Title: SWFWMD. Monthly Construction Progress Report. 31 January 1979. 4p.
CITATION PAGE IMAGE ZOOMABLE
Full Citation
STANDARD VIEW MARC VIEW
Permanent Link: http://ufdc.ufl.edu/UF00052438/00001
 Material Information
Title: SWFWMD. Monthly Construction Progress Report. 31 January 1979. 4p.
Physical Description: Book
 Subjects
Spatial Coverage: North America -- United States of America -- Florida
 Notes
Funding: Digitized by the Legal Technology Institute in the Levin College of Law at the University of Florida.
 Record Information
Bibliographic ID: UF00052438
Volume ID: VID00001
Source Institution: University of Florida
Holding Location: Levin College of Law, University of Florida
Rights Management: All rights reserved by the source institution and holding location.

Full Text


MONTHLY
'-" CONSTRUCTION DIVISION
J DIVICTCONSTR UCTION PROGRESS REPORT PAGE 1 OF 3
- "JACKSONVILLE DISTRICT
CIVIL
31 JANUARY 1979 DATE RCS SADVS- 91
PROJECT DATE DATE COMPLETION DATES % COMPL. %
DIRECTIVE DATE CONTRACT DATE DATE
LINE ITEM PROJECT CONTRACTOR CONTRACT NOTICE TO WORK SCHEDULED ESTIMATED THIS REMARKS
NUMBER AWARDED AMOUNT PROCEED STARTED B.O COMPLETION B.O. COMPLETION SCH. ACT. POR.

CENTRAL AN ) SOUTHERN FLORIDA

(M) 79-0014 Pumping Station 332 Metro Metal. 12/14/78 $1,589,833.00 1/15/79 1/22/79 9/6/80 9/80
Inc.

(M) 79-0019 Pumping Sta. 331 and C-103, Enlarge- Renel Const 1/26/79 3,398,980.00
ment, C&SFFCP


(M) 79-0021 Sta 339 and 340, Alligator Alley Fla. Engr. &
Plugs & Culverts Construction 1/26/79 1,648,600.00

1/26/79
(M) 77-0078 L-31 (N) (REM) Enlargement, C-1,S-194 Fla. Engr 8/26/77 1,738,075.00 9/10/77 11/15/77 3/12/79 1/79 99 100 6 Completed
(Mod) and S-338 Const, Co.



(C) 77-0081 Structure 310 Renel Const. 9/29/77 2.896,483.58 10/13/77 10/26/77 10/20/79 12/79 68 56 6 2nd Stage dewatering
Inc. (4 Mods) blow out in Stage 2 de-
watered area.



FOUR RIVER BASINS


76-0058 Tampa Bypass Canal 135 Section 4A C. H. Barco 3/31/76 4,365,659.92 4/8/76 4/8/7678 (gr ) 1/79 100 100 0 er or
Const Co. (8 Mods)


77-0024 C-135, Section 43 and L-112 Fla Engr Const 1/21/77 2,841,308.91 2/14/77 3/21/77 8/3/79 8/79 94 84 3 continue Excavation &
Co. (4 Mods) wet weather delay.

77-0090 Recreation Facility, Irooker Creek Paul Smith 9/30/77 2,375,849.88 10/13/77 11/4/77 1/4/79 1/79 100 100 1 Work complete.
Park Contr Co. (6 Mods)




5/8/78 6/21/80 6/80 14 34 3 Cont. levee fill, & well
78-0038 Structures 155 & 163, L-112R & Paul Smith 4/25/78 4,302,519.57 5/8/78 points at S-155, S-163
Floodway Contr. Co. (1 Mod) Pre-load. Test-Piling.





79-0016 Const. Tampa Area Office Bldg Angle & 11/13/78 180,900.00 12/6/78 1/5/79 7/4/79 7/79 2 1 1 Inall sign Bldg
Schmid Inc, culvert.





(M)- Miam
(C)- Clew ston

SAD FORM 3033-R




197q










MONTHLY
CONSTRUCTION VISION
CONSTR AUCTION PROGRESS REPORT PAGE Eof

JACKSONVILLE DISTRICT
CIVIL
31 January 1979 DATE RCS SADVS 91
PROJECT, DATE DATE DATE COMPLETION DATES % COMPL %
DIRECTIVE PROJECT CONTRACTOR NTRACT C CONTRACT NOTICE TO WORK SCHEDULED ESTIMATED HIS REMARKS
LINE ITEM AMOUNT RACT. TO..... WOR A
NUMBER AWARDED PROCEED STARTED B.. COMPLETION B.O. COMPLETION POR

TAMPA HARB01

77-0015 43-Ft. Proj, Egmont Channel, Cut 1, Const Aggre- 12/2/76 17,213,800.00 12/17/76 1/11/77 5/15/79 6/79 96 72 1 Dredging Egnont & Mullet
Sec 18, Egmont Channel to Mullet Key, gates Corp. Channels & Pump CDA 17.
Sec 2A Delay due to not manning
job.
78-0003 43-Ft. Proj, Alafia River to East Bay Western Cont. 10/18/77 26,475,860.00 11/3/77 11/2/77 3/3/81 6/79 36 71 8 Contd sec 18 thru 22 &
Section 5 Corp. (3 Mods) Circut 3 to 14 & pumping

to CMDA 2D2 & between D//AS

78-0064 43-Ft. Proj, Egmont Cut 1, Sec IC & T. L. James & 6/16/78 14,842,375.00 7/10/78 11/8/78 7/28/80 7/80 20 32 4 Dredging Mullet Egmont
Mullet Key- Mariposa Key/Tampa Harbor Co., Inc. (1 Mod) Channel & Pump to CDA 13,
15 & 20.

78-0066 Haint, Dredg., 30-Ft. Proj, Alafia Trans-State 7/11/78 1,374,000.00 7/19/78 7/21/78 4/15/79 1/79 100 100 1 Work complete.
River Channel, Tampa Harbor Dredging Co. Final Report.


SAN JUAN, PIERTO RICO

78-0006 Upper Bucana Channel Improvements, Conduit & Foun 11/28/77 7,885,030.71 1/3/78 2/5/78 2/16/81 2/81 30 31 6 Work progressing satis-
Section 3 Corp/SP&B (4 Mods) factorily.


78-0060 Test Excv., Test Grouting, Cerrillos Rexach Const. 6/1/78 1,649,555.90 7/3/78 8/16/78 1/29/79 4/79 100 32 5 Contractor requested to
Dam, P & B Project Co. increase personnel and
equip, to expedite com-
pletion.
79-0009 Foundation Treatment & Access Trail, Misener Marine 10/20/78 3,113,149.00 12/6/78 6/30/79 11/80 1 2 1
San Juan National Historic Site Const Inc. /14/79 Field wor started


79-0025 Upper Bucana Channel Improvement Conduit & 12/18/78 3,515,532.36 1/11/79 2/9/61 3/81
Sec. 4 Foundation Cor
SF&I


DUVAL COUNTY FLORIDA

77-0018 Reach Restoration & Advance Nourishment Const. Aggre- 6/1/77 4,372,500.00 6/16/77 7/22/77 7/16/78 2/79 100 99 0
gates Corp. (1 Mod)


78-0040 leach Restoration & Advance Nourishmen Hydromar/East- 4/13/78 4,229,000.00 5/12/78 8/17/78 5/12/79 5/79 65 15 10 Dredging started. Mech
Second Contract ern Seaboard (1 Mod) problems & weather causin

slow progress.

79-0030 Fort Clinch Fishing Pier Rec Fac., Spearin, Pres 1/2/79 1.315,560.00 Prework conference sche-
Fernandina Hbr ton & Burrows duled for Feb 16, 79.











SAD FORM 3033-R
U OCT 73




'- H-








MONTHLY
TIO DIVISION CONSTRUCTION -PROGRESS REPORT PAGE 3 OF- _

JACKSONVILLE DISTRICT
CIVIL
JCr DATERCS SADVS 91
21 January 1979 DA TE
PROJECT, DATE DATE DATE COMPLETION DATES % COMPLY. %

LINE M PROJECT CONTRACTOR CONTRACT CONT NOTICE TO WORK SCHEDULED ESTIMATED THS REMARKS
NUMBER AWARDED PROCEED STARTED B.0. COMPLETION B.O. COMPLETION


DADE COUNTY FLORIDA

78-0024 Beach Erosion Control & Hurricane Const Aggre- 3/31/79 2,849,770.00 4/13/78 3/13/79 3/79 61 55 9 Demob for winter, dresi
Protection, Second Contract gates Corp. (1 Mod) beach and hurricane dune
Co. removing rock a Project
accepted North to Sta.
380+00.

79-0027 Beach Erosion Control & Hurricane Gr Lakes 1/4/79 8,450,460.00
Protection, Third Contract Dredge & Dock
Co.






CANAVERAL HA BOR, FLORIDA



78-0083 Mn Dr 41' Proj, U S Nay Triden, Access Parkhill-Good- 9/28/78 304,800.00 10/23/78 7/30/79 7/79 0 0 0 No dredging until May 79.
Channel & Turning Basin loe



I.W.W.

78-0062 Maint. Dredging, 12-Ft Project, Parkhill-Cood 6/23/7 2,859,343.60 6/23/78 6/26/78 5/10/79 579 Reptening
Matanzas Inlet to New Smyrna Beach loe (I Mod)



KINGS BAY

78-0075 38' Proj, Entrance Channel FIM Subbase, Farkhill-Cood 9/7/78 2,191,700.00 10/18/78 11/27/78 4/18/79 /79 Expect timely
Kings Bay, St. Marys, GA. les completion.























SAD FORM 3033-R
I OCT 73








MONTHLY
OPERATIONS DIVISION ONTH
CONSTRUCTION 1 PROGRESS REPORT PAGE 01 OF01
JACKSONVILLE DIS CT
CIVIL
31 JANUARY 1979.DA TE ___RCS SADVS- 91
PROJECT, DATE DATE DATE COMPLETION DATES COMPLY.
DIRECTIVE DATE DATE DATE
DIRECTIVE CONTRACT
LINE ITEM PROJECT CONTRACTOR CONTRACT NT NOTICE TO WORK SCHEDULED ESTIMATED THIS REMARKS
NOIC TO AMOUNT ... STT I REAK
NUMBER AWARDED AMOUNT PROCEED STARTED COMPLETION B.O. COMPLETION SCH ACT POR

"DACWE7-7- AQUATIC PLANT CONTROL, FLORIDA STAI E OF Fu 1 OCT 77 N/A 1 OcT 77 N/A 30 SEP 79 /A 30 SEP 79 3 33
0046 CONTROL & ERADICATION OF-AQUATIC GF1F COMMIS
PLANTS






(







ACW17-78- PONCE DE LEON INLET ROSE MARINE 24 JUL 78 1,452,630 14 AUG 78 11 SEP 78 N/A 12 MAR 79 N/A 12 MAR 79 60 71 33 PlCIIG rTOI
C-0067 NORTH JETTY STONE PROTECTION




"H L. FERNANDINA HARBOR, FL, FMB SB- D.McFARLANI 4 AUG 78 6,430,000 4 AUG 78 4 AUG 78 N/A 1 JUN 79 N/A 1 JUN 79 69 9 0 PROGRESS CHART
MARINE SUPPORT BASE, KING'S BAY,
ST. MARYS, GA NEW SCHEDULE-WEATHER
AND MECHANICAL
DIFFICULTIES HAVE
SLOWED PROGRESS,


( II
















SAD FORM 3033-R
4 OCT 73





University of Florida Home Page
© 2004 - 2010 University of Florida George A. Smathers Libraries.
All rights reserved.

Acceptable Use, Copyright, and Disclaimer Statement
Last updated October 10, 2010 - - mvs