved by the AID office in Lahore, Contractors
presently prequalified may update their data, indicate that they are
no longer interested in prequalifying or accept prequalification
under the previously submitted data. All contractors who were
previously contracted have been notified that prequalification has
again been opened. New notices of prequalification have been
published as required by AID regulations.


ELECTRIFICATION

Lalian Unit

Electrification of the Lalian tubewells was completed by
Ingra in 1963 as part of the Contract covering construction of
tubewells,


-7-










The Engineer has received from the Robert W. Hunt Company,
and transmitted to the Authority to date, Inspection Report and
Inspection Certificates 352 JJC dated 14 June 1965; 350 JJC-1088AMcK
dated 27 April 19654 1079AMcK dated 5 April 1965; 1071 AMcK dated
10 February 1965; and 1060 AMcK dated 19 and 21 January 1965; and
Inspection Report No. 354 JJC. These certificates and reports cover
120,287.39 linear feet of 8 inch and 10 inch diameter fiberglass
pipe having .18 inch and .20 inch wall thickness and accessories such
as Delrin keys connectors, reducers, adhesive kits, end plates, etc.

Payments made to the Contractor during August are shown in
the following table :

Portion Tn Dollars Portion In Rupees
This Period To Date This Period To Date
Contract Earnings 277,171.30 933,866.43 360,199.34 1,446,716.71

Deductions Under
Advance of Funds 138,585.65 465,172.56 180,099.67 690,001.29

Net Amount Paid 138,585.65 468,693.87 180,099.67 756,715.42


Lower Jhelum Subproject

The Lower Jhelum Subproject of Project No.2 consists of
623,000 acres in the lower half of Chaj Doab in which it is planned
to construct approximately 760 tubewells.

No date has yet been established for calling for tenders on
Contract No. 2-107 for construction of the tubewells in the Lower
Jhelum Subproject. Prequalification of contractors for this contract
has been reopened. The prequalification questionnaire and project
synopsis have been approved by the AID office in Lahore, Contractors
presently prequalified may update their data, indicate that they are
no longer interested in prequalifying or accept prequalification
under the previously submitted data. All contractors who were
previously contracted have been notified that prequalification has
again been opened. New notices of prequalification have been
published as required by AID regulations.


ELECTRIFICATION

Lalian Unit

Electrification of the Lalian tubewells was completed by
Ingra in 1963 as part of the Contract covering construction of
tubewells,


-7-










The Engineer has received from the Robert W. Hunt Company,
and transmitted to the Authority to date, Inspection Report and
Inspection Certificates 352 JJC dated 14 June 1965; 350 JJC-1088AMcK
dated 27 April 19654 1079AMcK dated 5 April 1965; 1071 AMcK dated
10 February 1965; and 1060 AMcK dated 19 and 21 January 1965; and
Inspection Report No. 354 JJC. These certificates and reports cover
120,287.39 linear feet of 8 inch and 10 inch diameter fiberglass
pipe having .18 inch and .20 inch wall thickness and accessories such
as Delrin keys connectors, reducers, adhesive kits, end plates, etc.

Payments made to the Contractor during August are shown in
the following table :

Portion Tn Dollars Portion In Rupees
This Period To Date This Period To Date
Contract Earnings 277,171.30 933,866.43 360,199.34 1,446,716.71

Deductions Under
Advance of Funds 138,585.65 465,172.56 180,099.67 690,001.29

Net Amount Paid 138,585.65 468,693.87 180,099.67 756,715.42


Lower Jhelum Subproject

The Lower Jhelum Subproject of Project No.2 consists of
623,000 acres in the lower half of Chaj Doab in which it is planned
to construct approximately 760 tubewells.

No date has yet been established for calling for tenders on
Contract No. 2-107 for construction of the tubewells in the Lower
Jhelum Subproject. Prequalification of contractors for this contract
has been reopened. The prequalification questionnaire and project
synopsis have been approved by the AID office in Lahore, Contractors
presently prequalified may update their data, indicate that they are
no longer interested in prequalifying or accept prequalification
under the previously submitted data. All contractors who were
previously contracted have been notified that prequalification has
again been opened. New notices of prequalification have been
published as required by AID regulations.


ELECTRIFICATION

Lalian Unit

Electrification of the Lalian tubewells was completed by
Ingra in 1963 as part of the Contract covering construction of
tubewells,


-7-










Mona Unit


Electrification of the Mona tubewells is being accomplished
by the Electricity Department of WAPDA. The status of electrification
of the Mona tubewells is shown on Figures 2-103C and 2-103D.

The construction of substations and 11 KV distribution lines
was completed by the WAPDA Electricity Department in July. The
service drop was installed at 28 tubewells during August, bringing
the total number of service drops installed to 128. Ten service
drops remain to be installed. It is anticipated that this work will
be completed during September.

Upper Jhelum Subproject

Electrification of tubewells in the Upper Jhelum Subproject
will be carried out under a separate contract with the engineering
and supervision of construction being performed by Commonwealth
Associates. Figures 2-104C and 2-104D indicate the construction
schedules as proposed by Commonwealth in December 1964 and as
revised in August 1965.

Tender Documents for the 132 KV transmission lines are largely
completed and are expected to be issued early in September. Tower
designs have been selected, and economic conductor size and material
have been determined. Plans and profiles to be issued with the
Tender Documents are complete.

Strip maps showing routes for the 132 KV transmission lines
have been prepared. Following final inspection of routes now under
way, these maps are expected to be submitted to WAPDA for approval
by September 10.

Double-circuit, steel towers with single circuit installed
have been approved by V2DA':s General Consultants, Harza Engineering
Company, International, for the SCARP-2A Project. In view of the
small, 10 percent, additional cost of double-circuit towers over
single-circuit towers, it was considered desirable to build
double-circuit towers with single circuit installed on the 60 mile,
SCARP-2A portion of the line,

Final revision of the Tender Documents for Substation
construction as requested by AID and WAPDA has been made and the
revised Tender Documents are expected to be issued early in
September.

Site locations for the Helan and Busal Substations have
been selected and surveyed, and plot-plan drawings have been prepared.
Following completion of final field check, substation site-location
drawings will be submitted to WAPDA for approval.


-8-










Mona Unit


Electrification of the Mona tubewells is being accomplished
by the Electricity Department of WAPDA. The status of electrification
of the Mona tubewells is shown on Figures 2-103C and 2-103D.

The construction of substations and 11 KV distribution lines
was completed by the WAPDA Electricity Department in July. The
service drop was installed at 28 tubewells during August, bringing
the total number of service drops installed to 128. Ten service
drops remain to be installed. It is anticipated that this work will
be completed during September.

Upper Jhelum Subproject

Electrification of tubewells in the Upper Jhelum Subproject
will be carried out under a separate contract with the engineering
and supervision of construction being performed by Commonwealth
Associates. Figures 2-104C and 2-104D indicate the construction
schedules as proposed by Commonwealth in December 1964 and as
revised in August 1965.

Tender Documents for the 132 KV transmission lines are largely
completed and are expected to be issued early in September. Tower
designs have been selected, and economic conductor size and material
have been determined. Plans and profiles to be issued with the
Tender Documents are complete.

Strip maps showing routes for the 132 KV transmission lines
have been prepared. Following final inspection of routes now under
way, these maps are expected to be submitted to WAPDA for approval
by September 10.

Double-circuit, steel towers with single circuit installed
have been approved by V2DA':s General Consultants, Harza Engineering
Company, International, for the SCARP-2A Project. In view of the
small, 10 percent, additional cost of double-circuit towers over
single-circuit towers, it was considered desirable to build
double-circuit towers with single circuit installed on the 60 mile,
SCARP-2A portion of the line,

Final revision of the Tender Documents for Substation
construction as requested by AID and WAPDA has been made and the
revised Tender Documents are expected to be issued early in
September.

Site locations for the Helan and Busal Substations have
been selected and surveyed, and plot-plan drawings have been prepared.
Following completion of final field check, substation site-location
drawings will be submitted to WAPDA for approval.


-8-









In accordance with procedures established by the United
States Agency for International Development (AID) under the Loan
Agreement for the SCARP-2A Project, WAPDA submitted the proposed
Tender Documents for 11 KV distribution line construction with their
comments to AID. Conferences were then held between AID and
Commonwealth in AID's Karachi offices which necessitated making
changes to the Tender Document in addition to those previously made
by WAPDA. In view of these revisions, it was necessary to revise
the Tender Documents and to have them rebound instead of issuing an
addendum. This revision is currently in progress. It is expected
that the revised Tender Documents will be furnished to WAPDA on or
before September 11.

The tabulations summarizing Commonwealth's evaluation of bids
which were transmitted to WAPDA by letter of July 21, 1965, recommending
the supplier for the 12/16/Fut20-Mva transformers for the proposed
Helan and Busal Substations as well as for the 5.0/6.25 Mva transformer
to be installed at the present main grid station at Gujrat, were
revised to show values corresponding to the total quantity of each
bid item instead of unit quantities. The revision, which was
forwarded to WAPDA in August 26, did not affect Commonwealth's
original recommendations of July 21. Request for a Letter of
Commitment to cover the value of the transformers was made to AID
on August 9.

Evaluation of the proposals from four Pakistani manufacturers
for the supply of the 825 11/0.4 KV distribution transformers required
for the SCARP-2A Project was made, and a letter of recommendation,
including recommended delivery schedule, was transmitted to WAPDA.

To coordinate with the completion of tubewells in the eastern
portion of the Chaj Doab area, Commonwealth has completed 70 percent of
the survey work necessary for the routing of the two 11-KV distribution
circuits to be supplied from WAPDA's 132-KV main grid station at
Gujrat. Route maps are being prepared and upon completion will be
submitted to WAPDA for approval.

WAPDA has advised their Land Acquisition Officer to assign
a right-of-way man to the SCARP-2A Project to obtain rights of way
and easements and, where necessary, to arrange compensation for crop
damage.

Field trips were made by the Distribution Engineer during
August to the Gujrat Main Grid Station and to the Rasul Hydro Plant
Substation to obtain further detailed information in regard to a
temporary power supply for the 11 KV circuits for tubewells that
have been, or are expected to be completed within the next few months
in the Gujrat and Dinga areas.


.. 9 -










This investigation included (1) collection of load information
on present circuits, (2) survey of existing power transformer
capabilities, (3) determination of available circuit connections
and their capabilities, (4) study of what changes would be necessary
in the proposed 11-KV circuits of the SCARP-2A Project to adapt them
to temporary supply of power at their far end, and (5) how the
proposed circuits would correlate with existing 11 KV circuits.

In the case of distribution transformers manufactured in
Pakistan which WAPDA proposes to purchase, Commonwealth recommended
that 75 KVA transformers be purchased instead of 100 KVA
transformers that normally would be supplied because the additional
transformer capacity is not needed to supply 60 horsepower motors
and a saving of over $10,000 in investment cost, as well as a
considerable saving in annual cost of energy losses, could be
effected.

With respect to the number and range of 11 KV, no load
taps to raise or lower the utilization voltage, Commonwealth advised
that the recommendations of WAPDA's Standards Committee, namely,
two 2-1/2 percent taps above and two 2-1/2 percent taps below the
11 KV nominal voltage would be satisfactory. However, it is
recognized that in view of the present operating practice of
holding the substation bus voltage at nominal or a little below
nominal, there may be some advantage in purchasing distribution
transformers with one 2-1/2 percent tap above nominal and three
2-1/2 percent taps below, which is in accordance with transformers
previously purchased for other projects.

Charts showing both U.S. dollar and Pakistan rupee expenditures
for the SCARP-2A Project will be included in future monthly progress
reports on a quarterly basis beginning with the October report. The
initial chart will be for the first quarter of Fiscal Year 1965-1966.

Revised construction schedules of the electrification project
have been submitted which advance the construction completion date to
March 15, 1967.

Khadir Unit

Electrification of the Khadir tubewells is being carried out
by Energoinvest under a subcontract with Geoistrazivanja. Engineering
and supervision of construction are being performed by the Electricity
Department of WAPDA. The status of electrification of the Khadir
tubewells as reported to the Engineer to date is shown on Figures
2-103C and 2-103D.

On 1 July the construction of all 11 KV transmission line was
reported by Energoinvest to have been completed. One hundred eighty
three 11/0,4 KV transformers have been installed through the end of
August. The work on the construction of substations has been started.


- 10 -










It would appear that, in view of the fact that only 59 tubewells
have been constructed and developed and tested by the Tubewell
Contractor, the Electrification Contractor''s statement with respect
to completion of the 11 KV distribution lines, may require future
adjustment.

SURFACE DRAINAGE

Chot and Rukan Drains

The Chot Drain, consisting of 11 miles of enlarged drainage
channel and 29 structures; and the Rukan Drain, consisting of 8 miles
of new drainage channel and 31 structures, are located in the Upper
Jhelum Subproject in the north-central portion of Chaj Doab. The
location and status of construction of the Chot and Rukan Drains are
shown in Figure 2-200.

The excavation of the Chot and Rukan Drains will be carried
out by the MPO under the terms and conditions of Contract No.2-201
which was executed on 29 April 1965. It is estimated that there is
to be a total excavation of approximately 16,300,000 cubic feet of
material under the terms and conditions of this Contract. During
this report period it is estimated that approximately 471,000 cubic
feet of material was excavated. To date a total of 2,358,000 cubic
feet of material is estimated to have been excavated. This is
approximately 14.4 percent of the estimated total excavation to be
done. The excavation has been from RD 0+000 to about RD 20+000 an
the Chot Drain and from RD 0+000 to RD 4+450 on the Rukan Drain.

Contract No. 2-203 for the construction of 57 structures on
the Chot and Rukan Drains was awarded to Sultan Khan Khattak and
Company of Peshawar on 6 March. The Contract called for completion
of the structures within 450 days of the Date of Contract. The
Contractor was considerably behind schedule and indicated an
inability to cope with conditions at site. On 21 August 1965 the
Authority sent a letter of Contract cancellation to Sultan Khan
Khattak and Company listing lack of progress as the primary reason
for cancellation. At the end of the report period the Contractor
had not removed the cause for cancellation. The date of cancellation
will be 60 days after receipt of the letter of cancellation by the
Contractor.

At the time of cancellation of the Contract the Contractor
had completed less than one-half of one percent of the work while
approximately 37 percent of the contract time had elapsed.


- 11 -










It would appear that, in view of the fact that only 59 tubewells
have been constructed and developed and tested by the Tubewell
Contractor, the Electrification Contractor''s statement with respect
to completion of the 11 KV distribution lines, may require future
adjustment.

SURFACE DRAINAGE

Chot and Rukan Drains

The Chot Drain, consisting of 11 miles of enlarged drainage
channel and 29 structures; and the Rukan Drain, consisting of 8 miles
of new drainage channel and 31 structures, are located in the Upper
Jhelum Subproject in the north-central portion of Chaj Doab. The
location and status of construction of the Chot and Rukan Drains are
shown in Figure 2-200.

The excavation of the Chot and Rukan Drains will be carried
out by the MPO under the terms and conditions of Contract No.2-201
which was executed on 29 April 1965. It is estimated that there is
to be a total excavation of approximately 16,300,000 cubic feet of
material under the terms and conditions of this Contract. During
this report period it is estimated that approximately 471,000 cubic
feet of material was excavated. To date a total of 2,358,000 cubic
feet of material is estimated to have been excavated. This is
approximately 14.4 percent of the estimated total excavation to be
done. The excavation has been from RD 0+000 to about RD 20+000 an
the Chot Drain and from RD 0+000 to RD 4+450 on the Rukan Drain.

Contract No. 2-203 for the construction of 57 structures on
the Chot and Rukan Drains was awarded to Sultan Khan Khattak and
Company of Peshawar on 6 March. The Contract called for completion
of the structures within 450 days of the Date of Contract. The
Contractor was considerably behind schedule and indicated an
inability to cope with conditions at site. On 21 August 1965 the
Authority sent a letter of Contract cancellation to Sultan Khan
Khattak and Company listing lack of progress as the primary reason
for cancellation. At the end of the report period the Contractor
had not removed the cause for cancellation. The date of cancellation
will be 60 days after receipt of the letter of cancellation by the
Contractor.

At the time of cancellation of the Contract the Contractor
had completed less than one-half of one percent of the work while
approximately 37 percent of the contract time had elapsed.


- 11 -










TABLE 2-102


CONSTRUCTION PERSONNEL
Contractor Expatriates Pakistani Total

Geoistrazivanja 1 6 7
Samad-Vaughn Corporation 0 15 15
(E. F. U. Insurance Co.)


CONSTRUCTION PROGRESS (SEE FIGURE 28)
This Total
Description Period To Date

Tubewell sites located in the field Completed 138
Tubewells constructed Completed 138
Tubewells developed and tested Completed 138
Concrete pump pedestals and slabs constructed Completed 138
Equipment installed (pumps, motors and motor controls) Completed 138
Pumphouses and discharge boxes constructed Completed 138
Tubewell installations accepted 24 88



MISCELLANEOUS

Eastern Federal Union Insurance Co. (bond company for Samad-Vaughn) took over pumphouse construction work with
effect from 3 April, 1965 when Samad-Vaughn's Contract was terminated.


I I _









































LEGEND

, Unit Boundory

*f Tubewell, No /copocity

o Private tubewell

A New substation

SExisting substation to be
renovated
-- Existing transmission line

Rs Rail Station

RH Rest House


LSONPUR


SCALE OF MILES


SALAM


PROJECT NO.2- CHAJ DOAB

MONA UNIT

TUBEWELLS AND ELECTRIFICATION

1ax.n-s2a .1. 2-.


o0
00

MELOWAL


0 0


o o
0 o


0


KOT HAXIM KHAN
3


de'
co

















'CD
----/------ ------- --- -

I I(
I-
w





2
-- --- ---- ------- Ii-
I



/ z

J J A S "I




J J A S N J F M A M J J AS N J F M A M
1963 1964 1965



TUBEWELL COMPLETION
(Through equipment installation
and preliminary testing.)






Actual progress

--- Scheduled progress (2nd revision 6-25-63)


160




120




o 0




40
40----------------------- --- -- ----- --- -



C--_-_-_ ------ ---- -----

J J A SO N DJ FMAMJ J AS N J FMAM
1964 1965 1966



PUMPHOUSE CONSTRUCTION
(Pumphouse and tubewell accepted.)
(Scheduled completion date mid Nov.
1963.)




PROJECT NO.2 CHAJ DOAB

MONA UNIT


TUBEWELL CONSTRUCTION PROGRESS







O.u -- -- --1-I -- -- - -- -- -




0.6

,, /
z

LL

cn ----- -- -- ---
-/


O 0.4




0.2





S7J FM AM JJ AS OND J FMA1M J J A SON
1964 1965


60--i ----------------------|--------------------------,----|--|--
IO -








/60----


40



0---
20







-A" ///

DJFMAMJJASONDJFMAMS JASON
1964 1965
_ _ _/^ _
,o _ _/_ _
_ _ / _"^ _

4EEE / /-^E EE
_ _~ / _ _
:===:^:/====









IS64 196S5


66 K.V. TRANSMISSION LINES

(Towers, conductors and hardware)


Actual progress
Target progress


SUBSTATIONS

(Steel structures, transformers, sw.itchgear
and electrical equipment)


PROJECT NO.2 CHAJ DOAB
MONA UNIT


ELECTRIFICATION CONSTRUCTION PROGRESS
TRANSMISSION LINES AND SUBSTATIONS










160




720 Complete
---


80




40




0
J M A M JASON J F M A M JJ A S 0 N
1964 1965


120




80




40
I 60 --------- -- ---- ---- ---- -- -- -- -- -- -- -- -- ---


-- ---- --- -__ __ --__




: :/ : : /


80 -- ---------- --------------------------/-- -- -- ---+-- -- -- --





o--i ^- ii-- --

DJ FM AMJ J AS OND JF M AM JJA S N
1964 1965


II KV DISTRIBUTION LINES
(Towers, conductors and protective devices)






Actual progress
--- Target progress


SERVICES
(Service tower, 11/0.4 KV. transformer,
service drop and connection to
service entrance)





PROJECT NO. 2 CHAJ DOA B
MONA UNIT


ELECTRIFICATION CONSTRUCTION PROGRESS
DISTRIBUTION LINES AND SERVICES










TABLE 2-103


4 Power units 90 HP diesel 4 Pump setting rig
3 Turbine pumps 0 Pump setting tripods, 5 ton
1 Slotting machine (steel pipe) 8 Trailers, 8 ton







CONSTRUCTION PERSONNEL


Contractor Expatriate Pakistani Total

Geoistrazivanja 23 307 330



CONSTRUCTION PROGRESS (SEE FIGURE 4B) Total
Description This Period To Date

Tubewell sites located in the field 7 108
Tubewells constructed 16 75
Tubewells developed and tested 11 70
Concrete pump pedestals and slabs constructed 26 47


-I



MISCELLANEOUS 215 Tubewells now scheduled for construction.


______________________ __ ____01


_ __ I






















































/ PROJECT NO. 2 CHAJ DOAB
,____ _________ KHADIR UNIT
SCr lLE O,. TUBEWELLS AND ELECTRIFICATION
TeS,. 0. -103-












200



I SO

I. - - -_ _
I 5I-- J- -- -
ISO






100 ____
---1------J-------------- -- -






50
0----- -{-- -- --- -









AM J A S ON DJ F M A M J J A S ONDJ F M
1964 1965 1966


TUBEWELL CONSTRUCTION

(Construction through developing

and testing of Tubewells)




Actual progress

---- Scheduled progress


200





CD ---- j -- ---

S150
- I
150
w I
,I


SI

0 10


CO

I'
z

50----
-~ -,-- ----------------








0C -- --- ---- -- ---- -------- --
A MJ JA S O N O J F M A M J J A S N J F M
1964 1965 1966


TUBEWELL COMPLETION

(Installation and testing equipment-
and construction of pumphouse)





PROJECT NO. 2 CHAJ D.OAB

KHADIR UNIT



TUBEWELL CONSTRUCTION PROGRESS


i










20 i- --i--i--i-i----l---l---- ---- -- --------









* 0----- /---/-






------I---------
15












5





0 -
A M J JASON 0 J F MA JJASONDJFSO NO F
1964 1965 1966


80-U- ---- ---*-- --------- --- --------- -- --







60--
80 --------------------- -^- -
I










40









0
0------------------- -- -------- *-- -j - - -

--i-_____---_--- _







A MJ JA S O N J F M AM J J A S O N 0 J F M
1964 1965 1966


TRANSMISSION LINES

(Towers, conductors and hardware)


Actual progress

Target progress


SUBSTATIONS

(Steel structures,-transformers, switchgear
and electrical equipment)


PROJECT NO.2 CHAJ DOAB

KHADIR UNIT


ELECTRIFICATION CONSTRUCTION PROGRESS
TRANSMISSION LINES AND SUBSTATIONS


w
z

u.
0
11)
WI
J
.J










200 - -








120-


0 -




40

0

A M 1964 J1965 19A S


II KV DISTRIBUTION LINES
(Towers, conductors and protective devices)


Actual progress
Target progress


SERVICES
(Service tower,11/0.4 KV transformer, service
drop and connection to service entrance)



PROJECT NO.2 CHAJ DOAB
KHADIR UNIT

ELECTRIFICATION CONSTRUCTION PROGRESS
DISTRIBUTION LINES AND SERVICES









TABLE 2-104

IIPPFR .IMFI. q-I. H. T. Smith Inc. ending machines 2 Crawler tractor, w/front end loader
7 Drilling r's 2 Pump setting rigs 1 Wheel tractor, w/front end loader
14 Tractors, wheel 12 Centrifugal pumps 2 Automobiles
5 Tractor, crawler w/blade and engines 2 Electric logging units
14 Trailers, 4-wheel Bunger 10 Electric generators 3 Slotting machines (steel pipe)
6 Trucks Bedford w/min. 12ft. bed 11 Diesel engines 2 Slotting machines (fiberglass pipe)
22 Trucks, light, 4 x 4 8 Vertical turbine 1 Gravel screening plant
test pumps
CONSTRUCTION PERSONNEL

Contractor Expatriate Pakistani Total

Southeastern Asia Drilling Company 3 18 21
Harold T. Smith, Inc. 11 504 515


CONSTRUCTION PROGRESS (SEE FIGURE 3B)
Total
Description This Period To Date

Tubewell sites to the Contractor 49 406
Tubewells constructed 43 276
Tubewells developed and tested 43 251
Concrete pump pedestals and slabs constructed 28 38
Pumping equipment installed (Pump and motor) 2 2




MISCELLANEOUS




__j















4.








roBr..


HEAD


LEGEND


--- Sub-project Boundary

S Tubewell

A New substation

A Esisting substation to be
renovated


Existing substation

--~-- New transmission line

--- Existing transmission line

R.s. Rail Station


PROJECT NO.2-CHAJ DOAB

UPPER JHELUM SUB-PROJECT

TUBEWELLS AND ELECTRIFICATION


~
rcrcr orullrr













800 --





S----------------- - -


- -- -, --- _- -_-
/ __ _







------


_____ '--7 ----= '_ _
/ 0




M J J A S O N D J FM A M J A S O N J F M A
1964 1965 1966


TUBEWELL CONSTRUCTION

(Construction through developing
and testing of tubewells)









Actual progress

Scheduled progress

Revised schedule 16/11/64
Revised schedule 25/5/65


800


w
-J



600
-J



0

It 400
m

z

200





0


/








__- ___ __--- _---z-- -^


--_--_-----------:--/-
o f







o
------- -------------^





M J JASON D J FMAMJ JASON D J F M A
1964 1965 1966


TUBEWELL COMPLETION

(Installation and testing equipment
and tubewell acceptance)







PROJECT NO.2 CHAJ DOAB

UPPER JHELUM. SUB-PROJECT


TUBEWELL CONSTRUCTION PROGRESS


-w
-I
UJ


Co


0

at 400
LaJ
0)



200





0







































TRANSMISSION LINES

(Towers, conductors and hardware)


Actual progress
Scheduled progress Dec.1964
Revised schedule Aug.1965

iofte : Scheduled progress based
on Commonwealth data.


/



60 1 40
-- /





0 20
20 /^Z-Z-----
I-.








w I




D0 -JFM AMJ J A N J- F M A M J JAS
0 -- --- ---- ----- --


1966 1967

SUBSTATIONS

(Steel structures, transformers, switchgear
and electrical equipment )


PROJECT NO. 2 CHAJ DOAB
UPPER JH ELUM SUB-PROJECT


ELECTRIFICATION CONSTRUCTION PROGRESS
TRANSMISSION LINES AND SUBSTATIONS


_ _1__II_ __~_________~__~IWIU_____~~~_~___ _


-











'- ------------- ---- -

jJI1Z4iZj I/IIIiit




600 H-


DJ"FM AMJJ IN IAO JM JJ AS
S9 66 1967

II KV DISTRIBUTION LINES

(Towers, conductors and protective devices)


Actual progress

--- Scheduled progress Dec.1964
Revised schedule Aug. 1965
-.-._Revised schedule Aug. 1965


1000.


800



o /
1 600 ___
co
w _

U- 400






P E NC- -- H
200 _






D J F M A M J J A S O N O J F MA M J AS
1966 1967

SERVICES

(Service tower, 11/0.4 KV transformer, service
drop and connection to service entrance)



PROJECT NO.2 CHAJ DOAB

UPPER JHELUM SUB-PROJECT


Note: Scheduled progress based
on Commonwealth data


ELECTRIC FICTION

DISTRIBUTION


CONSTRUCTION PROGRESS

LINES AND SERVICES


Innn


(,


W
_j


L- 400
o

0
LU

200
z




0


.~~'"U-~-~-----II`YI-
















JHELUM


A,-


CHOT


N.


LEGEND


< Surface droin unden contract


__Z2 Excavation in progress


Z= Excavation complete


1 Completed sunface drain
(Excavation and structures)


'4 .' PROJECT NO.2
CHAJ DOAB

SURFACE DRAINS
TROS. OOS .0-a- es


I A 1o I, 1.
SCALE OF MILES


RUKAN


































PROJECT 3

LOWER THAL DOAB










PROJECT NO. 3 LOWER THAL DOAB


TUBEWELLS

Kot Adu Unit

The Kot Adu Unit of Project No, 3 consists of 400,000 acres
in the northwest portion of Lower Thal Doab. It is planned to
construct approximately 475 tubewells in this area.

No date has yet been established for the calling of tenders
for Contract No. 3-106 for the construction of the tubewells in the
Kot Adu Unit. Applications for prequalification were due from
contractors interested in the work on March 15. Applications were
received from 13 firms located in 5 countries. Evaluation of the
prequalification applications and data by the Engineer was completed
and the Engineer's recommendations were forwarded to the Authority.
Since it appears that there may be some delay in calling for tenders
for this work, the deadline for submission of prequalification data
has not been strictly adhered to.

A draft copy of the proposed Contract Documents has been sent
to Kreditanstalt for their comments.

Alipur Unit

The Alipur Unit consists of approximately 400,000 acres in
the lower end of Lower Thal Doab. The unit is bounded on the west
by the Indus River and on the east by the Panjnad and Chenab rivers.
The northern boundary runs approximately west from the village of
Kinjar Khas to the Indus River and southeast from Kinjar Khan to the
Chenab river. In this area the Authority will construct approximately
500 tubewells.

At the end of this report period the Authority; Geoistrazivanja,
the tubewell construction contractor; and Energoinvest, the electrical
construction contractor had agreed to the terms and conditions of the
third draft of the proposed Contract Agreement.. This Contract
Agreement was based upon the Letter of Intent dated 30 June 1965.

The tubewell construction contractor began construction of
his field base camp in the Alipur Unit area in late July. At the
end of this report period the camp was about 70 percent complete.
Tubewell siting work has been started in the Alipur Unit.

SURFACE DRAINAGE
Kot Adu Main Drain
The Kot Adu Main Drain, consisting of approximately 26 miles
of existing drainage channel which is to be enlarged and 72 new
structures which are to be constructed, is located in the Kot Adu Unit
in the northwest portion of Lower Thal Doab, Project No.3. The location
and status of construction of the Kot Adu Main Drain is shown in
Figure 3-200.
12 -










PROJECT NO. 3 LOWER THAL DOAB


TUBEWELLS

Kot Adu Unit

The Kot Adu Unit of Project No, 3 consists of 400,000 acres
in the northwest portion of Lower Thal Doab. It is planned to
construct approximately 475 tubewells in this area.

No date has yet been established for the calling of tenders
for Contract No. 3-106 for the construction of the tubewells in the
Kot Adu Unit. Applications for prequalification were due from
contractors interested in the work on March 15. Applications were
received from 13 firms located in 5 countries. Evaluation of the
prequalification applications and data by the Engineer was completed
and the Engineer's recommendations were forwarded to the Authority.
Since it appears that there may be some delay in calling for tenders
for this work, the deadline for submission of prequalification data
has not been strictly adhered to.

A draft copy of the proposed Contract Documents has been sent
to Kreditanstalt for their comments.

Alipur Unit

The Alipur Unit consists of approximately 400,000 acres in
the lower end of Lower Thal Doab. The unit is bounded on the west
by the Indus River and on the east by the Panjnad and Chenab rivers.
The northern boundary runs approximately west from the village of
Kinjar Khas to the Indus River and southeast from Kinjar Khan to the
Chenab river. In this area the Authority will construct approximately
500 tubewells.

At the end of this report period the Authority; Geoistrazivanja,
the tubewell construction contractor; and Energoinvest, the electrical
construction contractor had agreed to the terms and conditions of the
third draft of the proposed Contract Agreement.. This Contract
Agreement was based upon the Letter of Intent dated 30 June 1965.

The tubewell construction contractor began construction of
his field base camp in the Alipur Unit area in late July. At the
end of this report period the camp was about 70 percent complete.
Tubewell siting work has been started in the Alipur Unit.

SURFACE DRAINAGE
Kot Adu Main Drain
The Kot Adu Main Drain, consisting of approximately 26 miles
of existing drainage channel which is to be enlarged and 72 new
structures which are to be constructed, is located in the Kot Adu Unit
in the northwest portion of Lower Thal Doab, Project No.3. The location
and status of construction of the Kot Adu Main Drain is shown in
Figure 3-200.
12 -










PROJECT NO. 3 LOWER THAL DOAB


TUBEWELLS

Kot Adu Unit

The Kot Adu Unit of Project No, 3 consists of 400,000 acres
in the northwest portion of Lower Thal Doab. It is planned to
construct approximately 475 tubewells in this area.

No date has yet been established for the calling of tenders
for Contract No. 3-106 for the construction of the tubewells in the
Kot Adu Unit. Applications for prequalification were due from
contractors interested in the work on March 15. Applications were
received from 13 firms located in 5 countries. Evaluation of the
prequalification applications and data by the Engineer was completed
and the Engineer's recommendations were forwarded to the Authority.
Since it appears that there may be some delay in calling for tenders
for this work, the deadline for submission of prequalification data
has not been strictly adhered to.

A draft copy of the proposed Contract Documents has been sent
to Kreditanstalt for their comments.

Alipur Unit

The Alipur Unit consists of approximately 400,000 acres in
the lower end of Lower Thal Doab. The unit is bounded on the west
by the Indus River and on the east by the Panjnad and Chenab rivers.
The northern boundary runs approximately west from the village of
Kinjar Khas to the Indus River and southeast from Kinjar Khan to the
Chenab river. In this area the Authority will construct approximately
500 tubewells.

At the end of this report period the Authority; Geoistrazivanja,
the tubewell construction contractor; and Energoinvest, the electrical
construction contractor had agreed to the terms and conditions of the
third draft of the proposed Contract Agreement.. This Contract
Agreement was based upon the Letter of Intent dated 30 June 1965.

The tubewell construction contractor began construction of
his field base camp in the Alipur Unit area in late July. At the
end of this report period the camp was about 70 percent complete.
Tubewell siting work has been started in the Alipur Unit.

SURFACE DRAINAGE
Kot Adu Main Drain
The Kot Adu Main Drain, consisting of approximately 26 miles
of existing drainage channel which is to be enlarged and 72 new
structures which are to be constructed, is located in the Kot Adu Unit
in the northwest portion of Lower Thal Doab, Project No.3. The location
and status of construction of the Kot Adu Main Drain is shown in
Figure 3-200.
12 -










PROJECT NO. 3 LOWER THAL DOAB


TUBEWELLS

Kot Adu Unit

The Kot Adu Unit of Project No, 3 consists of 400,000 acres
in the northwest portion of Lower Thal Doab. It is planned to
construct approximately 475 tubewells in this area.

No date has yet been established for the calling of tenders
for Contract No. 3-106 for the construction of the tubewells in the
Kot Adu Unit. Applications for prequalification were due from
contractors interested in the work on March 15. Applications were
received from 13 firms located in 5 countries. Evaluation of the
prequalification applications and data by the Engineer was completed
and the Engineer's recommendations were forwarded to the Authority.
Since it appears that there may be some delay in calling for tenders
for this work, the deadline for submission of prequalification data
has not been strictly adhered to.

A draft copy of the proposed Contract Documents has been sent
to Kreditanstalt for their comments.

Alipur Unit

The Alipur Unit consists of approximately 400,000 acres in
the lower end of Lower Thal Doab. The unit is bounded on the west
by the Indus River and on the east by the Panjnad and Chenab rivers.
The northern boundary runs approximately west from the village of
Kinjar Khas to the Indus River and southeast from Kinjar Khan to the
Chenab river. In this area the Authority will construct approximately
500 tubewells.

At the end of this report period the Authority; Geoistrazivanja,
the tubewell construction contractor; and Energoinvest, the electrical
construction contractor had agreed to the terms and conditions of the
third draft of the proposed Contract Agreement.. This Contract
Agreement was based upon the Letter of Intent dated 30 June 1965.

The tubewell construction contractor began construction of
his field base camp in the Alipur Unit area in late July. At the
end of this report period the camp was about 70 percent complete.
Tubewell siting work has been started in the Alipur Unit.

SURFACE DRAINAGE
Kot Adu Main Drain
The Kot Adu Main Drain, consisting of approximately 26 miles
of existing drainage channel which is to be enlarged and 72 new
structures which are to be constructed, is located in the Kot Adu Unit
in the northwest portion of Lower Thal Doab, Project No.3. The location
and status of construction of the Kot Adu Main Drain is shown in
Figure 3-200.
12 -










PROJECT NO. 3 LOWER THAL DOAB


TUBEWELLS

Kot Adu Unit

The Kot Adu Unit of Project No, 3 consists of 400,000 acres
in the northwest portion of Lower Thal Doab. It is planned to
construct approximately 475 tubewells in this area.

No date has yet been established for the calling of tenders
for Contract No. 3-106 for the construction of the tubewells in the
Kot Adu Unit. Applications for prequalification were due from
contractors interested in the work on March 15. Applications were
received from 13 firms located in 5 countries. Evaluation of the
prequalification applications and data by the Engineer was completed
and the Engineer's recommendations were forwarded to the Authority.
Since it appears that there may be some delay in calling for tenders
for this work, the deadline for submission of prequalification data
has not been strictly adhered to.

A draft copy of the proposed Contract Documents has been sent
to Kreditanstalt for their comments.

Alipur Unit

The Alipur Unit consists of approximately 400,000 acres in
the lower end of Lower Thal Doab. The unit is bounded on the west
by the Indus River and on the east by the Panjnad and Chenab rivers.
The northern boundary runs approximately west from the village of
Kinjar Khas to the Indus River and southeast from Kinjar Khan to the
Chenab river. In this area the Authority will construct approximately
500 tubewells.

At the end of this report period the Authority; Geoistrazivanja,
the tubewell construction contractor; and Energoinvest, the electrical
construction contractor had agreed to the terms and conditions of the
third draft of the proposed Contract Agreement.. This Contract
Agreement was based upon the Letter of Intent dated 30 June 1965.

The tubewell construction contractor began construction of
his field base camp in the Alipur Unit area in late July. At the
end of this report period the camp was about 70 percent complete.
Tubewell siting work has been started in the Alipur Unit.

SURFACE DRAINAGE
Kot Adu Main Drain
The Kot Adu Main Drain, consisting of approximately 26 miles
of existing drainage channel which is to be enlarged and 72 new
structures which are to be constructed, is located in the Kot Adu Unit
in the northwest portion of Lower Thal Doab, Project No.3. The location
and status of construction of the Kot Adu Main Drain is shown in
Figure 3-200.
12 -












The excavation of the Kot Adu Main Drain from RD 0+000 to
RD 88+008 is being carried out under Contract No. 3-205 by the
Machinery Pool Organization (MPO) of WAPDA. This Contract originally
called for excavation of the drain to RD 130+000, but it has been
decided to let the reach of the drain from RD 88+008 to beyond
RD 130+000 be constructed by another Contractor. This change has
reduced the quantity of excavation to be done by the MPO from an
estimated 40,000,000 cubic feet to an estimated 30,800,000 cubic feet.
During this report period it is estimated that approximately 2,000,000
cubic feet of material was excavated by the MPO, bringing total
excavation to date to 15,500,000 cubic feet. It has been reported
that the MPO has excavated from the outfall to RD 60 on the Kot Adu
Main Drain and has excavated to section from the outfall to RD 45.
This excavation work is approximately 50 percent complete, using the
revised total quantity of excavation of 30,800,000 cubic feet.

The MPO is using 8 draglines, supported by 1 crawler tractor,
1 heavy truck, 2 light vehicles and 1 mobile workshop truck to
execute this work.

Contract No. 3-204 for the construction of structures on the
first 16.6 miles of the Kot Adu Main Drain was executed between the
Authority and the firm Engineering Services of Lahore on 24 Ap1wrl, 196
The tender price for this work was Rs725,220.00. There are 44
structures to be constructed under the terms and conditions of this
Contract. The Contractor has started construction at 9 of these
structures. Four percent of the work required under the Contract has
been done while 25 percent of the time of contract has expired.

A Tender Notice for Contract No. 3-210, Construction of
Excavation and Structures for Kot Adu Main Drain RD 88+008 to
RD 138+150 was placed in a local newspaper, The Pakistan Times, on
6 August 1965. The opening date for Tenders is scheduled for 4
September 1965. At the end of this report period 6 sets of Tender
Documents had been sold to prospective bidders. This Contract is
for the remaining 10 miles of the Kot Adu Main Drain.

The Contract will provide for the construction of 28
structures and the excavation of an estimated 9,200,000 cubic feet
of material from approximately 50,000 feet of reach of the drain
in a period of 365 days.

Budh Branch Drain

The Budh Branch Drain, consisting of 17 miles of new drainage
channel and 24 structures, is a branch of the Kot Adu Main Drain and
is located in the Kot Adu Unit of Project No.3 in the northwest
portion of Lower Thal Doab. The location and status of construction
of the Budh Branch Drain is shown in Figure 3-200.


- 13 -









Contract No. 3-207 for the excavation of Budh Branch Drain
and for the construction of structures thereon, was executed between
the Authority and the firm "Desert Cat" of Lahore on 26 April 1965.
The tender price for this work was Rs 693,905.00. There is estimated
to be 12,600,000 cubic feet of material to be excavated and 24
structures to be built under the terms and conditions of this
Contract. The Contractor has been hampered by their being no outfall
from Budh Branch Drain into Kot Adu Main Drain because the MPO
has not yet excavated up to RD 87 on Kot Adu Main Drain. During
this period the Contractor is estimated to have excavated approximately
790,000 cubic yards of material. The total volume of material
excavated by the Contractor to date is 1,540,000 cubic feet. The
Contractor has not yet started work on structures. The excavation
work is approximately 12 percent complete.


- 14 -














lc~i~-


e--UnfH BtANAH DRAIN

S/-4
^<.
I ~


ADU MAIN DRAIN


SCALE OF MILES


LEGEND

' Surface droin under contract

f Ecavation in progress


11111 1 Excavation complete

Completed surface drain
(Excavation and structures)


PROJECT NO.3
LOWER THAL DOAB

SURFACE DRAINS


_I __ I
































PROJECT 4

UPPER RECHNA DOAB










PROJECT NO. 4 UPPER RECHNA DOAB


TUBEWELLS


Marala-Ravi Unit

The Marala-Ravi Unit consists of approximately 178,000
acres in the Project No.4 area of the Upper Rechna Doab between
the B.R.B.D. and the Marala-Ravi Link Canals. The Authority will
construct approximately 300 tubewells in this area.

On 30 June Contract No. 4-105 for the construction and
electrification of approximately 300 tubewells in the Marala-Ravi
Unit of Project No.4 was executed. The estimated cost of tubewell
construction by Geoistrazivanja was Equivalent Rupees 15,116,536
($3,175,743) and the estimated cost of unit electrification by
Energoinvest was Eq. Rs 10,019,486 ($2,104,934). The total cost
for both unit electrification and tubewell construction is estimated
to be Eq.Rs25,136,022 ($5,280,677). Energoinvest and Geoistrazivanja
posted the required Fidelity Bonds and advances were made to them
as required by the Contract Documents. No construction work has
begun.

Siting work has been started in the Marala-Ravi Unit.


- 15 -










PROJECT NO. 4 UPPER RECHNA DOAB


TUBEWELLS


Marala-Ravi Unit

The Marala-Ravi Unit consists of approximately 178,000
acres in the Project No.4 area of the Upper Rechna Doab between
the B.R.B.D. and the Marala-Ravi Link Canals. The Authority will
construct approximately 300 tubewells in this area.

On 30 June Contract No. 4-105 for the construction and
electrification of approximately 300 tubewells in the Marala-Ravi
Unit of Project No.4 was executed. The estimated cost of tubewell
construction by Geoistrazivanja was Equivalent Rupees 15,116,536
($3,175,743) and the estimated cost of unit electrification by
Energoinvest was Eq. Rs 10,019,486 ($2,104,934). The total cost
for both unit electrification and tubewell construction is estimated
to be Eq.Rs25,136,022 ($5,280,677). Energoinvest and Geoistrazivanja
posted the required Fidelity Bonds and advances were made to them
as required by the Contract Documents. No construction work has
begun.

Siting work has been started in the Marala-Ravi Unit.


- 15 -




University of Florida Home Page
© 2004 - 2010 University of Florida George A. Smathers Libraries.
All rights reserved.

Acceptable Use, Copyright, and Disclaimer Statement
Last updated October 10, 2010 - - mvs